CN108086539A - A kind of assembled protection wall and its installation method for bank - Google Patents
A kind of assembled protection wall and its installation method for bank Download PDFInfo
- Publication number
- CN108086539A CN108086539A CN201711479094.5A CN201711479094A CN108086539A CN 108086539 A CN108086539 A CN 108086539A CN 201711479094 A CN201711479094 A CN 201711479094A CN 108086539 A CN108086539 A CN 108086539A
- Authority
- CN
- China
- Prior art keywords
- wallboard
- keel
- vertical keel
- bolt
- wall frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 20
- 238000000034 method Methods 0.000 title claims abstract description 10
- 239000002131 composite material Substances 0.000 claims abstract description 21
- 239000011490 mineral wool Substances 0.000 claims abstract description 10
- 238000009413 insulation Methods 0.000 claims abstract description 9
- 238000005516 engineering process Methods 0.000 abstract description 4
- 239000000463 material Substances 0.000 abstract description 4
- 238000004140 cleaning Methods 0.000 abstract description 3
- 238000010276 construction Methods 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000012545 processing Methods 0.000 abstract description 3
- 238000004064 recycling Methods 0.000 abstract description 3
- 230000008901 benefit Effects 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 2
- 238000012856 packing Methods 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000032258 transport Effects 0.000 description 2
- 210000000988 bone and bone Anatomy 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000004880 explosion Methods 0.000 description 1
- 230000001771 impaired effect Effects 0.000 description 1
- 210000003734 kidney Anatomy 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000012827 research and development Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/7407—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts
- E04B2/7409—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts special measures for sound or thermal insulation, including fire protection
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/7407—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts
- E04B2/7409—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts special measures for sound or thermal insulation, including fire protection
- E04B2/7414—Posts or frame members with projections for holding sound or heat insulating fillings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/7407—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts
- E04B2/7448—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts with separate framed panels without intermediary posts, extending from floor to ceiling
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/82—Removable non-load-bearing partitions; Partitions with a free upper edge characterised by the manner in which edges are connected to the building; Means therefor; Special details of easily-removable partitions as far as related to the connection with other parts of the building
- E04B2/825—Removable non-load-bearing partitions; Partitions with a free upper edge characterised by the manner in which edges are connected to the building; Means therefor; Special details of easily-removable partitions as far as related to the connection with other parts of the building the connection between the floor and the ceiling being achieved without any restraining forces acting in the plane of the partition
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2002/7461—Details of connection of sheet panels to frame or posts
- E04B2002/7466—Details of connection of sheet panels to frame or posts using hooks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The present invention relates to ready-package wall technology fields, disclose a kind of assembled protection wall and its installation method for bank, including polylith wallboard (1) and wall frame (2), wallboard (1) is located on wall frame (2) and is connected with wall frame (2), wallboard (1) includes two pieces of installing plates (3) being arranged in parallel and the sound insulation rock wool (4) being located between installing plate (3), sound insulation rock wool (4) is filled between installing plate (3), wallboard (1) is equipped with composite hanging part (5), wallboard (1) is connected by composite hanging part (5) with wall frame (2).Wallboard of the present invention uses standard module, finished product can be produced in batches, the efficient and speed of installation is fast, it can be dismantled from inside, recycling, the module finished product of monoblock type are all transported to erecting bed in the form of standarized component, material are not carried out at the scene the processing such as to cut, ensure the cleaning of construction site, have standardized production with it is more quick, advantage is easily installed.
Description
Technical field
The present invention relates to assembled protection wall technology field more particularly to a kind of assembled protection walls for bank
And its installation method.
Background technology
At present bank outlets cash area wall, it is necessary to meet it is antitheft shellproof explosion-proof, the prior art use armored concrete
Or 240mm thickness brick wall installs sheet metal protection additional, the prior art is time-consuming and laborious in practical applications, and protection effect is unstable,
Repairing efficiency after wall is damaged is long, constructional difficulties, influences site operation, and weight must be removed when resettlement or general layout adjust in site
It builds, take consumptive material and generates a large amount of building wastes.Therefore while research and development can meet antitheft, shellproof, requirement of explosion proof and
It is quick to repair, there is the product that function can be recycled, be the development trend of modern bank protecting wall.
The content of the invention
The present invention is complicated for dismounting inconvenience, repair in the prior art, it is impossible to which the shortcomings that reusing provides a kind of full
Sufficient barrier propterty demand, have convenient for disassembly and assembly, repairing efficiency is short, it is repeatable utilizes, barrier propterty is stablized is used for bank
Assembled protection wall and its installation method.
In order to solve the above-mentioned technical problem, this reality invention is addressed by following technical proposals:
For the assembled wall of bank, including polylith wallboard and wall frame, wallboard be located on wall frame and with wall frame
Connection, wallboard include two pieces of installing plates being arranged in parallel and the sound insulation rock wool being located between installing plate, and sound insulation rock wool is filled in peace
Between loading board, wallboard is equipped with composite hanging part, and wallboard is connected by composite hanging part with wall frame, and wall frame is equipped with pendant hole,
Composite hanging part is equipped with hook, and composite hanging part is connected by linking up with pendant hole.Wallboard by between two blocks of steel plates fill every
Sound rock wool so that wall has good soundproof effect, while enhances fire prevention and heat-insulated ability, and wallboard is coordinated by composite hanging part
On wall frame, wallboard is directly up hung, and installs rapid and convenient.
Preferably, wall frame includes upper keel and lower keel, it is perpendicular equipped with what is be vertically arranged between upper keel and lower keel
To keel, vertical keel is evenly distributed with spread configuration from left to right, and vertical keel vertical keel is equipped with the horizontal square tube laterally set, horizontal
Square tube is connected with vertical keel by connector.
Preferably, connector include riser and with the vertically disposed transverse slat of riser, riser and transverse slat be an integral structure,
Transverse slat and riser are integrated riser and are connected with vertical keel, and transverse slat is connected with horizontal square tube.Horizontal square tube is fixed by connector and is erected
Connection to keel enhances the intensity of integral wall frame.
Preferably, the upper end of vertical keel is equipped with connecting hole, wallboard is connected by bolt with vertical keel, bolt
Through connecting hole, one end of bolt is connected with wallboard, and the other end of bolt is equipped with the nut being connected with bolt thread.Topmost
The wallboard of one row is fixedly connected by bolt with vertical keel, and the stability of fixed upper end wall frame cornice sheathing connection avoids wall
Plate drops.
The installation method of a kind of assembled protection wall for bank, including following installation steps:(1) upper keel is led to
The lower section that setscrew is installed on roof is crossed, lower keel is mounted on by setscrew above bottom plate;
(2) vertical keel is mounted on upper keel and lower keel, the upper and lower ends of vertical keel pass through fastening bolt respectively
It is connected with upper keel and lower keel;
(3) between horizontal square tube being located at vertical keel, the both ends of horizontal square tube are fixedly connected by connector with vertical keel;
(4) by the wallboard of vertical keel upper end by bolt through the bolt hole on vertical keel, by nut by wallboard
It is fixedly mounted on vertical keel;
(5) wallboard is hung on vertical keel by remaining wallboard by composite hanging part, and fastened with hook is on vertical keel
Pendant hole in.
The present invention has significant technique effect as a result of above technical scheme:Wallboard uses standard module, can be with
Produce finished product in batches, the efficient and speed of installation is fast, can be dismantled from inside, recycling, the impaired mould during use
Block fast changeable, fabricated module finished product packing all transport to erecting bed in the form of standarized component, and finished productization is installed not
Material is carried out at the scene the processing such as to cut, it is ensured that the stabilization of product quality, the cleaning of construction site avoid construction site from building
The generation of building refuse has standardized production and advantage that is more quick, easily installing.
Description of the drawings
Fig. 1 is the structure chart of the present invention.
Fig. 2 is the structure chart of wallboard and wall frame cooperation installation of the present invention.
Fig. 3 is wall frame upper end of the present invention and the structure chart of wallboard cooperation installation.
Fig. 4 is the sectional view after present invention installation.
The toponym that each number designation is referred in attached drawing is as follows:1-wallboard, 2-wall frame, 3-installing plate, 4-
Sound insulation rock wool, 5-composite hanging part, 6-upper keel, 7-lower keel, 8-vertical keel, 9-horizontal square tube, 10-connector,
11-pendant hole, 12-hook, 13-riser, 14-transverse slat, 15-connecting hole, 16-bolt, 17-nut.
Specific embodiment
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings.
Embodiment 1
A kind of assembled protection wall and its installation method for bank, as shown in Figures 1 to 4, including polylith wallboard 1
With wall frame 2, wallboard 1 is located on wall frame 2 and is connected with wall frame 2, and wallboard 1 includes two pieces of 3 Hes of installing plate being arranged in parallel
The distance between the sound insulation rock wool 4 being located between installing plate 3, two pieces of installing plates 3 are 100mm, and sound insulation rock wool 4 is filled in installing plate
Between 3, wallboard 1 is equipped with composite hanging part 5, and wallboard 1 is connected by composite hanging part 5 with wall frame 2, and wall frame 2 is equipped with pendant
Hole 11, composite hanging part 5 are equipped with hook 12, and composite hanging part 5 12 is connected by hook with pendant hole 11, wallboard 1 be 800mm ×
The standard module of 600mm can produce finished product in batches, and the efficiency produced is fast at high speed, and installing plate 3 is the steel plate of 8mm thickness, can
To meet the demands for security such as shellproof bank, antiknock, antitheft.
Wall frame 2 includes upper keel 6 and lower keel 7, and the vertical dragon being vertically arranged is equipped between upper keel 6 and lower keel 7
Bone 8, vertical keel 8 are c-type keel, and vertical keel 8 is evenly distributed with spread configuration from left to right, and 8 vertical keel 8 of vertical keel is equipped with
The horizontal square tube 9 laterally set, horizontal square tube 9 and vertical keel 8 are connected by connector 10, and pendant hole 11 is located on vertical keel 8,
Composite hanging part 5 is connected by hook 12 with pendant hole 11, and vertical keel 8 and horizontal square tube 9 are cross-linked to form installing frame, wallboard 1
It is fitted to by composite hanging part 5 and pendant hole 11 in installing frame, after installing wall frame 2, wallboard 1, which is directly up hung, is
Can, installation speed is fast and dismountable moving, change are laid out.
Connector 10 includes riser 13 and is integral type knot with 13 vertically disposed transverse slat 14 of riser, riser 13 and transverse slat 14
Structure, transverse slat 14 and riser 13 are integrated riser 13 and are connected with vertical keel 8, and transverse slat 14 is connected with horizontal square tube 9, vertical keel 8
Upper end is equipped with connecting hole 15, and connecting hole 15 is kidney slot, facilitates alignment error when installing wallboard 1, wallboard 1 passes through bolt 16
It is connected with vertical keel 8, bolt 16 is connected through connecting hole 15, one end of bolt 16 with wallboard 1, and the other end of bolt 16 is set
There is the nut 17 being threadedly coupled with bolt 16, the efficient and speed of this technology installation is fast, can be dismantled from inside, repeat profit
With the module finished product packing of monoblock type all transports to erecting bed in the form of standarized component, material is not cut at the scene
Deng processing, secondary cleaning is avoided.
The installation method of a kind of assembled protection wall for bank, including following installation steps:(1) by upper keel 6
The lower section on roof is installed on by setscrew, lower keel 7 is mounted on by setscrew above bottom plate;
(2) vertical keel 8 is mounted on upper keel 6 and lower keel 7, the upper and lower ends of vertical keel 8 pass through fastening respectively
Bolt is connected with upper keel 6 and lower keel 7;
(3) between horizontal square tube 9 being located at vertical keel 8, the both ends of horizontal square tube 9 are solid by connector 10 and vertical keel 8
Fixed connection;
(4) wallboard 1 of 8 upper end of vertical keel by bolt 16 is passed through to the bolt hole on vertical keel 8, passes through nut 17
Wallboard 1 is fixedly mounted on vertical keel 8;
(5) wallboard 1 is hung on vertical keel 8 by remaining wallboard 1 by composite hanging part 5, and hook 12 is fastened on vertical
In pendant hole on keel 8;This wall body structure is simple, have standardized production with it is more quick, install it is easier, and can be from
Inside dismounting, recycling
In short, the foregoing is merely presently preferred embodiments of the present invention, all equalizations made according to scope of the present invention patent
Variation and modification should all belong to the covering scope of patent of the present invention.
Claims (5)
1. for the assembled protection wall of bank, it is characterised in that:Including polylith wallboard (1) and wall frame (2), wallboard (1)
It is located on wall frame (2) and is connected with wall frame (2), wallboard (1) includes two pieces of installing plates (3) being arranged in parallel and is located at installation
Sound insulation rock wool (4) between plate (3), sound insulation rock wool (4) are filled between installing plate (3), and wallboard (1) is equipped with composite hanging part
(5), wallboard (1) is connected by composite hanging part (5) with wall frame (2), and wall frame (2) is equipped with pendant hole (11), composite hanging part
(5) hook (12) is equipped with, composite hanging part (5) is connected by linking up with (12) with pendant hole (11).
2. the assembled protection wall according to claim 1 for bank, it is characterised in that:Wall frame (2) includes upper
Keel (6) and lower keel (7) are equipped with the vertical keel (8) being vertically arranged, vertical keel between upper keel (6) and lower keel (7)
(8) spread configuration is evenly distributed with from left to right, and vertical keel (8) vertical keel (8) is equipped with the horizontal square tube (9) laterally set, horizontal stroke side
(9) and vertical keel (8) is managed to connect by connector (10).
3. the assembled protection wall according to claim 2 for bank, it is characterised in that:Connector (10) includes perpendicular
It plate (13) and is an integral structure with riser (13) vertically disposed transverse slat (14), riser (13) and transverse slat (14), transverse slat (14)
Riser (13) is integrated with riser (13) to be connected with vertical keel (8), transverse slat (14) is connected with horizontal square tube (9).
4. the assembled protection wall according to claim 2 for bank, it is characterised in that:Vertical keel (8) it is upper
End is equipped with connecting hole (15), and wallboard (1) is connected by bolt (16) with vertical keel (8), and bolt (16) is through connection
Hole (15), one end of bolt (16) are connected with wallboard (1), and the other end of bolt (16) is equipped with the spiral shell being threadedly coupled with bolt (16)
Female (17).
5. a kind of installation method of assembled protection wall for bank, it is characterised in that:Including following installation steps:(1)
Upper keel (6) is installed on to the lower section on roof by setscrew, lower keel (7) is mounted on by setscrew above bottom plate;
(2) vertical keel (8) is mounted on upper keel (6) and lower keel (7), the upper and lower ends of vertical keel (8) pass through respectively
Fastening bolt is connected with upper keel (6) and lower keel (7);
(3) between horizontal square tube (9) being located at vertical keel (8), the both ends of horizontal square tube (9) pass through connector (10) and vertical keel
(8) it is fixedly connected;
(4) wallboard (1) of vertical keel (8) upper end by bolt (16) is passed through to the bolt hole on vertical keel (8), passes through spiral shell
Wallboard (1) is fixedly mounted on vertical keel (8) by female (17);
(5) wallboard (1) is hung on vertical keel (8) by remaining wallboard (1) by composite hanging part (5), and hook (12) fastens
In pendant hole on vertical keel (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711479094.5A CN108086539A (en) | 2017-12-29 | 2017-12-29 | A kind of assembled protection wall and its installation method for bank |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711479094.5A CN108086539A (en) | 2017-12-29 | 2017-12-29 | A kind of assembled protection wall and its installation method for bank |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108086539A true CN108086539A (en) | 2018-05-29 |
Family
ID=62180640
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711479094.5A Pending CN108086539A (en) | 2017-12-29 | 2017-12-29 | A kind of assembled protection wall and its installation method for bank |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108086539A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108871093A (en) * | 2018-07-20 | 2018-11-23 | 陈可晴 | A kind of shellproof wall of live-fire training |
CN110284631A (en) * | 2019-04-12 | 2019-09-27 | 深圳全景空间工业有限公司 | A kind of metope and its installation method |
CN114319767A (en) * | 2021-12-21 | 2022-04-12 | 日照大象房屋建设有限公司 | Peripheral revetment system of prefabricated building |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08326187A (en) * | 1996-06-17 | 1996-12-10 | Shimizu Corp | Intermediate post |
CN202706408U (en) * | 2012-07-23 | 2013-01-30 | 万利(中国)太阳能科技有限公司 | Ceramic plate hanger |
CN102926559A (en) * | 2012-11-29 | 2013-02-13 | 南京银豪系统工程有限公司 | Independent self-service bank |
CN103343574A (en) * | 2013-07-26 | 2013-10-09 | 山东莱钢建设有限公司 | Assembly type integrated house |
CN204139359U (en) * | 2014-09-26 | 2015-02-04 | 深圳中雅机电实业有限公司 | The syndeton of quickly dismantled acoustical board |
CN204401941U (en) * | 2015-01-08 | 2015-06-17 | 山东陶氏新材料有限公司 | A kind of decorative heat preservation fire prevention integrated wallboard |
CN204715588U (en) * | 2015-04-23 | 2015-10-21 | 天津金邦建材有限公司 | Novel curtain wall aluminum veneer |
CN204919387U (en) * | 2015-09-10 | 2015-12-30 | 上海众汇泡沫铝材有限公司 | Sound protective screen |
CN204940684U (en) * | 2015-06-25 | 2016-01-06 | 天津市建筑设计院 | A kind of novel combined wall board |
CN205776919U (en) * | 2016-06-07 | 2016-12-07 | 汉尔姆(杭州)家具有限公司 | The modularity partition wall being easily installed |
CN107401234A (en) * | 2017-08-15 | 2017-11-28 | 广东萨米特陶瓷有限公司 | The big plate curtain wall dried hanging structure of architectural pottery and its construction method |
-
2017
- 2017-12-29 CN CN201711479094.5A patent/CN108086539A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08326187A (en) * | 1996-06-17 | 1996-12-10 | Shimizu Corp | Intermediate post |
CN202706408U (en) * | 2012-07-23 | 2013-01-30 | 万利(中国)太阳能科技有限公司 | Ceramic plate hanger |
CN102926559A (en) * | 2012-11-29 | 2013-02-13 | 南京银豪系统工程有限公司 | Independent self-service bank |
CN103343574A (en) * | 2013-07-26 | 2013-10-09 | 山东莱钢建设有限公司 | Assembly type integrated house |
CN204139359U (en) * | 2014-09-26 | 2015-02-04 | 深圳中雅机电实业有限公司 | The syndeton of quickly dismantled acoustical board |
CN204401941U (en) * | 2015-01-08 | 2015-06-17 | 山东陶氏新材料有限公司 | A kind of decorative heat preservation fire prevention integrated wallboard |
CN204715588U (en) * | 2015-04-23 | 2015-10-21 | 天津金邦建材有限公司 | Novel curtain wall aluminum veneer |
CN204940684U (en) * | 2015-06-25 | 2016-01-06 | 天津市建筑设计院 | A kind of novel combined wall board |
CN204919387U (en) * | 2015-09-10 | 2015-12-30 | 上海众汇泡沫铝材有限公司 | Sound protective screen |
CN205776919U (en) * | 2016-06-07 | 2016-12-07 | 汉尔姆(杭州)家具有限公司 | The modularity partition wall being easily installed |
CN107401234A (en) * | 2017-08-15 | 2017-11-28 | 广东萨米特陶瓷有限公司 | The big plate curtain wall dried hanging structure of architectural pottery and its construction method |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108871093A (en) * | 2018-07-20 | 2018-11-23 | 陈可晴 | A kind of shellproof wall of live-fire training |
CN108871093B (en) * | 2018-07-20 | 2020-10-27 | 陈可晴 | Bullet-proof equipment for live ammunition training |
CN110284631A (en) * | 2019-04-12 | 2019-09-27 | 深圳全景空间工业有限公司 | A kind of metope and its installation method |
CN110284631B (en) * | 2019-04-12 | 2024-08-27 | 深圳全景空间工业有限公司 | Wall surface and installation method thereof |
CN114319767A (en) * | 2021-12-21 | 2022-04-12 | 日照大象房屋建设有限公司 | Peripheral revetment system of prefabricated building |
CN114319767B (en) * | 2021-12-21 | 2024-02-02 | 日照大象房屋建设有限公司 | Peripheral retaining wall system of assembled building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102216539B (en) | Unitised building system | |
CN109024993B (en) | Assembled concrete frame infilled wall structure system and construction method thereof | |
CN108086539A (en) | A kind of assembled protection wall and its installation method for bank | |
CN107806183A (en) | Modular architectural unit | |
CN108560725A (en) | A kind of container house column and panel wall system | |
CN206174138U (en) | Joint construction suitable for steel house room externally -hanging wallboard and major structure | |
CN108277917A (en) | A kind of sustainable full module-assembled building system of green and construction method | |
CN103485414A (en) | Prefabricated assembled type steel structure house building system and construction method thereof | |
CN102720268A (en) | Modularized steel structure unit construction | |
CN106193402B (en) | Girder truss integrated form flooring module and its installation method | |
CN109404010A (en) | A kind of aluminum tunnel modular system and its operating method | |
CN107246154A (en) | A kind of fast construction method in light steel house | |
CN111236470A (en) | Energy-saving and environment-friendly assembly type wall and assembly method thereof | |
CN110005069A (en) | Multilayer assembled modular house | |
CN207812748U (en) | Assembled protection wall for bank | |
CN205712585U (en) | Combination type integral wall | |
AU2018102135A4 (en) | Floor slab system | |
CN103628692A (en) | Floor beam mounting bracket and use and construction method thereof | |
CN2739288Y (en) | Mould for producing flyash cast-in-place integral hollow wallboard | |
CN207131976U (en) | One kind building electromechanical engineering screw suspension rod comprehensive support | |
CN104847038A (en) | Progressive collapse resistant cold-formed thin-walled profile combined wall and quick field mounting method thereof | |
CN103469892A (en) | Primary and secondary module unit combination structure of high-rise module building space and connection method thereof | |
CN106906905A (en) | A kind of steel construction board house of convenient disassembly | |
CN108999318B (en) | Unit curtain wall side buried single pendant structure, unit body with side buried single pendant and unit curtain wall mounting method | |
CN207277601U (en) | A kind of lightweight steel construction assembles the metope modular system of decoration integrated inner wall of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180529 |