CN108221947A - Ultra-large type soot entirety drainage and construction method - Google Patents

Ultra-large type soot entirety drainage and construction method Download PDF

Info

Publication number
CN108221947A
CN108221947A CN201711464410.1A CN201711464410A CN108221947A CN 108221947 A CN108221947 A CN 108221947A CN 201711464410 A CN201711464410 A CN 201711464410A CN 108221947 A CN108221947 A CN 108221947A
Authority
CN
China
Prior art keywords
construction
ultra
drainage
reinforcement cage
large type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711464410.1A
Other languages
Chinese (zh)
Inventor
邹毅
江涌波
林君伟
陈嘉威
黎强
原炜阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU FOURTH CONSTRUCTION Co Ltd
Original Assignee
GUANGZHOU FOURTH CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU FOURTH CONSTRUCTION Co Ltd filed Critical GUANGZHOU FOURTH CONSTRUCTION Co Ltd
Priority to CN201711464410.1A priority Critical patent/CN108221947A/en
Publication of CN108221947A publication Critical patent/CN108221947A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • E02D3/106Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by forming sand drains containing only loose aggregates

Abstract

The invention discloses a kind of ultra-large type soot entirety drainage and construction method, including:Double-layer combined Construction of Silo and multilayer packaging type blind ditch construction, realize ultra-large type soot vertically and horizontally, the depth layer method that synchronizes draining.The vertical shaft of the steel reinforcement cage of package tiling TGXG and the trepanning coating steel pipe composition of package geotextiles, it plays preferably fixed well head and improves drainage, the horizontal guide french drain being made of geomembrane, inflection TGXG, perforated pipe, deformability is strong, guide speed is fast, it is combined with double-layer combined vertical shaft, greatly improves refuse landfill drainage problem.

Description

Ultra-large type soot entirety drainage and construction method
Technical field
The invention belongs to cities and city life garbage burying field engineering, and it is whole to specifically relate to a kind of ultra-large type soot Body drainage and construction method.
Background technology
Urban garbage disposal mainly has three ways, such as landfill, burning and compost, is applied wherein being handled with land-fill method At most.In ultra-large type garbage loading embeading, due to filling task amount weight, the percolate accumulated daily is more, and discharge pressure is very big, such as Fruit cannot effectively reduce leachate level, may lead to entire landfill yard unstability.Rubbish often occurs for traditional well-digging pump drainage technique Rubbish silting leads to the problem of evacuation system inefficiency, and uses that other forms draining is not only costly, and difficulty of construction is big instead, efficiency Also it is difficult to reach expected requirement.Intractable drainage problem causes refuse landfill to be difficult to continue expansion scale, and newly-built rubbish is filled out It is difficult to promote again in addressing and expense to bury field.
For the entirety draining of ultra-large type soot there are the problem of, the present invention regarding to the issue above to existing construction technology into Row improves, and forms a kind of completely new ultra-large type soot entirety drainage and construction method.
Invention content
In order to solve defect of the existing technology, present invention offer is a kind of effectively to reduce percolate from garbage filling field water The stability of junk-heap body is improved in position, shortens the construction period, reduces the whole drainage construction side of refuse landfill operations risks Method.
The present invention realizes that a kind of technical solution that above-mentioned purpose uses is:A kind of ultra-large type soot entirety drainage construction side Method, including:Double-layer combined Construction of Silo and multilayer packaging type blind ditch construction.
Further, the double-layer combined Construction of Silo step is:First several proper alignments are drilled out in junk-heap body Jing Dong;Then steel reinforcement cage is placed in each well hole, steel reinforcement cage is enclosed with tiling TGXG;And then it is put in steel reinforcement cage Enter coating steel pipe, coating steel pipe package geotextiles;Followed by filling rubble between steel reinforcement cage and coating steel pipe;Finally backfill is viscous Soil, and it is laid with bentonite and clay composite soil.
Further, the multilayer packaging type blind ditch construction step is:Groove is first excavated in rubbish heap;Then in groove Bottom is laid with geomembrane and inflection geotechnique's lattice canopy;And then it backfills and cleans rubble, while discharge guiding pipe is planted in metalling;Finally Backfill rubbish.
Implement above-mentioned technical proposal, this water discharge method is made of two parts:Drainage construction process is broadly divided into two-layer compound Formula Construction of Silo and multilayer packaging type blind ditch construction, realize ultra-large type soot vertically and horizontally, the depth layer method that synchronizes draining.More Specifically, the vertical shaft of the steel reinforcement cage of package tiling TGXG and the trepanning coating steel pipe composition of package geotextiles, is played more Good fixation well head and raising drainage, the horizontal guide french drain being made of geomembrane, inflection TGXG, perforated pipe can Morphotropism is strong, and guide speed is fast, is combined with double-layer combined vertical shaft, greatly improves refuse landfill drainage problem.
The beneficial effects of the invention are as follows:
1st, spiral-digging pore and blind ditch construction possess complete construction technology, double-layer combined shaft pore-forming rate on junk-heap body Height, multilayer packaging type french drain disposal molding effect are good, and whole drainage effect is good, reduces ultra-large type soot due to draining Freely junk-heap body comes down caused by possibility.
2nd, double-layer combined vertical shaft steel reinforcement cage and coating steel pipe construction are compact, and sewage is percolated through rubble to trepanning galvanized steel Pipe, reduces vertical shaft silting problem.
3rd, multilayer packaging type french drain is simple for process, and speed of application is fast, saves the duration.
Description of the drawings
Fig. 1 is double-layer combined shaft structure schematic diagram.
Fig. 2 is multilayer packaging type french drain structure diagram.
In figure label for:1- junk-heap bodies;2- tiling TGXG;3- steel reinforcement cages;4- metallings;5- geotextiles;6- is plated Zinc steel pipe;7- argillic horizons;8- bentonites and clay mixed layer;9- geomembranes;10-HDPE discharge guiding pipes:11- cleans rubble;12- is returned Roll over TGXG;13- Jing Dong.
Specific embodiment
Ultra-large type soot entirety drainage and construction method is applied including double-layer combined Construction of Silo and multilayer packaging type french drain Work.
With reference to Fig. 1, the double-layer combined a diameter of 1000mm of vertical shaft, well depth 25m, before construction, worker dresses appliances for labor protection, with Anti- biogas poisoning, clears up rubbish facial mask and discarded pipeline, and the steel plate box for machine-walking is laid on junk-heap body 1;So Spiral digging machine to designated position is moved along steel plate box afterwards to drill, hole top installation casing prevents collapse hole, the rubbish that drills out and Shi Qingli;Wrap up steel reinforcement cage 3 with tiling TGXG 2, and it is vertical under be put into well hole 13, wrap up coating steel pipe with geotextiles 5 6, it is accurate to be placed in steel reinforcement cage 3;Then steel reinforcement cage 3 and galvanized steel in well hole 13 will be put into using hopper under metalling 4 Between pipe 6, and uniformly fill;After rubble is filled into designed elevation, argillic horizon 7 and ginseng are backfilled above well opening and metalling 10% bentonite and clay mixed soil 8;The compound vertical shaft of pair of lamina is often completed, marks, is hidden to prevent garbage loading embeading complete Into well head, and shift drilling machine to next well location and put construction.
Double-layer combined Construction of Silo:1) preparation before construction is carried out, including:It is laid on junk-heap body for machine Steel plate box, cleaning rubbish facial mask and discarded pipeline, the appliances for labor protection wearing of tool walking;2) unwrapping wire positioning and drilling:Along steel plate Case moves Spiral digging machine to designated position and drills, and hole top installation casing prevents collapse hole, and the rubbish drilled out is cleared up in time;3) under The steel reinforcement cage of package tiling TGXG is put, steel reinforcement cage should be transferred as early as possible after pore-forming, accomplishes decentralization steel reinforcement cage on the day of same day pore-forming, It avoids leading to not transfer steel reinforcement cage because of collapse hole;4) decentralization package geotextiles trepanning coating steel pipe, alignment hole position during construction are kept Vertically enter hole, should not rotate left and right, prevent that height proposes pelter and forces tripping in;5) rubble backfills:It will be put under rubble using hopper It in well, is uniformly filled in well surrounding, reduces the lateral pressure to coating steel pipe;6) clay and swelling earthen backfill:Rubble is filled into After designed elevation, clay and bentonite and clay composite soil are backfilled;7) after the completion of a well is by design requirement construction, the movement of stake machine Continue to construct to next well location;8) well location is often completed, is marked, is hidden to prevent garbage loading embeading and completed well head.
With reference to Fig. 2, multilayer packaging type french drain is inverted trapezoidal section, and bottom, upper bottom width are respectively 1200mm and 1600mm, high It is 1200mm, 10 centre-to-centre spacing bottom of HDPE discharge guiding pipes is 350mm.Multilayer packaging type french drain is carried out using the special digging machine in soot It excavates, excavates to pay attention to avoiding and completed double-layer combined vertical shaft.The rubbish dug out is stored toward french drain side, and rubble is cleaned to backfill 11 processes reserve backfill road.After ditch Slot shaping, groove bottom of trench has been completed in artificial leveling, is laid with geomembrane 9, is laid on it flat TGXG 2 is spread, tiling TGXG 2 is fixed on french drain furrow bank, and stone backfill is avoided to pound and falls tiling TGXG;And then Rubble 11 is backfilled, rubble 11 is cleaned before backfilling using pool specialized, is layered uniformly backfill, and rubble 11 is backfilled and examined in compactness HDPE discharge guiding pipes 10 are transferred after testing qualification, continue to backfill clean rubble 11 on it, then the package of inflection TGXG 12 is cleaned Rubble 11.The rubbish that finally backfill groove is excavated flattens rubbish and carries out pipeline label after backfill.
Multilayer packaging type blind ditch construction:1) channel excavation:Multilayer packaging type french drain excavates, and pays attention to avoiding and has completed bilayer again Box-like vertical shaft.The rubbish dug out is stored toward french drain side, and backfill road is reserved for backfill stone process;2) geomembrane, tiling soil Work grid is laid with:Groove bottom of trench has been completed in artificial leveling, is laid with geomembrane, is laid with two-way tiling TGXG in the above, is put down Paving TGXG is fixed on french drain furrow bank, and stone backfill is avoided to pound and falls tiling TGXG;3) rubble backfill and HDPE guides Pipe is placed:It is to clean rubble to backfill stone, is layered uniformly backfill, stone transfers center HDPE discharge guiding pipes after the assay was approved, at it On continue to backfill rubble, last inflection lower floor tiling TGXG package rubble;4) rubbish backfills:Backfill rubbish is channel excavation Rubbish out flattens rubbish and carries out pipeline label after backfill.
Finally, soot longitudinal direction evacuation system being formed by multiple double-layer combined vertical shafts, vertical shaft is 15m with vertical shaft spacing, Lateral guide system is formed by a plurality of multilayer packaging type french drain, french drain is connect with vertical shaft spare interface so that ultra-large type soot Vertically and horizontally, depth layer synchronizes draining qualified to exploit.

Claims (3)

1. a kind of ultra-large type soot entirety drainage and construction method, it is characterised in that step includes:Double-layer combined Construction of Silo With multilayer packaging type blind ditch construction.
2. ultra-large type soot entirety drainage and construction method according to claim 1, which is characterized in that described double-layer combined Construction of Silo step is:
The Jing Dong of several proper alignments is first drilled out in junk-heap body;
Then steel reinforcement cage is placed in each well hole, steel reinforcement cage is enclosed with tiling TGXG;
And then coating steel pipe, coating steel pipe package geotextiles are placed in steel reinforcement cage;
Followed by filling rubble between steel reinforcement cage and coating steel pipe;
Clay is finally backfilled, and is laid with bentonite and clay composite soil.
3. ultra-large type soot entirety drainage and construction method according to claim 1, which is characterized in that the multilayer packaging type Blind ditch construction step is:
Groove is first excavated in rubbish heap;
Then geomembrane and inflection geotechnique's lattice canopy are laid in channel bottom;
And then it backfills and cleans rubble, while discharge guiding pipe is planted in metalling;
Finally backfill rubbish.
CN201711464410.1A 2017-12-28 2017-12-28 Ultra-large type soot entirety drainage and construction method Pending CN108221947A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711464410.1A CN108221947A (en) 2017-12-28 2017-12-28 Ultra-large type soot entirety drainage and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711464410.1A CN108221947A (en) 2017-12-28 2017-12-28 Ultra-large type soot entirety drainage and construction method

Publications (1)

Publication Number Publication Date
CN108221947A true CN108221947A (en) 2018-06-29

Family

ID=62646547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711464410.1A Pending CN108221947A (en) 2017-12-28 2017-12-28 Ultra-large type soot entirety drainage and construction method

Country Status (1)

Country Link
CN (1) CN108221947A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827324A (en) * 2020-07-20 2020-10-27 浙江国丰集团有限公司 Construction method of deep-layer dewatering pumping shaft of refuse landfill
CN114960690A (en) * 2022-06-02 2022-08-30 中国建筑第八工程局有限公司 Seepage ditch backfill diversion tool for automatically separating natural-grade distributed sand and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101113057A (en) * 2006-07-27 2008-01-30 深圳市金达莱环保股份有限公司 Combined technique for garbage filter liquor treatment
CN206706846U (en) * 2016-12-27 2017-12-05 浙江国丰集团有限公司 A kind of garbage stacking yard pump drainage shaft structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101113057A (en) * 2006-07-27 2008-01-30 深圳市金达莱环保股份有限公司 Combined technique for garbage filter liquor treatment
CN206706846U (en) * 2016-12-27 2017-12-05 浙江国丰集团有限公司 A kind of garbage stacking yard pump drainage shaft structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈云敏等: "垃圾填埋场渗沥液水位壅高及工程控制", 《岩石力学与工程学报》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827324A (en) * 2020-07-20 2020-10-27 浙江国丰集团有限公司 Construction method of deep-layer dewatering pumping shaft of refuse landfill
CN111827324B (en) * 2020-07-20 2021-02-26 浙江国丰集团有限公司 Construction method of deep-layer dewatering pumping shaft of refuse landfill
CN114960690A (en) * 2022-06-02 2022-08-30 中国建筑第八工程局有限公司 Seepage ditch backfill diversion tool for automatically separating natural-grade distributed sand and construction method thereof

Similar Documents

Publication Publication Date Title
CN107100171A (en) A kind of foundation ditch construction method
CN102383413A (en) Method for constructing strengthened saturated-flow plastic silt soft soil foundation
CN107859041B (en) The construction method of collapsible loess zanjon high roadbed structure
CN102787236B (en) Ion-absorbing type rare earth in-situ mineral leaching mother liquor recovery process
CN101949153A (en) Foundation drainage control method
CN106759463A (en) A kind of hypogee and its construction method
CN101328710A (en) Synchronous soil lifting grouting rectangular filling pile apparatus and method
CN108057706B (en) Method and system for setting percolate layering guide drainage blind ditch for refuse landfill
CN110029690A (en) A kind of percolate leak detection collection structure and its construction method
CN106498959A (en) Gutter for deep overburden
CN108221947A (en) Ultra-large type soot entirety drainage and construction method
CN111608174A (en) Karst area karst cave treatment method based on punched cast-in-place pile
CN111962459A (en) Urban debris flow channel type comprehensive treatment system for abandoned slag yard and construction method thereof
CN1804235A (en) Horizontal leakage preventing structure for red mud dump in karst terrain
CN207537975U (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN212641685U (en) Underground garage drainage open ditch and blind ditch combine antiseep system
CN109235469A (en) A kind of Cut Slopes of Expansive Soil structure and its construction method
CN2908612Y (en) Level anti-leakage structure for red mud field of karst ared
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN107881987A (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN108277815B (en) Cofferdam structure for construction of water taking head structure in river and construction method thereof
CN110185051A (en) Deep narrow excavation water discharge method
CN105002883A (en) Indirect hierarchical relay type drainage consolidation method of soft foundation
CN110080234A (en) A method of it is excavated in the secondary central island of deep foundation pit of soft soil foundation
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180629