CN108252501A - A kind of combined scaffold of architectural engineering - Google Patents

A kind of combined scaffold of architectural engineering Download PDF

Info

Publication number
CN108252501A
CN108252501A CN201810204845.0A CN201810204845A CN108252501A CN 108252501 A CN108252501 A CN 108252501A CN 201810204845 A CN201810204845 A CN 201810204845A CN 108252501 A CN108252501 A CN 108252501A
Authority
CN
China
Prior art keywords
side frame
architectural engineering
scaffold
bottom bar
stent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810204845.0A
Other languages
Chinese (zh)
Inventor
李丽娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Yake Hengyuan Technology Co Ltd
Original Assignee
Foshan Yake Hengyuan Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Yake Hengyuan Technology Co Ltd filed Critical Foshan Yake Hengyuan Technology Co Ltd
Priority to CN201810204845.0A priority Critical patent/CN108252501A/en
Publication of CN108252501A publication Critical patent/CN108252501A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/14Comprising essentially pre-assembled two-dimensional frame-like elements, e.g. of rods in L- or H-shape, with or without bracing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The invention discloses a kind of combined scaffolds of architectural engineering, including the first side frame and the second side frame, the top both sides of second side frame are mounted on engaging stent, card slot is provided at the top of the engaging stent, the bottom of the engaging stent is respectively connected with reinforcement support column, the reinforcement support column is mounted on the second side frame, several equally distributed jacks are offered on second side frame, the jack is internally connected with ladder bars, symmetrical fixed bayonet is offered on the inner wall of second side frame, the inside of the fixed bayonet is equipped with fixed link.The beneficial effects of the invention are as follows:Stent is engaged by design, flexible, convenient in carrying is dismounted between single assembly for scaffold, can be required according to Specific construction, it forms different groups of frame sizes and avoids the inconvenience that bolt operation is brought, without scattered fastener easy to be lost, component loss is reduced to minimum degree, load-carrying properties are good, securely and reliably.

Description

A kind of combined scaffold of architectural engineering
Technical field
The invention belongs to construction engineering technical fields, and in particular to a kind of combined scaffold of architectural engineering.
Background technology
Scaffold is to ensure each work progress is smoothed out and is set up workbench.Position by setting up is divided into outer Scaffold, internal scaffolding;It can be divided into timber scaffolding, bamboo scaffolding, steel pipe scaffold by material difference;It is divided by structural form vertical Rod-type scaffold, door-type scaffold, swinging scaffold, suspended scaffold, chooses formula scaffold, climbs formula foot hand bridge scaffold Frame.The scaffold of different purposes is selected in different types of engineering construction.Bridge support frame is in the majority using bowl buckle scaffold, also has Use door-type scaffold.As China largely modernizes the appearance of heavy construction system, fastener type steel pipe scaffold cannot The needs of construction development are adapted to, Devoting Major Efforts To Developing and popularization and application new type scaffold are the task of top priority.It was verified that using new Not only construction safety is reliable for type scaffold, and assembling and dissembling speed is fast, and scaffold steel using amount can reduce 33%, and assembly and disassembly work efficiency improves two Times or more, construction cost can be decreased obviously, and construction site is civilized, clean and tidy.
Existing technology has the following problems:1st, the universal scaffold safety assurance of current application is poor, and construction efficiency is low, The needs of capital construction projects development are not adapted to, and fastener is easily lost, quality of quality of connection fastener itself and operation Influence it is notable;2nd, the rod piece at node is connected to be eccentric, and load and internal force are transmitted by skid resistance, thus its bearing capacity drops It is low.
Invention content
To solve the problems mentioned above in the background art.The present invention provides a kind of combined foot hands of architectural engineering Frame has the characteristics that install convenient.
To achieve the above object, the present invention provides following technical solution:A kind of combined scaffold of architectural engineering, including First side frame and the second side frame, the top both sides of second side frame are mounted on engaging stent, the top of the engaging stent Card slot is provided with, the bottom of the engaging stent is respectively connected with reinforcement support column, and the reinforcement support column is mounted on the second side frame On, offering several equally distributed jacks on second side frame, the jack is internally connected with ladder bars, and described Symmetrical fixed bayonet is offered on the inner wall of two side frames, the inside of the fixed bayonet is equipped with fixed link, and two described solid Pedal is connected between fixed pole, the both ends of the fixed link offer connecting hole, set on the both sides outer wall of second side frame Scissors strut is equipped with, the both ends of the scissors strut are mounted in ladder bars, and the bottom of second side frame is equipped with the second bottom bar, The both ends of second bottom bar are mounted on pedestal, are provided with tenon at the top of second side frame, second side frame it is upper Side is provided with the first side frame, and first side frame is identical with the second side cage structure, and the bottom of first side frame is equipped with first Bottom bar, the both ends of first bottom bar are fixed on inside card slot, and first side frame is mounted on the by the first bottom bar and card slot On two side frames.
Preferably, the connection mode of first bottom bar and card slot is is connected together.
Preferably, it is provided with anti-skid chequer at the top of the pedal.
Preferably, it is connected with reinforcing bolt on the scissors strut.
Preferably, the engaging stent is an integral structure with strengthening support column.
Preferably, the connection mode of the scissors strut and ladder bars is socket.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, the present invention engages stent by design, and flexible, convenient in carrying is dismounted between single assembly for scaffold, can be according to tool Body construction requirement forms different groups of frame sizes and avoids the inconvenience that bolt operation is brought, without scattered fastener easy to be lost, structure Part loss is reduced to minimum degree, and load-carrying properties are good, securely and reliably.
2nd, the present invention effectively prevent scaffold linear deformation, enhances foot hand by the external installation scissors strut in side frame The overall stiffness of frame, rational in infrastructure, stress performance is good, makes full use of steel strength, and bearing capacity is high.
Description of the drawings
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the front view of the present invention;
Fig. 3 is the structure diagram of the present invention;
In figure:1st, fixed bayonet;2nd, tenon;3rd, engage stent;4th, ladder bars;5th, the first side frame;6th, the first bottom bar;7th, strengthen Support column;8th, the second side frame;9th, the second bottom bar;10th, jack;11st, card slot;12nd, fixed link;13rd, scissors strut;14th, pedestal; 15th, pedal;16th, connecting hole.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the present invention provides following technical scheme:The combined scaffold of a kind of architectural engineering, including One side frame 5 and the second side frame 8, the top both sides of the second side frame 8 are mounted on engaging stent 3, and the top of engaging stent 3 is provided with Card slot 11, the bottom of engaging stent 3, which is respectively connected with, strengthens support column 7, strengthens support column 7 and is mounted on the second side frame 8, engaging branch Frame 3 is an integral structure with strengthening support column 7, several equally distributed jacks 10, jack 10 are offered on the second side frame 8 Be internally connected with ladder bars 4, symmetrical fixed bayonet 1, the inside installation of fixed bayonet 1 are offered on the inner wall of the second side frame 8 There is fixed link 12, be connected with pedal 15 between two fixed links 12, the top of pedal 15 is provided with anti-skid chequer, and the two of fixed link 12 End offers connecting hole 16, and scissors strut 13 is provided on the both sides outer wall of the second side frame 8, is connected with and adds on scissors strut 13 Fixing bolt, the both ends of scissors strut 13 are mounted in ladder bars 4, and the connection mode of scissors strut 13 and ladder bars 4 is to be socketed, the second side The bottom of frame 8 is equipped with the second bottom bar 9, and the both ends of the second bottom bar 9 are mounted on pedestal 14, and the top of the second side frame 8 is provided with Tenon 2, the top of the second side frame 8 are provided with the first side frame 5, and the first side frame 5 is identical with 8 structure of the second side frame, the first side frame 5 Bottom is equipped with the first bottom bar 6, and the both ends of the first bottom bar 6 are fixed on inside card slot 11, the connection side of the first bottom bar 6 and card slot 11 To be connected together, the first side frame 5 is mounted on by the first bottom bar 6 and card slot 11 on the second side frame 8 formula.
The operation principle and process for using of the present invention:The present invention pacifies 8 bottom end of the second side frame of bottom in installation The second bottom bar 9 is loaded onto, upper bed-plate 14 is installed at the both ends of the second bottom bar 9, fixes in bayonet 1 and installs on the side frame top of top layer Upper fixed link 12, and ladder bars 4 are installed in the inside of jack 10 successively, it is assembled into helper, 4 both ends of ladder bars of side frame the top Across connecting hole 16, also so as to fix pedal 15, scissors strut 13 is installed in the both sides of side frame, the second side frame 8 is used as foot First side frame 5 on upper strata is directed at the top that tenon 2 is connected to the second side frame 8 by hand cradle base foundation, while the first bottom bar 6 Both ends are each attached to inside the card slot 11 on engaging stent 3, are required overlap-add operation according to Specific construction, are completed multi-layer constructed.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (6)

1. a kind of combined scaffold of architectural engineering, including the first side frame (5) and the second side frame (8), it is characterised in that:It is described The top both sides of second side frame (8) are mounted on engaging stent (3), and card slot (11) is provided at the top of the engaging stent (3), The bottom of the engaging stent (3), which is respectively connected with, strengthens support column (7), and the reinforcement support column (7) is mounted on the second side frame (8) On, several equally distributed jacks (10) are offered on second side frame (8), jack (10) are internally connected with Ladder bars (4) offer symmetrical fixed bayonet (1), the inside of the fixed bayonet (1) on the inner wall of second side frame (8) Fixed link (12) is installed, pedal (15) is connected between two fixed links (12), the both ends of the fixed link (12) are equal Connecting hole (16) is offered, scissors strut (13), the scissors strut are provided on the both sides outer wall of second side frame (8) (13) both ends are mounted in ladder bars (4), and the bottom of second side frame (8) is equipped with the second bottom bar (9), second bottom bar (9) both ends are mounted on pedestal (14), and tenon (2), second side frame (8) are provided at the top of second side frame (8) Top be provided with the first side frame (5), first side frame (5) is identical with the second side frame (8) structure, first side frame (5) Bottom the first bottom bar (6) is installed, it is internal that the both ends of first bottom bar (6) are fixed on card slot (11), first side frame (5) by the first bottom bar (6) and card slot (11) on the second side frame (8).
2. a kind of combined scaffold of architectural engineering according to claim 1, it is characterised in that:First bottom bar (6) with the connection mode of card slot (11) to be connected together.
3. a kind of combined scaffold of architectural engineering according to claim 1, it is characterised in that:The pedal (15) Top is provided with anti-skid chequer.
4. a kind of combined scaffold of architectural engineering according to claim 1, it is characterised in that:The scissors strut (13) reinforcing bolt is connected on.
5. a kind of combined scaffold of architectural engineering according to claim 1, it is characterised in that:The engaging stent (3) it is an integral structure with strengthening support column (7).
6. a kind of combined scaffold of architectural engineering according to claim 1, it is characterised in that:The scissors strut (13) it is socket with the connection mode of ladder bars (4).
CN201810204845.0A 2018-03-13 2018-03-13 A kind of combined scaffold of architectural engineering Withdrawn CN108252501A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810204845.0A CN108252501A (en) 2018-03-13 2018-03-13 A kind of combined scaffold of architectural engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810204845.0A CN108252501A (en) 2018-03-13 2018-03-13 A kind of combined scaffold of architectural engineering

Publications (1)

Publication Number Publication Date
CN108252501A true CN108252501A (en) 2018-07-06

Family

ID=62746842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810204845.0A Withdrawn CN108252501A (en) 2018-03-13 2018-03-13 A kind of combined scaffold of architectural engineering

Country Status (1)

Country Link
CN (1) CN108252501A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778268A (en) * 2019-10-29 2020-02-11 新昌县凌智机械有限公司 A equipment mounting bracket for mine engineering construction

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002066765A2 (en) * 2001-02-22 2002-08-29 Wilhelm Layher Vermögensverwaltungs-Gmbh Connection device for scaffolding
CN205330126U (en) * 2015-12-03 2016-06-22 无锡市晨源建筑器材有限公司 High scaffold of security for building
CN206397111U (en) * 2017-01-13 2017-08-11 黄伟明 Novel building engineering scaffold device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002066765A2 (en) * 2001-02-22 2002-08-29 Wilhelm Layher Vermögensverwaltungs-Gmbh Connection device for scaffolding
CN205330126U (en) * 2015-12-03 2016-06-22 无锡市晨源建筑器材有限公司 High scaffold of security for building
CN206397111U (en) * 2017-01-13 2017-08-11 黄伟明 Novel building engineering scaffold device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778268A (en) * 2019-10-29 2020-02-11 新昌县凌智机械有限公司 A equipment mounting bracket for mine engineering construction

Similar Documents

Publication Publication Date Title
CN101503908B (en) Construction method for spacing suspension cable structural template support platform
CN102877638A (en) Operating platform and operating method for constructing suspension steel structure system
CN108252501A (en) A kind of combined scaffold of architectural engineering
CN201661066U (en) Scaffold connecting mechanism
CN201712776U (en) Support for building scaffold boards
CN219528334U (en) Scaffold for building construction
CN203846791U (en) Beam-column joint reinforcing pipa bracket system used for archaistic buildings or historic building restoration
CN215671992U (en) Construction cat ladder
CN215168009U (en) Novel combined building curtain wall template for building
CN201873949U (en) Bride prestress stretch-draw trolley
CN209369330U (en) A kind of rail brackets of jumping formwork
CN2519833Y (en) Fastener for scaffold
CN217680342U (en) Scaffold for house construction
CN204212069U (en) Hanging basket for building construction
CN109898816A (en) A kind of housing construction scaffold
CN217998865U (en) Wall scaffold board installation device is leaned on to activity assembled scaffold frame
CN220747577U (en) Reinforced steel structure platform
CN212689545U (en) Corner pole setting device for lifting aluminum alloy climbing frame
CN215671235U (en) High-strength assembly type steel structure support
CN218205592U (en) Scaffold frame that construction was used
CN213868823U (en) Convenient stable gate-type scaffold
CN218912152U (en) Disc buckle type scaffold structure
CN216471922U (en) Transition joint structure
CN204326122U (en) Foundation pile pressure-resistant static load test girder connector
CN210140988U (en) Hydraulic climbing formwork bearing triangular frame lengthening device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180706