CN108223924A - A kind of assembled vertical shaft air hose combined bracket - Google Patents
A kind of assembled vertical shaft air hose combined bracket Download PDFInfo
- Publication number
- CN108223924A CN108223924A CN201810171645.XA CN201810171645A CN108223924A CN 108223924 A CN108223924 A CN 108223924A CN 201810171645 A CN201810171645 A CN 201810171645A CN 108223924 A CN108223924 A CN 108223924A
- Authority
- CN
- China
- Prior art keywords
- crosspiece
- anchor ear
- air hose
- main
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 60
- 239000010959 steel Substances 0.000 claims abstract description 60
- 230000007246 mechanism Effects 0.000 claims description 20
- 239000011148 porous material Substances 0.000 claims description 5
- 239000007787 solid Substances 0.000 claims description 2
- 238000009434 installation Methods 0.000 abstract description 12
- 101100460844 Mus musculus Nr2f6 gene Proteins 0.000 description 11
- 238000003466 welding Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 210000005069 ears Anatomy 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 238000012423 maintenance Methods 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000005034 decoration Methods 0.000 description 2
- 238000011065 in-situ storage Methods 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000004080 punching Methods 0.000 description 2
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000003801 milling Methods 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/08—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
- F16L3/10—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing
- F16L3/1091—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing with two members, the two members being fixed to each other with fastening members on each side
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/22—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets specially adapted for supporting a number of parallel pipes at intervals
- F16L3/237—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets specially adapted for supporting a number of parallel pipes at intervals for two pipes
Abstract
The present invention provides a kind of assembled vertical shaft air hose combined bracket, including band steel anchor ear, secondary crosspiece, main crosspiece, bracket upright post and anchor ear tapered end.Bracket upright post top is fixed at the bottom at main crosspiece both ends.Bracket upright post bottom is fixed on external floor.Secondary crosspiece is across on the main crosspiece of two or two or more.Secondary crosspiece and the movable setting of main crosspiece.Band steel anchor ear is fastened on around external vertical air hose, and the band steel anchor ear is locked by anchor ear tapered end and is arranged on time crosspiece.The present invention is by being that movable connection is set between the secondary crosspiece of setting and main crosspiece, so that adjusting size that can be careless when installing vertical air hose, meet the installation requirements of the vertical air hose of different sizes, be bolted simultaneously so that overhauled in the later stage more convenient.
Description
Technical field
The present invention relates to air hose installing areas, particularly, are related to a kind of assembled vertical shaft air hose combined bracket.
Background technology
In traditional vertical electromechanical air hose installation, the combined bracket of vertical duct is all utilized in prefabricated processing space or library
After room welding fabrication, then installed to construction site.Vertical air hose joint suspension and support, the main crosspiece of stent and branch sortie crosspiece are equal
Using being welded to connect, welding job amount is very big.If deviation occurs in fruit structure reserved opening, the secondary crosspiece of combined bracket is with combining
The relative position needs of stent are adjusted, and time crosspiece needs scene to be welded in this way, cause a large amount of fragmentary work in this way
Industry, fragmentary operation work efficiency is low, and construction site weld job increases fire hazard.If pipeline maintenance dismounting is relatively large, some
Position also needs to carry out fire operation.So that the maintenance process in installation needs a large amount of human resources, while the time is long, no
The demand of enterprise can be met.
Therefore, it is necessary to design a kind of assembled vertical shaft air hose combined bracket, so as to meet the daily vertical shaft air hose peace of people
The demand of dress.
Invention content
Present invention aims at a kind of assembled vertical shaft air hose combined bracket is provided, to solve traditional vertical shaft support of duct
Assembled in situ is unable to, fragmentary operation is more, there is technical issues that.
To achieve the above object, the present invention provides a kind of assembled vertical shaft air hose combined brackets, are embraced including band steel
Hoop, secondary crosspiece, main crosspiece, bracket upright post and anchor ear tapered end;The bracket upright post top is fixed at main crosspiece
The bottom at both ends, the bracket upright post bottom are fixed on external floor;The secondary crosspiece is across at two or two
On above main crosspiece, the secondary crosspiece and the movable setting of main crosspiece;The band steel anchor ear is fastened on external vertical air hose
Around, the band steel anchor ear is locked by anchor ear tapered end and is arranged on time crosspiece.
The invention also includes protection pier, the protection pier is arranged between bracket upright post and floor, protection pier top portion
It is fixedly connected with bracket upright post bottom, protection pier bottom portion is fixedly installed with floor, and the protection pier is set as rectangular
Pier body structure.
The invention also includes vertical duct sleeves to close pier, and vertical duct sleeve closes pier and is arranged on the side that time crosspiece and main crosspiece surround
Shape frame bottom;Vertical duct sleeve closes the pier shape structure that pier is set as protrusion, and vertical duct sleeve closes and is provided with vertical air hose among pier
Hole, external vertical duct sleeve, which enters in vertical wind pore, to be fixedly installed.
Main crosspiece central bottom is arranged on the invention also includes stent central post described in stent central post, in the stent
Column top and main crosspiece are fixedly installed, stent central post) low side is fixedly installed with floor.
In said program, preferably main crosspiece is set as Two bors d's oeuveres " C " profile steel mechanism, and Two bors d's oeuveres " C " profile steel mechanism level is opened
Mouth is set up;The secondary crosspiece is set as " C " profile steel mechanism structure, and " C " profile steel mechanism horizontal opening is set up.
It in said program, is set between preferably main crosspiece and secondary crosspiece by fixing bolt, secondary crosspiece both ends offer
Bolt hole, the bottom bolts cap sleeve of fixing bolt enter in Two bors d's oeuveres " C " profile steel mechanism, and the bolt body of rod of fixing bolt penetrates time crosspiece
Bolt hole in, and pass through screw tightening set.
In said program, preferably it is fixedly installed between band steel anchor ear and secondary crosspiece by anchor ear bolt, anchor ear bolt
Nuts is inserted in " C " profile steel mechanism, and the bolt body of rod of anchor ear bolt is penetrated in anchor ear tapered end to be set by screw tightening.
In said program, preferably band steel anchor ear sets two semicircular structures, semicircular structure and semicircular structure
Between one end be flexibly connected, the other end between semicircular structure and semicircular structure is fixedly installed by anchor ear tapered end, band steel anchor ear
It is provided with elastoplastic glue-line.
The invention has the advantages that:
The present invention is by being that movable connection is set between the secondary crosspiece of setting and main crosspiece, so that in installation vertical wind
Adjusting size that can be careless during pipe, meets the installation requirements of the vertical air hose of different sizes, is bolted, makes simultaneously
Must be more convenient in later stage maintenance, secondary crosspiece and main crosspiece are set as " C " profile steel mechanism, and C-type steel mechanical property is good, save steel
Dosage reduces cost, and C-type steel end can cover its section with special plastic end socket, and rack forming effect is good, reaches decoration
Electromechanical effect;Main crosspiece connects fixation, and secondary crosspiece can be taken up an official post according to pipeline location in main crosspiece with time crosspiece material bolt
Meaning position is fixed, and stent in-site installation is without weld job, and construction efficiency is high, no fire hazard;Primary and secondary crosspiece can take horizontal stroke
To with vertical arrangement, met all kinds of installations into discharge pipe, if main crosspiece span is excessive, can among main crosspiece position
Upright bar is added, to meet the mechanical requirements of C-type steel;If air-line system needs to overhaul, only primary and secondary crosspiece need to be connected bolt and twisted
It opens and moves, then air-line system is disassembled, after the completion of reparation, and can reinstall.
Other than objects, features and advantages described above, the present invention also has other objects, features and advantages.
Below with reference to figure, the present invention is described in further detail.
Description of the drawings
The attached drawing for forming the part of the application is used to provide further understanding of the present invention, schematic reality of the invention
Example and its explanation are applied for explaining the present invention, is not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is that the pipeline of the preferred embodiment of the present invention is vertically arranged side elevational view.
Fig. 2 is that the pipeline of the preferred embodiment of the present invention is vertically arranged front elevation view.
Fig. 3 is the pipeline transverse direction arrangement front elevation view of the preferred embodiment of the present invention.
Fig. 4 is the vertical alignment plane figure of pipeline of the preferred embodiment of the present invention.
Fig. 5 is the pipeline transverse direction alignment plane figure of the preferred embodiment of the present invention.
Figure label:The vertical air hoses of 1-;2- band steel anchor ears;3- crosspiece;The main crosspieces of 4-;5- bracket upright posts;6- anchor ears are locked
Head;7- fixing bolts;8- protects pier, 9- stent central posts.
Specific embodiment
The embodiment of the present invention is described in detail below in conjunction with attached drawing, but the present invention can be limited according to claim
Fixed and covering multitude of different ways is implemented.
A kind of assembled vertical shaft air hose combined bracket, as shown in Figs. 1-5, including band steel anchor ear 2, secondary crosspiece 3, main crosspiece 4,
Bracket upright post 5 and anchor ear tapered end 6.Each vertical air hose 1 needs minimum twice crosspieces 3 and two main crosspieces 4, twice crosspieces
3 and two main crosspieces 4 form one can activity change four side rods of intermediate square box size so that being suitble to perpendicular in installation
It to fragmentary operation not many during air hose 1, while is set between main crosspiece 4 and secondary crosspiece 3 by fixing bolt 7, secondary 3 both ends of crosspiece
Bolt hole is offered, the bottom bolts cap sleeve of fixing bolt 7 enters in Two bors d's oeuveres " C " profile steel mechanism, and the bolt body of rod of fixing bolt 7 is worn
In the bolt hole for entering time crosspiece 3, and set by screw tightening.Reduce the welding procedure in installation process, prevent because of weldering
Pick up the accident of fire.
5 top of bracket upright post is fixed at the bottom at main 4 both ends of crosspiece.5 bottom of bracket upright post is fixed at outside
Floor on.Secondary crosspiece 3 is across on the main crosspiece 4 of two or two or more.Secondary crosspiece 3 and main 4 movable setting of crosspiece.It is flat
Steel hoop 2 is fastened on around external vertical air hose 1.Band steel anchor ear 2 is locked by anchor ear tapered end 6 and is arranged on time crosspiece 3
On.Protection pier 8 is further included, the protection pier 8 is arranged between bracket upright post 5 and floor, 8 top of protection pier and bracket upright post 5
Bottom is fixedly connected, and protection 8 bottom of pier is fixedly installed with floor, and the protection pier 8 is set as rectangular pier body structure.Protect pier 8
For the fixed setting between further protective cradle column 5 and floor.
Wherein, it further includes vertical duct sleeve and closes pier, vertical duct sleeve closes that pier is arranged on time crosspiece 3 and main crosspiece 4 surrounds
Rectangular frame bottom.Vertical duct sleeve closes the pier shape structure that pier is set as protrusion, and vertical duct sleeve closes and is provided with vertical wind among pier
Pore, external vertical air hose 1 are inserted in vertical wind pore and are fixedly installed.In order to enable main 4 bottom of crosspiece fixation is more steady, also
Including stent central post 9, stent central post 9 is arranged on main 4 central bottom of crosspiece, 9 top of stent central post and main crosspiece 4
Fixed setting, 9 low side of stent central post are fixedly installed with floor.The structure phase of the structure of stent central post 9 and bracket upright post 5
Seemingly, identical supporting role is played.
Main crosspiece 4 is set as Two bors d's oeuveres " C " profile steel mechanism, and Two bors d's oeuveres " C " profile steel mechanism horizontal opening is set up;Described time horizontal
Shelves 3 are set as " C " profile steel mechanism structure, and " C " profile steel mechanism horizontal opening is set up.By solid between main crosspiece 4 and secondary crosspiece 3
Determine bolt 7 to set, secondary 3 both ends of crosspiece offer bolt hole, and the bottom bolts cap sleeve of fixing bolt 7 enters Two bors d's oeuveres " C " profile steel mechanism
Interior, the bolt body of rod of fixing bolt 7 is penetrated in the bolt hole of time crosspiece 3, and is set by screw tightening.Band steel anchor ear 2 with time
It is fixedly installed between crosspiece 3 by anchor ear bolt, the nuts of anchor ear bolt is inserted in " C " profile steel mechanism, the bolt of anchor ear bolt
The body of rod is penetrated in anchor ear tapered end 6 and is set by screw tightening.Band steel anchor ear 2 set two semicircular structures, semicircular structure with
One end is flexibly connected between semicircular structure, and the other end between semicircular structure and semicircular structure is set by the fixation of anchor ear tapered end 6
It puts, band steel anchor ear 2 is provided with elastoplastic glue-line.The column of combined bracket, main crosspiece use C using Two bors d's oeuveres C-type steel, secondary crosspiece
Shaped steel.The bracket upright post of the combined bracket and main crosspiece using be welded to connect, main crosspiece and secondary crosspiece are connected by screw bolts, c-type
Steel end can cover its section with special plastic end socket, achieve the effect that decoration is electromechanical.Main crosspiece and time crosspiece are C-type steel
Between connection, without punching connection according to field condition, meeting time crosspiece can be arbitrary according to pipeline location on main crosspiece
It slides, meets the various working condition requirements in scene.Vertical air hose 1 is embraced with 2 semicircle (or square) band steel anchor ears, semicircle (or
Square) openend be connected with, be fixed on wind pipe wall with and with rivet, openend is set plus floor, will be with ribbed panel
Linkage section freely-supported on secondary crosspiece, realize the vertical supporting of air hose and fixed with level.When more into discharge pipe in same pipe
When well, main crosspiece span are excessive, supporting point can be increased among main crosspiece, vertical arrangement can also be changed into lateral arrangement, it is secondary
Crosspiece can arbitrarily be arranged according to caliber and pipeline location.
The present invention is made of C-type steel, and combined bracket uses site assembly mounting, and main crosspiece 4 and time crosspiece 3 pass through spiral shell
It tethers and connects, prevented construction site weld job, reduce the fragmentary operation of welding, while decrease fire hazard.Secondary crosspiece 3
It can be slid in main 4 direction of crosspiece of main 4 upper edge of crosspiece, to meet the installation of different tube diameters and Duo Gen pipelines.Semicircle (or side
Type) rivet of band steel anchor ear 2 and air hose fix to form entirety, and the close segments of semicircle (or square) band steel anchor ear 2 are using with ribbing
Anchor ear tapered end 6, increase the forced area of band steel anchor ear 2 and time crosspiece 3, one end in time crosspiece 3 buckled into for one section using bolt
6 top of anchor ear tapered end is buckled in, anchor ear tapered end 6 is fixed on time crosspiece, strength and stability when ensure that air hose installation.Assembling
Formula vertical shaft air hose combined bracket can be arranged to vertical and lateral 2 kinds of modes.The present invention is for architectural engineering electro-mechanical arts
Vertical air hose installation in building realizes the assembled in situ of vertical shaft air hose combined bracket.
Installation process:
Bracket upright post 5 is welded on main crosspiece 4 in prefabricated processing space, the pedestal of 5 bottom of bracket upright post welding punching is applied
Work scene squeezes into bracket upright post 5 in bearing hole with expansion bolt, and bearing column 5 and main crosspiece 4 are fixed on floor, by master
After crosspiece leveling, expansion bolt is tightened.Nut and gasket left-hand thread are become owner of in the C-type steel of crosspiece 5, the screw of nut passes through time
In the slot hole of the hole milling at 3 both ends of crosspiece, it is screwed on screw rod, wouldn't be tightened with nut on secondary crosspiece top;Air hose 1 is installed, it will
Secondary crosspiece 3 slides onto 1 attachment of air hose from main crosspiece 5, and vertical air hose 1 is embraced with semicircle (or square) band steel anchor ear 2;It is with ribbing
Anchor ear tapered end 2 semicircle (or square) band steel anchor ears 2 locked lock air hose 1, and with rivet by semicircle (or square)
Band steel anchor ear 2 is fixed on air hose 1, and semicircle (or square) band steel anchor ear 2 and air hose 1 are become an entirety, and will be with ribbing
Anchor ear tapered end fall the vertical supporting in secondary crosspiece 3, realizing air hose and fixed with level.Secondary crosspiece 3 can be on main crosspiece 5 on
Lower sliding adapts to installation and fixation without caliber, different arrangement pipelines, can be among main crosspiece 5 if main crosspiece 5 is long
Support post 9 is added, meets different operating mode needs.According to pipe arrangement situation, 3 or more main crosspieces can be set, by secondary crosspiece 3
It is slid up and down on main crosspiece 5, meets the needs of different operating modes.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field
For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, that is made any repaiies
Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.
Claims (8)
1. a kind of assembled vertical shaft air hose combined bracket, which is characterized in that including band steel anchor ear (2), secondary crosspiece (3), main crosspiece
(4), bracket upright post (5) and anchor ear tapered end (6);Bracket upright post (5) top is fixed at the bottom at main crosspiece (4) both ends
Portion, bracket upright post (5) bottom are fixed on external floor;The secondary crosspiece (3) across two or two with
On main crosspiece (4) on, the secondary crosspiece (3) and main crosspiece (4) movable setting;The band steel anchor ear (2) is fastened on outside
Vertical air hose (1) around, the band steel anchor ear (2) is locked by anchor ear tapered end (6) and is arranged on time crosspiece (3).
2. a kind of assembled vertical shaft air hose combined bracket according to claim 1, which is characterized in that further include protection pier
(8), the protection pier (8) is arranged on bracket upright post (5) between floor, solid with bracket upright post (5) bottom at the top of protection pier (8)
Fixed connection, protection pier (8) bottom are fixedly installed with floor, and the protection pier (8) is set as rectangular pier body structure.
3. a kind of assembled vertical shaft air hose combined bracket according to claim 1, which is characterized in that further include vertical air hose
Fitting pier, vertical duct sleeve close pier and are arranged on the rectangular frame bottom that time crosspiece (3) and main crosspiece (4) surround;Vertical duct sleeve closes
Pier is set as the pier shape structure of protrusion, and vertical duct sleeve closes and vertical wind pore is provided among pier, external vertical air hose (1) set
Enter in vertical wind pore and be fixedly installed.
4. a kind of assembled vertical shaft air hose combined bracket according to claim 1, which is characterized in that further include stent neutrality
Column (9) the stent central post (9) is arranged on main crosspiece (4) central bottom, stent central post (9) top and main crosspiece
(4) it is fixedly installed, stent central post (9) low side is fixedly installed with floor.
A kind of 5. assembled vertical shaft air hose combined bracket according to claim 1, which is characterized in that the main crosspiece (4)
Two bors d's oeuveres " C " profile steel mechanism is set as, Two bors d's oeuveres " C " profile steel mechanism horizontal opening is set up;The secondary crosspiece (3) is set as " C "
Profile steel mechanism structure, " C " profile steel mechanism horizontal opening are set up.
A kind of 6. assembled vertical shaft air hose combined bracket according to claim 5, which is characterized in that the main crosspiece (4)
It is set between secondary crosspiece (3) by fixing bolt (7), secondary crosspiece (3) both ends offer bolt hole, the bottom of fixing bolt (7)
Nuts is inserted in Two bors d's oeuveres " C " profile steel mechanism, and the bolt body of rod of fixing bolt (7) is penetrated in the bolt hole of time crosspiece (3), and lead to
Cross screw tightening setting.
A kind of 7. assembled vertical shaft air hose combined bracket according to claim 5, which is characterized in that the band steel anchor ear
(2) it is fixedly installed between time crosspiece (3) by anchor ear bolt, the nuts of anchor ear bolt is inserted in " C " profile steel mechanism, anchor ear spiral shell
The bolt body of rod of bolt is penetrated in anchor ear tapered end (6) and is set by screw tightening.
A kind of 8. assembled vertical shaft air hose combined bracket according to claim 7, which is characterized in that the band steel anchor ear
(2) two semicircular structures are set, and one end is flexibly connected between semicircular structure and semicircular structure, semicircular structure and semicircle
The interstructural other end is fixedly installed by anchor ear tapered end (6), and band steel anchor ear (2) is provided with elastoplastic glue-line.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810171645.XA CN108223924A (en) | 2018-03-01 | 2018-03-01 | A kind of assembled vertical shaft air hose combined bracket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810171645.XA CN108223924A (en) | 2018-03-01 | 2018-03-01 | A kind of assembled vertical shaft air hose combined bracket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108223924A true CN108223924A (en) | 2018-06-29 |
Family
ID=62662425
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810171645.XA Pending CN108223924A (en) | 2018-03-01 | 2018-03-01 | A kind of assembled vertical shaft air hose combined bracket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108223924A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111691642A (en) * | 2020-06-22 | 2020-09-22 | 中建三局安装工程有限公司 | Novel anti-skidding limiting device for air duct flip-chip |
CN115654214A (en) * | 2022-11-29 | 2023-01-31 | 北京建工集团有限责任公司 | Sliding type vertical pipe support and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000154932A (en) * | 1998-11-18 | 2000-06-06 | Taisei Corp | Vertical duct fixing mechanism in building |
CN203703378U (en) * | 2013-12-17 | 2014-07-09 | 广州广船国际股份有限公司 | Adjustable air pipe hanging bracket structure |
CN204922225U (en) * | 2015-09-17 | 2015-12-30 | 江苏扬子鑫福造船有限公司 | Marine tuber pipe installing support |
CN205424196U (en) * | 2016-01-12 | 2016-08-03 | 中国建筑第八工程局有限公司 | Shaft wind pipe connection |
CN205472102U (en) * | 2016-01-11 | 2016-08-17 | 上海威茨堡电梯有限公司 | Modular well frame |
CN206159665U (en) * | 2016-10-12 | 2017-05-10 | 中建五局工业设备安装有限公司 | Mounting system for vertical duct |
CN208074278U (en) * | 2018-03-01 | 2018-11-09 | 中建五局安装工程有限公司 | A kind of assembled vertical shaft air hose combined bracket |
-
2018
- 2018-03-01 CN CN201810171645.XA patent/CN108223924A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000154932A (en) * | 1998-11-18 | 2000-06-06 | Taisei Corp | Vertical duct fixing mechanism in building |
CN203703378U (en) * | 2013-12-17 | 2014-07-09 | 广州广船国际股份有限公司 | Adjustable air pipe hanging bracket structure |
CN204922225U (en) * | 2015-09-17 | 2015-12-30 | 江苏扬子鑫福造船有限公司 | Marine tuber pipe installing support |
CN205472102U (en) * | 2016-01-11 | 2016-08-17 | 上海威茨堡电梯有限公司 | Modular well frame |
CN205424196U (en) * | 2016-01-12 | 2016-08-03 | 中国建筑第八工程局有限公司 | Shaft wind pipe connection |
CN206159665U (en) * | 2016-10-12 | 2017-05-10 | 中建五局工业设备安装有限公司 | Mounting system for vertical duct |
CN208074278U (en) * | 2018-03-01 | 2018-11-09 | 中建五局安装工程有限公司 | A kind of assembled vertical shaft air hose combined bracket |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111691642A (en) * | 2020-06-22 | 2020-09-22 | 中建三局安装工程有限公司 | Novel anti-skidding limiting device for air duct flip-chip |
CN115654214A (en) * | 2022-11-29 | 2023-01-31 | 北京建工集团有限责任公司 | Sliding type vertical pipe support and construction method thereof |
CN115654214B (en) * | 2022-11-29 | 2023-03-10 | 北京建工集团有限责任公司 | Sliding type vertical pipe support and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206555567U (en) | A kind of antidetonation suspension and support | |
US6782668B2 (en) | Roof-screen system | |
CN208074278U (en) | A kind of assembled vertical shaft air hose combined bracket | |
CN108223924A (en) | A kind of assembled vertical shaft air hose combined bracket | |
EP3572602A1 (en) | Vertical cable barrier | |
CN104791984B (en) | A kind of bracket of outdoor machine of air conditioner of vibration damping antirust | |
CN203947756U (en) | Exterior wall protective frame | |
CN205369978U (en) | Prefabricated plate support frame | |
CN108360830B (en) | On-site construction protector | |
CN203663277U (en) | Falling-prevention safety device for high-attitude air conditioner repair | |
CN114558261B (en) | Underground space construction is with fire prevention safety control system | |
CN105863192B (en) | A kind of balcony guardrail | |
KR102281205B1 (en) | Extension arm and construction method of transmission tower | |
CN108265861A (en) | A kind of aluminium-plastic panel mounting connection structure | |
CN210369867U (en) | Overhanging type outer discharge frame protection device | |
CN104912373B (en) | Assembly type supporting switching device for temporary power consumption at construction site | |
CN104975707A (en) | Shed frame and triangular support frame body of shed frame | |
CN208503173U (en) | A kind of fastener of screen carrier round tube and round tube interconnection | |
CN206053050U (en) | Glass curtain wall mounting structure | |
CN203715127U (en) | General safety rod system for tower crane attaching device | |
CN207739733U (en) | A kind of corner protective fence connector | |
KR20200135257A (en) | Flexible Tube For Sprinkler | |
CN216429112U (en) | Adjustable faces limit protector | |
CN206503284U (en) | A kind of semicircle vertex of a cone combines paulin room with curved surface top | |
CN109610798A (en) | A kind of architectural engineering height-adjustable scaffold easy to remove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 410004 No. 158 Zhongyi Road, Yuhua District, Changsha, Hunan Applicant after: China Construction five Bureau Installation Engineering Co., Ltd. Address before: 410004 20, Zhongjian mansion, 158 Zhongyi Road, Changsha, Hunan. Applicant before: CCFEB Industrial Equipment Installation Co., Ltd. |