CN108019040B - A construction method for the Bailey frame platform of the transfer floor of a high-rise building - Google Patents

A construction method for the Bailey frame platform of the transfer floor of a high-rise building Download PDF

Info

Publication number
CN108019040B
CN108019040B CN201710326359.1A CN201710326359A CN108019040B CN 108019040 B CN108019040 B CN 108019040B CN 201710326359 A CN201710326359 A CN 201710326359A CN 108019040 B CN108019040 B CN 108019040B
Authority
CN
China
Prior art keywords
formwork
girder
bailey
floor
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201710326359.1A
Other languages
Chinese (zh)
Other versions
CN108019040A (en
Inventor
邓凯
姜方敏
吴刚
刘成
吴碧桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huajian Construction Co Ltd
Original Assignee
Jiangsu Huajian Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huajian Construction Co Ltd filed Critical Jiangsu Huajian Construction Co Ltd
Priority to CN201710326359.1A priority Critical patent/CN108019040B/en
Publication of CN108019040A publication Critical patent/CN108019040A/en
Application granted granted Critical
Publication of CN108019040B publication Critical patent/CN108019040B/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to a kind of high-rise building transfer floor Bailey bracket platform construction methods, belong to technical field of building construction.This method mainly includes installation lattice column, sets up Bailey beam, lift I-beam, build big beam form bottom, sandwich boards for construction plate, construction conversion layer step.Compared with prior art, easy to implement, safe and reliable present invention can ensure that under the premise of quality, there are many remarkable advantages.

Description

一种高层建筑转换层贝雷架平台施工方法A construction method for the Bailey frame platform of the transfer floor of a high-rise building

技术领域technical field

本发明涉及一种建筑物转换层贝雷架平台,尤其是一种高层建筑转换层贝雷架平台,同时还涉施工方法,属于建筑施工技术领域。The invention relates to a building transfer floor belay frame platform, in particular to a high-rise building transfer floor bere frame platform, and also relates to a construction method, which belongs to the technical field of building construction.

背景技术Background technique

高层建筑常常因楼层之间的建筑结构变化而需要构筑转换层贝雷架平台。High-rise buildings often need to build transfer floor beret platforms due to structural changes between floors.

检索可知,申请号为201010135856.1的中国发明专利公开了一种高层建筑梁式结构转换层的施工方法,该方法包括模板支撑体系的设计与布置、钢筋工程、混凝土工程等步骤,据介绍具有效率高、质量容易控制、造价低、施工方便的优点。然而实际上由于其转换层采用满堂脚手架,支撑模板用木龙骨制作,不仅需要投入较多的人工、材料,而且存在以下问题:1)需在地下和首层(-2、-1、1)搭设三层满堂支撑架,难以保证各层的支撑系统立杆在同一位置,受力不佳;2)地下层的满堂支撑架必须在首层梁板混凝土达到设计强度时才能拆除,因此影响转换层的施工工期;3)只适用于转换层处于低层(例如二层)。According to the search, the Chinese invention patent with the application number of 201010135856.1 discloses a construction method for the transfer floor of a high-rise building beam structure. , easy quality control, low cost, and convenient construction. However, in fact, because the transfer floor is full of scaffolding, and the supporting formwork is made of wooden keels, it not only requires a lot of labor and materials, but also has the following problems: 1) It needs to be installed on the ground floor and the first floor (-2, -1, 1) It is difficult to ensure that the vertical poles of the support system on each floor are at the same position when erecting a three-story full hall support frame, and the force is not good; 2) The full hall support frame on the basement floor must be removed when the beam-slab concrete on the first floor reaches the design strength, thus affecting the conversion 3) It is only applicable to the transfer floor in the lower floor (such as the second floor).

申请号为201410337666.6的中国发明专利公开了一种贝雷梁悬吊模板支撑体系施工工法,包括贝雷梁组成的纵横向受力桁架;在横向贝雷梁上设有吊杆,所述吊杆穿过混凝土层结构底模悬挂双向工字钢承重平台;所述平台上方设有钢管脚手架模板支撑体系,所述横向贝雷梁按间距垂直布置于纵向贝雷梁之上,纵向贝雷梁支承在框架结构或临时支撑上。其工法包括:增建层上部预先架设贝雷梁模板支撑体系悬吊系统,下铺设模板支架操作平台。其优点是不占用施工场地,适用于钢筋混凝土或型钢组合结构的空中连廊、高大中庭及转换层工程现浇混凝土施工,尤其适用于不与原结构发生受力关系的加建工程。实践表明,上述现有技术存在如下缺点:1)在缺乏框架支撑结构时,必须设置临时支撑承担贝雷梁,施工多有不便;2)模板支撑体系搭设完成后需对支架进行预压,施工难度较大。尤其是,悬挂系统中混凝土结构底模支撑于承重平台上,不仅对螺纹钢吊杆的质量要求高,而且容易受施工载荷影响,因为吊杆的质量直接影响平螺纹钢吊杆悬挂的“承重平台”的稳定性,而吊杆结构对承受施工过程中、浇筑混凝土等产生的水平冲击能力十分有限,因此难以保持稳定,不仅影响施工质量,还存在一定的安全隐患。The Chinese invention patent with the application number 201410337666.6 discloses a construction method of a Bailey beam suspended formwork support system, which includes a vertical and horizontal force truss composed of Bailey beams; A two-way I-beam load-bearing platform is suspended through the bottom formwork of the concrete layer structure; a steel pipe scaffolding formwork support system is provided above the platform, and the transverse Bailey beams are vertically arranged on the longitudinal Bailey beams at intervals, and the longitudinal Bailey beams support On framed structures or temporary supports. The construction method includes: pre-erecting the suspension system of the Bailey beam formwork support system on the upper part of the additional floor, and laying the formwork support operating platform below. Its advantage is that it does not occupy the construction site, and is suitable for the construction of cast-in-place concrete for reinforced concrete or steel composite structures such as air corridors, tall atriums, and transfer floor projects, especially for addition projects that do not have a stress relationship with the original structure. Practice has shown that the above prior art has the following disadvantages: 1) When there is no frame support structure, it is necessary to set up temporary supports to bear the Bailey beams, which is inconvenient for construction; It is more difficult. In particular, the bottom mold of the concrete structure in the suspension system is supported on the load-bearing platform, which not only has high requirements on the quality of the rebar suspender, but is also easily affected by the construction load, because the quality of the suspender directly affects the "load bearing" of the suspension of the flat rebar suspender. The stability of the "platform", and the suspender structure has very limited ability to withstand the horizontal impact generated during the construction process and pouring concrete, so it is difficult to maintain stability, which not only affects the construction quality, but also poses certain safety hazards.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于:针对现有技术存在的问题,提出一种不仅实施方便、易于保证质量,且安全可靠的高层建筑转换层贝雷架平台施工方法。The object of the present invention is: aiming at the problems existing in the prior art, propose a kind of not only convenient to implement, easy to guarantee the quality, but also safe and reliable construction method of high-rise building transfer floor Bailey frame platform.

为了达到上述目的,本发明高层建筑转换层贝雷架平台施工方法包括以下基本步骤:In order to achieve the above object, the construction method of the Bailey frame platform of the high-rise building transfer layer of the present invention comprises the following basic steps:

第一步、安装格构柱——在建筑物基础两侧对应转换层大梁下方的位置分别安装间隔分布的格构柱,柱顶至与待转换的楼层平齐;The first step is to install lattice columns - install lattice columns distributed at intervals on both sides of the building foundation corresponding to the positions below the transfer floor girders, and the tops of the columns are flush with the floors to be converted;

第二步、架设贝雷梁——吊装架设一组分别支撑于同侧格构柱及待转换楼层上的贝雷梁;The second step is to erect the Bailey beams - hoisting and erecting a group of Bailey beams respectively supported on the lattice columns on the same side and on the floor to be converted;

第三步、吊装工字梁——吊装架设固定在贝雷梁上且与之垂直的一组两端外伸的间隔分布工字梁,在工字梁上铺设安全防护层且外伸端搭建悬挑脚手架;The third step is to hoist the I-beam - hoisting and erecting a group of I-beams that are fixed on the Bailey beam and perpendicular to it. cantilevered scaffolding;

第四步、建大梁模底——在工字梁上支立间隔分布的顶托,并在顶托顶部安置分别支撑大梁和夹层浇筑模板的平架钢管;The fourth step is to build the bottom of the girder formwork—support the jacking brackets distributed at intervals on the I-beam, and place flat steel pipes on the top of the jacking brackets to support the girder and the interlayer pouring formwork respectively;

第五步、建筑夹层板——在顶托支撑平架钢管上构建大梁浇筑模板以及连接在两侧大梁浇筑模板中部之间的夹层浇筑模板,并在大梁浇筑模板内安置工字大梁,绑扎好钢筋后浇筑混凝土,大梁浇筑模板浇筑至一半高度;The fifth step, building interlayer slabs - build the girder pouring formwork on the steel pipe supporting the flat frame and the interlayer pouring formwork connected between the middle parts of the girder pouring formwork on both sides, and place the I-beam in the girder pouring formwork, and tie it up Concrete is poured after the reinforcement, and the girder pouring formwork is poured to half the height;

第六步、施工转换层——在浇筑好的夹层板及高跨工字钢上支立间隔分布的顶托,并在顶托顶部安置支撑转换层浇筑模板的平架钢管后,构建连接在两侧大梁浇筑模板上部之间的转换层浇筑模板,并在转换层浇筑模板中绑扎好钢筋,连同大梁上部一起浇筑混凝土。Step 6: Construction of the transfer layer——support the interval-distributed jacking brackets on the poured sandwich panels and high-span I-beams, and place the flat-frame steel pipes supporting the transfer layer pouring formwork on the top of the jacking brackets, and then construct the connection in the The formwork is poured in the transfer layer between the upper part of the girder pouring formwork on both sides, and the steel bars are bound in the transfer layer pouring formwork, and the concrete is poured together with the upper part of the girder.

与现有技术相比,采用本发明的方法无需搭设满堂支撑架、承力状体理想,易于保障转换层的施工工期,不受转换层楼层位置的限制;并且实施方便,支撑形成的贝雷架平台稳定可靠,可以保证质量和施工安全。Compared with the prior art, the method of the present invention does not need to set up a full hall support frame, the load-bearing shape is ideal, it is easy to guarantee the construction period of the transfer floor, and is not limited by the location of the transfer floor; and it is easy to implement, and the Bailey formed by supporting The platform is stable and reliable, which can guarantee the quality and construction safety.

本发明进一步的完善是,所述第一步的格构柱采用塔吊的标准塔节自下而上逐节拼接;拼接安装时,采用工具式操作平台,所述操作平台具有型材固连而成的“凹”字形台面围框,所述围框上表面覆盖固定盖板,所述围框的开口内廓与标准塔节的外廓相配,所述上表面外周焊接固定护栏。The further improvement of the present invention is that the lattice columns of the first step are spliced section by section from bottom to top using the standard tower section of the tower crane; when splicing and installing, a tool-type operating platform is used, and the operating platform is formed by solid connection of profiles. The "concave" shaped table top frame, the upper surface of the frame is covered with a fixed cover plate, the inner profile of the opening of the frame matches the outer profile of the standard tower section, and the outer periphery of the upper surface is welded to fix the guardrail.

本发明更进一步的完善是,所述第四步中,各顶托由上部具有内螺纹的撑杆和拧在内螺纹中的托杆组成,所述托杆的顶部固连撑托平架钢管的托头,各顶托的撑杆之间通过上、下间隔分布的横杆固连,构成框架结构。A further improvement of the present invention is that in the fourth step, each jacking bracket is composed of a support rod with an internal thread on the upper part and a support rod screwed into the internal thread, and the top of the support rod is fixedly connected to the steel pipe supporting the flat frame. The support heads of each support are fixedly connected by upper and lower horizontal bars distributed at intervals to form a frame structure.

附图说明Description of drawings

图1为本发明一个实施例的安装格构柱步骤结构示意图。Fig. 1 is a schematic structural diagram of steps for installing lattice columns according to an embodiment of the present invention.

图2.1为图1实施例安装格构柱用操作平台的结构示意图。Figure 2.1 is a schematic structural view of the operating platform for installing lattice columns in the embodiment of Figure 1.

图2.2为图2.1的俯视图结构示意图。Figure 2.2 is a schematic diagram of the top view of Figure 2.1.

图2.3为图2.2的A向视图。Figure 2.3 is the A-direction view of Figure 2.2.

图3为图1实施例采用的贝雷架结构示意图。Fig. 3 is a schematic diagram of the structure of the Bailey frame used in the embodiment of Fig. 1 .

图4为图1实施例的架设贝雷梁步骤示意图。Fig. 4 is a schematic diagram of the steps of erecting the Bailey beam in the embodiment of Fig. 1 .

图5为图1实施例的吊装工字梁步骤示意图。Fig. 5 is a schematic diagram of the steps of hoisting the I-beam in the embodiment of Fig. 1 .

图6和图7为图1实施例的建大梁模底步骤示意图。Fig. 6 and Fig. 7 are schematic diagrams of the steps of building the bottom of the girder mold in the embodiment of Fig. 1 .

图8.1至8.7为图1实施例的大梁钢筋绑扎过程示意图。Figures 8.1 to 8.7 are schematic diagrams of the binding process of the girder reinforcement in the embodiment of Figure 1 .

图9为图1实施例的建筑夹层板步骤示意图。Fig. 9 is a schematic diagram of the steps of building sandwich panels in the embodiment of Fig. 1 .

图10为图1实施例的施工转换层步骤示意图。Fig. 10 is a schematic diagram of the construction steps of the transfer layer in the embodiment of Fig. 1 .

具体实施方式Detailed ways

实施例一Example 1

本实施例的高层建筑转换层位于九层之上,其一侧具有夹层,另一侧没有夹层,贝雷架平台的施工方法如图所示,按以下步骤施工:The transfer floor of the high-rise building of this embodiment is located above the ninth floor, with a mezzanine on one side and no mezzanine on the other side. The construction method of the Bailey platform platform is as shown in the figure, and it is constructed according to the following steps:

第一步、安装格构柱——如图1所示,在与建筑物基础1-1连为一体的格构柱基础1-2两侧对应转换层大梁下方的位置分别通过预埋地脚螺栓1-3安装间隔分布的格构柱1,本实施例的格构柱1采用塔吊的标准塔节1-4自下而上逐节拼接;The first step is to install the lattice column - as shown in Figure 1, on the two sides of the lattice column foundation 1-2 that is integrated with the building foundation 1-1, the position below the beam of the transfer floor is respectively passed through the pre-buried foundation The bolts 1-3 are installed with lattice columns 1 distributed at intervals, and the lattice columns 1 of this embodiment adopt the standard tower sections 1-4 of the tower crane to be spliced section by section from bottom to top;

拼接安装时,采用图2.1、图2.2、图2.3所示的工具式操作平台2,该工具式操作平台2具有槽钢型材焊接而成“凹”字形台面围框2-1,该围框2-1上表面覆盖固定花纹钢板2-2,其开口内廓与标准塔节的外廓相配,上表面外周焊接固定钢管制成的护栏2-3;该围框2-1一端外侧焊接固连两根朝开口方向伸入开口内的悬臂梁2-4,其开口端的两侧分别焊接固连有带孔的水平耳板2-5,外周间隔焊接固连有带孔的垂向耳板2-6;使用时将工具式操作平台2卡装在已装好标准塔节外,借助耳板起吊并与已装好标准塔节固连,悬臂梁插入已装好标准塔节内起到安全保障作用;待当前格构柱节就位安装固定好之后,将操作平台上移至顶部,即可进行上一节格构柱节的安装;如此循环,直至格构柱的柱顶达到所需标高,十分方便安全。When splicing and installing, use the tool-type operating platform 2 shown in Figure 2.1, Figure 2.2, and Figure 2.3. The tool-type operating platform 2 has a "concave"-shaped table top frame 2-1 welded by channel steel profiles. The frame 2 -1 The upper surface is covered with a fixed checkered steel plate 2-2, the inner profile of the opening matches the outer profile of the standard tower section, and the outer periphery of the upper surface is welded with a guardrail 2-3 made of fixed steel pipes; one end of the enclosure 2-1 is welded and fixed on the outside Two cantilever beams 2-4 protruding into the opening towards the opening direction, horizontal ear plates 2-5 with holes are respectively welded and fixed on both sides of the opening ends, and vertical ear plates 2 with holes are welded and fixed at intervals on the outer circumference -6; When in use, install the tool-type operating platform 2 on the outside of the installed standard tower section, lift it with the help of lug plates and connect it with the installed standard tower section, and insert the cantilever beam into the installed standard tower section for safety. Guarantee function; after the current lattice column section is installed and fixed in place, move the operating platform up to the top, and then the installation of the previous section of lattice column section can be carried out; this cycle continues until the column top of the lattice column reaches the desired level. Elevation, very convenient and safe.

第二步、架设贝雷梁——如图3和图4所示,吊装架设一组分别支撑于同侧格构柱1及待转换楼层L上的贝雷梁3;根据具体情况,贝雷梁3的两端可以搁置在现场相应固定的钢牛腿上。The second step is to erect Bailey beams—as shown in Figure 3 and Figure 4, hoist and erect a group of Bailey beams 3 respectively supported on the lattice column 1 on the same side and the floor L to be converted; The two ends of the beam 3 can be rested on corresponding fixed steel corbels on site.

第三步、吊装工字梁——如图5所示,吊装架设固定在贝雷梁上且与之垂直的一组两端外伸的间隔分布高400mm的工字梁5,在工字梁5上铺设安全防护层,本实施例的防护层具体由大眼安全网5-1、其上的钢板网5-2(网格30x40mm、丝径2.0mm),架在钢板网5-2之上的纵横交错间隔钢管(ф48x壁厚3.6mm)5-3、5-4,以及担在纵横交错间隔钢管之上的钢格栅5-5(俗称钢巴片)构成,其中5-1主要对上操作平台的人员起到安全防护作用,5-2主要防止小型工具坠落,5-3、5-4主要防护较大周材坠落。同时,如图6所示,未来有夹层一侧的外伸端搭建悬挑脚手架6,另一侧无夹层区域则固定高跨工字钢4。The third step, hoisting the I-beam—as shown in Figure 5, hoisting and erecting a group of I-beams 5 that are fixed on the Bailey beam and perpendicular to it with a spacing of 400mm at both ends. Lay safety protection layer on 5, and the protection layer of the present embodiment is specifically made of big eye safety net 5-1, expanded metal mesh 5-2 (grid 30x40mm, wire diameter 2.0mm) on it, frame on the expanded metal mesh 5-2 The criss-cross interval steel pipes (ф48x wall thickness 3.6mm) 5-3, 5-4, and the steel grid 5-5 (commonly known as steel bars) on the criss-cross interval steel pipes are composed of 5-1. It plays a role of safety protection for the personnel on the operating platform. 5-2 mainly prevents small tools from falling, and 5-3 and 5-4 mainly protect larger surrounding materials from falling. At the same time, as shown in Figure 6, in the future, a cantilevered scaffold 6 will be built at the overhanging end on the side with interlayer, and a high-span I-beam 4 will be fixed in the area without interlayer on the other side.

第四步、建大梁模底——如图7所示,在工字梁5上支立间隔分布的顶托7-1,各顶托7-1由上部具有内螺纹的撑杆7-D和拧在内螺纹中的托杆7-U组成,因此可以在一定范围内按需调高,托杆7-U的顶部固连撑托平架钢管7-2的托头,各顶托7-1之间通过上下间隔分布的横杆7-3固连,构成框架结构;平架钢管7-2用于支撑大梁和夹层浇筑模板;支撑大梁的顶托间距小于支撑夹层的顶托间距,从而形成合理的承力能力。The fourth step is to build the bottom of the beam formwork—as shown in Figure 7, support the jacking brackets 7-1 distributed at intervals on the I-beam 5, and each jacking bracket 7-1 is formed by a strut 7-D with an internal thread on the upper part. It is composed of a support rod 7-U screwed into the internal thread, so it can be adjusted within a certain range as needed. The top of the support rod 7-U is fixedly connected to the support head of the flat frame steel pipe 7-2, and each support 7-2 -1 are fixedly connected by horizontal bars 7-3 distributed up and down to form a frame structure; flat frame steel pipes 7-2 are used to support the girder and interlayer pouring formwork; the jacking distance of the supporting girder is smaller than that of the supporting interlayer, So as to form a reasonable bearing capacity.

第五步、建筑夹层板——如图9所示,在顶托7-1支撑平架钢管7-2上构建大梁浇筑模板以及连接在两侧大梁浇筑模板中部之间的夹层浇筑模板;大梁施工进程如图8.1至图8.7所示:The 5th step, construction interlayer board -- as shown in Figure 9, construct the girder pouring formwork and the interlayer pouring formwork connected between the middle part of the girder pouring formwork on both sides on the jacking 7-1 supporting the flat frame steel pipe 7-2; The construction process is shown in Figure 8.1 to Figure 8.7:

步骤一、铺梁底筋——如图8.1所示,铺设大梁浇筑模板底部间隔分布的底筋(即底部钢筋)9-1,并支设梁垫(俗称马镫)9-2;Step 1. Lay the bottom reinforcement of the beam - as shown in Figure 8.1, lay the bottom reinforcement (ie bottom reinforcement) 9-1 distributed at intervals at the bottom of the girder pouring formwork, and support the beam pad (commonly known as stirrup) 9-2;

步骤二、吊装大梁——如图8.2所示,将工字大梁9吊装到大梁浇筑模板中部就位,焊接固定后割去梁垫9-2;Step 2. Hoisting the girder—as shown in Figure 8.2, hoist the I-shaped girder 9 to the middle of the girder pouring formwork, and cut off the girder pad 9-2 after welding and fixing;

步骤三、铺梁面筋——如图8.3所示,在就位的工字大梁9上方铺设间隔分布的面筋9-3;Step 3, Laying Beam Gluten—As shown in Figure 8.3, lay gluten 9-3 distributed at intervals above the I-beam 9 in place;

步骤四、穿梁腰筋——如图8.4所示,铺设大梁浇筑模板两侧及工字大梁9中部两侧间隔分布的侧筋9-4,并通过两端弯头分别钩绕相应侧筋9-4的间隔分布腰筋9-5与工字大梁9焊连,构成肋骨状结构;Step 4, passing through the waist bars of the beam - as shown in Figure 8.4, lay the side bars 9-4 distributed on both sides of the girder pouring formwork and both sides of the middle part of the I-shaped girder 9, and hook the corresponding side bars through the elbows at both ends 9-4 are distributed at intervals and the waist ribs 9-5 are welded with the I-shaped girder 9 to form a rib-shaped structure;

步骤五、绑扎箍筋——如图8.5所示,绑扎间隔分布环绕大梁浇筑模板截面的箍筋9-6;Step 5. Binding the stirrups—as shown in Figure 8.5, the binding intervals are distributed around the stirrups 9-6 of the cross-section of the girder pouring formwork;

步骤六、封梁侧模——如图8.6所示,封闭大梁浇筑所有侧面模板9-7,留出浇筑口,侧面模板9-7下部用穿过两侧夹持木方9-9的对拉螺栓9-8加固;Step 6, beam sealing side formwork - as shown in Figure 8.6, close the girder and pour all the side formwork 9-7, leaving the pouring opening, and the lower part of the side formwork 9-7 is used to pass through the two sides to clamp the wooden square 9-9. Bolt 9-8 reinforcement;

步骤七、大梁浇筑——如图8.7所示,浇筑混凝土,大梁浇筑模板内浇筑至一半高度;Step 7, girder pouring - as shown in Figure 8.7, pour concrete, and pour the girder pouring formwork to half the height;

同时夹层浇筑模板内按常规绑扎好钢筋后,浇筑混凝土。At the same time, concrete is poured after binding steel bars in the interlayer pouring formwork as usual.

第六步、施工转换层——如图10所示,在浇筑好的夹层板G及高跨工字钢4上支立间隔分布的顶托,并在顶托顶部安置支撑转换层浇筑模板的平架钢管后,构建连接在两侧大梁浇筑模板上部之间的转换层浇筑模板,并在转换层浇筑模板中绑扎好钢筋,连同大梁上部一起浇筑混凝土。Step 6: Construction of the transfer layer—as shown in Figure 10, support the jacking brackets distributed at intervals on the poured sandwich panel G and the high-span I-beam 4, and place the supporting transfer layer pouring formwork on the top of the jacking brackets. After the steel pipes are flattened, the transfer layer pouring formwork connected between the upper part of the girder pouring formwork on both sides is constructed, and the steel bars are bound in the transfer layer pouring formwork, and the concrete is poured together with the upper part of the girder.

实践证明,本实施例与现有技术相比,不仅实施方便高效、安全可靠,可以保证质量,还具有如下显著优点:Practice has proved that compared with the prior art, this embodiment is not only convenient and efficient, safe and reliable, and can guarantee quality, but also has the following significant advantages:

1、本实施例转换层使用的格构柱、贝雷梁、工字钢约277吨,而如采用传统满堂脚手架搭设高支模,则需钢材约1044吨,因此节约周材效果显著。1. In this embodiment, about 277 tons of lattice columns, Bailey beams, and I-beams are used in the transfer floor, and about 1,044 tons of steel are needed if traditional full-house scaffolding is used to erect high formwork, so the effect of saving peripheral materials is remarkable.

2、工具式操作平台使用灵便,安全可靠,不仅可以在安装同一格构柱时反复使用,而且在各格构柱之间周转使用。2. The tool-type operating platform is easy to use, safe and reliable. It can not only be used repeatedly when installing the same lattice column, but also can be used alternately between lattice columns.

3、采用传统满堂脚手架搭设高支模时,将延长首层、-1层、-2层的拆模时间,以及影响地下室的装饰装修进度;而采用本实施例的方法完全不会延长首层、-1层、-2层的拆模时间,也不会影响装饰装修的进度。3. When using the traditional full hall scaffolding to set up high formwork, it will prolong the demolition time of the first floor, -1 floor, and -2 floor, and affect the decoration progress of the basement; and the method of this embodiment will not prolong the first floor at all. , -1 floor, -2 floor demoulding time will not affect the progress of decoration.

4、传统满堂脚手架搭设需要大量场地堆放周材,增加了塔吊负荷,影响其他工序的施工;而本实施例的贝雷架所需场地明显较少,且可堆放在塔吊半径范围内,拼装完成后直接吊装至施工楼层,大大方便了施工。4. The erection of traditional scaffolding requires a large amount of space to stack surrounding materials, which increases the load of the tower crane and affects the construction of other processes; however, the Bailey frame of this embodiment requires significantly less space, and can be stacked within the radius of the tower crane, and the assembly is completed After that, it is directly hoisted to the construction floor, which greatly facilitates the construction.

5、本实施例所用贝雷架总重量仅为采用高支模的1/4,而且装、拆时间明显缩短、安全防护难度也显著减小。5. The total weight of the Bailey frame used in this embodiment is only 1/4 of that of the high-support formwork, and the time for assembly and disassembly is significantly shortened, and the difficulty of safety protection is also significantly reduced.

Claims (4)

1. a kind of high-rise building transfer floor Bailey bracket platform construction method, it is characterised in that the following steps are included:
The first step, installation lattice column --- distinguish installation interval in the position below the corresponding conversion layer crossbeam of building basis two sides The lattice column of distribution, capital are extremely concordant with floor to be converted;
Second step sets up Bailey beam --- and lifting sets up one group of shellfish thunder being respectively supported on ipsilateral lattice column and floor to be converted Beam;
Third step, lifting I-beam --- lifting sets up and is fixed on the interval that in Bailey beam and one group of both ends normal thereto are overhanging It is distributed I-beam, safe protective covering is laid on I-beam and overhanging end builds builder's jack;
4th step builds big beam form bottom --- and the vertical jacking being spaced apart is propped up on I-beam, and is disposed at the top of jacking and propped up respectively Support the flatrack steel pipe of crossbeam and interlayer formwork for placing;
5th step, sandwich boards for construction plate --- beam placement template is constructed on jacking support flatrack steel pipe and to be connected to two sides big Interlayer formwork for placing between in the middle part of beam formwork for placing, and I-girder is disposed in beam placement template, after having bound reinforcing bar Casting concrete, beam placement template are poured to half height;
6th step, construction conversion layer --- in the sandwich plate and height poured across the vertical jacking being spaced apart of branch on I-steel, and At the top of the jacking after the flatrack steel pipe of placement support conversion layer formwork for placing, building be connected to two sides beam placement template top it Between conversion layer formwork for placing, and reinforcing bar has been bound in conversion layer formwork for placing, together with crossbeam top casting concrete.
2. high-rise building transfer floor Bailey bracket platform construction method according to claim 1, it is characterised in that: described first The lattice column of step is spliced section by section from bottom to top using the standard tower section of tower crane;When splicing installation, using tool-type operating platform, institute Concave table top peripheral frame made of operating platform is connected with profile is stated, the peripheral frame upper surface covers fixed cover board, described The wide gabarit with standard tower section matches in the opening of peripheral frame, and guardrail is welded and fixed in the upper surface periphery.
3. high-rise building transfer floor Bailey bracket platform construction method according to claim 2, it is characterised in that: the described 4th In step, each jacking is made of top tool internal thread strut and the pressure pin being screwed in internal screw thread, and the top of the pressure pin is connected The prop head of bracketing flatrack steel pipe is connected between the strut of each jacking by the cross bar being spaced apart above and below, constitutes frame structure.
4. high-rise building transfer floor Bailey bracket platform construction method according to claim 3, it is characterised in that: the described 5th In step, the construction progress step of crossbeam are as follows:
Step 1: paving beam bottom muscle --- it is laid with the bottom muscle of beam placement template bottom interval distribution, and installs beam pad;
Step 2: lifting crossbeam --- I-girder is lifted into the middle part of beam placement template in place, prescinds beam after being welded and fixed Pad;
Step 3: paving beam gluten --- the gluten being spaced apart is laid with above I-girder in place;
Step 4: wearing beam waist muscle --- it is laid with the side muscle that beam placement template two sides and I-girder on both sides of the middle are spaced apart, And by both ends elbow respectively hook around corresponding side muscle be spaced apart waist muscle and I-girder weldering connect, constitute rib cage shape structure;
Step 5: binding stirrup --- binding is spaced apart the stirrup around beam placement template section;
Step 6: envelope beam side --- closing all Side shutterings of beam placement, Side shuttering lower part is with across sandwich wood The split bolt of side is reinforced;
Step 7: beam placement --- casting concrete is poured to half height in beam placement template.
CN201710326359.1A 2017-05-10 2017-05-10 A construction method for the Bailey frame platform of the transfer floor of a high-rise building Withdrawn - After Issue CN108019040B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710326359.1A CN108019040B (en) 2017-05-10 2017-05-10 A construction method for the Bailey frame platform of the transfer floor of a high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710326359.1A CN108019040B (en) 2017-05-10 2017-05-10 A construction method for the Bailey frame platform of the transfer floor of a high-rise building

Publications (2)

Publication Number Publication Date
CN108019040A CN108019040A (en) 2018-05-11
CN108019040B true CN108019040B (en) 2019-08-02

Family

ID=62079206

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710326359.1A Withdrawn - After Issue CN108019040B (en) 2017-05-10 2017-05-10 A construction method for the Bailey frame platform of the transfer floor of a high-rise building

Country Status (1)

Country Link
CN (1) CN108019040B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944444B (en) * 2019-03-27 2021-03-02 中建三局集团有限公司 Template support system and reinforcement and adjustment device of high-precision concrete wall
CN114135096A (en) * 2021-12-31 2022-03-04 浙江城建建设集团有限公司 Ultrahigh structure formwork construction platform and implementation method thereof

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3638571B2 (en) * 2002-05-20 2005-04-13 株式会社竹中工務店 Support load transfer method for existing buildings
CN100460613C (en) * 2005-08-02 2009-02-11 浙江展诚建设集团股份有限公司 Suspension frame construction method
CN201254832Y (en) * 2008-09-10 2009-06-10 中国建筑第四工程局有限公司 Self-supporting template apparatus for conversion layer structure
CN101818570B (en) * 2010-03-23 2011-06-15 南通宏华建筑安装有限公司 Method for constructing girder structure conversion layer of high-rise building
CN102108788A (en) * 2010-12-31 2011-06-29 华煜建设集团有限公司 Method for constructing hanging in the air large-span support
CN103046746B (en) * 2012-12-03 2014-01-29 江苏通州四建集团有限公司 Construction method of conversion beam reinforcing bars for tall building structure
CN104110136A (en) * 2013-04-18 2014-10-22 中冶天工上海十三冶建设有限公司 Erecting method for concrete pouring formwork with structural transition layer comprising H-type steel crossbeam
CN104060760B (en) * 2014-06-19 2016-09-07 浙江勤业建工集团有限公司 High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN104141383B (en) * 2014-07-16 2016-06-01 北京万兴建筑集团有限公司 A kind of Bailey beam pendent form support system and construction thereof

Also Published As

Publication number Publication date
CN108019040A (en) 2018-05-11

Similar Documents

Publication Publication Date Title
JP7602661B2 (en) Lifting device for bridge water surface pile tie beam and its construction method
CN101886466B (en) Construction method for support structure of coal tower template for tamping type coke oven
CN103635643B (en) Construction Method of Reinforced Concrete Cylinder in High-rise Steel Structure Building
CN202227476U (en) High-altitude large-span overhung corridor-type reinforced concrete structure
CN103255838A (en) Construction method with adoption of large-tonnage long-stroke oil cylinder jacking mold frame
CN106400951A (en) Synchronous construction method for horizontal and vertical structures of super high-rise building
CN105863253A (en) Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN114658214A (en) High-rise building disc buckle type high-altitude large-cantilever support frame support and anchor pressing integrated construction method
CN113914223A (en) High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN112832368A (en) Quick construction process for cantilever beam at ultrahigh position
CN104989092B (en) A kind of construction method of high-altitude overhanging superposed type steel truss bearing platform
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN113279582A (en) Hanging construction method for overhanging and hanging type cast-in-place plate
CN115247498A (en) Fixed bolster of prefabricated wallboard and contain braced system of this support
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN108019040B (en) A construction method for the Bailey frame platform of the transfer floor of a high-rise building
CN117145043A (en) Prefabricated corridor, corridor end connection structure and construction method
CN217151150U (en) Overhanging steel truss formwork supporting platform for aluminum mould-full concrete outer wall
CN111847272A (en) Supporting method of tower crane for renovation of existing buildings
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN112960566A (en) Construction method of built-in tower crane of super high-rise building
CN115492389A (en) A Construction Method of Large Section Superelevation Transfer Beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20190802

Effective date of abandoning: 20251104

AV01 Patent right actively abandoned

Granted publication date: 20190802

Effective date of abandoning: 20251104