CN108179753A - A kind of construction method of bottom bridge pile foundation - Google Patents

A kind of construction method of bottom bridge pile foundation Download PDF

Info

Publication number
CN108179753A
CN108179753A CN201711458098.5A CN201711458098A CN108179753A CN 108179753 A CN108179753 A CN 108179753A CN 201711458098 A CN201711458098 A CN 201711458098A CN 108179753 A CN108179753 A CN 108179753A
Authority
CN
China
Prior art keywords
pile
steel
water
cement
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711458098.5A
Other languages
Chinese (zh)
Inventor
桂新辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Xin Rui Heavy Industry Co Ltd By Shares
Original Assignee
Anhui Xin Rui Heavy Industry Co Ltd By Shares
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Xin Rui Heavy Industry Co Ltd By Shares filed Critical Anhui Xin Rui Heavy Industry Co Ltd By Shares
Priority to CN201711458098.5A priority Critical patent/CN108179753A/en
Publication of CN108179753A publication Critical patent/CN108179753A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/10Placing gravel or light material under water inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/40Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater

Abstract

The invention discloses a kind of construction methods of water-bed bridge pile foundation, include the following steps:(1) water-bed Bridge Pile basal plane leveling, cleaning and water-bed bridge pile foundation planar survey operation;(2) it using jet drill rig construction cement mixing method, and is carried out using cement mortar spray regime, the density domination of cement mortar is 1.1 1.2kg/cm3;(3) pile pile stake holes is formed using steel pile casting is squeezed to cement mixing method center, the inner wall of pile pile stake holes is tamped later, the steel pile casting uses thickness to be made for the steel plate of 0.8 1mm;(4) it will be sunk in stake holes using the pile sinking casing static pressure or hammering for being set to its inside with the pile pile of annular steel pile tip and reach design position, pile pile is obtained after extracting pile sinking casing, the verticality of pile pile is within 0.5% and its position deviation is not greater than 15cm, and the pile sinking casing is made of stainless steel.The present invention effectively improves the durability of water-bed bridge pile foundation.

Description

A kind of construction method of bottom bridge pile foundation
Technical field
The present invention relates to technical field of bridge construction, and in particular to a kind of construction method of bottom bridge pile foundation.
Background technology
At present, it when pile foundation construction is carried out in muck soil environment coastal, riverine, along the lake, is mostly stirred using soil cement Mix pile-making method construction.Cement mixing method be by the use of cement as curing agent, by Mixing Machine, ground depths by weak soil and Curing agent action of forced stirring is chemically reacted using a series of physical generated between curing agent and weak soil, makes weak soil scleroma into tool There is the high-quality ground of globality, water stability and some strength.
The basic principle of soil-cement is the physical-chemical reaction process based on soil-cement, it and concrete hardening Mechanism is different, and since cement mixing content is few, cement is with certain active medium -- and native is reacted under, setting rate It is relatively slow, and complexity is acted on, after cement hydrolysis generates various hydrates with aquation, ion exchange occurs again for some and granule is turned into With and pozzolanic reaction, greatly improve soil-cement body intensity.But due to cement soil material itself, energy is carried Power is subject to certain restrictions, and its durability is also not as good as other pile-type, and intensity is met the requirements during construction, but as the time pushes away It moves, is particularly subject to the influence of sulfate ion, magnesium ion and calcium ion etc. in surrounding seawater, intensity can greatly be beaten with the time Discount brings hidden danger to the engineering in pile foundation.
Invention content
The purpose of the present invention is to provide a kind of construction methods of water-bed bridge pile foundation, can effectively solve background technology In the technical issues of being previously mentioned.
To achieve the above object, the present invention provides following technical solution:
A kind of construction method of bottom bridge pile foundation, which is characterized in that include the following steps:
(1) water-bed Bridge Pile basal plane leveling, cleaning and water-bed bridge pile foundation planar survey operation:It is clear using underwater diver Reason and the method for underwater demolition form work surface after excavation cleaning, as water-bed Bridge Pile basal plane, and complete water-bed bridge pile foundation Planar survey operation;
(2) it using jet drill rig construction cement mixing method, and is carried out using cement mortar spray regime, the density of cement mortar It controls as 1.1-1.2kg/cm3;
(3) pile pile stake holes is formed using steel pile casting is squeezed to cement mixing method center, later to pile pile stake holes Inner wall is tamped, and the steel pile casting uses thickness to be made for the steel plate of 0.8-1mm;
(4) stake will be sunk to using the pile sinking casing static pressure or hammering for being set to its inside with the pile pile of annular steel pile tip In hole and reach design position, extract and pile pile is obtained after pile sinking casing, the verticality of pile pile is within 0.5% and its position deviation 15cm is not greater than, the pile sinking casing is made of stainless steel;
(5) hard engineering plastic heavy wall Grouting Pipe in the cement mixing method of pile pile side is set, and is led to foundation pit Except, lateral surface 3-4cm of the Grouting Pipe apart from cement mixing method.
Preferably, lateral surface 4cm of the Grouting Pipe apart from cement mixing method.
Preferably, the steel pile casting uses thickness to be made for the steel plate of 1mm.
Compared with prior art, the beneficial effects of the invention are as follows:
The water-bed bridge pile foundation made using the construction method of bridge pile foundation water-bed in the present invention is with safety and reliably Property it is high, and greatly improve its durability under seawater eroding, compared to traditional cement mixing method, the water in the present invention Bottom bridge pile foundation service life can be longer.
Specific embodiment
With reference to the embodiment technical solution that the present invention will be described in detail, but protection domain is not limited thereto.
Embodiment one:
A kind of construction method of bottom bridge pile foundation, includes the following steps:
(1) water-bed Bridge Pile basal plane leveling, cleaning and water-bed bridge pile foundation planar survey operation:It is clear using underwater diver Reason and the method for underwater demolition form work surface after excavation cleaning, as water-bed Bridge Pile basal plane, and complete water-bed bridge pile foundation Planar survey operation;
(2) it using jet drill rig construction cement mixing method, and is carried out using cement mortar spray regime, the density of cement mortar It controls as 1.1-1.2kg/cm3;
(3) pile pile stake holes is formed using steel pile casting is squeezed to cement mixing method center, later to pile pile stake holes Inner wall is tamped, and the steel pile casting uses thickness to be made for the steel plate of 0.8-1mm;
(4) stake will be sunk to using the pile sinking casing static pressure or hammering for being set to its inside with the pile pile of annular steel pile tip In hole and reach design position, extract and pile pile is obtained after pile sinking casing, the verticality of pile pile is within 0.5% and its position deviation 15cm is not greater than, the pile sinking casing is made of stainless steel;
(5) hard engineering plastic heavy wall Grouting Pipe in the cement mixing method of pile pile side is set, and is led to foundation pit Except, lateral surface 3-4cm of the Grouting Pipe apart from cement mixing method, between Grouting Pipe and the lateral surface of cement mixing method Distance preferably 4cm.
The steel pile casting preferentially uses thickness to be made for the steel plate of 1mm.
Finally illustrate, the above embodiments are merely illustrative of the technical solutions of the present invention and it is unrestricted, although with reference to compared with The present invention is described in detail in good embodiment, it will be understood by those of ordinary skill in the art that, it can be to the skill of the present invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of the technical program, should all be covered in the present invention Right in.

Claims (3)

1. a kind of construction method of bottom bridge pile foundation, which is characterized in that include the following steps:
(1) water-bed Bridge Pile basal plane leveling, cleaning and water-bed bridge pile foundation planar survey operation:Using underwater diver cleaning and The method of underwater demolition forms work surface after excavation cleaning, as water-bed Bridge Pile basal plane, and completes water-bed Bridge Pile basal plane and surveys Measure operation;
(2) it using jet drill rig construction cement mixing method, and is carried out using cement mortar spray regime, the density domination of cement mortar For 1.1-1.2kg/cm3;
(3) pile pile stake holes is formed using steel pile casting is squeezed to cement mixing method center, later to the inner wall of pile pile stake holes It is tamped, the steel pile casting uses thickness to be made for the steel plate of 0.8-1mm;
(4) it will be sunk in stake holes using the pile sinking casing static pressure or hammering for being set to its inside with the pile pile of annular steel pile tip And reach design position, obtain pile pile after extracting pile sinking casing, pile pile verticality is within 0.5% and its position deviation must not More than 15cm, the pile sinking casing is made of stainless steel;
(5) hard engineering plastic heavy wall Grouting Pipe in the cement mixing method of pile pile side is set, and is led to except foundation pit, Lateral surface 3-4cm of the Grouting Pipe apart from cement mixing method.
2. the construction method of bottom bridge pile foundation according to claim 1, it is characterised in that:Grouting Pipe is stirred apart from soil cement Mix the lateral surface 4cm of stake.
3. the construction method of bottom bridge pile foundation according to claim 1, it is characterised in that:The steel pile casting uses thickness Steel plate for 1mm is made.
CN201711458098.5A 2017-12-28 2017-12-28 A kind of construction method of bottom bridge pile foundation Pending CN108179753A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711458098.5A CN108179753A (en) 2017-12-28 2017-12-28 A kind of construction method of bottom bridge pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711458098.5A CN108179753A (en) 2017-12-28 2017-12-28 A kind of construction method of bottom bridge pile foundation

Publications (1)

Publication Number Publication Date
CN108179753A true CN108179753A (en) 2018-06-19

Family

ID=62548093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711458098.5A Pending CN108179753A (en) 2017-12-28 2017-12-28 A kind of construction method of bottom bridge pile foundation

Country Status (1)

Country Link
CN (1) CN108179753A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113338272A (en) * 2021-06-15 2021-09-03 广州市公路工程公司 Annular reinforcing method for thick sand layer pile foundation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2353795Y (en) * 1999-01-13 1999-12-15 中国建筑科学研究院地基基础研究所 Prefabricated-tube composite pile of cement and soil
CN2509232Y (en) * 2001-08-31 2002-09-04 凌光荣 Long-corn cement soil combined piles
CN106284321A (en) * 2016-08-17 2017-01-04 刘从波 A kind of construction method of composite pile foundation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2353795Y (en) * 1999-01-13 1999-12-15 中国建筑科学研究院地基基础研究所 Prefabricated-tube composite pile of cement and soil
CN2509232Y (en) * 2001-08-31 2002-09-04 凌光荣 Long-corn cement soil combined piles
CN106284321A (en) * 2016-08-17 2017-01-04 刘从波 A kind of construction method of composite pile foundation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113338272A (en) * 2021-06-15 2021-09-03 广州市公路工程公司 Annular reinforcing method for thick sand layer pile foundation
CN113338272B (en) * 2021-06-15 2022-07-22 广州市公路工程公司 Annular reinforcing method for thick sand layer pile foundation

Similar Documents

Publication Publication Date Title
CN104929135A (en) Deep foundation pit underground diaphragm wall enclosure structure and chemical churning pile water stop construction method thereof
CN108060894A (en) A kind of boring method under complex geological condition
CN106244108A (en) A kind of water-proof repairing agent and preparation method thereof
CN102409666B (en) Construction process of pile foundation in air-raid shelter trend
CN101985836B (en) Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN108179753A (en) A kind of construction method of bottom bridge pile foundation
CN105386444B (en) A kind of basis pile pore-forming device and forming hole method
CN207862925U (en) A kind of slip casting casing device
CN103979880B (en) A kind of pipeline engineering trench backfill material cement many conjunctions compound and preparation method
CN101769157B (en) Construction method for tunnel working face counterpressure treatment during tunnel excavation
CN103343534A (en) Closed precipitation method for foundation pit construction
EP3581714A1 (en) Foundation treatment method for laying foundation structure by penetrating hardpan layer
CN108086897A (en) A kind of impact drill drilling construction method
CN102677630A (en) Construction method of concrete cut-off wall in sludge soil with high water content
CN205444192U (en) Bridge stake is towards pile driving construction system
CN205205811U (en) Drilling bit of deep submerged agitation pile
CN208563316U (en) A kind of large-section in-situ concrete pile pile-end sediment sediment processing unit
CN202031081U (en) Pipe sinking cast-in-place pile with soil discharge pipes
CN101793024B (en) Construction method for multi-head small-diameter deep mixing and high-pressure jet combined anti-seepage wall of foundation pit
Shen et al. Current state of the art in jet grouting for stabilizing soft soil
CN108842800A (en) A kind of drilling backfill The End-bearing Piles Foundation and its construction method
CN102444137A (en) Construction method of vacuum pre-pressed mortar enclosing wall
CN1429952A (en) Application of water injection method for making plastic concrete leakage proof wall in garbage sanitary embedding field
CN203755326U (en) Water stopping building envelope of soft soil foundation building foundation pit
CN102605775A (en) Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180619

RJ01 Rejection of invention patent application after publication