CN108035251B - High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device - Google Patents

High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device Download PDF

Info

Publication number
CN108035251B
CN108035251B CN201711235434.XA CN201711235434A CN108035251B CN 108035251 B CN108035251 B CN 108035251B CN 201711235434 A CN201711235434 A CN 201711235434A CN 108035251 B CN108035251 B CN 108035251B
Authority
CN
China
Prior art keywords
shield
reinforcement cage
steel reinforcement
concrete
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711235434.XA
Other languages
Chinese (zh)
Other versions
CN108035251A (en
Inventor
邓利平
许涛
冉华
杨华超
杨波
陈胜兵
袁大鹏
张骏程
蒋健
刘凌龙
郭伟
王昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201711235434.XA priority Critical patent/CN108035251B/en
Publication of CN108035251A publication Critical patent/CN108035251A/en
Application granted granted Critical
Publication of CN108035251B publication Critical patent/CN108035251B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of high-speed railway bridge floor shields without gasket prefabricated construction engineering method, it includes the following steps: step 1: the entering of reinforcing steel bar: step 2: steel reinforcement cage is made in steel bar meter: step 3: steel reinforcement cage enters mould;Step 4: installation of embedded parts;Step 5: concreting;Step 6: plastering.The present invention prepares bridge floor shield by way of making steel reinforcement cage, and manufactured shield quality is preferable, meets technique requirement, and since the globality and ease for use that are provided with built-in fitting, shield are all greatly improved.

Description

High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device
Technical field
This engineering method is suitable for the prefabricated field of all kinds of small precast parts of railway engineering, municipal works and house construction engineering, especially It is related to high-speed railway bridge floor shield without gasket prefabricated construction engineering method and device.
Background technique
With the fast development of China express railway, the requirement to high iron formation standard is also continuously improved, especially to height Fast railway deck system associated satellite component, for example more stringent requirements are proposed for shield manufacturing process.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of high-speed railway bridge floors for meeting technique requirement Shield is without gasket prefabricated construction engineering method and device.
The purpose of the present invention is achieved through the following technical solutions: high-speed railway bridge floor shield is without gasket prefabricated construction Engineering method, it includes the following steps:
Step 1: the entering of reinforcing steel bar;
Step 2: steel reinforcement cage is made in steel bar meter;
Step 3: steel reinforcement cage enters mould;
Step 4: installation of embedded parts;
Step 5: concreting;
Step 6: plastering.
It is preferred that this method or engineering method further include following steps:
Step 7: concrete plucking;
Step 8: curing in the mold;
Step 9: demoulding operating;
Step 10: spray maintenance;
Step 11: pile storage.
It is preferred that the entering of reinforcing steel bar: notifying testing crew to sample inspection after the entering of reinforcing steel bar in time, with Times supervisor Member's witness, raw material of reinforcement rebar can use after the assay was approved;
Steel bar meter: setting-out is carried out to various specifications reinforcing bar according to design drawing, is carried out by Lofting Calculation reinforcing bar length Blanking reinforcing bar is pressed design drawing bending forming, the reinforcing bar of bending forming is placed on the enterprising binding of welding tooling, handed over by cross by blanking Fork binding, gas shield welding welding, forbids iron wire head to stretch in concrete;
Steel reinforcement cage enters mould: the shield steel reinforcement cage of binding forming being put into assembled mold, if used before Mold needs to wait for reusing after release agent is dry;Steel reinforcement cage will be put down gently when being put into mold, forbid to collide mold;Embedded iron parts are fixed It is good, exempt from cushion block tooling fixture or bracket for steel reinforcement cage from 30~39mm of mold bottom with special, it is ensured that concrete protective thickness Degree;By exempting from cushion block tooling fixture or bracket spacer bar cage, guarantee steel reinforcement cage and mold bottom keep certain distance, this Behave still belongs to the first time, and traditional steel reinforcement cage needs to place cushion block in mold bottom before entering mould, increases construction cost, and this sets The support rack type tooling of meter, both ensure that the precise positioning of steel reinforcement cage, and can reduce construction cost, be to kill two birds with one stone.Bracket Be it is reusable, can reach reduction expenditure, the effect of save the cost.
Installation of embedded parts: after steel reinforcement cage installs, should also fix built-in fitting, and U-shaped pre-embedded bolt is inserted into steel reinforcement cage first Corresponding position and screw on nut, nut is twisted in correct position, U-shaped pre-embedded bolt is pierced into pre-embedded steel slab after being twisted by nut In hole, and pre-embedded steel slab and 4 nuts are tightened, is finally adjacent to pre-embedded steel slab and template, it is necessary to assure railing shield is pre-buried Bolt is higher by 50mm;Sound barrier shield pre-embedded bolt is higher by 80mm;
Concreting: including secondary vibration moulding process;
Plastering: a daubing, quadric-plastering moulding process: carrying out first time daubing after the completion of making firm by ramming for the first time, the Secondary make firm by ramming carries out primary essence plastering after the completion, carries out one-coat plastering again before pre-hardening, cap locations are opened before initial set, secondary to smear Face molding;
Concrete plucking: hair pulling treatment is carried out after concrete initial set in time;
Curing in the mold: it is conserved after the prefabricated initial set of shield, covers geotextiles when maintenance above shield, it is ensured that comprehensive to support Shield;
Demoulding transhipment: curing at moisture-retention and heat-insulation is carried out to concrete after pouring completion and plucking;
Spray maintenance: being transported to spray maintenance area after shield demoulding, shield puts underlay flitch, upper cover non-woven fabrics, spray When ensure 360 ° of shield maintenance without dead angle;
Pile storage: after concrete reaches regulation curing time, being transported to finished product pile field, and stacking of classifying, and Perform mark.
It is preferred that steel bar meter: using full-automatic numerical control stirrup bender, carry out straightening, scale, curved to reinforcing bar Hoop, cutting, greatly improved production work efficiency, it is ensured that product standard is unified.A new generation that full-automatic reinforcing bar hoop bender uses " surmounts No. 5 " type, each model round steel, the spiral of 6mm~12mm diameter can be processed;
The binding of shield steel reinforcement cage carries out scale positioning using shield steel reinforcement cage welding tooling;
Shield steel reinforcement cage binds the form combined with tied silk using welding, and welding uses carbon dioxide gas arc welding. Carbon dioxide gas arc welding is easy to operate, arc stability, welding quality is good, forming is beautiful, weldment deformation is small, postwelding is not required to clearly Slag can be effectively protected main reinforcement and not be soldered damage.
It is preferred that concreting:
1 concrete transports to small-sized prefabricated member factory, and concrete fills vehicle action of forced stirring 1 minute, keeps the concrete for filling vehicle uniform;
After 2 concrete fill vehicle stirring 1 minute, testing crew is surveyed the slump of concrete and can be poured after the slump is qualified It builds;Concrete curing test block processed simultaneously;
Check whether shield demoulding agent of mould is brushed uniformly before 3 concretings, whether built-in fitting, steel reinforcement cage installation are firm Gu whether position is accurate;
4 shield steel reinforcement cage displacements in order to prevent, are fixed framework of steel reinforcement using steel bar spacer bracket before making firm by ramming;Bracket Necessary fixation, quantity is enough, ensures to need each steel reinforcement cage of each prefabricated shield to have bracket before construction;Pad The taking-up when making firm by ramming for the second time of block bracket;
5 first times made firm by ramming, by coagulation poured into shield, were vibrated with 40mm immersion vibrator, spacing of vibrating 200mm It is uniformly, fast to insert slow pumping, a vibration point 20 seconds to 30 seconds, 6~7 vibration points of every block of shield to 300mm;Vibrating head is forbidden to contact template, Guarantee from template spacing 50mm;
6 make firm by ramming for second, and make time interval firm by ramming for the first time 10 minutes, are vibrated, are shaken with 30mm plug-in type vibrating stick Spacing 200mm to 300mm is smash, it is uniformly, fast to insert slow pumping, each vibration point 20 seconds to 30 seconds, 6~7 vibration points of every block of shield;Vibrating head From end template top 50mm to 100mm;Pass through the case where can be effectively solved bubble, pitted skin of vibrating twice.
It is preferred that plucking: the plucking time is 1 hour to 2 after the completion of concreting according to weather temperature conditions Hour, it is smooth to concrete surface progress, plucking is carried out after smooth, plucking uses special wire brush plucking, kerve depth 2mm, width 1mm, spacing 5mm guarantee that lines is uniform within the scope of plucking, and clear, neat, depth meets the requirements.
It is preferred that curing in the mold: shield curing in the mold system includes water pump, water supplying pipe and switch, spray head, support Quarter bend, gutter are conserved after the prefabricated initial set of shield, cover geotextiles, setting above each shield when maintenance above shield One spray head, it is ensured that comprehensive maintenance;
Moisturizing is carried out during curing in the mold, concrete component reaches 2.5MPa or more, and its surface and corner angle are not because of demoulding And when damaging, i.e., component is transported to maintenance area's automatic sprinkler fire-extinguishing system after demoulding and non-textile mulch is added to support by dismountable mold Shield;
It is preferred that spray maintenance: being transported to spray maintenance area using fork truck after shield demoulding, curing system includes High-pressure hydraulic pump, world spray head, water supplying pipe, time switch composition, spray interval time are set as 1 hour, and spray continues 5 points Clock, and adjusted at any time according to weather condition;World spray head works at the same time when spray system works, it is ensured that 360 ° of maintenances of shield are without dead Angle, spray-water use water circulation system, and maintenance is imported in sedimentation basin by ditch with water and is recycled, economical environment-protective;
It is preferred that pile is stored: shield being transported to finished product pile field, shield stacking form and finished product with fork truck Protection:
2 10cm*10cm flitches of underlay when 1 shield pile pile, stacking height is determining according to forklift lifting height, generally 6 layers of pile;
2 pile regions are separately provided, and separate with other regions, prevent other vehicle collisions from damaging shield;
3 pile regions setting mark.
For high-speed railway bridge floor shield without gasket prefabricated construction device, it includes welding tooling, bracket and mold;
Welding tooling includes steel reinforcement cage support, first crossbeam, second cross beam, the 4th crossbeam and the 5th crossbeam, steel reinforcement cage branch Support includes vertical supporting and cross-brace, and vertical supporting is connected into an entirety by cross-brace;
First crossbeam, second cross beam, the 4th crossbeam and the setting of the 5th crossbeam are in steel reinforcement cage support, wherein first crossbeam The side of steel reinforcement cage support is set with second cross beam, the other side of steel reinforcement cage support is arranged in the 4th crossbeam and the 5th crossbeam, Finite place piece is set on first crossbeam;
The mold includes bottom plate, backboard, end plate, cover board and baffle, and the end plate includes left side plate and right end plate;
Backboard, left side plate and right end plate are hinged with bottom plate respectively;
Baffle is bolted with left side plate, and baffle is connect by bolt with right end plate;
Cover board is arranged on end plate;
The bottom plate both ends are pasted with sealing strip, and sealing strip is posted at the backboard both ends;
The bracket includes bottom positioning plate and altitude location part, and altitude location part is fixed with bottom positioning plate.
It is preferred that sequence from top to bottom is followed successively by second cross beam, the 4th crossbeam, the 5th in spatial position Crossbeam and first crossbeam.
It is preferred that wherein second cross beam, third crossbeam and the 4th crossbeam are located at the invention also includes third crossbeam In same level, second cross beam is successively up the 4th crossbeam and first crossbeam.
It is preferred that locating part is Y shape or V-arrangement, for limiting the position of reinforcing bar.
It is preferred that being provided with several locating parts on first crossbeam, the lower section of each locating part is in second cross beam Corresponding position setting it is fluted;
Groove corresponding with locating part position is also equipped on the 5th crossbeam and the 4th crossbeam.
It is preferred that being arranged at third crossbeam position corresponding with locating part fluted.
It is preferred that first crossbeam is detachably connected with steel reinforcement cage support.First crossbeam can be placed directly in steel reinforcement cage In support or first crossbeam is bolted with steel reinforcement cage support.Preferably, first crossbeam is made of angle steel.
It is preferred that vertical supporting and cross-brace are detachably connected, for example it is bolted or passes through method Blue disk connection.
It is made it is preferred that vertical supporting and cross-brace are all made of angle steel, passes through bolt between angle steel and angle steel Connection.Altitude location part and bottom positioning plate are integrally formed or weld.
It is preferred that a bracket is placed at the both ends of mold respectively, a bracket include a bottom positioning plate and Two altitude location parts, altitude location part are welded on the positioning plate of bottom.
It is preferred that the end of bottom positioning plate is provided with limiting section, between limiting section and bottom positioning plate middle part Form a U-lag.
It is preferred that altitude location part is L shape angle steel, bottom positioning plate is plain plate, and L shape angle steel is welded on flat steel On plate.
It is preferred that the end plate is L shape, baffle is vertically placed on the first order step of end plate and passes through spiral shell Bolt is fixed with end plate;Cover board is placed across on the first order step of end plate and is fixed by bolt and end plate;After mold installation, The top surface of end plate, backboard and baffle is on the same horizontal plane.
It is preferred that entire mold is L-shaped, it is provided with supporting plate on bottom plate, is all provided in backboard, left side plate and right end plate It is equipped with the rotation section with supporting plate cooperation, aperture on rotation section, rotation section is connect with supporting plate by pin shaft;Each rotation section with two Supporting plate is used cooperatively, and rotation section is arranged between two supporting plates, and two supporting plates include the first supporting plate and the second supporting plate, and pin shaft is successively Three is connected across the first supporting plate, rotation section and the second supporting plate.
It is preferred that the aperture of pin shaft front end is fixed after pin shaft passes through supporting plate and rotation section by split pin.
It is preferred that rotation section is a plate, plate is fixed with backboard or left side plate or right end plate;
Rotation section and backboard are welded or are integrally formed;
Rotation section and left side plate are welded or are integrally formed;
Rotation section and right end plate are welded or are integrally formed.
It is preferred that being provided with arcuate projection on bottom plate.
The beneficial effects of the present invention are: prepare bridge floor shield by way of making steel reinforcement cage, manufactured shield quality compared with It is good, meet technique requirement, and since the globality and ease for use that are provided with built-in fitting, shield are all greatly improved.
Detailed description of the invention
Fig. 1 is one of schematic structural view of the invention;
Fig. 2 is the two of schematic structural view of the invention;
Fig. 3 is the three of schematic structural view of the invention;
Fig. 4 is the four of schematic structural view of the invention;
Fig. 5 is reinforcement cage structure schematic diagram;
Fig. 6 is steel reinforcement cage partial structural diagram;
Fig. 7 is one of shield structure schematic diagram;
Fig. 8 is the two of shield structure schematic diagram;
Fig. 9 is one of the structural schematic diagram of pre-embedded steel slab;
Figure 10 is the second structural representation of pre-embedded steel slab;
Figure 11 is the structural schematic diagram of pre-embedded bolt;
Figure 12 is the structural schematic diagram of welding tooling;
Figure 13 is this engineering method flow diagram;
In figure, 1- end plate, 2- sealing strip, 3- backboard, 4- embedded hole, 5- bottom plate, 6- cover board, 7- slot, 8- shield, 9- Built-in fitting, 9.1- pre-embedded steel slab, 9.2- pre-embedded bolt, 10- mould support, 11- baffle, 12- bracket, 13- steel reinforcement cage, 13.1- Jiong shape reinforcing bar, 13.2- transverse direction fixed steel bars, 13.3-6 font reinforcing bar, 13.4- longitudinal reinforcement, the support of 14- steel reinforcement cage, 15- first Crossbeam, 16- locating part, 17- second cross beam, 18- third crossbeam, the 4th crossbeam of 19-, the 5th crossbeam of 20-, 21- groove.
Specific embodiment
Technical solution of the present invention is described in further detail with reference to the accompanying drawing, but protection scope of the present invention is not limited to It is as described below.
As shown in Figure 1, high-speed railway bridge floor shield is without gasket prefabricated construction engineering method, it includes the following steps:
Step 1: the entering of reinforcing steel bar;
Step 2: steel reinforcement cage 13 is made in steel bar meter;
Step 3: steel reinforcement cage 13 enters mould;
Step 4: installation of embedded parts;
Step 5: concreting;
Step 6: plastering.
In a preferred embodiment, as shown in figure 13, this method or engineering method further include following steps:
Step 7: concrete plucking;
Step 8: curing in the mold;
Step 9: demoulding operating;
Step 10: spray maintenance;
Step 11: pile storage.
In a preferred embodiment, the entering of reinforcing steel bar: testing crew is notified to sample inspection, same Times after the entering of reinforcing steel bar in time Supervisor's witness, raw material of reinforcement rebar can use after the assay was approved;
Steel bar meter: setting-out is carried out to various specifications reinforcing bar according to design drawing, is carried out by Lofting Calculation reinforcing bar length Blanking reinforcing bar is pressed design drawing bending forming, the reinforcing bar of bending forming is placed on the enterprising binding of welding tooling, handed over by cross by blanking Fork binding, gas shield welding welding, forbids iron wire head to stretch in concrete;
Steel reinforcement cage 13 enters mould: the shield steel reinforcement cage 13 of binding forming being put into assembled mold, if used before The mold crossed needs to wait for reusing after release agent is dry;Steel reinforcement cage 13 will be put down gently when being put into mold, forbid to collide mold;Embedded iron Part fixes, and exempts from cushion block tooling fixture (i.e. bracket 12) for steel reinforcement cage 13 from 30~39mm of mold bottom with special, it is ensured that coagulation Protective soil layer thickness;
Installation of embedded parts: after steel reinforcement cage 13 installs, should also fix built-in fitting, and U-shaped pre-embedded bolt is inserted into reinforcing bar first Nut is simultaneously screwed in the corresponding position of cage 13, nut is twisted in correct position, nut pierces into U-shaped pre-embedded bolt after being twisted pre-buried In steel plate hole, and pre-embedded steel slab and 4 nuts are tightened, is finally adjacent to pre-embedded steel slab and template, it is necessary to assure railing shield Pre-embedded bolt is higher by 50mm;Sound barrier shield pre-embedded bolt is higher by 80mm;
Concreting: including secondary vibration moulding process;
Plastering: a daubing, quadric-plastering moulding process: carrying out first time daubing after the completion of making firm by ramming for the first time, the Secondary make firm by ramming carries out primary essence plastering after the completion, carries out one-coat plastering again before pre-hardening, cap locations are opened before initial set, secondary to smear Face molding;
Concrete plucking: hair pulling treatment is carried out after concrete initial set in time;
Curing in the mold: it is conserved after the prefabricated initial set of shield, covers geotextiles when maintenance above shield, it is ensured that comprehensive to support Shield;
Demoulding transhipment: curing at moisture-retention and heat-insulation is carried out to concrete after pouring completion and plucking;
Spray maintenance: being transported to spray maintenance area after shield demoulding, shield puts underlay flitch, upper cover non-woven fabrics, spray When ensure 360 ° of shield maintenance without dead angle;
Pile storage: after concrete reaches regulation curing time, being transported to finished product pile field, and stacking of classifying, and Perform mark.
In a preferred embodiment, steel bar meter: use full-automatic numerical control stirrup bender, to reinforcing bar carry out straightening, Production work efficiency greatly improved in scale, bending hoop, cutting, it is ensured that product standard is unified.New the one of full-automatic reinforcing bar hoop bender use Generation " surmounting No. 5 " type, can process each model round steel, the spiral of 6mm~12mm diameter;
The binding of shield steel reinforcement cage 13 carries out scale positioning using 13 welding tooling of shield steel reinforcement cage;
Shield steel reinforcement cage 13 binds the form combined with tied silk using welding, and welding is using CO 2 gas-shielded Weldering.Carbon dioxide gas arc welding is easy to operate, arc stability, welding quality is good, forming is beautiful, weldment deforms small, postwelding not Scarfing cinder is needed, main reinforcement can be effectively protected and be not soldered damage.
In a preferred embodiment, concreting:
1 concrete transports to small-sized prefabricated member factory, and concrete fills vehicle action of forced stirring 1 minute, keeps the concrete for filling vehicle uniform;
After 2 concrete fill vehicle stirring 1 minute, testing crew is surveyed the slump of concrete and can be poured after the slump is qualified It builds;Concrete curing test block processed simultaneously;
Check whether shield demoulding agent of mould is brushed uniformly before 3 concretings, whether built-in fitting, the installation of steel reinforcement cage 13 are firm Gu whether position is accurate;
4 displacements of shield steel reinforcement cage 13 in order to prevent, are fixed framework of steel reinforcement using steel bar spacer bracket before making firm by ramming;Pad The necessary fixation of block bracket, quantity is enough, ensures to need each steel reinforcement cage 13 of each prefabricated shield equal before construction There is cushion block bracket;The taking-up when making firm by ramming for the second time of cushion block bracket;
5 first times made firm by ramming, by coagulation poured into shield, were vibrated with 40mm immersion vibrator, spacing of vibrating 200mm It is uniformly, fast to insert slow pumping, a vibration point 20 seconds to 30 seconds, 6~7 vibration points of every block of shield to 300mm;Vibrating head is forbidden to contact template, Guarantee from template spacing 50mm;
6 make firm by ramming for second, and make time interval firm by ramming for the first time 10 minutes, are vibrated, are shaken with 30mm plug-in type vibrating stick Spacing 200mm to 300mm is smash, it is uniformly, fast to insert slow pumping, each vibration point 20 seconds to 30 seconds, 6~7 vibration points of every block of shield;Vibrating head From end template top 50mm to 100mm;Pass through the case where can be effectively solved bubble, pitted skin of vibrating twice.
In a preferred embodiment, plucking: the plucking time is 1 after the completion of concreting according to weather temperature conditions Hour is smooth to concrete surface progress to 2 hours, and plucking is carried out after smooth, and plucking uses special wire brush plucking, kerve depth 2mm, width 1mm, spacing 5mm guarantee that lines is uniform within the scope of plucking, and clear, neat, depth meets the requirements.
In a preferred embodiment, curing in the mold: shield curing in the mold system includes water pump, water supplying pipe and switch, spray Head, support quarter bend, gutter are conserved after the prefabricated initial set of shield, cover geotextiles when maintenance above shield, on each shield One spray head of side's setting, it is ensured that comprehensive maintenance;
Moisturizing is carried out during curing in the mold, concrete component reaches 2.5MPa or more, and its surface and corner angle are not because of demoulding And when damaging, i.e., component is transported to maintenance area's automatic sprinkler fire-extinguishing system after demoulding and non-textile mulch is added to support by dismountable mold Shield;
In a preferred embodiment, spray maintenance area, maintenance system spray maintenance: are transported to using fork truck after shield demoulding Uniting includes high-pressure hydraulic pump, world spray head, water supplying pipe, and time switch composition, spray interval time is set as 1 hour, and spray is held It is 5 minutes continuous, and adjusted at any time according to weather condition;World spray head works at the same time when spray system works, it is ensured that 360 ° of shield are supported For shield without dead angle, spray-water uses water circulation system, and maintenance is imported in sedimentation basin by ditch with water and is recycled, and ring is saved It protects;
In a preferred embodiment, pile is stored: shield being transported to finished product pile field, shield stacking form with fork truck And finished product protection:
2 10cm*10cm flitches of underlay when 1 shield pile pile, stacking height is determining according to forklift lifting height, generally 6 layers of pile;
2 pile regions are separately provided, and separate with other regions, prevent other vehicle collisions from damaging shield;
3 pile regions setting mark.
In a preferred embodiment, engineering method further includes checking procedure, project and processing mode such as Figure 13 of required inspection It is shown, specifically:
The entering of reinforcing steel bar needs, if unqualified, to carry out processing of withdrawing from the arena by examining;
After steel reinforcement cage is made in Steel Reinforcing Bar Material, welding, binding, inspection of applying for checking and examination is carried out, it is qualified then steel reinforcement cage enters mould, do not conform to Lattice are welded again or are bound;
Built-in fitting needs to test after marching into the arena, disqualified upon inspection, carries out processing of withdrawing from the arena, and carries out again after the assay was approved pre-buried Part installation;
It needs to check concrete quality before concreting, passed examination carries out concreting again;
After pile storage, if necessary to shield, need to test to shield before appearance, qualified shield can go out , underproof shield carries out scrapping processing.
Traditional high-speed railway bridge floor shield 8 as shown in Figure 7 and Figure 8, during production, by will tie up in advance or The steel reinforcement cage 13 (as shown in Figure 5 and Figure 6) that person is welded is placed in mold, refills concrete realization.Steel reinforcement cage 13 needs A part of reinforcing bar is exposed outside, therefore steel reinforcement cage 13 includes preburying part and exposed portion, and exposed portion is U-shaped reinforcing bar.More specifically, Steel reinforcement cage 13 includes Jiong shape reinforcing bar 13.1, lateral fixed steel bars 13.2, figure-six reinforcing bar 13.3 and longitudinal reinforcement 13.4, laterally solid Determine reinforcing bar 13.2 and fixes Jiong shape reinforcing bar 13.1, figure-six reinforcing bar 13.3 and longitudinal reinforcement 13.4 respectively.
As shown in FIG. 1 to FIG. 4 and Figure 12, for high-speed railway bridge floor shield without gasket prefabricated construction device, it includes welding Tooling, bracket 12 and mold;
Welding tooling includes steel reinforcement cage support 14, first crossbeam 15, second cross beam 17, the 4th crossbeam 19 and the 5th crossbeam 20, steel reinforcement cage support 14 includes vertical supporting and cross-brace, and vertical supporting is connected into an entirety by cross-brace;
First crossbeam 15, second cross beam 17, the 4th crossbeam 19 and the setting of the 5th crossbeam 20 support on 14 in steel reinforcement cage, In, the side that steel reinforcement cage supports 14, the 4th crossbeam 19 and the setting of the 5th crossbeam 20 is arranged in first crossbeam 15 and second cross beam 17 In the other side of steel reinforcement cage support 14, finite place piece 16 is set on first crossbeam 15;
The mold includes bottom plate 5, backboard 3, end plate 1, cover board 6 and baffle 11, the end plate 1 include left side plate and Right end plate;Mold needs to carry out before use mold selection and two steps of Mold polishing;
Backboard 3, left side plate and right end plate are hinged with bottom plate 5 respectively;
Baffle 11 is bolted with left side plate, and baffle 11 is connect by bolt with right end plate;
Cover board 6 is arranged on end plate 1;
5 both ends of bottom plate are pasted with sealing strip 2, and sealing strip 2 is posted at 3 both ends of backboard;
The bracket 12 includes bottom positioning plate and altitude location part, and altitude location part is fixed with bottom positioning plate.
Altitude location part: for limiting the height of steel reinforcement cage 13, it is accordingly required in particular to, it is emphasized that traditional mold is not due to having The bracket 12 for playing the role of lifting generally requires to place gasket on bottom plate 5, for being lifted steel reinforcement cage 13, avoids steel reinforcement cage 13 Bottom reinforcement bars it is exposed.But traditional approach, 8 mass of shield is influenced, and shape is unsightly, and increases construction cost.Highly Locating piece can according to need, and adjusts the distance between 13 bottom of steel reinforcement cage and bottom plate 5, reduces while meeting production requirement Construction cost, and due to the reusable property of bracket 12, it brings great convenience to production, in production with a batch of It is very convenient when shield 8.
In a preferred embodiment, the plank of adjustment height can be made in altitude location part, for example, by altitude location part Two parts, such as the first height part and the second height part is made, is connected between two altitude location parts by tunable arrangement.Than Such as, the first height part is the first height cylinder, and the second height part is the second height cylinder, is connected through a screw thread between two cylinders, can be with It realizes flexible.
In a preferred embodiment, in spatial position, it is horizontal that sequence from top to bottom is followed successively by second cross beam the 17, the 4th Beam 19, the 5th crossbeam 20 and first crossbeam 15.
In a preferred embodiment, the invention also includes third crossbeam 18, wherein second cross beam 17, third crossbeam 18 with 4th crossbeam 19 is located in same level, and second cross beam 17 is successively up the 4th crossbeam 19 and first crossbeam 15.
In a preferred embodiment, locating part 16 is Y shape or V-arrangement, for limiting the position of reinforcing bar.
In a preferred embodiment, several locating parts 16 is provided on first crossbeam 15, under each locating part 16 Side is arranged fluted 21 in the corresponding position of second cross beam 17;
Groove 21 corresponding with 16 position of locating part is also equipped on the 5th crossbeam 20 and the 4th crossbeam 19.
In a preferred embodiment, fluted 21 are arranged at the position corresponding with locating part 16 of third crossbeam 18.
In a preferred embodiment, first crossbeam 15 is detachably connected with steel reinforcement cage support 14.First crossbeam 15 can be straight It connects and is placed in steel reinforcement cage support 14 or first crossbeam 15 and steel reinforcement cage support 14 to be bolted.Preferably, first crossbeam 15 are made of angle steel.
In a preferred embodiment, vertical supporting and cross-brace are detachably connected, for example, be bolted or It is connected by ring flange.
In a preferred embodiment, vertical supporting and cross-brace are all made of angle steel and are made, and lead between angle steel and angle steel It crosses and is bolted.
Altitude location part and bottom positioning plate are integrally formed or weld.
In a preferred embodiment, a bracket 12 is placed at the both ends of mold respectively, and a bracket 12 includes a bottom Portion's positioning plate and two altitude location parts, altitude location part are welded on the positioning plate of bottom.
In a preferred embodiment, the end of bottom positioning plate is provided with limiting section, in limiting section and bottom positioning plate A U-lag is formed between portion.Limiting section protrusion, steel reinforcement cage 13 are placed between limiting section the left and right, it can be achieved that steel reinforcement cage 13 Limit, simultaneously as the effect of transverse slat ontology, may be implemented the front and back positioning of steel reinforcement cage 13.
In a preferred embodiment, altitude location part is L shape angle steel, and bottom positioning plate is plain plate, the welding of L shape angle steel On plain plate.
In a preferred embodiment, mould support 10 is set below bottom plate 5.Mould support 10 includes being arranged in bottom plate 5 Under column, the column quantity preferably 4.It is highly preferred that mould support 10 includes column and the plate being arranged on column, Plate is fixed with column, and bottom plate 5 is placed on plate, can also be further fixed by bolt.It is excellent at another It selects in embodiment, universal wheel, mold easy to remove is arranged in the lower section of column.
In a preferred embodiment, the bolt hole that cover board 6 is connect with end plate 1 is slot 7, and baffle 11 and end plate 1 connect The bolt hole connect is slot 7.
In a preferred embodiment, the end plate 1 is L shape, and baffle 11 is vertically placed on the first order step of end plate 1 It goes up and passes through bolt and end plate 1 is fixed;Cover board 6 is placed across on the first order step of end plate 1 and is consolidated by bolt and end plate 1 It is fixed;After mold installation, the top surface of end plate 1, backboard 3 and baffle 11 is on the same horizontal plane.
In a preferred embodiment, entire mold is L-shaped, and supporting plate, backboard 3, left side plate and right end are provided on bottom plate 5 The rotation section with supporting plate cooperation is provided on plate, aperture on rotation section, rotation section is connect with supporting plate by pin shaft;Each rotation Portion is used cooperatively with two supporting plates, and rotation section is arranged between two supporting plates, and two supporting plates include the first supporting plate and the second supporting plate, Pin shaft sequentially passes through the first supporting plate, rotation section and the second supporting plate and connects three.
In a preferred embodiment, pin shaft front end aperture, it is solid by split pin after pin shaft passes through supporting plate and rotation section It is fixed.
In a preferred embodiment, rotation section is a plate, and plate is fixed with backboard 3 or left side plate or right end plate;
Rotation section and backboard 3 are welded or are integrally formed;
Rotation section and left side plate are welded or are integrally formed;
Rotation section and right end plate are welded or are integrally formed.
In a preferred embodiment, arcuate projection is provided on bottom plate 5, it is preferable that arcuate projection can be by cutting Face is semicircular pipe and the fixed realization of bottom plate 5, for example welds, is integrally formed.Moreover, arcuate projection can also lead to It crosses and welds a round tube or flat tube realization on bottom plate 5.
In a preferred embodiment, it is provided with embedded hole 4 on backboard 3, it is highly preferred that being provided on backboard 3 pre- at two Two strip-shaped holes are arranged in buried via hole 4, every place's embedded hole 4, and embedded hole 4 is arranged in 3 two sides of backboard at two.Embedded hole 4 is pre- for installing Embedded part 9, the built-in fitting 9 includes pre-embedded steel slab 9.1 and pre-embedded bolt 9.2, as shown in Fig. 9~Figure 11.
After 8 reinforcement installation of shield is good, built-in fitting 9 should be also fixed, first by U-shaped pre-embedded bolt 9.2 insertion steel reinforcement cage 13 Nut is simultaneously screwed in corresponding position, nut is twisted in correct position, U-shaped pre-embedded bolt 9.2 is pierced into pre-buried steel after being twisted by nut In 9.1 hole of plate, and pre-embedded steel slab 9.1 and 4 nut is tightened, be finally adjacent to pre-embedded steel slab 9.1 and template (or it is U-shaped pre- Bolt 9.2 is buried first to be fixed on backboard 3), guarantee that 8 pre-embedded bolt 9.2 of railing shield is higher by 50mm;The pre-buried spiral shell of sound barrier shield 8 Bolt 9.2 is higher by 80mm.
13 preparation method of steel reinforcement cage:
Step 1: fixture for assembling and welding, but first crossbeam 15 is not installed first;
Step 2: reinforcing bar is bent into Jiong shape reinforcing bar 13.1, lateral fixed steel bars 13.2, figure-six reinforcing bar 13.3 and is indulged To reinforcing bar 13.4, preferably, in one crotch of end reinforced setting;
Step 3: first by figure-six reinforcing bar 13.3 and/or longitudinal reinforcement 13.4 according to certain intervals (such as between groove Away from) be placed on welding tooling;
Step 4: after first crossbeam 15 is installed, then placing Jiong shape reinforcing bar 13.1, later by lateral fixed steel bars 13.2 Pierce into Jiong shape reinforcing bar 13.1, figure-six reinforcing bar 13.3 and/or longitudinal reinforcement 13.4 and figure-six reinforcing bar 13.3 and longitudinal reinforcement In 13.4 spaces formed;
Step 5: by Jiong shape reinforcing bar 13.1 and the lateral welding of fixed steel bars 13.2 and/or binding;By figure-six reinforcing bar 13.3 And/or longitudinal reinforcement 13.4 and lateral fixed steel bars 13.2 are welded and/or are bound;By Jiong shape reinforcing bar 13.1 and figure-six reinforcing bar 13.3 and/or longitudinal reinforcement 13.4 welding and/or binding.
It should be noted that the sequence of above-mentioned steps one and step 2 can exchange.In step 4, Jiong can be first placed After shape reinforcing bar 13.1, then first crossbeam 15 is installed.Special construction and special manufacture craft in view of steel reinforcement cage 13, therefore this steel Muscle cage 13 can also be used as a part of engineering method device.
Project management department's precasting yard conserves component band mould, demoulding, together respectively by studying shield appearance quality trait When by setting timing control, reach maintenance automation, by using exempt from cushion block bracket, hinge-type punching block, digital control hoop bender and The techniques such as carbon dioxide gas arc welding, have saved cost of labor, improve presentation quality, meet owner's requirement, in owner, prison Good reputation is achieved before reason and headquarter, office, the affirmative for having arrived certain headquarter of the presentation quality of shield also is commented by expert For " shield presentation quality is completely best ", public praise is won for company, has achieved good social benefit.
The effect to require emphasis is:
Using exempting from cushion block construction technology
Cushion block construction technology is exempted from the construction process using shield, concrete pad can be replaced by exempting from cushion block steel bracket, from And the cost of concrete pad has greatly been saved, according to on-site actual situations, each shield needs 5~7 cushion blocks, Gong Jijie About 150000 cushion blocks, achieve preferable economic benefit.It is convenient to assemble and disassemble using bracket, quick, save cost of labor;Using Bracket thickness of concrete cover can satisfy requirement, and surface is without cushion block pitted skin, it is ensured that presentation quality.In process aspect, More stringent requirements are proposed for presentation quality of the Party A to shield.In order to reach these requirements, we change uses gasket in the past The construction technology poured, the influence to avoid concrete gasket to the presentation quality of shaped component outer surface.Meanwhile it also saving Purchase the construction cost of gasket.Improved by a series of innovation, new process and new material obtained Party A, management side and The consistent favorable comment of design side.
Using digital control hoop bender construction technology
It is processed using traditional reinforcing steel bar hoop bending and needs 4~5 people, 1 people is only needed using digital control hoop bender, and can be round-the-clock Reinforcing bar production is carried out, steel bar meter is daily more than 8t at full capacity.According to live actual count statistics indicate that, using digital control hoop bender It processes machining accuracy and improves 50% or more than traditional artificial processing precision of reinforcing steel bar, the size for considerably reducing steel bar meter is missed Difference avoids doing over again.The technique save the cost improves work efficiency, has biggish economic value.
The present invention innovatively devises the outer steel reinforcement cage positioning device of convenient and fast mold bracket in other words for the first time, to realize The positioning process of embedded bar cage four direction up and down, avoids because of gasket caused by gasket is exposed and perfusion coagulation The color difference of soil, and, steel reinforcement cage is excessively close to lower die face in a mold, causes dew muscle and other issues occur.This engineering method phase Than previous construction technology, required construction personnel is less, and high production efficiency is with short production cycle, and construction cost is low, and construction quality is easy Guarantee, operation is simple.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, it is noted that all Made any modifications, equivalent replacements, and improvements etc. within the spirit and principles in the present invention should be included in guarantor of the invention Within the scope of shield.

Claims (8)

1. high-speed railway bridge floor shield is without gasket prefabricated construction engineering method, which is characterized in that it includes the following steps:
Step 1: the entering of reinforcing steel bar;
Step 2: steel reinforcement cage is made in steel bar meter;
Step 3: steel reinforcement cage enters mould;
Step 4: installation of embedded parts;
Step 5: concreting;
Step 6: plastering;
Step 7: concrete plucking;
Step 8: curing in the mold;
Step 9: demoulding operating;
Step 10: spray maintenance;
Step 11: pile storage;
The entering of reinforcing steel bar: notifying testing crew to sample inspection in time after the entering of reinforcing steel bar, witnesses with Times supervisor, raw material of reinforcement rebar It can use after the assay was approved;
Steel bar meter: carrying out setting-out to various specifications reinforcing bar according to design drawing, carry out blanking by Lofting Calculation reinforcing bar length, Blanking reinforcing bar is pressed into design drawing bending forming, the reinforcing bar of bending forming is placed on the enterprising binding of welding tooling, is tied up by right-angled intersection It pricks, gas shield welding welding forbids iron wire head to stretch in concrete;
Steel reinforcement cage enters mould: the shield steel reinforcement cage of binding forming is put into assembled mold;Steel reinforcement cage is put into light when mold It puts, forbids to collide mold;Embedded iron parts fix, with exempting from cushion block tooling fixture for steel reinforcement cage from 30~39mm of mold bottom, really Protect thickness of concrete cover;
Installation of embedded parts: after steel reinforcement cage installs, built-in fitting should be also fixed, first by the phase of U-shaped pre-embedded bolt insertion steel reinforcement cage It answers position and screws on nut, nut is twisted in correct position, U-shaped pre-embedded bolt is pierced into pre-buried steel plate hole after being twisted by nut It is interior, and pre-embedded steel slab and 4 nuts are tightened, finally pre-embedded steel slab and template are adjacent to, it is necessary to assure the pre-buried spiral shell of railing shield Bolt is higher by 50mm;Sound barrier shield pre-embedded bolt is higher by 80mm;
Concreting: including secondary vibration moulding process;
Plastering: quadric-plastering moulding process: a daubing carries out first time daubing, for the second time after the completion of making firm by ramming for the first time Carry out primary essence plastering after the completion of making firm by ramming, carry out one-coat plastering again before initial set, cap locations are opened before initial set, quadric-plastering at Type;
Concrete plucking: hair pulling treatment is carried out after concrete initial set in time;
Curing in the mold: it is conserved after the prefabricated initial set of shield, covers geotextiles when maintenance above shield, it is ensured that comprehensive maintenance;
Demoulding transhipment: curing at moisture-retention and heat-insulation is carried out to concrete after pouring completion and plucking;
Spray maintenance: being transported to spray maintenance area after shield demoulding, shield puts underlay flitch, upper cover non-woven fabrics, and when spray is true 360 ° of shield maintenances are protected without dead angle;
Pile storage: after concrete reaches regulation curing time, it is transported to finished product pile field, and stacking of classifying, and performed Mark.
2. high-speed railway bridge floor shield according to claim 1 is without gasket prefabricated construction engineering method, it is characterised in that:
Steel bar meter: using full-automatic numerical control stirrup bender, carries out straightening, scale, bending hoop, cutting to reinforcing bar, greatly improves Production work efficiency, it is ensured that product standard is unified;
The binding of shield steel reinforcement cage carries out scale positioning using shield steel reinforcement cage welding tooling;
Shield steel reinforcement cage binds the form combined with tied silk using welding, and welding uses carbon dioxide gas arc welding.
3. high-speed railway bridge floor shield according to claim 1 is without gasket prefabricated construction engineering method, it is characterised in that:
Concreting:
1 concrete transports to small-sized prefabricated member factory, and concrete fills vehicle action of forced stirring 1 minute, keeps the concrete for filling vehicle uniform;
After 2 concrete fill vehicle stirring 1 minute, testing crew is surveyed the slump of concrete and can be poured after the slump is qualified;Together When concrete curing test block;
Check whether shield demoulding agent of mould is brushed uniformly before 3 concretings, built-in fitting, steel reinforcement cage install whether secured, position Whether set accurate;
4 shield steel reinforcement cage displacements in order to prevent, are fixed framework of steel reinforcement using steel bar spacer bracket before making firm by ramming;Bracket is necessary Fixation, quantity is enough, ensures to need each steel reinforcement cage of each prefabricated shield to have bracket before construction;Cushion block branch Frame taking-up when making firm by ramming for the second time;
5 first times made firm by ramming, by coagulation poured into shield, were vibrated with 40mm immersion vibrator, and spacing of vibrating 200mm is extremely 300mm is uniformly, fast to insert slow pumping, a vibration point 20 seconds to 30 seconds, 6~7 vibration points of every block of shield;Vibrating head is forbidden to contact template, protects It demonstrate,proves from template spacing 50mm;
6 make firm by ramming for second, and make time interval firm by ramming for the first time 10 minutes, are vibrated with 30mm plug-in type vibrating stick, between vibrating It is uniformly, fast to insert slow pumping, each vibration point 20 seconds to 30 seconds, 6~7 vibration points of every block of shield away from 200mm to 300mm;Vibrating head is the bottom of from Template top 50mm to 100mm;Pass through the case where can be effectively solved bubble, pitted skin of vibrating twice.
4. high-speed railway bridge floor shield according to claim 1 is without gasket prefabricated construction engineering method, it is characterised in that:
Plucking: the plucking time is 1 hour to 2 hours after the completion of concreting, to concrete surface according to weather temperature conditions Carry out it is smooth, it is smooth after carry out plucking, plucking use special wire brush plucking, kerve depth 2mm, width 1mm, spacing 5mm, guarantee drawing Lines is uniform in hair range, and clear, neat, depth meets the requirements.
5. high-speed railway bridge floor shield according to claim 1 is without gasket prefabricated construction engineering method, it is characterised in that:
Curing in the mold: shield curing in the mold system includes water pump, water supplying pipe and switch, spray head, support quarter bend, gutter, shield It is conserved after prefabricated initial set, covers geotextiles when maintenance above shield, a spray head is set above each shield, it is ensured that Quan Fang Position maintenance;
Moisturizing is carried out during curing in the mold, concrete component reaches 2.5MPa or more, and its surface and corner angle are not damaged because of demoulding Component is transported to maintenance area's automatic sprinkler fire-extinguishing system after demoulding and non-textile mulch is added to conserve by bad when, i.e., dismountable mold.
6. high-speed railway bridge floor shield according to claim 1 is without gasket prefabricated construction engineering method, it is characterised in that:
Spray maintenance: being transported to spray maintenance area using fork truck after shield demoulding, and curing system includes high-pressure hydraulic pump, world spray Head, water supplying pipe, time switch composition, spray interval time are set as 1 hour, and spray continues 5 minutes, and according to weather condition It adjusts at any time;World spray head works at the same time when spray system works, it is ensured that 360 ° of shield maintenances use water without dead angle, spray-water The circulatory system, maintenance are imported in sedimentation basin by ditch with water and are recycled, economical environment-protective.
7. high-speed railway bridge floor shield according to claim 1 is without gasket prefabricated construction engineering method, it is characterised in that: pile is deposited It puts: shield being transported to finished product pile field, shield stacking form and finished product protection with fork truck:
2 10cm*10cm flitches of underlay when 1 shield pile pile, stacking height is determining according to forklift lifting height, general pile 6 layers;
2 pile regions are separately provided, and separate with other regions, prevent other vehicle collisions from damaging shield;
3 pile regions setting mark.
8. a kind of device applied to engineering method described in claim 1, it is characterised in that: it includes welding tooling, bracket and mold;
Welding tooling includes steel reinforcement cage support, first crossbeam, second cross beam, the 4th crossbeam and the 5th crossbeam, steel reinforcement cage support packet Vertical supporting and cross-brace are included, vertical supporting is connected into an entirety by cross-brace;
First crossbeam, second cross beam, the 4th crossbeam and the setting of the 5th crossbeam are in steel reinforcement cage support, wherein first crossbeam and the Two crossbeams are arranged in the side of steel reinforcement cage support, and the 4th crossbeam and the 5th crossbeam are arranged in the other side of steel reinforcement cage support, and first Finite place piece is set on crossbeam;
The mold includes bottom plate, backboard, end plate, cover board and baffle, and the end plate includes left side plate and right end plate;
Backboard, left side plate and right end plate are hinged with bottom plate respectively;
Baffle is bolted with left side plate, and baffle is connect by bolt with right end plate;
Cover board is arranged on end plate;
The bottom plate both ends are pasted with sealing strip, and sealing strip is posted at the backboard both ends;
The bracket includes bottom positioning plate and altitude location part, and altitude location part is fixed with bottom positioning plate.
CN201711235434.XA 2017-11-30 2017-11-30 High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device Active CN108035251B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711235434.XA CN108035251B (en) 2017-11-30 2017-11-30 High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711235434.XA CN108035251B (en) 2017-11-30 2017-11-30 High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device

Publications (2)

Publication Number Publication Date
CN108035251A CN108035251A (en) 2018-05-15
CN108035251B true CN108035251B (en) 2019-08-02

Family

ID=62094544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711235434.XA Active CN108035251B (en) 2017-11-30 2017-11-30 High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device

Country Status (1)

Country Link
CN (1) CN108035251B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1193119A (en) * 1997-09-16 1999-04-06 純夫 ▲はま▼田 Connection of precast concrete slab
AU2003259613A1 (en) * 2002-11-01 2004-05-20 Bridge & Marine Engineering Pty. Ltd. Structural Beam and Method of Manufacture
JP3666326B2 (en) * 1999-12-06 2005-06-29 鹿島建設株式会社 Cross-section precast segment method
CN101476290A (en) * 2008-12-08 2009-07-08 中铁十五局集团有限公司 Cast-in-place construction method for bridge curtain board
CN203624937U (en) * 2013-12-19 2014-06-04 中铁十二局集团第一工程有限公司 Curtain board installing machine
CN105625636A (en) * 2014-10-29 2016-06-01 中铁十四局集团有限公司 Continuous beam curtain board construction technology
CN106223187A (en) * 2016-08-30 2016-12-14 株洲时代新材料科技股份有限公司 Shield for mining under railways

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1193119A (en) * 1997-09-16 1999-04-06 純夫 ▲はま▼田 Connection of precast concrete slab
JP3666326B2 (en) * 1999-12-06 2005-06-29 鹿島建設株式会社 Cross-section precast segment method
AU2003259613A1 (en) * 2002-11-01 2004-05-20 Bridge & Marine Engineering Pty. Ltd. Structural Beam and Method of Manufacture
CN101476290A (en) * 2008-12-08 2009-07-08 中铁十五局集团有限公司 Cast-in-place construction method for bridge curtain board
CN203624937U (en) * 2013-12-19 2014-06-04 中铁十二局集团第一工程有限公司 Curtain board installing machine
CN105625636A (en) * 2014-10-29 2016-06-01 中铁十四局集团有限公司 Continuous beam curtain board construction technology
CN106223187A (en) * 2016-08-30 2016-12-14 株洲时代新材料科技股份有限公司 Shield for mining under railways

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"桥梁遮板制造于安装施工";曹玉新;《水利水电施工》;20140415(第2期);第104页

Also Published As

Publication number Publication date
CN108035251A (en) 2018-05-15

Similar Documents

Publication Publication Date Title
CN104846744B (en) Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN104963289B (en) A kind of abnormity pier stud mass concrete overall time pouring construction method
CN108789815A (en) A kind of manufacturing method of shield prefabricated reinforced concrete section of jurisdiction
CN208884783U (en) Assembled architecture PCF plate and connection component
CN106182359A (en) The concrete list storehouse horizontal mould of pipe gallery, system and piping lane molding methods
CN105201204B (en) A kind of method and structure of rotten when preventing pouring reinforcement concrete column suspension column
CN114411945A (en) Bin jump construction method based on BIM technology
CN104831932A (en) Construction technology for high-grade concrete column base
CN203174510U (en) Movable assembly type hanging basket for bridge anti-collision guardrail construction and formwork for construction
CN113389379A (en) Construction method of post-cast strip floor with independent support
CN104153573B (en) V-type cylinder concrete pour mould and construction method
CN108035251B (en) High-speed railway bridge floor shield is without gasket prefabricated construction engineering method and device
CN104947853B (en) A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method
CN102121312B (en) Construction process for concrete bargeboard in pseudo-classic architecture
CN105804448A (en) Vertical prefabricating construction method of cooling tower herringbone column
CN211817964U (en) Post-cast strip template supporting structure with cleaning opening
CN204001713U (en) V-type cylinder oblique line section concrete is built mould
TW200540319A (en) Method for manufacturing pre-cast hollow shell column and forming device thereof
CN209466399U (en) A kind of assembling type steel structure beam making bench
CN208163928U (en) A kind of producing device of stiffened column
CN206941628U (en) A kind of construction site enclosing prefabricated foundation
CN110409299A (en) A kind of processing method of high-intensitive thinned Bridge guardrail
CN106320101B (en) A kind of precast concrete rail pedestal and preparation method thereof
CN107905106A (en) Method for bridge construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200416

Address after: 610000, No. two, section 100, North Ring Road, Jinniu District, Sichuan, Chengdu

Patentee after: CONSTRUCTION COMPANY OF CHINA RAILWAY NO.8 ENGNEERING GROUP Co.,Ltd.

Address before: 610000 No. 4 Qiaodong street, northwest Jinniu District, Sichuan, Chengdu

Patentee before: NO.4 ENGINEERING CO., LTD. OF CHINA RAILWAY NO.8 BUREAU

TR01 Transfer of patent right