CN108086144A CN201711271632.1A CN201711271632A CN108086144A CN 108086144 A CN108086144 A CN 108086144A CN 201711271632 A CN201711271632 A CN 201711271632A CN 108086144 A CN108086144 A CN 108086144A
Authority
CN
China
Prior art keywords
bridge
groove body
concrete
construction method
expansion joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711271632.1A
Other languages
Chinese (zh)
Inventor
胡海潮
芮宝东
张锐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING CCCC QIAOYU SCIENCE AND TECHNOLOGY Co Ltd
Original Assignee
BEIJING CCCC QIAOYU SCIENCE AND TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING CCCC QIAOYU SCIENCE AND TECHNOLOGY Co Ltd filed Critical BEIJING CCCC QIAOYU SCIENCE AND TECHNOLOGY Co Ltd
Priority to CN201711271632.1A priority Critical patent/CN108086144A/en
Publication of CN108086144A publication Critical patent/CN108086144A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of bridge shrinking cracks jumpings to prevent construction method, belong to bridge technology field, if the present invention paves and rolls condition by secondary excavation, pre-buried dried layer casing and using what fiber concrete filled etc. that techniques greatly improved concrete near expansion joint, it can guarantee its compactness, reduce height difference caused by vehicle effect secondary compaction;Also the tensile strength of the neighbouring concrete in expansion joint is strengthened, reduce the air shrinkage value of concrete, effectively improving expansion joint, nearby concrete cracking, drying shrinkage happen, and then are effectively improved bumping at bridge-head situation.

Description

A kind of bridge shrinking cracks jumping prevents construction method
Technical field
The present invention relates to a kind of bridge shrinking cracks jumpings to prevent construction method, belongs to bridge technology field.
Background technology
Extension joint refers to deformation around expansion joint, fracture or even pit slot, so as to influence the normal use of bridge, together When also influence traffic safety, speed, comfortable and its service life.For Extension joint, expansion joint jump how is effectively eliminated Vehicle or the minimum level that vehicle reduction will be jumped, it has also become urgent problem to be solved in bridge maintenance.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of bridge shrinking cracks jumping prevention construction method.
To achieve the above object, the present invention provides a kind of bridge shrinking cracks jumping prevention construction method, including following step Suddenly,
Step 1: milling bridge floor and cutting the expansion joint adjacent with bridge floor so that milling and the part cut form one A groove body, the expansion joint are located at the center of groove body;
Step 2: cleaning groove body cuts place, and so that groove body bottom is smooth in groove body bottom asphalt concrete layer;
Step 3: groove body surface and bituminous concrete surface smear epoxy resin in step 2;
If Step 4: presetting dried layer casing in groove body, every layer of described sleeve pipe includes several groups of casings along groove body length side To evenly distributed, every group of described sleeve pipe includes two casings being oppositely arranged along groove body width, and every group of described sleeve pipe is led to A slide-bar connection is crossed, the slide-bar is threaded through in two casings being oppositely arranged;
Step 5: fiber concrete is taken to fill groove body, and compacting so that the fiber concrete after compacting and bridge floor are neat repeatedly It is flat.
Preferably, the groove body depth in step 1 is 8-10cm.
Preferably, step 4 middle sleeve is provided with three layers.
Preferably, the interlamellar spacing of casing described in step 4 is identical.
Preferably, the tail end connection of casing described in step 3 is on the supporting plate, the support plate is fitted in the side of groove body On wall, the described sleeve pipe horizontal abutment of the bottom is on bituminous concrete.
The beneficial effects of the invention are as follows:The present invention by more than construction technology, to the secondary excavation of bridge floor and expansion joint with And filling is repaired, and by service sleeve and slide-bar and fiberfill fibers concrete, greatly improved expansion joint concrete nearby Pave and roll condition, can guarantee its compactness, reduce height difference caused by vehicle effect secondary compaction, and then be effectively improved bridge Head jump vehicle situation;By service sleeve and slide-bar and fiberfill fibers concrete, the anti-of the neighbouring concrete in expansion joint is also strengthened Tensile strength reduces the air shrinkage value of concrete, and effectively improving expansion joint, nearby concrete cracking, drying shrinkage happen, into And it is effectively improved bumping at bridge-head situation.
Description of the drawings
Fig. 1 is bridge expanssion joint prototype structure figure;
Fig. 2 is structure chart after bridge expanssion joint nearby excavates;
Fig. 3 is structure chart after bridge expanssion joint is nearby filled;
Specific embodiment
With reference to embodiment, the invention will be further described:
A kind of bridge shrinking cracks jumping prevention construction method includes following steps:
Step 1: milling bridge floor and cutting the expansion joint 7 adjacent with bridge floor so that milling and the part cut form one A groove body 1, the expansion joint 7 are located at the center of groove body 1, and 1 depth of groove body is 8-10cm.;
Step 2: cleaning groove body 1 cuts place, and in 2 layers of 1 bottom asphalt concrete of groove body so that 1 bottom of groove body It is smooth;
Step 3: the 2 surface smear epoxy resin of 1 surface of groove body and bituminous concrete in step 2;
Step 4: being preset with three layers of casing 3 in groove body 1, the interlamellar spacing of every layer of casing is identical, and every layer of described sleeve pipe 3 is wrapped It is evenly distributed along 1 length direction of groove body to include several groups of casings 3, every group of described sleeve pipe 3 includes setting along groove body width is opposite Two casings put, every group of described sleeve pipe 3 are connected by a slide-bar 4, and the slide-bar 4 is threaded through two casings being oppositely arranged It is interior;The tail end of its middle sleeve 3 is connected in support plate 6, and the support plate 6 is fitted on the side wall of groove body 1, the bottom it is described 3 horizontal abutment of casing is on bituminous concrete 2.
Step 5: fiber concrete 5 is taken to fill groove body 1, and compacting causes the fiber concrete 5 and bridge floor after compacting repeatedly It flushes.
The preferred embodiment of the present invention described in detail above.It should be appreciated that those of ordinary skill in the art without Creative work is needed according to the present invention can to conceive and makes many modifications and variations.Therefore, all technologies in the art Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Technical solution, all should be in the protection domain being defined in the patent claims.

Claims (5)

1. a kind of bridge shrinking cracks jumping prevents construction method, it is characterised in that comprises the following steps:
Step 1: milling bridge floor and cutting the expansion joint adjacent with bridge floor so that milling and the part cut form a slot Body, the expansion joint are located at the center of groove body;
Step 2: cleaning groove body cuts place, and so that groove body bottom is smooth in groove body bottom asphalt concrete layer;
Step 3: groove body surface and bituminous concrete surface smear epoxy resin in step 2;
If Step 4: presetting dried layer casing in groove body, it is equal along groove body length direction that every layer of described sleeve pipe includes several groups of casings Even arrangement, every group of described sleeve pipe include two casings being oppositely arranged along groove body width, and every group of described sleeve pipe passes through one Root slide-bar connects, and the slide-bar is threaded through in two casings being oppositely arranged;
Step 5: fiber concrete is taken to fill groove body, and compacting causes the fiber concrete after compacting to be flushed with bridge floor repeatedly.
2. a kind of bridge shrinking cracks jumping prevention construction method as described in claim 1, it is characterised in that:Slot in step 1 Body depth is 8-10cm.
3. a kind of bridge shrinking cracks jumping prevention construction method as described in claim 1, it is characterised in that:Step 4 middle sleeve It is provided with three layers.
4. a kind of bridge shrinking cracks jumping prevention construction method as described in claim 1, it is characterised in that:Described in step 4 The interlamellar spacing of casing is identical.
5. a kind of bridge shrinking cracks jumping prevention construction method as described in claim 1, it is characterised in that:Described in step 4 On the supporting plate, the support plate is fitted on the side wall of groove body for the tail end connection of casing, the horizontal patch of described sleeve pipe of the bottom It closes on bituminous concrete.
CN201711271632.1A 2017-12-05 2017-12-05 A kind of bridge shrinking cracks jumping prevents construction method Pending CN108086144A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711271632.1A CN108086144A (en) 2017-12-05 2017-12-05 A kind of bridge shrinking cracks jumping prevents construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711271632.1A CN108086144A (en) 2017-12-05 2017-12-05 A kind of bridge shrinking cracks jumping prevents construction method

Publications (1)

Publication Number Publication Date
CN108086144A true CN108086144A (en) 2018-05-29

Family

ID=62173857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711271632.1A Pending CN108086144A (en) 2017-12-05 2017-12-05 A kind of bridge shrinking cracks jumping prevents construction method

Country Status (1)

Country Link
CN (1) CN108086144A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842605A (en) * 2018-07-09 2018-11-20 贵州新联爆破工程集团有限公司 A kind of simply supported girder bridge expansion gap device
CN111118971A (en) * 2020-01-17 2020-05-08 中铁二院工程集团有限责任公司 End socket expansion device of roadbed pile plate structure and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01322003A (en) * 1988-06-24 1989-12-27 Nippon Telegr & Teleph Corp <Ntt> Mending pipe for splice pipe of bridge
RU2267573C1 (en) * 2004-04-20 2006-01-10 Общество с ограниченной ответственностью "РУССЕРБМОСТ" Control joint for highway bridge
CN202543762U (en) * 2012-02-10 2012-11-21 成都市新筑路桥机械股份有限公司 Jointless elastomer expansion device
CN103205922A (en) * 2013-05-06 2013-07-17 成都市新筑路桥机械股份有限公司 Stable element for seamless elastomer extension device
CN204039908U (en) * 2014-06-05 2014-12-24 青岛海力威新材料科技股份有限公司 Bridge expanssion joint end liner support nail and bridge
CN104612018A (en) * 2014-12-25 2015-05-13 东南大学 Dowel bar with combined structure for cement concrete pavements and durable stitch contracting structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01322003A (en) * 1988-06-24 1989-12-27 Nippon Telegr & Teleph Corp <Ntt> Mending pipe for splice pipe of bridge
RU2267573C1 (en) * 2004-04-20 2006-01-10 Общество с ограниченной ответственностью "РУССЕРБМОСТ" Control joint for highway bridge
CN202543762U (en) * 2012-02-10 2012-11-21 成都市新筑路桥机械股份有限公司 Jointless elastomer expansion device
CN103205922A (en) * 2013-05-06 2013-07-17 成都市新筑路桥机械股份有限公司 Stable element for seamless elastomer extension device
CN204039908U (en) * 2014-06-05 2014-12-24 青岛海力威新材料科技股份有限公司 Bridge expanssion joint end liner support nail and bridge
CN104612018A (en) * 2014-12-25 2015-05-13 东南大学 Dowel bar with combined structure for cement concrete pavements and durable stitch contracting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842605A (en) * 2018-07-09 2018-11-20 贵州新联爆破工程集团有限公司 A kind of simply supported girder bridge expansion gap device
CN111118971A (en) * 2020-01-17 2020-05-08 中铁二院工程集团有限责任公司 End socket expansion device of roadbed pile plate structure and construction method

Similar Documents

Publication Publication Date Title
CN108086061B (en) Limiting structure of ballastless track
CN104480868B (en) On tear beam method open across the highway bridge of railway in operation
CN104060631B (en) A kind of manhole mouth elevation Dynamic controlling structure
CN108086144A (en) A kind of bridge shrinking cracks jumping prevents construction method
WO2016138776A1 (en) Lowly disposed line structure used in medium-low speed magnetic levitation traffic engineering fill section
CN105755954A (en) Construction technology of interchange type bare concrete anti-collision guardrails
CN103485281A (en) Construction method of assembly-type external transverse prestressed hollow plate bridge
CN106869145A (en) Rapid rush-repair method for local collapse of highway embankment based on waste tires
CN210194361U (en) Splicing structure for widening new and old roadbeds on road
CN103741597B (en) A kind of without transition section concrete bridge expansion joint installation and mounting method thereof
CN106088757B (en) A kind of construction method for ring beam in the middle part of ultra-large silo and top barrel
CN106320192A (en) Beam section replacement reinforcement method for large-span concrete continuous beam bridge
CN203768800U (en) Non-transition-section concrete bridge expansion joint device
CN205741814U (en) A kind of asphalt pavement structure
CN203559345U (en) Non-concrete bridge expansion joint device
CN210599103U (en) Satisfy high environmental requirement&#39;s tunnel separation escape canal of decontaminating
CN210507176U (en) Road and bridge crack reinforced structure
CN207032320U (en) For subway station main body and the waterproof construction of accessory structure seam crossing
CN213836694U (en) Slope protection device for building engineering
CN205444258U (en) Highway subtracts vibration isolation integrated configuration in succession
CN107740353A (en) The longitudinal spliced structure of highway hollow slab girder and joining method
CN210238373U (en) Guardrail stand rising structure
CN211815445U (en) Road and bridge crack reinforced structure
CN209975293U (en) Road bridge road bed reinforced structure
CN203878968U (en) Connecting structure between scaffold and main body structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180529