CN108222947B - A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion - Google Patents

A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion Download PDF

Info

Publication number
CN108222947B
CN108222947B CN201711433447.8A CN201711433447A CN108222947B CN 108222947 B CN108222947 B CN 108222947B CN 201711433447 A CN201711433447 A CN 201711433447A CN 108222947 B CN108222947 B CN 108222947B
Authority
CN
China
Prior art keywords
tunnel
top bar
super
span
pilot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711433447.8A
Other languages
Chinese (zh)
Other versions
CN108222947A (en
Inventor
陈建勋
陈丽俊
罗彦斌
刘瑞辉
张少强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201711433447.8A priority Critical patent/CN108222947B/en
Publication of CN108222947A publication Critical patent/CN108222947A/en
Application granted granted Critical
Publication of CN108222947B publication Critical patent/CN108222947B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices

Abstract

The invention belongs to Tunnel Engineering technical fields, and in particular to a kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion.The construction method improves for leading pilot drift country rock in the construction of top bar CD method, needs the case where carrying out engineering method conversion (country rock is changed from IV to III grade or II grade), under the premise of guaranteeing that leading pilot tunnel and rear row pilot drift are not stopped work, realize super-span constructing tunnel by the conversion of two benching tunnelling method of top bar CD normal direction, thus influence of the engineering method conversion in super-span tunnel to the construction period can be greatly reduced, there is significant economic and social benefit.

Description

A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion
Technical field
The invention belongs to Tunnel Engineering technical fields, and in particular to a kind of two step of super-span tunnel top bar CD normal direction The construction method of method conversion.
Background technique
Different from single two lane of hole, three lanes tunnel, single-hole with four lanes tunnel mostly uses substep or piecemeal to excavate.Country rock grade Not Bian Hua when, influence of the engineering method conversion to the duration is very big.By taking the conversion of two benching tunnelling method of top bar CD normal direction as an example, when leading pilot tunnel When face country rock improves (country rock is changed from IV to III grade or II grade), needs to carry out engineering method conversion, often existing pilot tunnel is slapped Sub- face suspension of works can carry out engineering method conversion when same to the leading pilot tunnel section of row pilot drive after, cause since then Leading pilot tunnel shut-down will seriously affect construction speed.It is, therefore, desirable to provide the reasonable conversion mode between different engineering methods, to subtract Small engineering method converts the influence to the super-span constructing tunnel duration.
Summary of the invention
In view of the above technical problems, the present invention provides a kind of conversion of two benching tunnelling method of super-span tunnel top bar CD normal direction Construction method, row pilot drive to the same section of leading pilot tunnel can carry out engineering method turn after stopping work, waiting to avoid leading pilot tunnel Change and caused by serious construction delay.
The present invention is achieved by the following technical solutions:
A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion, the construction method is leading Under the premise of pilot tunnel and rear row pilot drift are not stopped work, temporarily propped up by gradually increasing the leading pilot tunnel of top bar to median septum The excavation area of side is protected, corresponding rear row pilot drive area constantly reduces, until the excavation area of the leading pilot tunnel of top bar It is extended to the entire upper half section in tunnel, rear row pilot drive area is then reduced to zero, realizes super-span constructing tunnel by appearing on the stage The conversion of two benching tunnelling method of rank CD normal direction.
Further, the Specific construction process of the construction method is as follows:
(1) leading pilot tunnel is excavated: on the basis of top bar CD method leading pilot drive, to the side close to rear row pilot tunnel It is digged, leading pilot tunnel preliminary bracing of constructing applies median septum gib;
(2) row pilot tunnel after excavating: with digging for leading pilot tunnel, the excavation area of rear row pilot tunnel constantly reduces;After construction Median septum gib is removed in row pilot tunnel preliminary bracing;
(3) left side of getting out of a predicament or an embarrassing situation is excavated, and applies left side preliminary bracing of getting out of a predicament or an embarrassing situation in time;
(4) right side of getting out of a predicament or an embarrassing situation is excavated, and applies right side preliminary bracing of getting out of a predicament or an embarrassing situation in time;
(5) Core Soil of getting out of a predicament or an embarrassing situation is excavated;
(6) inverted arch, and inverted arch preliminary bracing of constructing are excavated;
(7) step (1)~(6) are repeated, the circulation for carrying out tunnel is excavated and preliminary bracing, during tunnel excavation, first The excavation area of row pilot tunnel constantly expands, and corresponding rear row pilot drive area constantly reduces, final leading pilot drive section It is extended to the entire upper half section in tunnel, rear row pilot drive area is then reduced to zero, completes super-span tunnel top bar CD method The engineering method constructed to two benching tunnelling methods of constructing converts.
Further, the leading pilot tunnel in tunnel often pushes ahead 5~10m, and leading pilot tunnel expands to the side close to rear row pilot tunnel 1~2m is dug, until leading pilot tunnel is digged to the entire section in tunnel.
Further, the super-span tunnel be single-hole with four lanes vcehicular tunnel or excavate span be not less than 18m its His tunnel.
Advantageous effects of the invention:
The construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion provided by the invention, is guaranteeing in advance Under the premise of pilot tunnel and rear row pilot drift are not stopped work, super-span constructing tunnel is realized by top bar CD normal direction two The conversion of rank method, row pilot drive is same to leading pilot tunnel after needing leading pilot tunnel to stop work when avoiding the conversion of current engineering method, wait One section can carry out engineering method conversion and caused by serious construction delay, substantially reduce the conversion of super-span tunnel engineering method to applying The influence of work duration, thus there is significant economic and social benefit.
Detailed description of the invention
Fig. 1 is that the construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion in the embodiment of the present invention is faced Figure;
Fig. 2 is that the construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion in the embodiment of the present invention is overlooked Figure;
Appended drawing reference: 1. excavate leading pilot tunnel;2. leading pilot tunnel preliminary bracing;3. median septum gib;4. row is led after Hole;Row pilot tunnel preliminary bracing after 5.;6. left side of getting out of a predicament or an embarrassing situation;7. left side of getting out of a predicament or an embarrassing situation applies preliminary bracing;8. right side of getting out of a predicament or an embarrassing situation;Under 9. Preliminary bracing on the right side of step;10. Core Soil of getting out of a predicament or an embarrassing situation;11. inverted arch;12. inverted arch preliminary bracing;13. top bar CD method is constructed; 14. liang benching tunnelling method construction.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is explained in further detail.It should be appreciated that specific embodiment described herein is used only for explaining the present invention, and It is not used in the restriction present invention.
On the contrary, the present invention covers any substitution done on the essence and scope of the present invention being defined by the claims, repairs Change, equivalent method and scheme.Further, in order to make the public have a better understanding the present invention, below to of the invention thin It is detailed to describe some specific detail sections in section description.Part without these details for a person skilled in the art The present invention can also be understood completely in description.
Embodiment 1
The present embodiment provides a kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion, the sides Method leading pilot drift country rock suitable for the construction of top bar CD method improves, needs the case where carrying out engineering method conversion, specially Changed suitable for country rock from IV to III grade or II grade, under the premise of leading pilot tunnel and rear row pilot drift are not stopped work, is led to It crosses and gradually increases excavation area of the leading pilot tunnel of top bar to median septum gib side, until the entire upper half section in tunnel, Realize super-span constructing tunnel by the conversion of two benching tunnelling method of top bar CD normal direction.Wherein, above-mentioned country rock grade is according to " highway tunnel Road design specification " the surrounding rock mass classification standard of (JTG_D70-2004) divided, specifically it is divided into I grade of country rock, II Grade country rock, III grade of country rock, IV grade of country rock and V grade of country rock.
The Specific construction process of the construction method is illustrated with reference to the accompanying drawing.
As depicted in figs. 1 and 2, the specific of the construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion is applied Work process is as follows:
(1) leading pilot tunnel 1 is excavated: on the basis of top bar CD method leading pilot drive, to close to the one of rear row pilot tunnel Side is digged, and leading pilot tunnel preliminary bracing 2 of constructing applies median septum gib 3;
(2) row pilot tunnel 4 after excavating: with digging for leading pilot tunnel, the excavation area of rear row pilot tunnel constantly reduces;After construction Median septum gib 3 is removed in row pilot tunnel preliminary bracing 5;
(3) left side 6 of getting out of a predicament or an embarrassing situation is excavated, and left side of getting out of a predicament or an embarrassing situation in time applies preliminary bracing 7;
(4) right side 8 of getting out of a predicament or an embarrassing situation is excavated, and applies right side preliminary bracing 9 of getting out of a predicament or an embarrassing situation in time;
(5) Core Soil 10 of getting out of a predicament or an embarrassing situation is excavated;
(6) inverted arch 11, and inverted arch preliminary bracing 12 of constructing are excavated;
(7) step (1)~(6) are repeated, the circulation for carrying out tunnel is excavated and preliminary bracing, during tunnel excavation, first The excavation area of row pilot tunnel constantly expands, and corresponding rear row pilot drive area constantly reduces, final leading pilot drive section It is extended to the entire upper half section in tunnel, rear row pilot drive area is then reduced to zero, completes super-span tunnel top bar CD method The engineering method constructed to two benching tunnelling methods of constructing converts.
Direction is excavated in arrow instruction in Fig. 2.
When two benching tunnelling method of super-span tunnel top bar CD normal direction is converted, the leading pilot tunnel in tunnel often pushes ahead 5~ 10m, leading pilot tunnel dig 1~2m to the side close to rear row pilot tunnel, until leading pilot tunnel is digged to the entire section in tunnel.
The super-span tunnel is other tunnels that single-hole with four lanes vcehicular tunnel or excavation span are not less than 18m.

Claims (4)

1. a kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion, which is characterized in that the construction Method is not under the premise of leading pilot tunnel and rear row pilot drift are stopped work, by gradually increasing the leading pilot tunnel of top bar in The excavation area of next door gib side, corresponding rear row pilot drive area constantly reduces, until the leading pilot tunnel of top bar Excavation area be extended to the entire upper half section in tunnel, rear row pilot drive area is then reduced to zero, realizes super-span tunnel The conversion constructed by two benching tunnelling method of top bar CD normal direction.
2. a kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion according to claim 1, It is characterized in that, the Specific construction process of the construction method is as follows:
(1) it excavates leading pilot tunnel: on the basis of top bar CD method leading pilot drive, being carried out to the side close to rear row pilot tunnel It digs, leading pilot tunnel preliminary bracing of constructing applies median septum gib;
(2) row pilot tunnel after excavating: with digging for leading pilot tunnel, the excavation area of rear row pilot tunnel constantly reduces;Row is led after construction Median septum gib is removed in hole preliminary bracing;
(3) left side of getting out of a predicament or an embarrassing situation is excavated, and applies left side preliminary bracing of getting out of a predicament or an embarrassing situation in time;
(4) right side of getting out of a predicament or an embarrassing situation is excavated, and applies right side preliminary bracing of getting out of a predicament or an embarrassing situation in time;
(5) Core Soil of getting out of a predicament or an embarrassing situation is excavated;
(6) inverted arch, and inverted arch preliminary bracing of constructing are excavated;
(7) step (1) ~ (6) are repeated, the circulation for carrying out tunnel is excavated and preliminary bracing, during tunnel excavation, leading pilot tunnel Excavation area constantly expand, it is corresponding after row pilot drive area constantly reduce, final leading pilot drive section is extended to The entire upper half section in tunnel, rear row pilot drive area are then reduced to zero, complete super-span tunnel top bar CD method construct to The engineering method conversion of two benching tunnelling methods construction.
3. a kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion according to claim 1, It is characterized in that, the leading pilot tunnel in tunnel often pushes ahead 5 ~ 10m, and leading pilot tunnel digs 1 ~ 2m to the side close to rear row pilot tunnel, directly It digs to leading pilot tunnel to the entire section in tunnel.
4. a kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion according to claim 1, It is characterized in that, the super-span tunnel is other tunnels that single-hole with four lanes vcehicular tunnel or excavation span are not less than 18m.
CN201711433447.8A 2017-12-26 2017-12-26 A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion Active CN108222947B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711433447.8A CN108222947B (en) 2017-12-26 2017-12-26 A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711433447.8A CN108222947B (en) 2017-12-26 2017-12-26 A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion

Publications (2)

Publication Number Publication Date
CN108222947A CN108222947A (en) 2018-06-29
CN108222947B true CN108222947B (en) 2019-05-21

Family

ID=62647890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711433447.8A Active CN108222947B (en) 2017-12-26 2017-12-26 A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion

Country Status (1)

Country Link
CN (1) CN108222947B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108979667B (en) * 2018-07-15 2019-09-10 中铁二十局集团有限公司 Penetrating ground crushed zone tunnel top bar interval wall construction method
CN109594991A (en) * 2018-12-29 2019-04-09 中铁隧道集团二处有限公司 Shallow Buried Soft Rock Super-large-section tunnel CD method combines rapid constructing method with benching tunnelling method
CN109707399B (en) * 2019-02-21 2024-01-30 中铁二院工程集团有限责任公司 Tunnel exit supporting structure and construction method thereof
CN112228076B (en) * 2020-08-27 2022-10-18 中铁十局集团有限公司 Fast excavation construction method for hard rock large-span tunnel
CN113216976A (en) * 2021-04-09 2021-08-06 中交第一公路勘察设计研究院有限公司 Tunnel HCD excavation method suitable for soft rock and gravel soil
CN115142878B (en) * 2022-07-04 2023-05-16 中铁十二局集团有限公司 CRD method subsection linkage rapid construction method for upper soft and lower hard strata

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1563671A (en) * 2004-03-19 2005-01-12 刘昌用 Dormant digging and separating construction method for underground two layers and multilayer composite lining structure
CN1873187A (en) * 2006-06-23 2006-12-06 董淑练 Method of digging for tunnel construction
CN102182466A (en) * 2011-04-08 2011-09-14 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN104879131A (en) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 Large-span tunnel excavation method for upper soft and lower hard compound strata
CN107060771A (en) * 2016-12-28 2017-08-18 广东省长大公路工程有限公司 Middle short tunnel is unidirectionally appeared excavation method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1563671A (en) * 2004-03-19 2005-01-12 刘昌用 Dormant digging and separating construction method for underground two layers and multilayer composite lining structure
CN1873187A (en) * 2006-06-23 2006-12-06 董淑练 Method of digging for tunnel construction
CN102182466A (en) * 2011-04-08 2011-09-14 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN104879131A (en) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 Large-span tunnel excavation method for upper soft and lower hard compound strata
CN107060771A (en) * 2016-12-28 2017-08-18 广东省长大公路工程有限公司 Middle short tunnel is unidirectionally appeared excavation method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
上台阶CD法在客专某浅埋隧道中的开发应用;褚晓辉;《科学之友》;20101031(第10期);第55-56页
王村隧道采用上台阶CD法施工监测结果与分析;邓永峰、王龙、韩冰凌;《公路交通科技》;20170731(第7期);第70-71页

Also Published As

Publication number Publication date
CN108222947A (en) 2018-06-29

Similar Documents

Publication Publication Date Title
CN108222947B (en) A kind of construction method of two benching tunnelling method of super-span tunnel top bar CD normal direction conversion
CN100487224C (en) Rapid-construction method for rapid change of small-section into large-section tunnel
CN105240013B (en) Broadwall N00 engineering methods
CN104314578B (en) Construction method for continuous construction by using shield construction machine and matched station thereof
CN110219654A (en) The leading construction method of mud stone multiple-arch tunnel side pilot tunnel
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN108166979A (en) A kind of construction method of super-span tunnel top bar two side-wall pilot tunnel
CN103590406A (en) Construction method for synchronously excavating ultra-large type deep foundation pits in partitioned mode
CN104165056A (en) Construction method for excavating water-rich shallow underground excavation tunnel
CN108150176A (en) A kind of excavation method of different surrounding rock rank super-span vcehicular tunnel
WO2019015362A1 (en) Shallow seam water conservation mining method and application thereof
CN205532615U (en) Super large section tunnel excavates structure
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN102767375B (en) Tunnel construction method
CN110242305A (en) A kind of inclined shaft applies the construction technique in main hole into single side heading method
CN206111199U (en) Weak surrounding rock super large section tunnel excavation and support structure
CN104564085A (en) Comprehensive construction method for excavating tunnel with super large cross-section under urban super shallow-buried condition
CN103291312B (en) The shield machine of three-dimensional slip casting can be realized
CN108131143A (en) A kind of construction method of super-span tunnel top bar CD methods
CN105275487A (en) Long-arm mining N00 construction method ventilation system
CN105401973A (en) Method for performing extraction treatment on corner gas on work faces of adjacent roadways
CN106640155A (en) Large-span underground space structure and construction method thereof
CN106812156A (en) A kind of assembled hypogee and its construction method
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN203835401U (en) Construction structure for arranging construction vertical shaft above underground engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant