CN108190685A - Movable type super high-rise construction elevator guide rail frame attachment device and construction method thereof - Google Patents
Movable type super high-rise construction elevator guide rail frame attachment device and construction method thereof Download PDFInfo
- Publication number
- CN108190685A CN108190685A CN201711454984.0A CN201711454984A CN108190685A CN 108190685 A CN108190685 A CN 108190685A CN 201711454984 A CN201711454984 A CN 201711454984A CN 108190685 A CN108190685 A CN 108190685A
- Authority
- CN
- China
- Prior art keywords
- guide rail
- body frame
- movable
- wall
- construction elevator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 51
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 24
- 239000010959 steel Substances 0.000 claims abstract description 24
- 230000000694 effects Effects 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 6
- 238000001514 detection method Methods 0.000 claims 1
- 238000009435 building construction Methods 0.000 abstract description 2
- 239000000725 suspension Substances 0.000 abstract 2
- 239000000463 material Substances 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B7/00—Other common features of elevators
- B66B7/02—Guideways; Guides
- B66B7/023—Mounting means therefor
- B66B7/024—Lateral supports
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B11/00—Main component parts of lifts in, or associated with, buildings or other structures
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B9/00—Kinds or types of lifts in, or associated with, buildings or other structures
- B66B9/04—Kinds or types of lifts in, or associated with, buildings or other structures actuated pneumatically or hydraulically
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Mechanical Engineering (AREA)
- Automation & Control Theory (AREA)
- Types And Forms Of Lifts (AREA)
Abstract
The invention discloses a movable type super high-rise construction elevator guide rail frame attachment device and a construction method thereof, and relates to the technical field of super high-rise building construction; the guide rail frame unit comprises a plurality of guide rail frame units which are longitudinally spliced, each guide rail frame unit comprises a sheet type auxiliary joint, a connecting arm, a standard joint and a suspension cage, the sheet type auxiliary joint is connected with the standard joint through the connecting arm, and the suspension cage is arranged on the standard joint; the auxiliary segment is characterized by also comprising a plurality of movable auxiliary walls, wherein the movable auxiliary walls are arranged on the sheet type auxiliary segments; the invention effectively solves the problem that the existing construction elevator can not be connected with the hydraulic lifting steel platform; the invention is used for the movable type super high-rise construction elevator guide rail frame.
Description
Technical field:
The present invention relates to a kind of movable ultrahigh layer construction elevator guide rail bracket attachment device and its construction methods, belong to superelevation
Layer technical field of building construction.
Background technology:
The commonly used Integral type hydraulic lifting formula steel platform (hereinafter referred to as steel platform) of construction of super highrise building is with auxiliary in recent years
Help construction.Steel platform multi rack is located in the core tube region of high-rise building, can voluntarily be promoted with hydraulic jacking device, as
Platform that is entirety, safe, being promoted certainly facilitate worker to carry out reinforcing bar and template work to the Core Walls Structure wall of high-rise building
Industry.Construction elevator be in construction it is common it is manned cargo transport vertical transport machinery, conventional construction elevator guide rail bracket one
As construction elevator is fixed under construction on completed wall using wall-attaching equipment, met construction elevator and lifted safely, side
Person who happens to be on hand for an errand person and the upper and lower construction work surface of material.
Using Integral type hydraulic lifting steel platform system, the wall of steel platform operation layer is in Construction State, it is impossible to effective
Firm attachment point is provided and provides attachment for construction elevator guide rail bracket.Operating personnel can only take construction elevator to completed building
Level, then operation layer is risen to by temporary stairways, this means of conveyance efficiency is low, safety is poor, and pole is generated to manpower and materials
The earth wastes, while drags slow construction operation progress, there is higher security risk.
Invention content:
In view of the above-mentioned problems, the present invention provides a kind of movable ultrahigh layer construction elevator guide rail bracket attachment device, solve existing
There is the problem of construction elevator cannot be connect with hydraulic pressure lift steel platform.
A kind of movable ultrahigh layer construction elevator guide rail bracket attachment device of the present invention, it includes several guide rail bracket lists
Member, several guide rail bracket units are longitudinal spliced, and each guide rail bracket unit includes chip auxiliary section, link arm, standard knot and cage,
Chip auxiliary section is connect by link arm with standard knot, and cage is equipped on standard knot;It further includes several movable attached walls, living
Dynamic attached wall is mounted on chip auxiliary section.
Preferably, each activity attached wall includes upper body frame, lower wall-attaching base, lower body frame, upper wall-attaching base, two braces
First, two braces, two, two hitch and several assembling pulleys;Upper body frame passes through two braces one and two braces
It is connected between two and lower body frame, upper body frame is connect by connection component with upper wall-attaching base, and lower body frame is attached under by connection component
Wall base connects, and upper body frame is connect with the rear end of lower body frame with hitch, several assembling pulleys is equipped on each hitch, often
A hitch and several assembling pulleys and chip auxiliary section connection.
Preferably, the both ends of brace one and brace two are mounted on connection sheet, and connection is provided in connection sheet
Through-hole, brace one and brace two are connect by connection sheet with upper body frame with lower body frame.
Preferably, connection component includes two engaging lugs, two adjusting rod upper covers, two adjusting screw rods and two adjustings
Bar lower cover, the front end of each adjusting rod upper cover are equipped with engaging lug, engaging lug by bolt respectively with upper wall-attaching base, lower wall-attaching base
The connecting seat connection of front end, the rear end installation and adjustment screw rod of adjusting rod upper cover, adjusting screw rod are distinguished respectively by adjusting rod lower cover
On upper body frame and lower body frame.
Its construction method is:
Step 1:The movable attached wall of processing suitable dimension is designed according to on-site actual situations;
Step 2:Assembled good movable attached wall is mounted on hydraulic pressure steel platform side wall;
Step 3:Link arm is fixed on the standard knot of construction elevator guide rail bracket by high-strength bolt;
Step 4:Chip auxiliary section is mounted in link arm as the guide rail at the assembled pulley end of movable attached wall;
Step 5:Assembled standard knot and chip auxiliary section are hoisted to mounted construction electricity by tower crane
Terraced guide rail bracket standard knot top, the installation for carrying out standard knot are reinforced, while docked with the assembled pulley of movable attached wall;
Step 6:Chip auxiliary section on movable attached wall and cage guide frame standard knot is subjected to last debugging and inspection
It surveys;
Step 7:When steel platform is climbed upwards, movable attached wall climbs with steel platform, while the horizontal trajectory to climb is limited to
On construction elevator guide rail bracket standard knot.
Compared with prior art, beneficial effects of the present invention are:Movable attached wall dependable performance in this programme, it is effective to solve
The problem of existing construction elevator of having determined cannot be connect with hydraulic pressure lift steel platform;Realization personnel, material can be stablized, quickly arrive
Up in hydraulic pressure steel platform;Construction elevator can also normal use during hydraulic pressure steel platform is promoted.
Description of the drawings:
For ease of explanation, the present invention is described in detail by following specific implementations and attached drawing.
Fig. 1 a to Fig. 1 d are ramp-up period schematic diagram in the present invention;
Fig. 2 is the structure diagram of the present invention;
Fig. 3 is the structure diagram of movable attached wall in the present invention.
In figure:1- activity attached walls;2- chips auxiliary section;3- link arms;4- standard knots;5- cages;6- engaging lugs;7- is adjusted
Bar upper cover;8- adjusting screw rods;9- adjusting rod lower covers;The upper body frames of 10-;Wall-attaching base under 11-;Body frame under 12-;13- braces one;
14- braces two;The upper wall-attaching bases of 15-;16- hitch;17- assembles pulley;18- connection sheets.
Specific embodiment:
Understand to make the object, technical solutions and advantages of the present invention clearer, it is specific below by what is shown in attached drawing
Embodiment describes the present invention.However, it should be understood that these descriptions are merely illustrative, and it is not intended to limit the model of the present invention
It encloses.In addition, in the following description, the description to known features and technology is omitted, to avoid unnecessarily obscuring the present invention's
Concept.
As shown in Figure 2 and Figure 3, present embodiment uses following technical scheme:It includes several guide rail bracket units,
Several guide rail bracket units are longitudinal spliced, and each guide rail bracket unit includes chip auxiliary section 2, link arm 3, standard knot 4 and cage
5, chip auxiliary section 2 is connect by link arm 3 with standard knot 4, and cage 5 is equipped on standard knot 4;It further includes several activities
Attached wall 1, movable attached wall 1 are mounted on chip auxiliary section 2, and movable attached wall effectively connects construction elevator and hydraulic pressure lift steel platform
It connects, realization personnel, material can stablize, quickly reach in hydraulic pressure steel platform.
Further, each movable attached wall 1 includes upper body frame 10, lower wall-attaching base 11, lower body frame 12, upper wall-attaching base 15, two
A hitch 16 of brace 2 14, two of brace one 13, two and several assembling pulleys 17;Upper body frame 10 is oblique by two
It is connected between pull rod 1 and two braces 2 14 and lower body frame 12, upper body frame 10 is connected by connection component and upper wall-attaching base 15
It connecing, lower body frame is connect by connection component with lower wall-attaching base 11, and upper body frame 10 is connect with the rear end of lower body frame 12 with hitch 16,
Several assembling pulleys 17 are installed, each hitch 16 and several assembling pulleys 17 are assisted with chip on each hitch 16
2 connection of section.
According to construction elevator size in steel platform reserving hole;Movable attached wall 1 passes through upper wall-attaching base 15 and lower wall-attaching base
11 are fixed on steel platform side wall;Upper body frame 10, brace 1, brace 2 14 and lower body frame 12 play connection and adjustment length
Effect;Assembling pulley 17 is made of multigroup idler wheel, and during steel platform is climbed, idler wheel end allows carrying attachment device common
It climbs upwards, while attachment device need not be dismantled;Chip auxiliary section 2 is fixed on by link arm on people's Cargo Lift standard knot, for dress
Guide rail with pulley 17.
Further, the both ends of brace 1 and brace 2 14 are mounted on connection sheet 18, and are set in connection sheet 18
Connection through-hole is equipped with, brace 1 and brace 2 14 are connect by connection sheet 18 with upper body frame 10 with lower body frame 12, this
Connection structure consolidates.
Further, connection component includes two adjusting screw rods 8 of adjusting rod upper cover 7, two of engaging lug 6, two and two
Adjusting rod lower cover 9, the front end of each adjusting rod upper cover 7 are equipped with engaging lug 6, engaging lug 6 by bolt respectively with upper wall-attaching base
15th, the connecting seat connection of lower 11 front end of wall-attaching base, the rear end installation and adjustment screw rod 8 of adjusting rod upper cover 7, adjusting screw rod 8 leads to respectively
Toning pole lower cover 9 is separately mounted to body frame 10 and on lower body frame 12, above structure is easy to make, and the activity duration is short, is convenient for
The time is saved in sharp work on construction ground.
As shown in Fig. 1 a to Fig. 1 d, a kind of construction method of movable ultrahigh layer construction elevator guide rail bracket attachment device, it
Construction method be:
Step 1:The movable attached wall 1 of processing suitable dimension is designed according to on-site actual situations;
Step 2:Assembled good movable attached wall 1 is mounted on hydraulic pressure steel platform side wall;
Step 3:Link arm 3 is fixed on the standard knot 4 of construction elevator guide rail bracket by high-strength bolt;
Step 4:Chip auxiliary section 2 is mounted in link arm as the guide rail at the assembled pulley end of movable attached wall 1;
Step 5:Assembled standard knot 4 and chip auxiliary section 2 are hoisted to mounted construction by tower crane
Cage guide frame standard knot top, the installation for carrying out standard knot are reinforced, while are carried out pair with the assembled pulley of movable attached wall 1
It connects;
Step 6:Chip auxiliary section 2 on movable attached wall 1 and cage guide frame standard knot is subjected to last debugging and inspection
It surveys;
Step 7:When steel platform is climbed upwards, movable attached wall 1 climbs with steel platform, while the horizontal trajectory to climb limits
On construction elevator guide rail bracket standard knot.
This construction method quickly realizes firm attachment point, and attachment can be provided for construction elevator guide rail bracket, saves manpower object
Power avoids the generation of security risk.
Claims (5)
1. a kind of movable ultrahigh layer construction elevator guide rail bracket attachment device, it includes several guide rail bracket units, several are led
Rail gantry unit is longitudinal spliced, and each guide rail bracket unit includes chip auxiliary section 2, link arm 3, standard knot 4 and cage 5, and chip is auxiliary
Section 2 is helped to be connect by link arm 3 with standard knot 4, cage 5 is installed on standard knot 4;It is characterized in that:It further includes several
Movable attached wall 1, movable attached wall 1 are mounted on chip auxiliary section 2.
2. a kind of movable ultrahigh layer construction elevator guide rail bracket attachment device according to claim 1, it is characterised in that:Often
It is oblique that a activity attached wall 1 includes upper body frame 10, lower wall-attaching base 11, lower body frame 12, the brace one 13, two of upper wall-attaching base 15, two
2 14, two hitch 16 of pull rod and several assembling pulleys 17;Upper body frame 10 passes through two braces 1 and two oblique pulls
It is connected between bar 2 14 and lower body frame 12, upper body frame 10 is connect by connection component with upper wall-attaching base 15, and lower body frame passes through connection
Component is connect with lower wall-attaching base 11, and upper body frame 10 is connect with the rear end of lower body frame 12 with hitch 16, is pacified on each hitch 16
Equipped with several assembling pulleys 17, each hitch 16 and several assembling pulleys 17 are connect with chip auxiliary section 2.
3. a kind of movable ultrahigh layer construction elevator guide rail bracket attachment device according to claim 1 or 2, feature exist
In:The both ends of brace 1 and brace 2 14 are mounted on connection sheet 18, and connection through-hole is provided in connection sheet 18, tiltedly
Pull rod 1 and brace 2 14 are connect by connection sheet 18 with upper body frame 10 with lower body frame 12.
4. a kind of movable ultrahigh layer construction elevator guide rail bracket attachment device according to claim 3, it is characterised in that:Even
Connected components include two adjusting screw rods 8 of adjusting rod upper cover 7, two of engaging lug 6, two and two adjusting rod lower covers 9, each to adjust
The front end of bar upper cover 7 is equipped with engaging lug 6, engaging lug 6 by bolt respectively with upper wall-attaching base 15, the company of 11 front end of lower wall-attaching base
Joint chair connects, and the rear end installation and adjustment screw rod 8 of adjusting rod upper cover 7, adjusting screw rod 8 is installed respectively by adjusting rod lower cover 9 respectively
On upper body frame 10 and lower body frame 12.
5. a kind of construction method of movable ultrahigh layer construction elevator guide rail bracket attachment device, it is characterised in that:Step 1:According to
The movable attached wall 1 of on-site actual situations design processing suitable dimension;
Step 2:Assembled good movable attached wall 1 is mounted on hydraulic pressure steel platform side wall;
Step 3:Link arm 3 is fixed on the standard knot 4 of construction elevator guide rail bracket by high-strength bolt;
Step 4:Chip auxiliary section 2 is mounted in link arm as the guide rail at the assembled pulley end of movable attached wall 1;
Step 5:Assembled standard knot 4 and chip auxiliary section 2 are hoisted to mounted construction elevator by tower crane
Guide rail bracket standard knot top, the installation for carrying out standard knot are reinforced, while docked with the assembled pulley of movable attached wall 1;
Step 6:Chip auxiliary section 2 on movable attached wall 1 and cage guide frame standard knot is subjected to last debugging and detection;
Step 7:When steel platform is climbed upwards, movable attached wall 1 climbs with steel platform, while the horizontal trajectory to climb is limited to and applies
On work cage guide frame standard knot.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711454984.0A CN108190685A (en) | 2017-12-28 | 2017-12-28 | Movable type super high-rise construction elevator guide rail frame attachment device and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711454984.0A CN108190685A (en) | 2017-12-28 | 2017-12-28 | Movable type super high-rise construction elevator guide rail frame attachment device and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108190685A true CN108190685A (en) | 2018-06-22 |
Family
ID=62584991
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711454984.0A Pending CN108190685A (en) | 2017-12-28 | 2017-12-28 | Movable type super high-rise construction elevator guide rail frame attachment device and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108190685A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109095318A (en) * | 2018-07-25 | 2018-12-28 | 中国建筑第四工程局有限公司 | A kind of high-order attached wall method and device of the movable connection of construction elevator |
CN109095319A (en) * | 2018-07-25 | 2018-12-28 | 中国建筑第四工程局有限公司 | A kind of construction elevator operating system integrated with climbing frame |
CN109775511A (en) * | 2019-01-30 | 2019-05-21 | 中建四局第六建筑工程有限公司 | A kind of the construction elevator attaching structure and adherence method of lifting platform |
CN114229653A (en) * | 2021-12-23 | 2022-03-25 | 中建三局集团有限公司 | Construction elevator that is integrated in synchronous climbing of lightweight top die platform attaches wall device |
CN115028043A (en) * | 2022-06-06 | 2022-09-09 | 浙江省建设工程机械集团有限公司 | Inclined elevator guide rail frame adjusting and mounting tool and adjusting and controlling method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001270669A (en) * | 2000-03-28 | 2001-10-02 | Mitsubishi Electric Corp | Guide device for elevator |
CN103342269A (en) * | 2013-07-11 | 2013-10-09 | 中建三局建设工程股份有限公司 | Attaching mechanism and ejecting method for super high-rise construction elevator |
CN104310165A (en) * | 2014-09-29 | 2015-01-28 | 中建三局集团有限公司 | Guide rail type adhesion construction lifter and construction method thereof |
CN207827621U (en) * | 2017-12-28 | 2018-09-07 | 上海建工二建集团有限公司 | Movable type super high-rise construction elevator guide rail frame attachment device |
-
2017
- 2017-12-28 CN CN201711454984.0A patent/CN108190685A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001270669A (en) * | 2000-03-28 | 2001-10-02 | Mitsubishi Electric Corp | Guide device for elevator |
CN103342269A (en) * | 2013-07-11 | 2013-10-09 | 中建三局建设工程股份有限公司 | Attaching mechanism and ejecting method for super high-rise construction elevator |
CN104310165A (en) * | 2014-09-29 | 2015-01-28 | 中建三局集团有限公司 | Guide rail type adhesion construction lifter and construction method thereof |
CN207827621U (en) * | 2017-12-28 | 2018-09-07 | 上海建工二建集团有限公司 | Movable type super high-rise construction elevator guide rail frame attachment device |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109095318A (en) * | 2018-07-25 | 2018-12-28 | 中国建筑第四工程局有限公司 | A kind of high-order attached wall method and device of the movable connection of construction elevator |
CN109095319A (en) * | 2018-07-25 | 2018-12-28 | 中国建筑第四工程局有限公司 | A kind of construction elevator operating system integrated with climbing frame |
CN109775511A (en) * | 2019-01-30 | 2019-05-21 | 中建四局第六建筑工程有限公司 | A kind of the construction elevator attaching structure and adherence method of lifting platform |
CN114229653A (en) * | 2021-12-23 | 2022-03-25 | 中建三局集团有限公司 | Construction elevator that is integrated in synchronous climbing of lightweight top die platform attaches wall device |
CN115028043A (en) * | 2022-06-06 | 2022-09-09 | 浙江省建设工程机械集团有限公司 | Inclined elevator guide rail frame adjusting and mounting tool and adjusting and controlling method |
CN115028043B (en) * | 2022-06-06 | 2024-02-27 | 浙江省建设工程机械集团有限公司 | Adjustment control method for adjustment installation tool of inclined elevator guide rail frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108190685A (en) | Movable type super high-rise construction elevator guide rail frame attachment device and construction method thereof | |
CN103206074B (en) | Elevator shaft template construction method, platform and support | |
CN207827621U (en) | Movable type super high-rise construction elevator guide rail frame attachment device | |
CN214195484U (en) | All-steel attached lifting scaffold | |
CN202117247U (en) | Stairway capable of eliminating diagonal bracing effect | |
CN107720575B (en) | A kind of towing type construction method for hanging of tower crane support system | |
CN206418751U (en) | One kind can freely lift flexible assembled hoistway operation platform | |
CN214302811U (en) | Self-adaptive all-steel attached lifting scaffold in micro-tilt building | |
CN203128099U (en) | Slipping type pipeline lifting device | |
CN105776011B (en) | Method for mounting crane beam at top of blast furnace | |
CN106904538A (en) | A kind of installation method of cucurbit gantry crane | |
CN106351441A (en) | Chimney creeping formwork construction device and construction method | |
CN205777428U (en) | Elevator is from climbing platforms | |
CN203874306U (en) | Rescue vehicle for climbing building | |
CN110593582A (en) | High-rise curtain wall installation auxiliary assembly with safety facility | |
CN104612060B (en) | Construction working stand under prefabricated side bar lateral roof | |
CN104847283A (en) | Drilling module drill pipe ramp for offshore cluster wells | |
CN103977512A (en) | Building climbing rescue vehicle | |
CN206110636U (en) | Burst formula hydraulic lifting climbs frame | |
CN204455839U (en) | Construction working stand under prefabricated side bar lateral roof | |
CN204643664U (en) | A kind of building tower crane | |
CN204823738U (en) | Two roof beam electric hoist formula hoist girder orthotic devices | |
CN209924409U (en) | Wall-attached self-climbing electric lifting platform | |
US7232009B1 (en) | Ascension/descension apparatus and method | |
CN209890045U (en) | Lifting equipment for manual hole digging pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180622 |
|
WD01 | Invention patent application deemed withdrawn after publication |