CN108222962A - A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology - Google Patents

A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology Download PDF

Info

Publication number
CN108222962A
CN108222962A CN201810263191.9A CN201810263191A CN108222962A CN 108222962 A CN108222962 A CN 108222962A CN 201810263191 A CN201810263191 A CN 201810263191A CN 108222962 A CN108222962 A CN 108222962A
Authority
CN
China
Prior art keywords
main body
body mechanism
release
release main
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810263191.9A
Other languages
Chinese (zh)
Other versions
CN108222962B (en
Inventor
赵洪宝
王涛
张勉
张欢
刘洪�
刘一洪
魏子强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN201810263191.9A priority Critical patent/CN108222962B/en
Publication of CN108222962A publication Critical patent/CN108222962A/en
Application granted granted Critical
Publication of CN108222962B publication Critical patent/CN108222962B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of placing concrete opening steel pipes for allowing anti-binding to prevent pucking device and technology, the anti-release main body mechanism, which comes into full contact with pressure relief vent and carries pressure relief vent edge stress, occurs corresponding deformation, carrying pallet is placed in by suspension rope in anti-release main body mechanism, suspension rope upper end is connect by orientation stent with reel, highly sensitive strain transducer is pasted on anti-release main body mechanism inner wall, is connect by low resistance electric signal connecting line with portable deformeter.The present invention realizes the resistance to roadway floor crustal stress and release simultaneously by a kind of device, alleviate crustal stress using the section release of anti-release main body mechanism gap to act on, filling concrete segment forms crucial rock beam with periphery rock stratum, increase rock stratum rigidity, the deformation of lower part rock stratum is hindered to be communicated up, that is, limits the movement of rock stratum, crustal stress effect is alleviated again, and device makes simply, construction technology is easy, can effectively solve the problems, such as Floor Heave in Roadway.

Description

A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology
Technical field
The present invention relates to Floor Heave in Roadway Prevention Technique fields in mining engineering, it is proposed that a kind of pouring coagulation for allowing anti-binding Soil opening steel pipe prevention pucking device and technology.
Background technology
The geological disaster phenomenon that roadway floor swells upwards is Floor Heave in Roadway.For a long time, Floor Heave in Roadway is always coal One of problem in the underground engineerings such as ore deposit exploitation.Floor Heave in Roadway causes former design standard drift section product to reduce, and then influence lane Road pedestrian and transport, interfere mine ventilation.It largely repaired caused by strong pucking, overhaul work, considerably increase tunnel Maintenance cost.Excessively high stress and the soft rock stratum of bottom plate around the reason of Floor Heave in Roadway mainly tunnel, for this 2 points The Floor Heave in Roadway administering method that reason is applied at present mainly has method for strengthening, destressing method and combination method.Reinforcement means mainly includes Two kinds of bottom plate anchor pole and floor grouting, bottom plate anchor pole requirement floor strata have medium ground, to provide anchor force, use item Part is restricted;The flow direction of floor grouting method slurries is difficult to control, and slurry consumption amount is big, of high cost.Destressing method is by tunnel week The concentrated stress on side (particularly bottom plate) shifts to achieve the purpose that floor lift control to roadway surrounding rock deep, and application is more universal. Combination method is that two or three in the above method is applied in combination, and is mainly used in that stress concentration degree is big, pucking is serious Situation, but construction technology is complex.Therefore research and development one kind can improve Surrounding Rock Strength, reduce surrouding rock deformation, and can discharge and enclose Rock mass internal stress delays the device of surrouding rock deformation, among by method for strengthening and destressing method respectively the advantages of is integrated into a kind of device, letter Change construction technology, reduce construction cost, for safeguarding that mine working is stablized, improve mine economic profit and be of great significance.
Invention content
It is an object of the invention to overcome the shortcomings of existing Floor Heave in Roadway control measures, the reinforcing that comprehensive Floor Heave in Roadway is administered The advantages of method and destressing method, provides a kind of placing concrete opening steel pipe for allowing anti-binding and prevents pucking device and technology, realizes The validity of Floor Heave in Roadway disaster is administered, safeguards Drift stability, improves mine economic profit.
To achieve these goals, the technical solution adopted in the present invention is:
It is a kind of that the placing concrete opening steel pipe prevention pucking device of anti-binding and technology, the device is allowed to include anti-release Main body mechanism, carrying pallet, suspension rope, Grouting Pipe, grouting pump, orientation stent, reel, highly sensitive strain transducer are low Resistance value electric signal connecting line, portable deformeter, closure plate;The anti-release main body mechanism comes into full contact with and holds with pressure relief vent It carries pressure relief vent edge stress and corresponding deformation occurs;The carrying pallet is placed in by suspension rope in anti-release main body mechanism;It is described Suspension rope upper end is connect by orientation stent with reel;The slip casting infratubal port be in carrying pallet above, upper port with Grouting pump connects;The high sensitivity strain transducer is pasted on anti-release main body mechanism inner wall, is connected by low resistance electric signal Wiring is connect with portable deformeter.
The anti-release main body mechanism be a steel pipe, length 1m, diameter 20cm, anti-release main body mechanism side edge Its length direction opens bar shaped gap, gap arc length 8cm, and anti-release main body mechanism cross section is a sector;Anti- release main body Mechanism inner wall bar shaped gap offside has a groove, connects up and uses for low resistance electric signal connecting line;Anti- release main body mechanism end Head expands, to be connect with another anti-release main body mechanism nesting screw.
The carrying pallet is a round iron pan, thickness 10mm, the more anti-small 3mm of release main body mechanism internal diameter of diameter, can be It is freely up and down moved in anti-release main body mechanism, suspension eye is beaten every 120 ° at carrying tray edge, three altogether, respectively Suspension eye is equal with the distance in the carrying pallet center of circle, and a balance thin wire is drawn outside each suspension eye, and three balance thin wires intersect It in a bit, and binds together, binding point carries pallet water in the surface in the carrying pallet center of circle when guarantee is suspended vertically It is flat.
The suspension rope is nylon rope, lower end and the balance thin wire binding point connection above carrying pallet, and upper end passes through Orientation stent is connect with reel, and suspension rope does a label every 0.2m.
The Grouting Pipe is the steel pipe of outer diameter 25mm, can pass through screw thread spreading, Grouting Pipe vertical direction according to actual demand On overlapped as possible with pressure relief vent axle center, lower end be located at carrying pallet above, upper end is connect with grouting pump.
The orientation stent is the intermediate A-frame containing fixed pulley, and the A-frame is by three isometric reinforcing bars and reinforcing bar Annulus is welded, and the fixed pulley is welded by a fine steel rib and reinforcing bar annulus, and fine steel rib is passed through by fixed pulley center, carefully Reinforcing bar length is equal with reinforcing bar circle diameter.
The reel is made of stent, kinking disk, joystick, by the kinking disk on joystick swinging mounting, Realize the lifting of carrying pallet.
The high sensitivity strain transducer includes foil gauge, wire connection terminal, foil gauge, wire connection terminal and anti-release master Body mechanism inner wall is connected by pasting, and foil gauge length direction and anti-release main body mechanism are axially vertical, with anti-release main body Mechanism cooperative transformation.
The low resistance electric signal connecting line be outer diameter 1.2mm copper wire, low resistance electric signal connecting line lower end with it is highly sensitive The wire connection terminal welding in strain transducer is spent, is answered by anti-release main body mechanism groove upper berth to release aperture with portable Become the connection of instrument nut.
The portable deformeter is connect with low resistance electric signal connecting line, is read and is stored highly sensitive strain transducer Measured data.
The closure plate is made of the up big and down small thin cylinder of two ironys, roundlet column diameter 19cm, height 5cm, and big cylinder is straight Diameter 22cm, height 3cm.
A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology, includes the following steps:
A, pressure relief vent excavates
According to tunnel geological environment to be onstructed, crustal stress size, by method for numerical simulation be calculated release hole depth, Spacing and array pitch, and pressure relief vent is excavated, release bore dia is 22cm.
B, anti-release main body mechanism is connected
Anti- release main body mechanism number is determined according to release hole depth is excavated, and connected anti-release main body mechanism with screw It picks up and.
C, highly sensitive strain transducer is connected
Low resistance electric signal connecting line one end and wire connection terminal are welded first, foil gauge conducting wire is welded with wire connection terminal, Secondly according to position of stratum to be measured, foil gauge and wire connection terminal are pasted;Foil gauge and wire connection terminal 502 glue and anti-release Main body mechanism inner wall connects;It should ensure that anti-release main body mechanism inner wall smooth before stickup;During stickup foil gauge long side should with it is anti- Release main body mechanism is axially vertical;It should ensure that foil gauge and anti-release main body mechanism contact surface bubble-free after stickup and use ohm Whether table monitoring foil gauge damages;Low resistance electric signal connecting line by anti-release main body mechanism groove be laid with to nozzle with just Take the connection of formula deformeter.
D, local resistance to compression section slip casting
Quality evaluation is carried out to the mechanical strength of pressure relief vent rock stratum according to geological mapping data, specifies hard rock layer thickness, bottom Board position and absolute altitude;Suspension rope and carrying pallet are connected, is transferred by orienting stent to the bottom plate of pressure relief vent lowest part hard formation Place keeps carrying tray position constant, connects Grouting Pipe, starts slip casting, and slurries are quick setting and high strength concrete, slip casting height with it is hard Depth of stratum is equal, after grouting layer solidification and anti-release main body mechanism are integral, cuts short suspension rope;Reconnect suspention Rope and carrying pallet, every a depth of stratum, reserve gap section, start a upper hard formation position slip casting, recycle this work, Stop at nozzle, and ensure there is a non-grouting layer among adjacent two slip casting section.
E, it seals
Slip casting covers anti-release main body mechanism after hours, with closure plate, and top gravel mulch restores original appearance.
Beneficial effects of the present invention:
1st, the present invention combines currently used two kinds of Floor Heave in Roadway administering method advantage, is on the one hand unloaded using gap section Pressure, alleviates crustal stress effect, on the other hand fills quick setting and high strength concrete segment and forms crucial rock beam with periphery rock stratum, increases rock stratum Rigidity, hinder its underpart rock stratum deformation move up, realize effective improvement to pucking.
2nd, the present invention can monitor the deflection of rock mass and deformation inside roadway floor while Floor Heave in Roadway problem is administered Rate, this contributes to the changing rule for probing into crustal stress, formulates more rational pucking resolution.
3rd, present invention design each component of device is easy to make, and simple in structure, construction technology is simple, is combined by anti-release Mode realize improvement to Floor Heave in Roadway.
Description of the drawings:
Fig. 1 is the structure diagram of the present invention;
Fig. 2 is the vertical view that pallet is carried in Fig. 1;
Fig. 3 is the front view of closure plate.
In figure:1-anti-release main body mechanism;2-carrying pallet;3-balance thin wire;4-Grouting Pipe;5-slip casting Pump;6-orientation stent;7-reel;8-high sensitivity strain transducer;9-low resistance electric signal connecting line;10-portable Formula deformeter;11-closure plate;12-suspension rope;13-stratum;14-quick setting and high strength concrete;15-gap section
Specific embodiment:
Below in conjunction with the accompanying drawings, specific implementation of the patent mode is further described.
As shown in Figures 1 to 3, a kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology, the dress It puts including anti-release main body mechanism 1, positions grouting device, deformation monitoring device, closing device;The anti-release main body mechanism 1 comes into full contact with pressure relief vent, on the one hand using gap section release, alleviates crustal stress effect, on the other hand fills quick setting and high strength and mix Solidifying soil section forms crucial rock beam with periphery rock stratum, increases the rigidity of rock stratum, and the deformation of its underpart rock stratum is hindered to move up, described Deformation monitoring device is located inside anti-release main body mechanism, realizes and roadway floor rock deformation is monitored.
Steel pipe of the anti-release main body mechanism 1 for the open and clear mouth in side, length 1m, diameter 20cm, gap arc length 8cm, anti-release main body mechanism inner wall bar shaped gap offside have a groove, connect up and use for low resistance electric signal connecting line 9; Anti- release main body mechanism reamed end, to be connect with another anti-release main body mechanism nesting screw.
The positioning grouting device includes carrying pallet 2, balance thin wire 3, suspension rope 12, Grouting Pipe 4, grouting pump 5, determines To stent 6, reel 7, carrying pallet 2 is in horizontality by balancing the suspention of thin wire 3, and 12 traction balance of suspension rope is thin 3 intersection point of iron wire makes carrying pallet 2 be moved up and down in anti-release main body mechanism 1, and suspension rope 12 has a label number every 0.2m, To carry out determining for 2 position of carrying pallet, reel 7 makes suspension rope 12 be in anti-release main body mechanism by orienting stent 6 1 axial location, and the lifting of suspension rope 12 is controlled, Grouting Pipe 4 abuts suspension rope 12, and lower port is in the upper of carrying pallet 2 Quick setting and high strength concrete is injected into anti-release main body mechanism 1 by side, the pressure generated by grouting pump 5, forms quick setting and high strength Concrete 14.
The deformation monitoring device include highly sensitive strain transducer 8, low resistance electric signal connecting line 9, it is portable should Become instrument 10, highly sensitive strain transducer 8 is made of foil gauge, wire connection terminal, and the two is pasted on anti-release main body mechanism 1 Inner wall, foil gauge length direction and anti-release main body mechanism 1 are axially vertical, with anti-1 cooperative transformation of release main body mechanism, low-resistance 9 one end of value electric signal connecting line is connect with highly sensitive strain transducer 8, by anti-1 groove upper berth of release main body mechanism to unloading Pressure aperture is connect with portable deformeter 10.
The closing device is closure plate 11, is composed of the thin cylinder of two ironys to differ in size, small column can be embedded in In anti-release main body mechanism 1, big cylinder is located at except anti-release main body mechanism 1, plays the anti-release main body mechanism 1 of closing Effect.
The stratum 13 stratigraphic horizon obtained by geological mapping, the gap section 15 are filled for two quick setting and high strength concrete 14 Gap section is reserved between section, plays release.
A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology, utilizes above device, implements Method specifically comprises the following steps:
A, pressure relief vent excavates
According to tunnel geological environment to be onstructed, crustal stress size, by method for numerical simulation be calculated release hole depth, Spacing and array pitch, and pressure relief vent is excavated, release bore dia is 22cm.
B, anti-release main body mechanism is connected
Anti- release main body mechanism number is determined according to release hole depth is excavated, and connected anti-release main body mechanism with screw It picks up and.
C, highly sensitive strain transducer is connected
Low resistance electric signal connecting line one end and wire connection terminal are welded first, foil gauge conducting wire is welded with wire connection terminal, Secondly according to position of stratum to be measured, foil gauge and wire connection terminal are pasted;Foil gauge and wire connection terminal 502 glue and anti-release Main body mechanism inner wall connects;It should ensure that anti-release main body mechanism inner wall smooth before stickup;During stickup foil gauge long side should with it is anti- Release main body mechanism is axially vertical;It should ensure that foil gauge and anti-release main body mechanism contact surface bubble-free after stickup and use ohm Whether table detection foil gauge damages;Low resistance electric signal connecting line by anti-release main body mechanism groove be laid with to nozzle with just Take the connection of formula deformeter.
D, local resistance to compression section slip casting
Quality evaluation is carried out to the mechanical strength of pressure relief vent rock stratum according to geological mapping data, specifies hard rock layer thickness, bottom Board position and absolute altitude;Suspension rope and carrying pallet are connected, is transferred by orienting stent to the bottom plate of pressure relief vent lowest part hard formation Place keeps carrying tray position constant, connects Grouting Pipe, start slip casting, slip casting height is equal with hard rock layer thickness, treats grouting layer After solidification and anti-release main body mechanism are integral, suspension rope is cut short;Suspension rope and carrying pallet are reconnected, every a rock Layer thickness reserves gap section, starts a upper hard formation position slip casting, recycle this work, stop at nozzle, and ensures There is a non-grouting layer among adjacent two slip casting section.
E, it seals
Slip casting covers anti-release main body mechanism after hours, with closure plate, and top gravel mulch restores original appearance.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not limitation with the present invention, all in essence of the invention The all any modification, equivalent and improvement made within refreshing and principle such as change anti-release main body mechanism material, carrying pallet Method for improving etc., should all be included in the protection scope of the present invention.

Claims (9)

  1. Steel pipe prevention pucking device and technology 1. a kind of placing concrete for allowing anti-binding is open, including anti-release main body mechanism, Position grouting device, deformation monitoring device, closure plate, it is characterised in that:The anti-release main body mechanism fully connects with pressure relief vent It touches, cooperative transformation;The positioning grouting device realizes anti-release main body mechanism by the orientation injection of quick setting and high strength concrete Resistance to compression function;The deformation monitoring device is located at anti-release main body mechanism inner wall, is connected by pasting.
  2. 2. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 prevents pucking device and technology, It is characterized in that:The anti-release main body mechanism is a steel pipe, and bar shaped gap, gap opposite pipe are opened in pipe side Prefabricated strip groove at inner wall.
  3. 3. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 and 2 prevents pucking device and skill Art, it is characterised in that:The anti-release main body mechanism is intersegmental every laying, rapid hardening height with gap for quick setting and high strength concrete segment Reinforced concrete section forms crucial rock beam with periphery rock stratum, and lower part rock deformation is hindered to move up, and ground is alleviated in the release of gap section should Power.
  4. 4. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 prevents pucking device and technology, It is characterized in that:The positioning grouting device includes reel, orientation stent, suspension rope, balance thin wire, carrying pallet, note Slurry pipe, grouting pump, the suspension rope have an identification number every 0.2m, are connect, twined with balance thin wire intersection point by orienting stent Line device controls its lifting.
  5. 5. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 and 4 prevents pucking device and skill Art, it is characterised in that:The carrying pallet is uniformly distributed the disks of three apertures for edge, balance thin wire pass through circular hole with Disk binding connection, three balance thin wire top intersection points are located at the surface of circle disk center.
  6. 6. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 prevents pucking device and technology, It is characterized in that:The deformation monitoring device includes highly sensitive strain transducer, low resistance electric signal connecting line, portable Deformeter, the highly sensitive strain transducer include foil gauge, wire connection terminal, the foil gauge, wire connection terminal welding Connection, is pasted on anti-release main body mechanism inner wall.
  7. 7. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 and 6 prevents pucking device and skill Art, it is characterised in that:Described low resistance electric signal connecting line one end is welded with wire connection terminal, passes through anti-release main body mechanism Strip groove upper berth to release aperture is connect with portable deformeter nut.
  8. 8. a kind of placing concrete opening steel pipe for allowing anti-binding according to claim 1 prevents pucking device and technology, It is characterized in that:The closure plate is the up big and down small thin cylinder assembly of irony.
  9. 9. a kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology, one of claim 1 to 9 is utilized A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology, it is characterised in that:Including as follows Step:
    A, pressure relief vent excavates
    According to tunnel geological environment to be onstructed, crustal stress size, release hole depth, spacing are calculated by method for numerical simulation And array pitch, and pressure relief vent is excavated, release bore dia is 22cm.
    B, anti-release main body mechanism is connected
    According to release hole depth is excavated determine anti-release main body mechanism number, and anti-release main body mechanism is connected with screw Come.
    C, highly sensitive strain transducer is connected
    Low resistance electric signal connecting line one end and wire connection terminal are welded first, foil gauge conducting wire is welded with wire connection terminal, secondly According to position of stratum to be measured, foil gauge and wire connection terminal are pasted;Foil gauge and 502 glue of wire connection terminal and anti-release main body Mechanism inner wall connection;It should ensure that anti-release main body mechanism inner wall smooth before stickup;Foil gauge long side should be with anti-release during stickup Main body mechanism is axially vertical;It should ensure that foil gauge and anti-release main body mechanism contact surface bubble-free after stickup and examined with ohmmeter Survey whether foil gauge damages;Low resistance electric signal connecting line by anti-release main body mechanism groove be laid with to nozzle with it is portable Deformeter connects.
    D, local resistance to compression section slip casting
    Quality evaluation is carried out to the mechanical strength of pressure relief vent rock stratum according to geological mapping data, specifies hard rock layer thickness, bottom plate position It puts and absolute altitude;Suspension rope and carrying pallet are connected, transfers to the bottom plate of pressure relief vent lowest part hard formation, protects by orienting stent It is constant to hold carrying tray position, connects Grouting Pipe, starts slip casting, slip casting height is equal with hard rock layer thickness, treats that grouting layer solidifies With anti-release main body mechanism it is integral after, cut short suspension rope;Suspension rope and carrying pallet are reconnected, every a rock stratum thickness Degree, starts a upper hard formation position slip casting, recycles this work, stops at nozzle, and ensures in adjacent two slip casting section Between have a non-grouting layer.
    E, it seals
    Slip casting covers anti-release main body mechanism after hours, with closure plate, and top gravel mulch restores original appearance.
CN201810263191.9A 2018-03-28 2018-03-28 Device and method for preventing and controlling bottom drum of anti-bonding cast concrete open steel pipe Active CN108222962B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810263191.9A CN108222962B (en) 2018-03-28 2018-03-28 Device and method for preventing and controlling bottom drum of anti-bonding cast concrete open steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810263191.9A CN108222962B (en) 2018-03-28 2018-03-28 Device and method for preventing and controlling bottom drum of anti-bonding cast concrete open steel pipe

Publications (2)

Publication Number Publication Date
CN108222962A true CN108222962A (en) 2018-06-29
CN108222962B CN108222962B (en) 2023-11-28

Family

ID=62659082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810263191.9A Active CN108222962B (en) 2018-03-28 2018-03-28 Device and method for preventing and controlling bottom drum of anti-bonding cast concrete open steel pipe

Country Status (1)

Country Link
CN (1) CN108222962B (en)

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088985A (en) * 1996-09-11 1998-04-07 Saga Kogyo Kk Grout pipe mounting device and grout injecting method using the same
JPH10280860A (en) * 1997-04-01 1998-10-20 Shimizu Corp Method for connecting existing tunnel to new tunnel
CA2566986A1 (en) * 2006-11-02 2008-05-02 Jonathan Jonny Melic Grip anchor for concrete
CN101560764A (en) * 2009-05-22 2009-10-21 天津大学 Method for calking exploratory hole by intermittent high-pressure rotary jet grouting
US20100011678A1 (en) * 2008-07-15 2010-01-21 Mimi Management Services Lp Double anchor and lifting shackle for concrete slabs
CN101737063A (en) * 2009-11-16 2010-06-16 西安理工大学 Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN101975074A (en) * 2010-10-16 2011-02-16 山东科技大学 Soft rock roadway anchored concrete filled steel tube anti-floor heave device and construction method thereof
CN102418536A (en) * 2012-01-10 2012-04-18 中国矿业大学 Large-aperture pretension base plate hollow grouting device
CN102661856A (en) * 2012-02-28 2012-09-12 中国矿业大学 Simulation experiment platform and experiment method for motion of cord suspension parallel mechanism
CN103206224A (en) * 2013-04-26 2013-07-17 山东科技大学 Strong resistance and strong evasion floor heave governing construction method of high-stress large-deformation soft rock drift
CN204002836U (en) * 2014-06-07 2014-12-10 中国矿业大学 The high-strength yield supporting structure of heavily stressed broken soft rock chamber
CN104763432A (en) * 2015-01-27 2015-07-08 安徽理工大学 Method for controlling large deformation by releasing pressure of high-stress roadway surrounding rocks
CN106351572A (en) * 2016-09-26 2017-01-25 中国冶集团有限公司 Roof positioning device, drilling device comprising same as well as grouting device and method
CN206129285U (en) * 2016-10-27 2017-04-26 山东科技大学 Deep soft rock roadway under high stress crossover point supporting construction
CN107035382A (en) * 2017-06-22 2017-08-11 中铁十局集团第五工程有限公司 Tunnel portal support system under weak surrounding rock
CN208057124U (en) * 2018-03-28 2018-11-06 中国矿业大学(北京) A kind of placing concrete for allowing anti-binding is open steel pipe prevention pucking device

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088985A (en) * 1996-09-11 1998-04-07 Saga Kogyo Kk Grout pipe mounting device and grout injecting method using the same
JPH10280860A (en) * 1997-04-01 1998-10-20 Shimizu Corp Method for connecting existing tunnel to new tunnel
CA2566986A1 (en) * 2006-11-02 2008-05-02 Jonathan Jonny Melic Grip anchor for concrete
US20100011678A1 (en) * 2008-07-15 2010-01-21 Mimi Management Services Lp Double anchor and lifting shackle for concrete slabs
CN101560764A (en) * 2009-05-22 2009-10-21 天津大学 Method for calking exploratory hole by intermittent high-pressure rotary jet grouting
CN101737063A (en) * 2009-11-16 2010-06-16 西安理工大学 Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN101975074A (en) * 2010-10-16 2011-02-16 山东科技大学 Soft rock roadway anchored concrete filled steel tube anti-floor heave device and construction method thereof
CN102418536A (en) * 2012-01-10 2012-04-18 中国矿业大学 Large-aperture pretension base plate hollow grouting device
CN102661856A (en) * 2012-02-28 2012-09-12 中国矿业大学 Simulation experiment platform and experiment method for motion of cord suspension parallel mechanism
CN103206224A (en) * 2013-04-26 2013-07-17 山东科技大学 Strong resistance and strong evasion floor heave governing construction method of high-stress large-deformation soft rock drift
CN204002836U (en) * 2014-06-07 2014-12-10 中国矿业大学 The high-strength yield supporting structure of heavily stressed broken soft rock chamber
CN104763432A (en) * 2015-01-27 2015-07-08 安徽理工大学 Method for controlling large deformation by releasing pressure of high-stress roadway surrounding rocks
CN106351572A (en) * 2016-09-26 2017-01-25 中国冶集团有限公司 Roof positioning device, drilling device comprising same as well as grouting device and method
CN206129285U (en) * 2016-10-27 2017-04-26 山东科技大学 Deep soft rock roadway under high stress crossover point supporting construction
CN107035382A (en) * 2017-06-22 2017-08-11 中铁十局集团第五工程有限公司 Tunnel portal support system under weak surrounding rock
CN208057124U (en) * 2018-03-28 2018-11-06 中国矿业大学(北京) A kind of placing concrete for allowing anti-binding is open steel pipe prevention pucking device

Also Published As

Publication number Publication date
CN108222962B (en) 2023-11-28

Similar Documents

Publication Publication Date Title
CN101487249B (en) Embedding apparatus and method for earth pressure box
CN104329076B (en) A kind of deviational survey hole osmotic pressure counter device and installation method
CN105804761B (en) Construction method suitable for liquefied sand stratum shield near-distance passing through building
CN107975375B (en) A kind of miniature steel pipe pile reinforced soft foundation construction method of city tunnel
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN201665871U (en) Long screw drilling bored pile post-grouting technology device
CN105040775B (en) Deep layer pressure-bearing artesian well plugging system and method
CN104500082A (en) Mining-method tunnel inner shield receiving construction method
CN107724383B (en) Rotary digging cast-in-place pile construction method
CN111734482A (en) Method for reducing damage by utilizing gangue cementation and bag grouting combined support
CN108005129A (en) A kind of safeguard structure system and method for controlling tunnel vertical deformation
CN108755699A (en) The deformation control method and device of a kind of foundation pit periphery soil body
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN107023027A (en) A kind of building concentration zones large-scale well-sinking construction method
Littlejohn Overview of rock anchorages
CN208057124U (en) A kind of placing concrete for allowing anti-binding is open steel pipe prevention pucking device
CN112228081A (en) Method for reinforcing pile foundation of shield tunnel side-through high-speed rail viaduct
CN110514184A (en) One kind being used for deeper formation deformation measurement easy device and its method for measurement
CN108661090B (en) Stress testing method for closed prestressed concrete pipe pile
CN108532650B (en) Method for in-situ determination of water buoyancy borne by underground structure
CN108222962A (en) A kind of placing concrete opening steel pipe for allowing anti-binding prevents pucking device and technology
CN102979087A (en) Construction method for rotary excavation pile
CN110055957A (en) A kind of strong development ultra-fine hole pile construction method in karst region
CN110672062A (en) Embedding method of monitoring points for monitoring settlement of bedrock
Pellegrini et al. Sao Paulo Metro Project–Control of Settlements in variable soil conditions through EPB pressure and bicomponent backfill grout

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant