CN108277817A - High Pile Cap for Tower Crane Foundation ruggedized construction and its construction method - Google Patents

High Pile Cap for Tower Crane Foundation ruggedized construction and its construction method Download PDF

Info

Publication number
CN108277817A
CN108277817A CN201810001964.6A CN201810001964A CN108277817A CN 108277817 A CN108277817 A CN 108277817A CN 201810001964 A CN201810001964 A CN 201810001964A CN 108277817 A CN108277817 A CN 108277817A
Authority
CN
China
Prior art keywords
sleeve
steel
reinforcing bar
tower crane
cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810001964.6A
Other languages
Chinese (zh)
Other versions
CN108277817B (en
Inventor
吕奇峰
王成骁
高东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201810001964.6A priority Critical patent/CN108277817B/en
Publication of CN108277817A publication Critical patent/CN108277817A/en
Application granted granted Critical
Publication of CN108277817B publication Critical patent/CN108277817B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention provides a kind of High Pile Cap for Tower Crane Foundation ruggedized constructions, including steel-pipe pile, cushion cap, sleeve, cover tube end plate and connection reinforcing bar, concrete has been poured in the steel-pipe pile, one end of the connection reinforcing bar is fixed in the cushion cap, the other end of the connection reinforcing bar is fixed in the sleeve, the sleeve is sheathed on the outside of the steel-pipe pile, the set tube end plate is fixed on the bottom of the sleeve, the outer wall of the set tube end plate and the steel-pipe pile is fixed, injected hole is offered on the barrel of the sleeve, it is connected with grout pipe at the injected hole, the cushion cap injects grouting material by the grout pipe with the steel-pipe pile into the sleeve to be fixed.Ruggedized construction of the present invention can greatly reinforce the anti-overturning of tower crane stake, buckling.Construction procedure has been simplified, it is easy to operate, the input of construction human cost has been saved, can be that unit in charge of construction creates certain economic benefit, also significantly meet the related request of green construction.

Description

High Pile Cap for Tower Crane Foundation ruggedized construction and its construction method
Technical field
The present invention relates to technical field of building construction, relate in particular to a kind of High Pile Cap for Tower Crane Foundation ruggedized construction and Its construction method.
Background technology
With sharply increasing for urban population, urban land is precious, City Building towards high-rise and Super High and Big scale of construction direction is developed, and under ground portion is increasing, and more and more deeply, original console mode tower crane construction does not adapt to Engineering requires the duration.Console mode tower crane is constructed after needing earth excavation, the drawbacks of causing duration cycle stretch-out.It is outstanding Empty formula tower crane carries out tower crane pile foundation bearing platform construction in advance, and consolidation process is carried out to tower crane, reinforces anti-overturning, resists Warping property.
Invention content
In view of the foregoing, the present invention provides a kind of High Pile Cap for Tower Crane Foundation reinforcing knot simple in structure, easy for construction Structure and its construction method are effectively improved existing tower crane and reinforce lacking for tedious process, inefficiency and anti-overturning difference Point.
To achieve the above object, the technical solution adopted by the present invention is that:A kind of High Pile Cap for Tower Crane Foundation ruggedized construction, packet Steel-pipe pile and the cushion cap above the steel-pipe pile are included, concrete has been poured in the steel-pipe pile, the ruggedized construction includes One end of sleeve, set tube end plate and connection reinforcing bar, the connection reinforcing bar is fixed in the cushion cap, described to connect the another of reinforcing bar End is fixed in the sleeve, and the sleeve is sheathed on the outside of the steel-pipe pile, and the set tube end plate is fixed on the sleeve Bottom, it is described set tube end plate and the steel-pipe pile outer wall fix, injected hole is offered on the barrel of the sleeve, it is described to hold Platform is fixed with the steel-pipe pile by injecting grouting material into the sleeve.
In the embodiment of the present invention, the other end for connecting reinforcing bar is configured to hook-shaped.
In the embodiment of the present invention, the connection reinforcing bar is arranged in a ring around the steel-pipe pile.
In the embodiment of the present invention, the external hoop of the connection reinforcing bar is equipped with ring-shaped stirrup.
In the embodiment of the present invention, the connection reinforcing bar is fixed by anchoring adhesive and the cushion cap.
In the embodiment of the present invention, injected hole is offered on the barrel of the sleeve.
A kind of construction method of High Pile Cap for Tower Crane Foundation ruggedized construction, includes the following steps:
A. it is fixedly connected with reinforcing bar below the cushion cap;
B., the sleeve is set outside the steel-pipe pile, injected hole is reserved on the barrel of the sleeve, the sleeve Bottom is fixed by covering tube end plate with the steel-pipe pile, and the connection reinforcing bar extends downward into the sleeve;
C. Grouting Pipe is connected at the injected hole, injects grouting material into the sleeve.
Further include to the cushion cap drill and sundries in cleaning hole in the embodiment of the present invention, before the step a.
In the embodiment of the present invention, the connection reinforcing bar is arranged in the sleeve along the steel-pipe pile in a ring.
In the embodiment of the present invention, the external hoop of the connection reinforcing bar is equipped with ring-shaped stirrup.
The present invention makes it have following advantageous effect as a result of above technical scheme:
(1) sleeve wall of the present invention is fixed on by full weld on bottom steel plate and tower crane steel-pipe pile, then is injected by grout pipe Grouting material.This measure can greatly reinforce the anti-overturning of tower crane stake, buckling.
(2) construction method of the present invention has simplified construction procedure, easy to operate, has saved the input of construction human cost, can Certain economic benefit is created for unit in charge of construction, also significantly meets the related request of green construction.
(3) other end of present invention connection reinforcing bar is configured to hook-shaped, is conducive to improve perfusion in connection reinforcing bar and sleeve and is starched The bond stress of material.
Description of the drawings
Fig. 1 is High Pile Cap for Tower Crane Foundation ruggedized construction schematic diagram of the present invention.
Fig. 2 is sleeve node schematic diagram of the present invention.
Fig. 3 is the partial enlarged view at S in Fig. 1.
The correspondence of reference numeral and component is as follows:
Steel-pipe pile 1;Cushion cap 2;Tower crane installs built-in fitting 3;Ruggedized construction 4;Sleeve 40;Cover tube end plate 41;Connect reinforcing bar 42; Grout pipe 43;Ring-shaped stirrup 44;Steel reinforcement cage 5;Raft foundation 6.
Specific implementation mode
For the benefit of to the understanding of the present invention, illustrate with reference to the accompanying drawings and embodiments.
It please refers to Fig.1, shown in Fig. 3, the present invention provides a kind of High Pile Cap for Tower Crane Foundation ruggedized construction, including steel-pipe pile 1 And the cushion cap 2 above the steel-pipe pile 1, concrete is poured in the steel-pipe pile 1, the cushion cap 2 is pacified equipped with tower crane Built-in fitting 3 is filled, the ruggedized construction 4 includes sleeve 40, set tube end plate 41 and connection reinforcing bar 42, one end of the connection reinforcing bar 42 It is fixed in the cushion cap 2, the other end of the connection reinforcing bar 42 is fixed in the sleeve 40, and the sleeve 40 is sheathed on institute The outside of steel-pipe pile 2 is stated, the set tube end plate 41 is fixed on the bottom of the sleeve 40, the set tube end plate 41 and the steel pipe The outer wall of stake 1 is fixed, and injected hole is offered on the barrel of the sleeve 40, grout pipe 43 is connected at the injected hole, described Cushion cap 2 injects grouting material by the grout pipe 43 with the steel-pipe pile 1 into the sleeve 40 to be fixed.
As shown in Fig. 2, the connection reinforcing bar 42 has multiple, the multiple connection reinforcing bar 42 is in the sleeve 40 in ring Shape arranges that the external hoop of the connection reinforcing bar 42 is equipped with ring-shaped stirrup 44, and the ring-shaped stirrup 44 is solid with the connection reinforcing bar 42 Surely it is connected to form one.In the present embodiment, hole is opened up on the cushion cap 2, one end of the connection reinforcing bar 42 passes through bar planting Glue is fixed on the lower section of the cushion cap 2, the other end of the connection reinforcing bar 42 be configured to it is hook-shaped, more preferably, the connection reinforcing bar 42 Reinforcing bar ontology and coupler body connecting portion be in 135 °, with increase connection reinforcing bar 42 and grouting material between bond stress.
In the embodiment of the present invention, the connection reinforcing bar 42 is C20 reinforcing bars, and the ring-shaped stirrup is C8 reinforcing bars, the sleeve 40 be the metal sleeve of 10mm thickness, and the set tube end plate 41 is the metallic plate of 10mm thickness, and the sectional area of the set tube end plate 41 is small In and close to the sleeve 40 floor space, it is described to prevent welding to be unsatisfactory for force request to ensure that it is close that installation coincide Sleeve 40 is connected as one with the set tube end plate 41 by groove full weld.
Grout pipe 43 of the present invention is metal grout pipe, and one end of the grout pipe 43 is by groove welding in the cylinder of sleeve 40 On wall, for full weld without gas overflowing, the other end is higher by cushion cap 150mm to ensure that grouting material is injected by pressure inside sleeve 40.
As shown in Figure 1, the bottom outside of the steel pipe column 1 is equipped with steel reinforcement cage 5, the top of the steel reinforcement cage 5 is equipped with raft plate Basis 6.
The details described above structure of High Pile Cap for Tower Crane Foundation ruggedized construction of the present invention, illustrates its construction party below Method mainly includes the following steps that:
A. to the cushion cap drill and cleaning hole in sundries, the one end for connecting reinforcing bar is fixed on by institute by anchoring adhesive It states in cushion cap;
B., the sleeve is set outside the steel-pipe pile, injected hole is reserved on the barrel of the sleeve, the sleeve Bottom is fixed by covering the outer wall of tube end plate and the steel-pipe pile, and the other end of the connection reinforcing bar extends downward into the sleeve It is interior;
The connection reinforcing bar arranges that the external of connection reinforcing bar is bound round in a ring in the sleeve along the steel-pipe pile Equipped with ring-shaped stirrup, the connection site of cushion cap and steel-pipe pile can be improved in the setting of multigroup connection reinforcing bar, and the setting of ring-shaped stirrup carries Connective stability between high each connection reinforcing bar;
C. Grouting Pipe is connected at the injected hole, injects grouting material into the sleeve.
It is described the invention in detail above in association with accompanying drawings and embodiments, those skilled in the art can basis Above description makes many variations example to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, The present invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (10)

1. a kind of High Pile Cap for Tower Crane Foundation ruggedized construction, including steel-pipe pile and the cushion cap above the steel-pipe pile, described Concrete is poured in steel-pipe pile, which is characterized in that the ruggedized construction includes sleeve, set tube end plate and connects reinforcing bar, described One end of connection reinforcing bar is fixed in the cushion cap, and the other end of the connection reinforcing bar is fixed in the sleeve, the sleeve It is sheathed on the outside of the steel-pipe pile, the set tube end plate is fixed on the bottom of the sleeve, the set tube end plate and the steel The outer wall of pile pile is fixed, and the cushion cap is fixed with the steel-pipe pile by injecting grouting material into the sleeve.
2. High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 1, which is characterized in that described to connect the another of reinforcing bar One end is configured to hook-shaped.
3. High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 1, which is characterized in that the connection reinforcing bar surrounds The steel-pipe pile is arranged in a ring.
4. High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 1, which is characterized in that outside the connection reinforcing bar Portion's hoop is equipped with ring-shaped stirrup.
5. High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 1, which is characterized in that the connection reinforcing bar passes through Anchoring adhesive is fixed with the cushion cap.
6. High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 1, which is characterized in that on the barrel of the sleeve Offer injected hole.
7. a kind of construction party of High Pile Cap for Tower Crane Foundation ruggedized construction as described in any claim in claim 1 to 6 Method, which is characterized in that include the following steps:
A. it is fixedly connected with reinforcing bar below the cushion cap;
B., the sleeve is set outside the steel-pipe pile, injected hole, the bottom of the sleeve are reserved on the barrel of the sleeve It is fixed with the steel-pipe pile by covering tube end plate, the connection reinforcing bar extends downward into the sleeve;
C. Grouting Pipe is connected at the injected hole, injects grouting material into the sleeve.
8. the construction method of High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 7, which is characterized in that the step Further include to the cushion cap drill and sundries in cleaning hole before rapid a.
9. the construction method of High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 7, which is characterized in that the company Reinforcing bar is connect to arrange in a ring along the steel-pipe pile in the sleeve.
10. the construction method of High Pile Cap for Tower Crane Foundation ruggedized construction according to claim 9, which is characterized in that described The external hoop for connecting reinforcing bar is equipped with ring-shaped stirrup.
CN201810001964.6A 2018-01-02 2018-01-02 Construction method of high-pile bearing platform tower crane foundation reinforcing structure Active CN108277817B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810001964.6A CN108277817B (en) 2018-01-02 2018-01-02 Construction method of high-pile bearing platform tower crane foundation reinforcing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810001964.6A CN108277817B (en) 2018-01-02 2018-01-02 Construction method of high-pile bearing platform tower crane foundation reinforcing structure

Publications (2)

Publication Number Publication Date
CN108277817A true CN108277817A (en) 2018-07-13
CN108277817B CN108277817B (en) 2020-02-07

Family

ID=62802947

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810001964.6A Active CN108277817B (en) 2018-01-02 2018-01-02 Construction method of high-pile bearing platform tower crane foundation reinforcing structure

Country Status (1)

Country Link
CN (1) CN108277817B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952582A (en) * 2019-11-22 2020-04-03 江苏省中成建设工程总公司 Old and new combined pile-raft foundation structure considering old pile concrete aging and construction method
CN112814010A (en) * 2021-01-06 2021-05-18 四川路桥盛通建筑工程有限公司 Construction method of steep terrain high pile cap

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561384A (en) * 2012-01-31 2012-07-11 中天建设集团有限公司天津分公司 Steel hoop truss type elevated pile cap tower crane foundation construction method and structure
CN103967036A (en) * 2014-05-07 2014-08-06 中国水电顾问集团华东勘测设计研究院有限公司 Pile and sleeve grouting connecting structure for offshore wind power generation and construction method thereof
CN105951612A (en) * 2016-07-01 2016-09-21 杭州江润科技有限公司 Defect repairing reinforcing structure for underwater pile head of serving bridge and construction method of defect repairing reinforcing structure
CN105951826A (en) * 2016-05-04 2016-09-21 太原理工大学 Suction ground anchor device in tubular pile and water pressure injection method thereof
CN205676918U (en) * 2016-04-01 2016-11-09 江苏庞源机械工程有限公司 A kind of underlying structure of tower crane steel Platform pipe column foundation
CN106801428A (en) * 2017-01-16 2017-06-06 青岛中天斯壮科技有限公司 Reinforced tensile-shear PHC pipe pile foundation structure and construction method thereof
CN206635790U (en) * 2017-01-23 2017-11-14 中铁第四勘察设计院集团有限公司 Pile tube and cushion cap attachment structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561384A (en) * 2012-01-31 2012-07-11 中天建设集团有限公司天津分公司 Steel hoop truss type elevated pile cap tower crane foundation construction method and structure
CN103967036A (en) * 2014-05-07 2014-08-06 中国水电顾问集团华东勘测设计研究院有限公司 Pile and sleeve grouting connecting structure for offshore wind power generation and construction method thereof
CN205676918U (en) * 2016-04-01 2016-11-09 江苏庞源机械工程有限公司 A kind of underlying structure of tower crane steel Platform pipe column foundation
CN105951826A (en) * 2016-05-04 2016-09-21 太原理工大学 Suction ground anchor device in tubular pile and water pressure injection method thereof
CN105951612A (en) * 2016-07-01 2016-09-21 杭州江润科技有限公司 Defect repairing reinforcing structure for underwater pile head of serving bridge and construction method of defect repairing reinforcing structure
CN106801428A (en) * 2017-01-16 2017-06-06 青岛中天斯壮科技有限公司 Reinforced tensile-shear PHC pipe pile foundation structure and construction method thereof
CN206635790U (en) * 2017-01-23 2017-11-14 中铁第四勘察设计院集团有限公司 Pile tube and cushion cap attachment structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952582A (en) * 2019-11-22 2020-04-03 江苏省中成建设工程总公司 Old and new combined pile-raft foundation structure considering old pile concrete aging and construction method
CN112814010A (en) * 2021-01-06 2021-05-18 四川路桥盛通建筑工程有限公司 Construction method of steep terrain high pile cap

Also Published As

Publication number Publication date
CN108277817B (en) 2020-02-07

Similar Documents

Publication Publication Date Title
CN102536252B (en) Method for digging backward hole of tunnel with quite small clear distance
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN108412128A (en) A kind of connection structure of steel core concrete column
CN103032080A (en) Support method of weak and broken surrounding rock tunnel
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN103628571B (en) Beam-column joint for reverse construction method and construction method
CN103088830A (en) Construction method for composite outer wall structure of ultra-deep basement
CN106988303B (en) A kind of pile foundation and its construction method
CN208966352U (en) A kind of supporting construction in weak rocks matter region tunnel
CN107795326A (en) The construction method of damper and tunnel support structure
CN105525753A (en) Method and structure for simultaneously constructing constructional column and main body structure
CN109113749A (en) Four line large section railway tunnel construction method of weak surrounding rock
CN109440832A (en) Anchor cable can be recycled pressure dispersing type pouch and expand body anti-floating pile and construction method
CN108951614A (en) A kind of spigot-and-socket drilled pile steel pile casting and its construction method
CN108277817A (en) High Pile Cap for Tower Crane Foundation ruggedized construction and its construction method
CN204753836U (en) Connected node of precast reinforced concrete roof beam and coincide post
CN208934258U (en) A kind of prefabricated assembled steel core concrete column connected structure part
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN114483081A (en) Construction method of deflection-preventing structure of curved middle wall of multi-arch tunnel under terrain bias pressure
CN105421488A (en) Constriction method for changing support of foundation slab in underground composite enclosure system
CN104594343A (en) Fabricated pile and construction method thereof
CN209066594U (en) The connection structure of contrary sequence method foundation pit construction central sill and steel core concrete column
CN105971196A (en) Method for constructing masonry structure embedded square concrete filled steel tube ring beam-constructional column
CN210288522U (en) Dam foundation rock mass reinforced structure based on prefabricated hollow pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant