CN108154349A - Concrete station whole-process management system and its management method - Google Patents
Concrete station whole-process management system and its management method Download PDFInfo
- Publication number
- CN108154349A CN108154349A CN201810046309.2A CN201810046309A CN108154349A CN 108154349 A CN108154349 A CN 108154349A CN 201810046309 A CN201810046309 A CN 201810046309A CN 108154349 A CN108154349 A CN 108154349A
- Authority
- CN
- China
- Prior art keywords
- production
- module
- management
- management module
- concrete station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Economics (AREA)
- Marketing (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Abstract
The present invention discloses and provides a kind of high efficiency, saves whole process is carried out to concrete station and carries out one-stop management the concrete station whole-process management system and its management method of cost.Concrete station whole-process management system in the present invention includes central processing module and the order management module being connected respectively with the central processing module, production schedule module, formulation management module, production scheduling module, production control terminal, statement management module, vehicle localization module, weighbridge management module and inventory management module.The present invention is suitable for process industry production line production monitoring field.The present invention is suitable for concrete station production management field.
Description
Technical field
The present invention relates to a kind of concrete station whole-process management system and its management methods.
Background technology
In the production management at concrete station, for concrete station it is full-range management in the past be all by being manually managed step by step,
Each step is required for technical staff or administrative staff be analyzed to identify after could carry out in next step, it is both inefficient time-consuming in this way,
Have also increased dramatically the cost of labor of enterprise.
Invention content
The technical problems to be solved by the invention be overcome the deficiencies of the prior art and provide a kind of high efficiency, save into
This whole process is carried out to concrete station and carries out one-stop management concrete station whole-process management system and its management method.
The technical solution adopted in the present invention is:Concrete station whole-process management system in the present invention includes central processing module
And be connected respectively with the central processing module order management module, production schedule module, formulation management module, production
Scheduler module, production control terminal, statement management module, vehicle localization module, weighbridge management module and inventory management module.
The production control terminal is connected with external production equipment.
The weighbridge management module is connected with external weighbridge.
The order management module is connected by wireless signal with external mobile terminal.
The vehicle localization module is connected by GPS signal with haulage vehicle.
A kind of concrete station whole-process management method realized by above-mentioned concrete station whole-process management system, it includes following step
Suddenly:
A. order management:Client is release order by the APP of mobile terminal, and the order management module transmits the sequence information
To the production schedule module;
B. the production schedule:The production schedule module receive first pass through after the sequence information that the order management module is sent out it is described
Formulation management module is formulated to set, and production time and material quantity are formulated further according to the actual amount of the formula and order;
C. production scheduling:How many amounts is specifically produced according to the production time that the production schedule is formulated to each concrete station to give birth to
Production arranges an order according to class and grade and specifies corresponding haulage vehicle, while send dispatch command, the production control terminal control to the production control terminal
External production equipment processed is produced;
D. delivery management:After the amount of production reaches the amount that the production schedule is formulated, the production control terminal control external production
Equipment stops production, and then each designated vehicle send product to customers' place, and the vehicle localization module to carry out haulage vehicle
Positioning in real time, after client signs for, the order management module delimit order and completes and close order;
E. stock control:The weighbridge at each concrete station is connected with the weighbridge management module, the weighbridge management module
The difference information of the charging gross weight and discharging gross weight at each concrete station is received, and the difference information is transmitted to the stock control mould
Block is summarized, and obtains final quantity in stock;
F. report management:The statement management module in production process supplies consumption, backlog total and haulage vehicle
Transport track is counted, and obtains final production report.
Beneficial effects of the present invention:In the present invention, order management module, production schedule module, formulation management are employed
Module, production scheduling module, production control terminal, statement management module, vehicle localization module, weighbridge management module and inventory's pipe
Reason module to carry out whole-process management to concrete station, supernumerary's work management process is eliminated, in addition to being effectively improved concrete station
Whole production efficiency and save huge cost of labor, additionally it is possible to so that the workflow management standardization at concrete station and intelligent.
Description of the drawings
Fig. 1 is the attachment structure schematic diagram of the present invention.
Specific embodiment
As shown in Figure 1, the concrete station whole-process management system in the present invention include central processing module 1 and respectively with
Order management module 2 that the central processing module 1 is connected, production schedule module 3, formulation management module 4, production scheduling mould
Block 5, production control terminal 6, statement management module 7, vehicle localization module 10, weighbridge management module 8 and inventory management module 9.
The production control terminal 6 is connected with external production equipment.The weighbridge management module 5 is connected with external weighbridge
It connects.The order management module 2 is connected by wireless signal with external mobile terminal.The vehicle localization module 10 passes through
GPS signal is connected with haulage vehicle.
A kind of concrete station whole-process management method realized by above-mentioned concrete station whole-process management system, it includes following step
Suddenly:
A. order management:Client is release order by the APP of mobile terminal, and the order management module 2 passes the sequence information
It send to the production schedule module 3;
B. the production schedule:The production schedule module 3 first passes through institute after receiving the sequence information that the order management module 2 is sent out
Formulation management module 4 is stated to set formula, production time and materials are formulated further according to the actual amount of the formula and order
Amount;
C. production scheduling:How many amounts is specifically produced according to the production time that the production schedule is formulated to each concrete station to give birth to
Production arranges an order according to class and grade and specifies corresponding haulage vehicle, while send dispatch command, the production control terminal 6 to the production control terminal 6
Control external production equipment is produced;
D. delivery management:After the amount of production reaches the amount that the production schedule is formulated, the production control terminal 6 controls external production
Equipment stop production, then each designated vehicle send product to customers' place, the vehicle localization module 10 come to haulage vehicle into
Row positioning in real time, after client signs for, the order management module 2 delimit order and completes and close order;
E. stock control:The weighbridge at each concrete station is connected with the weighbridge management module 8, the weighbridge management module
8 receive the difference information of the charging gross weight and discharging gross weight at each concrete station, and the difference information is transmitted to the stock control
Module 9 is summarized, and obtains final quantity in stock;
F. report management:The statement management module 7 in production process supplies consumption, backlog total and haulage vehicle
Transport track is counted, and obtains final production report.
The present invention is suitable for concrete station production management field.
Claims (6)
1. a kind of concrete station whole-process management system, it is characterised in that:It includes central processing module(1)And respectively with it is described in
Entreat processing module(1)The order management module being connected(2), production schedule module(3), formulation management module(4), production scheduling
Module(5), production control terminal(6), statement management module(7), vehicle localization module(10), weighbridge management module(8)And library
Deposit management module(9).
2. whole-process management system in concrete station according to claim 1, it is characterised in that:The production control terminal(6)With it is outer
Portion's production equipment is connected.
3. whole-process management system in concrete station according to claim 2, it is characterised in that:The weighbridge management module(5)With
External weighbridge is connected.
4. whole-process management system in concrete station according to claim 3, it is characterised in that:The order management module(2)It is logical
Wireless signal is crossed with external mobile terminal to be connected.
5. whole-process management system in concrete station according to claim 4, it is characterised in that:The vehicle localization module(10)It is logical
GPS signal is crossed with haulage vehicle to be connected.
6. a kind of concrete station whole-process management system by described in claim 5 is the concrete station whole-process management method realized,
It is characterized in that:It includes the following steps:
A. order management:Client is release order by the APP of mobile terminal, the order management module(2)By the sequence information
It is sent to the production schedule module(3);
B. the production schedule:The production schedule module(3)Receive the order management module(2)First lead to after the sequence information sent out
Cross the formulation management module(4)Come set formula, further according to the actual amount of the formula and order come formulate the production time with
And material quantity;
C. production scheduling:How many amounts is specifically produced according to the production time that the production schedule is formulated to each concrete station to give birth to
Production arranges an order according to class and grade and specifies corresponding haulage vehicle, while to the production control terminal(6)Send dispatch command, the production control terminal
(6)Control external production equipment is produced;
D. delivery management:After the amount of production reaches the amount that the production schedule is formulated, the production control terminal(6)Control is external raw
It produces equipment and stops production, then each designated vehicle send product to customers' place, the vehicle localization module(10)Come to transport vehicle
It is positioned in real time, after client signs for, the order management module(2)Order delimited to complete and close order;
E. stock control:The weighbridge at each concrete station and the weighbridge management module(8)It is connected, the weighbridge manages mould
Block(8)The difference information of the charging gross weight and discharging gross weight at each concrete station is received, and the difference information is transmitted to the inventory
Management module(9)Summarized, obtain final quantity in stock;
F. report management:The statement management module(7)To supplies consumption, backlog total and the haulage vehicle in production process
Transport track counted, obtain final production report.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810046309.2A CN108154349A (en) | 2018-01-17 | 2018-01-17 | Concrete station whole-process management system and its management method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810046309.2A CN108154349A (en) | 2018-01-17 | 2018-01-17 | Concrete station whole-process management system and its management method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108154349A true CN108154349A (en) | 2018-06-12 |
Family
ID=62461757
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810046309.2A Pending CN108154349A (en) | 2018-01-17 | 2018-01-17 | Concrete station whole-process management system and its management method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108154349A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115081991A (en) * | 2022-07-21 | 2022-09-20 | 北矿智云科技(北京)有限公司 | Raw material management method and device, electronic equipment and storage medium |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103687980A (en) * | 2011-06-13 | 2014-03-26 | 理查德·西利·克莱顿 | Processes and apparatus for making concrete and concrete products |
CN106570673A (en) * | 2016-11-10 | 2017-04-19 | 广州市图吉信息科技有限公司 | Commercial concrete online ordering system based on intelligent mobile phone application |
-
2018
- 2018-01-17 CN CN201810046309.2A patent/CN108154349A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103687980A (en) * | 2011-06-13 | 2014-03-26 | 理查德·西利·克莱顿 | Processes and apparatus for making concrete and concrete products |
CN106570673A (en) * | 2016-11-10 | 2017-04-19 | 广州市图吉信息科技有限公司 | Commercial concrete online ordering system based on intelligent mobile phone application |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115081991A (en) * | 2022-07-21 | 2022-09-20 | 北矿智云科技(北京)有限公司 | Raw material management method and device, electronic equipment and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204528304U (en) | For the control system of refuse transfer station active schedule vehicle transhipment rubbish | |
CN107016599A (en) | A kind of order set group technology and device | |
CN106033558A (en) | Communication interface device used between MES system and ERP system and communication method thereof | |
CN107067201A (en) | Intelligent logistics dispatch system | |
CN108288084A (en) | A kind of concrete mixing plant vehicle cargo transport statistical system based on RFID | |
CN104801495A (en) | Full-automatic total-package sorting system and method | |
CN111985889A (en) | Concrete digital cloud factory system | |
CN106845707A (en) | The wisdom logistics service system and method for a kind of information realtime interactive | |
CN108154349A (en) | Concrete station whole-process management system and its management method | |
CN103870949B (en) | A kind of metallurgical production Process Tracking system and method | |
CN116384716A (en) | Intelligent factory operation method and platform device based on unified data management | |
CN108491900A (en) | A kind of raw material alarm purchasing system of concrete mixing plant | |
CN106780159A (en) | A kind of construction information management system | |
CN115293390A (en) | System and method for planning logistics outside plant | |
CN207817486U (en) | A kind of collecting vehicle information monitoring system of concrete mixing plant | |
CN110969544A (en) | Intelligent tracking material distribution and feeding system and method for high-rise building construction | |
CN103996109A (en) | Logistics classifier | |
CN104123606A (en) | Public bicycle dispatching data collecting and processing method based on radio frequency identification device (RFID) | |
CN205451163U (en) | Stirring station raw and other materials warehouse entry management system | |
CN104392326A (en) | Iron-contained solid waste circulation utilization monitoring method for iron and steel enterprise | |
CN114897450A (en) | Cloud digital supply chain service management platform | |
CN114581001A (en) | Supply chain management system based on Internet of things and block chain | |
CN103891626A (en) | Breeding boar feed accurate feeding method and device | |
CN113706083A (en) | Intelligent logistics scheduling method | |
CN202093572U (en) | Intelligent logistic distribution and delivery system based on Internet of things |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180612 |