CN108222072A - Reinforced construction method is risen after asphalt concrete pavement inspection shaft - Google Patents

Reinforced construction method is risen after asphalt concrete pavement inspection shaft Download PDF

Info

Publication number
CN108222072A
CN108222072A CN201810140484.8A CN201810140484A CN108222072A CN 108222072 A CN108222072 A CN 108222072A CN 201810140484 A CN201810140484 A CN 201810140484A CN 108222072 A CN108222072 A CN 108222072A
Authority
CN
China
Prior art keywords
inspection shaft
risen
concrete
pedestal
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810140484.8A
Other languages
Chinese (zh)
Inventor
黄轶
方慧琴
张婷婷
赵海莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd filed Critical WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201810140484.8A priority Critical patent/CN108222072A/en
Publication of CN108222072A publication Critical patent/CN108222072A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/128Repairs of manhole shafts
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Road Repair (AREA)

Abstract

The object of the present invention is to provide rise reinforced construction method after a kind of asphalt concrete pavement inspection shaft, the point centered on well lid center, inscribed circle radius using well lid diameter length as regular hexagon makees regular hexagon setting-out, cut the sideline of regular hexagon, by the pitch in the range of regular hexagon and concrete chisel removal to certain depth, pedestal framework of steel reinforcement is risen after installation check well in pit slot, it is risen after inspection shaft on pedestal framework of steel reinforcement and is fixed with several adjusting bolts, leveling steel plate is installed in adjusting bolt, pedestal template is risen after installation check well on the inside of inspection shaft, well seat is placed on leveling steel plate, by adjusting bolt and leveling leveling steel plate well seat and reach absolute altitude, pedestal is risen after pouring inspection shaft, before concrete initial set, one layer of black cement is dispensed in concrete surface.This method solve risen after inspection shaft can form certain height difference between well lid and former road surface at reinforcing the problem of, it is consistent with dark-coloured pavement color coordination to rise seat surface after inspection shaft.

Description

Reinforced construction method is risen after asphalt concrete pavement inspection shaft
Technical field
The invention belongs to road construction fields, and in particular to rise reinforced construction method after a kind of asphalt concrete pavement inspection shaft.
Technical background
In Reconstruction of City Road construction, the Normal practice of lifting transformation inspection shaft is the concrete base first poured below well seat Seat, then the asphalt concrete topping after installation well seat and well lid.But found in practice of construction, first lifting transformation checks Progress asphalt concrete pavement, which paves, after well has the following problems:1) certain height difference can be formed between well lid and former road surface, no Certain obstacle can be only caused to machine spreading operation, and after whole picture road surface brush is black, well lid periphery is combined with asphalt surface course Easily there is faulting of slab ends in place, and inspection shaft will appear the phenomenon that rough and uneven in surface in road surface, be commonly called as " navel ", has both influenced the comfortable of driving Property, and influence the impression quality of dark-coloured pavement;2) using black top road surface after first gug lid, can because well lid periphery asphalt surface course compared with It is thin, the phenomenon that causing well lid periphery Damages of Asphalt Road Surface cracking, pavement quality and inspection shaft service life are influenced, after also increasing Phase road maintenance cost;3) asphalt face layer after first lifting transformation inspection shaft, can also be in asphalt paving roller compaction process to well Lid and pedestal concrete damage, and form hidden danger of quality.
Invention content
The object of the present invention is to provide reinforced construction method is risen after a kind of asphalt concrete pavement inspection shaft, this method solve right The problem of original road surface structare layer is disturbed, certain height can be formed at reinforcing between well lid and former road surface by solving to rise after inspection shaft The problem of poor, it is consistent with dark-coloured pavement color coordination to rise seat surface after inspection shaft.
The technical solution adopted in the present invention is:
Reinforced construction method is risen after a kind of asphalt concrete pavement inspection shaft, including step:
Before S1, asphalt concrete pavement carry out asphalt paving, inspection shaft is counted and is marked;
After S2, asphalt concrete pavement asphalt paving, the point centered on well lid center, using well lid diameter length as regular hexagon Inscribed circle radius makees regular hexagon setting-out;
S3, the sideline for first cutting regular hexagon, then by the pitch in the range of regular hexagon and concrete chisel removal to certain Depth;
S4, will cut after hole bottom and crater wall clean out, in pit slot after installation check well rise pedestal framework of steel reinforcement, inspection It looks into after well to rise and is fixed with several adjusting bolts on pedestal framework of steel reinforcement, leveling steel plate is installed in adjusting bolt;
S5, pedestal template is risen after installation check well on the inside of inspection shaft, well seat is placed on leveling steel plate, passes through adjusting Bolt and leveling leveling steel plate well seat simultaneously reach absolute altitude;
S6, pedestal is risen after pouring inspection shaft, before concrete initial set, one layer of black cement, coagulation is dispensed in concrete surface Pedestal is risen after soil solidification, after inspection shaft and is fixed as an entirety with well seat, pedestal template is risen after removing inspection shaft and well lid is installed.
Further, in S3, depth is cut as 30cm below grade elevation.
Further, in S3, when cutting, vertical road surface carries out downwards, when encountering original concrete plate, first by coagulation Native plate is cut again after being cut along sideline.
Further, in S6, the concrete poured is the steel fiber reinforced concrete mixed with micro-expanding agent.
Further, in S6, black cement is iron oxide black cement.
Further, in S6, during concrete setting, in inspection shaft periphery installation activity enclosing.
Further, in S6, during concrete setting, with covered rearing with plastic film curing concrete to design strength.
Further, the frame that pedestal framework of steel reinforcement is circular ring shape, the inner ring including being located at upper and lower both sides are risen after inspection shaft Reinforcing bar, outer shroud reinforcing bar and intermediate ring reinforcing bar and connection reinforcing bar.
The beneficial effects of the invention are as follows:
By well lid periphery certain distance range internal cutting, pitch and concrete are then cut, is finally poured, using first cutting The mode poured again solves the problems, such as disturbed to original road surface structare layer, it is possible to reduce later period maintenance cost of upkeep.
Using adjusting bolt and leveling leveling steel plate well seat and absolute altitude is reached, well at reinforcing is risen after solving inspection shaft The problem of forming certain height difference between lid and former road surface, can effectively improve bituminous paving driving comfort level, and reduce well Lid is by the vehicle-mounted rear impact noise generated.
Before concrete initial set, one layer of black cement is dispensed in concrete surface, seat surface and black road are risen after making inspection shaft Face color is harmonious.
It cuts range to determine with well lid positions and dimensions, the inspection shaft of arbitrary dimension is all suitable for, setting-out shape is positive six Side shape, conveniently cuts operation and reduction as far as possible cuts space.
Description of the drawings
Fig. 1 is the schematic diagram for rising reinforcing in the present invention after asphalt concrete pavement inspection shaft.
Fig. 2 is to rise to reinforce full-size drawing after asphalt concrete pavement inspection shaft in the present invention.
Fig. 3 is the schematic diagram for rising pedestal framework of steel reinforcement part in the present invention after inspection shaft.
Fig. 4 is the vertical view for rising pedestal framework of steel reinforcement, adjusting bolt and leveling steel plate in the present invention after inspection shaft.
In figure:1- adjusting bolts;2- leveling steel plates;Pedestal framework of steel reinforcement is risen after 3- inspection shafts;4- inspection shafts;5- well lids; 6- well seats;Pedestal is risen after 7- inspection shafts.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Reinforced construction method is risen after a kind of asphalt concrete pavement inspection shaft, including step:
Before S1, asphalt concrete pavement carry out asphalt paving, inspection shaft is counted and is marked.
S2, as shown in Fig. 2, after asphalt concrete pavement asphalt paving, the point centered on 5 center of well lid, with 5 diameter length of well lid Inscribed circle radius for regular hexagon makees regular hexagon setting-out.
S3, the sideline (passing through cutting machine) for first cutting regular hexagon, then by the pitch and coagulation in the range of regular hexagon Soil is cut to certain depth (by pneumatic pick or electric pick).
In the present embodiment, depth is cut as 30cm below grade elevation.
In the present embodiment, when cutting, vertical road surface carries out downwards, when encountering original concrete plate, first by concrete Plate is cut again after being cut along sideline, to avoid the disturbance to original pavement structure.
S4, will cut after hole bottom and crater wall clean out, as shown in Figure 1, rising pedestal after installation check well in pit slot Framework of steel reinforcement 3 rises several adjusting bolts 1 are fixed on pedestal framework of steel reinforcement 3 as shown in Figures 3 and 4, after inspection shaft, adjusts spiral shell Leveling steel plate 2 is installed on bolt 1.
As shown in Figures 3 and 4, in the present embodiment, the frame that pedestal framework of steel reinforcement 3 is circular ring shape is risen after inspection shaft, including Positioned at the inner ring reinforcing bar of upper and lower both sides, outer shroud reinforcing bar and intermediate ring reinforcing bar and connection reinforcing bar.
S5, pedestal template is risen after installation check well on the inside of inspection shaft, well seat 6 is placed on leveling steel plate 2, passes through tune Section bolt 1 and 2 leveling well seat 6 of leveling steel plate simultaneously reach absolute altitude.
S6, pedestal 7 is risen after pouring inspection shaft, before concrete initial set, one layer of black cement, coagulation is dispensed in concrete surface Pedestal 7 is risen after soil solidification, after inspection shaft and is fixed as an entirety with well seat 6, pedestal template is risen after removing inspection shaft and well is installed Lid 5.
In the present embodiment, the concrete poured is the steel fiber reinforced concrete mixed with micro-expanding agent, mixed with micro-expanding agent Steel fiber reinforced concrete solves the problems, such as that flexural strength is poor.
In the present embodiment, black cement is iron oxide black cement.
In the present embodiment, during concrete setting, in the peripheral installation activity enclosing of inspection shaft 4.
In the present embodiment, during concrete setting, with covered rearing with plastic film curing concrete to design strength.
In the present invention, by 5 periphery certain distance range internal cutting of well lid, pitch and concrete is then cut, is finally poured It builds, by the way of first cutting and pouring again, solves the problems, such as disturbed to original road surface structare layer, it is possible to reduce later period maintenance Cost of upkeep.Using adjusting bolt 1 and 2 leveling well seat 6 of leveling steel plate and absolute altitude is reached, reinforcing is risen after solving inspection shaft The problem of forming certain height difference between place's well lid 5 and former road surface, can effectively improve bituminous paving driving comfort level, and subtract Few well lid is by the vehicle-mounted rear impact noise generated.Before concrete initial set, one layer of black cement is dispensed in concrete surface, makes inspection It is consistent with dark-coloured pavement color coordination that seat surface is risen after well.It cuts range to determine with 5 positions and dimensions of well lid, to arbitrary dimension Inspection shaft 4 is all suitable for, and setting-out shape is regular hexagon, conveniently cuts operation and reduction as far as possible cuts space.
It should be understood that for those of ordinary skills, can be improved or converted according to the above description, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (8)

1. rise reinforced construction method after a kind of asphalt concrete pavement inspection shaft, it is characterised in that:Including step,
Before S1, asphalt concrete pavement carry out asphalt paving, inspection shaft is counted and is marked;
After S2, asphalt concrete pavement asphalt paving, the point centered on well lid center, using well lid diameter length as the inscribe of regular hexagon Radius of circle makees regular hexagon setting-out;
S3, the sideline for first cutting regular hexagon, then by the pitch in the range of regular hexagon and concrete chisel removal to certain depth;
S4, will cut after hole bottom and crater wall clean out, in pit slot after installation check well rise pedestal framework of steel reinforcement, inspection shaft It rises afterwards on pedestal framework of steel reinforcement and is fixed with several adjusting bolts, leveling steel plate is installed in adjusting bolt;
S5, pedestal template is risen after installation check well on the inside of inspection shaft, well seat is placed on leveling steel plate, passes through adjusting bolt With leveling leveling steel plate well seat and reach absolute altitude;
S6, pedestal is risen after pouring inspection shaft, before concrete initial set, dispenses one layer of black cement in concrete surface, concrete coagulates Gu pedestal is risen after, after inspection shaft and is fixed as an entirety with well seat, pedestal template is risen after removing inspection shaft and well lid is installed.
2. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:In S3, chisel Except depth is 30cm below grade elevation.
3. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:In S3, chisel Except when, vertical road surface carries out downwards, when encountering original concrete plate, is dug again after first concrete plate is cut along sideline It removes.
4. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:In S6, pour The concrete built is the steel fiber reinforced concrete mixed with micro-expanding agent.
5. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:It is black in S6 Cement is iron oxide black cement.
6. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:In S6, mix During solidifying soil solidification, in inspection shaft periphery installation activity enclosing.
7. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:In S6, mix During solidifying soil solidification, with covered rearing with plastic film curing concrete to design strength.
8. rise reinforced construction method after asphalt concrete pavement inspection shaft as described in claim 1, it is characterised in that:It is risen after inspection shaft Pedestal framework of steel reinforcement is the frame of circular ring shape, including be located at the inner ring reinforcing bars of upper and lower both sides, outer shroud reinforcing bar and intermediate ring reinforcing bar with And connection reinforcing bar.
CN201810140484.8A 2018-02-09 2018-02-09 Reinforced construction method is risen after asphalt concrete pavement inspection shaft Pending CN108222072A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810140484.8A CN108222072A (en) 2018-02-09 2018-02-09 Reinforced construction method is risen after asphalt concrete pavement inspection shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810140484.8A CN108222072A (en) 2018-02-09 2018-02-09 Reinforced construction method is risen after asphalt concrete pavement inspection shaft

Publications (1)

Publication Number Publication Date
CN108222072A true CN108222072A (en) 2018-06-29

Family

ID=62661569

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810140484.8A Pending CN108222072A (en) 2018-02-09 2018-02-09 Reinforced construction method is risen after asphalt concrete pavement inspection shaft

Country Status (1)

Country Link
CN (1) CN108222072A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984232A (en) * 2019-11-28 2020-04-10 上海二十冶建设有限公司 Well lid lifting device and method for asphalt pavement of municipal road
WO2021213099A1 (en) * 2021-02-22 2021-10-28 中铁九局集团第四工程有限公司 Structure and method for reinforcing manhole cover anchored with existing road surface foundation by means of dowel bars

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110002967U (en) * 2009-09-17 2011-03-23 임인택 Fixing and installation height adjuster for manhole cover assembly
CN102644295A (en) * 2012-04-28 2012-08-22 江苏阳湖建设项目管理有限公司 Construction method for preventing peripheral and local sedimentation of road surface inspection well
CN103835217A (en) * 2013-12-02 2014-06-04 天津炬实科技发展有限公司 Method for prevention and treatment on damage and depression of pavement around inspection well
CN104695300A (en) * 2015-02-06 2015-06-10 湖北益通建设股份有限公司 Process for lifting asphalt pavement inspection well and lifting structure
KR20150106130A (en) * 2014-03-11 2015-09-21 태평림건설 주식회사 The manhole repairing method using a manhol housing supporthing apparatus and a cast for the repair work of a manhole
GB2527541A (en) * 2014-06-25 2015-12-30 Saint Gobain Construction Products Uk Ltd An access cover assembly and methods of its installation and manufacture
CN105908781A (en) * 2016-06-08 2016-08-31 朱凤起 Manhole
CN107100202A (en) * 2017-03-28 2017-08-29 郑全兴 A kind of installation method of self-leveling catch basin cover and device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110002967U (en) * 2009-09-17 2011-03-23 임인택 Fixing and installation height adjuster for manhole cover assembly
CN102644295A (en) * 2012-04-28 2012-08-22 江苏阳湖建设项目管理有限公司 Construction method for preventing peripheral and local sedimentation of road surface inspection well
CN103835217A (en) * 2013-12-02 2014-06-04 天津炬实科技发展有限公司 Method for prevention and treatment on damage and depression of pavement around inspection well
KR20150106130A (en) * 2014-03-11 2015-09-21 태평림건설 주식회사 The manhole repairing method using a manhol housing supporthing apparatus and a cast for the repair work of a manhole
GB2527541A (en) * 2014-06-25 2015-12-30 Saint Gobain Construction Products Uk Ltd An access cover assembly and methods of its installation and manufacture
CN104695300A (en) * 2015-02-06 2015-06-10 湖北益通建设股份有限公司 Process for lifting asphalt pavement inspection well and lifting structure
CN105908781A (en) * 2016-06-08 2016-08-31 朱凤起 Manhole
CN107100202A (en) * 2017-03-28 2017-08-29 郑全兴 A kind of installation method of self-leveling catch basin cover and device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984232A (en) * 2019-11-28 2020-04-10 上海二十冶建设有限公司 Well lid lifting device and method for asphalt pavement of municipal road
WO2021213099A1 (en) * 2021-02-22 2021-10-28 中铁九局集团第四工程有限公司 Structure and method for reinforcing manhole cover anchored with existing road surface foundation by means of dowel bars

Similar Documents

Publication Publication Date Title
CN106759792B (en) A kind of inspection shaft construction technique
CN106088588B (en) A kind of cast-in-situ stair closes the construction of formwork erecting structure and its reverse irrigation concrete
CN105350559B (en) A kind of construction method of diamond dust structural floor suitable for large-sized workshop
CN108487323B (en) Construction process of manhole cover device of inspection well on road
CN104695300B (en) The technique of a kind of bituminous paving inspection shaft lifting and lift structure thereof
CN108222072A (en) Reinforced construction method is risen after asphalt concrete pavement inspection shaft
CN108360328A (en) The construction method and transition well lid of bituminous paving inspection shaft periphery compacting
CN210134291U (en) Broad structure of side of existing passenger dedicated line road bed
CN105544612A (en) Inspection well construction method
CN112796346B (en) A method for constructing an anti-sinking manhole cover
CN110258645A (en) Adjustable anti-settling inspection shaft adjusts ring and manhole cover combination structure
CN107012760A (en) Prevent the construction method of the periphery depression of urban road inspection shaft and local damage
CN104895582B (en) A kind of integral mold plate concrete constructions method of double track tunnel ditch cable trench
CN208293344U (en) Kerbstone, gutter and the molding pavement structure of top course one-time-concreting
CN217579581U (en) Bituminous paving inspection shaft reinforced structure
CN109056660A (en) A kind of gate ground sill mounting process
CN114622600A (en) Urban road assembled anti-settling well cover maintenance method
CN206971280U (en) A kind of special type checks well construction
CN211849540U (en) Building rubbish breaks room soil and handles weak foundation structure
CN203080429U (en) Pier stud splicing construction structure for jacking of bridge broken column
CN202416358U (en) Improved structure of manhole frame cover
CN106320343A (en) Automatic positioning device for building concrete pouring
CN207988637U (en) A kind of prefabricated post connection structure for being fixed temporarily, adjusting height
CN106498850B (en) A kind of bridge pavement component and preparation method thereof
CN206828966U (en) A kind of combined bridge anticollision revetment shaper component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180629

RJ01 Rejection of invention patent application after publication