CN108002208A - A kind of T beams suspender and its hanging method - Google Patents
A kind of T beams suspender and its hanging method Download PDFInfo
- Publication number
- CN108002208A CN108002208A CN201711294991.9A CN201711294991A CN108002208A CN 108002208 A CN108002208 A CN 108002208A CN 201711294991 A CN201711294991 A CN 201711294991A CN 108002208 A CN108002208 A CN 108002208A
- Authority
- CN
- China
- Prior art keywords
- beams
- steel
- bearing pin
- suspender
- arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 15
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 78
- 239000010959 steel Substances 0.000 claims abstract description 78
- 210000001364 upper extremity Anatomy 0.000 claims description 13
- 230000002787 reinforcement Effects 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 2
- 239000000725 suspension Substances 0.000 description 5
- 238000009434 installation Methods 0.000 description 4
- 238000010276 construction Methods 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 2
- 238000004080 punching Methods 0.000 description 2
- 230000006641 stabilisation Effects 0.000 description 2
- 238000011105 stabilization Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/122—Sling or load protectors
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/62—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
- B66C1/64—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled for T- or I-section beams or girders
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The invention discloses a kind of T beams suspender and its hanging method, the T beams suspender includes body, the body upper part is equipped with the coiling sheave coordinated with steel wire rope, and body lower part is equipped with two vertical parallel steel arms, dismountable bearing pin is equipped between the bottom of two steel arms.The present invention can lift by crane 50m across footpaths(Nearly weigh 180 tons)T-shaped beam, have cost it is low, service life length, lifting it is more stable, safely and conveniently the advantages that.
Description
Technical field
The present invention relates to a kind of T beams suspender and its hanging method, belongs to bridge construction ancillary equipment field.
Background technology
In road and bridge construction, prefabricated T-shaped beam needs to lift, and the conventional method lifted is first by steel wire rope lace
Hanging ring pass through the preformed hole of T-shaped beam upper limb, then bypassed from the bottom of prefabricated T-shaped beam, then from prefabricated T-shaped beam upper limb opposite side
Preformed hole be pierced by, finally the hanging ring at steel wire rope both ends is hung on the suspension hook of loop wheel machine in a manner of revealing all the details, can start to lift by crane.
Hoisting prefabricated T-shaped beam is carried out using above-mentioned steel wire rope and is primarily present following deficiency:First, the hanging ring of steel wire rope lace is through pre-
When boxing out, because the diameter of steel wire rope is big, hanging ring penetrates relatively difficult, adds working time and labor intensity;Second, using big
The steel wire rope lifting of diameter, not only of high cost and service life are short;Third, after the lifting of T beams is in place, easily disturbed when taking out steel wire rope
Beam body, causes beam body capsizing case to occur.
CN2011101523262 discloses a kind of hanging method of T-shaped beam, by penetrating stress structure in the bottom of T-shaped beam
Part, then penetrates steel suspender belt vertically in the preformed hole of T-shaped beam upper limb, and the bottom of steel suspender belt is equipped with that upper radius is big, lower part half
The small bar hole in footpath, then the steel suspender belt of T-shaped beam both sides be sleeved on by bar hole on steel pin, the top of steel suspender belt connects with suspension hook
Connect, the semicircle for slinging rear steel suspender belt lower part is stuck on steel pin, and after lifting in place, Panasonic's suspension hook, steel suspender belt moves down, bar hole top
Semicircle and knob end to it is corresponding when steel suspender belt exited under the restoring force effect of compression spring.Although steel suspender belt service life is grown, cost
It is low and relatively easy for installation, but still there are following defect:
1st, the maximum capacity point of lifting is on steel pin, and steel pin is divided into left steel pin, right steel pin, after a number of uses, steel pin meeting again
There is the situation for going out abjection from bar hole, and this can cause Hoisting Security accident, there is the risk for smashing, injuring by a crashing object;
When the 2nd, lifting by crane, the hole for hoist at steel suspender belt both ends is caught on by four suspension hooks, opereating specification span is big, and there are security risk;
3rd, through T beams bottom after steel suspender belt is passed through from T backs portion, lifting center is relatively low, and lifting is unstable while more laborious, hangs
Fill risk bigger.
The content of the invention
In view of the deficiency of the prior art, it is more reasonable the object of the present invention is to provide a kind of structure design and hang
Dress more stable T beams suspender and its hanging method.
To achieve the above object, one of the technical solution adopted by the present invention is:T beam suspenders, including body, on the body
Portion is equipped with the coiling sheave coordinated with steel wire rope, and body lower part is equipped with two vertical parallel steel arms, the bottom of two steel arms
Dismountable bearing pin is equipped between portion.
The coiling sheave is multiple composition sheave groups.
Described two steel arms are coaxially hinged on the body.
The bottom of described two steel arms is equipped with bolt hole, and the bearing pin is located at the spiral shell between two steel arm bottoms
In keyhole, and the outside screw positioned at steel arm on bearing pin both ends is connected with Safety nut.
The two of the technical solution adopted by the present invention are:T beam hanging methods, using the T beams suspender, include the following steps:
(1)The center hole of a perforation is had on the web at T beams both ends, the upper limb of web top both sides is located on T beams
On be symmetrically provided with arm hole corresponding with the center hole;
(2)Be respectively aligned to T beams both ends using two T beams suspenders, by two steel arms of each T beams suspender respectively on to
Under through symmetrical arm hole on the upper limb of T beams and the bolt hole of steel arm bottom is directed at center hole on the web, use
Bearing pin is from the center hole run through between the bolt hole of two steel arms in T beam webs, the then bearing pin on the outside of steel arm
Safety nut is fixed at both ends, completes assembling;
(3)Lifted by crane with lifting equipment by steel wire rope, unload suspender, complete the lifting of T beams.
Center hole present position in the T beam webs is apart from upper limb bottom 50-100cm.
Above-mentioned bearing pin selects No. 45 steel columns of a diameter of 80-100mm, and bearing pin both ends are machined with and spiral shell in Safety nut
The external screw thread that line matches, and attach safety anti-falling pin;The length of steel arm is 120-180cm, and steel arm thickness is 25-
35mm。
The raising of bearing pin position, preferably ensures stability during bale handle and falls the various safety of dismounting bearing pin after beam
Risk.
Center hole generation type in above-mentioned T beam webs is:In T beam manufacturing process, by T beams designated position it is pre-
Pvc pipes are buried, reinforcing bar reinforcement are used around pvc pipes, through being expounded through peer review and calculating, to beam body quality without any damage;After the completion of lifting,
Center hole is blocked, on presentation quality without influence.
Beneficial effect
Compared with prior art, advantages of the present invention is:
1st, bearing pin is integral, and is not easy to spin off from T beams, is reduced the risk that comes off;
2nd, single wire rope multiply can be used to concentrate lifting using sheave group, effectively raises the weight limit of lifting, also contract
Small hoisting span, opereating specification reduce, and reduce opereating specification risk;
3rd, steel length of boom greatly shortens, and lifting center is improved, the stabilization after being conducive to hanging beam process and fastening, and is lifted more
Steadily, it is laborsaving;
4th, T girder prefabricated pedestals need not reserve suspension centre notch, and globality is more preferable.
The present invention can lift by crane 50m across footpaths(Nearly weigh 180 tons)T-shaped beam, have cost it is low, service life length, lifting more
For stabilization, safely and conveniently the advantages that.
Brief description of the drawings
Attached drawing is for providing a further understanding of the present invention, and a part for constitution instruction, with following tool
Body embodiment is used to explain the present invention together, but is not construed as limiting the invention.
In the accompanying drawings:
Fig. 1 is the structural perspective of T beams punching suspender of the present invention.
Fig. 2 is the side view of the present invention.
Fig. 3 is the bottom view of the present invention.
Fig. 4 is the schematic diagram of present invention lifting T beams.
Fig. 5 is the left view of Fig. 4.
In attached drawing:1st, body, 2, fixing axle, 3, coiling sheave, 4, catch, 5, steel wire rope, 6, installation axle, 7, steel arm,
701st, bolt hole, 8, bearing pin, 9, Safety nut, 10, banking stop, 11, T beams, 1101, web, 1102, center hole, 1103, on
The wing, 1104, arm hole.
Embodiment
Presently in connection with accompanying drawings and embodiments, the invention will be further described.Obviously, it is impossible to therefore limit the present invention to
Among the embodiment described scope.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creativeness
All other embodiments obtained on the premise of work, are within the scope of protection of the invention.
Embodiment
As shown in Figs. 1-3, T beam suspenders of the invention, including body 1, the top of body 1 and bottom are open, 1 top of body
The sheave group being made of multiple coiling sheaves 3 is provided with by fixing axle 2, steel cable 5 is wound with each coiling sheave 3,
It is equidistant on body 1 to be welded with multiple catch 4 and separate each coiling sheave 3;The left and right both ends in 1 lower part of body pass through same
A installation axle 6 is fixed with two steel arms 7, is respectively fixed with positioned at the inner side of two steel arms 7 in installation axle 6 and is hung for limiting steel
The banking stop 10 of 7 transverse shifting of arm, the bottom of each steel arm 7 are provided with bolt hole 701, have a bearing pin 8 to pass through two steel
Bolt hole 701 on arm 7 is simultaneously connected with Safety nut 9 at 8 both ends of bearing pin and positioned at the outside screw of steel arm 7.
The hanging method of the present invention, as shown in Fig. 4-Fig. 5, comprises the following steps:
(1)The center hole 1102 of a perforation is had on the web 1101 at T beams both ends, on T beams on web 1101
Arm hole 1104 corresponding with the center hole 1102 is symmetrically provided with the upper limb 1103 of portion both sides, 11 height of T beams is 2.5m, is worn
1102 present position distance T beams upper limb of heart hole, 1103 bottom 80cm;The generation type of center hole 1102 is:Made in T beams 11
Cheng Zhong, by the pre-buried pvc pipes in designated position on T beams 11, reinforcing bar reinforcement is used around pvc pipes;
(2)Two T beam web punching suspenders are respectively aligned to T beams both ends, by two steel arms of each T beams suspender respectively by upper
It is passed down through symmetrical arm hole 1104 on the upper limb 1103 of T beams and the bolt hole 701 of 7 bottom of steel arm is directed at web 1101
On center hole 1102, with bearing pin 8 between the bolt hole 701 of two steel arms 7 run through T beam webs 1101 on center hole
1102, Safety nut 9 then is fixed at 8 both ends of bearing pin in the outside of steel arm 7, completes assembling;Bearing pin 8 is selected a diameter of
No. 45 steel columns of 80-100mm, 8 both ends of bearing pin are machined with the external screw thread to match with the internal thread of Safety nut, steel arm
Length 120-180cm, steel arm thickness are 25-35mm;
(3)Lifted by crane with lifting equipment by steel wire rope 5, unload suspender, complete the lifting of T beams 11.
Center hole present position in the T beam webs is apart from upper limb bottom 50-100cm.
Above-mentioned bearing pin selects No. 45 steel columns of a diameter of 80-100mm, and bearing pin both ends are machined with and spiral shell in Safety nut
The external screw thread that line matches, and attach safety anti-falling pin;The length of steel arm is 120-180cm, and steel arm thickness is 25-
35mm。
The raising of bearing pin position, preferably ensures stability during bale handle and falls the various safety of dismounting bearing pin after beam
Risk.
Center hole generation type in above-mentioned T beam webs is:In T beam manufacturing process, by T beams designated position it is pre-
Pvc pipes are buried, reinforcing bar reinforcement are used around pvc pipes, through being expounded through peer review and calculating, to beam body quality without any damage;After the completion of lifting,
Center hole is blocked, on presentation quality without influence.
The suspender and hanging method of the present invention, can control the quality of beam body, ensure the balance and stability of hoisting process beam body,
The security of suspender is taken after improving beam.
Claims (8)
1. a kind of T beams suspender, it is characterized in that including body, the body upper part is equipped with the coiling sheave coordinated with steel wire rope, this
Body lower part is equipped with two vertical parallel steel arms, and dismountable bearing pin is equipped between the bottom of two steel arms.
2. T beams suspender according to claim 1, it is characterized in that the coiling sheave is multiple composition sheave groups.
3. T beams suspender according to claim 2, it is characterized in that described two steel arms are coaxially hinged on the body.
4. T beams suspender according to claim 3, it is characterized in that the bottom of described two steel arms is equipped with bolt hole, institute
State in the bolt hole that bearing pin is located between two steel arm bottoms, and be located at the outside screw of steel arm on bearing pin both ends
It is connected with Safety nut.
A kind of 5. T beam hanging methods using T beams suspender as claimed in claim 4, it is characterized in that including the following steps:
(1)The center hole of a perforation is had on the web at T beams both ends, the upper limb of web top both sides is located on T beams
On be symmetrically provided with arm hole corresponding with the center hole;
(2)Be respectively aligned to T beams both ends using two T beams suspenders, by two steel arms of each T beams suspender respectively on to
Under through symmetrical arm hole on the upper limb of T beams and the bolt hole of steel arm bottom is directed at center hole on the web, use
Bearing pin is from the center hole run through between the bolt hole of two steel arms in T beam webs, the then bearing pin on the outside of steel arm
Safety nut is fixed at both ends, completes assembling;
(3)Lifted by crane with lifting equipment by steel wire rope, unload suspender, complete the lifting of T beams.
6. T beams hanging method according to claim 5, it is characterized in that center hole present position in the T beam webs away from
From upper limb bottom 50-100cm.
7. T beams hanging method according to claim 6, it is characterized in that above-mentioned bearing pin selects the 45 of a diameter of 80-100mm
Number steel column, bearing pin both ends are machined with the external screw thread to match with Safety nut internal thread, and attach safety anti-falling pin;Steel arm
Length be 120-180cm, steel arm thickness is 25-35mm.
8. T beams hanging method according to claim 7, it is characterized in that the center hole generation type in above-mentioned T beam webs is:
In T beam manufacturing process, by the pre-buried pvc pipes in designated position on T beams, reinforcing bar reinforcement is used around pvc pipes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711294991.9A CN108002208A (en) | 2017-12-08 | 2017-12-08 | A kind of T beams suspender and its hanging method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711294991.9A CN108002208A (en) | 2017-12-08 | 2017-12-08 | A kind of T beams suspender and its hanging method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108002208A true CN108002208A (en) | 2018-05-08 |
Family
ID=62057726
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711294991.9A Pending CN108002208A (en) | 2017-12-08 | 2017-12-08 | A kind of T beams suspender and its hanging method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108002208A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200397213Y1 (en) * | 2005-06-29 | 2005-09-29 | (주)한맥기술 | Mounting structure of Steel Cross-beam in Multi-girder concrete bridge and its construction method |
CN201169485Y (en) * | 2007-12-18 | 2008-12-24 | 中铁六局集团有限公司 | T-shaped girder hoisting tools |
CN102285582A (en) * | 2011-06-08 | 2011-12-21 | 中冶建工集团有限公司 | T-beam hoisting method |
CN202864667U (en) * | 2012-10-22 | 2013-04-10 | 中交第二航务工程局有限公司 | Auxiliary device for lifting beam body |
CN203754223U (en) * | 2014-04-01 | 2014-08-06 | 葛洲坝集团第五工程有限公司 | Lifting tool for lifting precast beams in bridge precast plant |
CN206052551U (en) * | 2016-07-26 | 2017-03-29 | 中铁十二局集团第四工程有限公司 | A kind of suspender |
CN207608203U (en) * | 2017-12-08 | 2018-07-13 | 湖南路桥建设集团有限责任公司 | A kind of T beams suspender |
-
2017
- 2017-12-08 CN CN201711294991.9A patent/CN108002208A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200397213Y1 (en) * | 2005-06-29 | 2005-09-29 | (주)한맥기술 | Mounting structure of Steel Cross-beam in Multi-girder concrete bridge and its construction method |
CN201169485Y (en) * | 2007-12-18 | 2008-12-24 | 中铁六局集团有限公司 | T-shaped girder hoisting tools |
CN102285582A (en) * | 2011-06-08 | 2011-12-21 | 中冶建工集团有限公司 | T-beam hoisting method |
CN202864667U (en) * | 2012-10-22 | 2013-04-10 | 中交第二航务工程局有限公司 | Auxiliary device for lifting beam body |
CN203754223U (en) * | 2014-04-01 | 2014-08-06 | 葛洲坝集团第五工程有限公司 | Lifting tool for lifting precast beams in bridge precast plant |
CN206052551U (en) * | 2016-07-26 | 2017-03-29 | 中铁十二局集团第四工程有限公司 | A kind of suspender |
CN207608203U (en) * | 2017-12-08 | 2018-07-13 | 湖南路桥建设集团有限责任公司 | A kind of T beams suspender |
Non-Patent Citations (2)
Title |
---|
成志辉;: "T型梁吊装方式的改进", 交通标准化, no. 09, pages 233 - 234 * |
谭逸波;谭昱;李志生;荣国城;: "大型预制墩台吊装吊具及抗浮装置设计", 公路, no. 05 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207192616U (en) | A kind of gantry crane for preventing that goods from rocking | |
CN105484503B (en) | One kind tilts fusiformis space truss hanging method | |
CN101880009A (en) | Flat-head tower crane | |
CN108892060A (en) | A kind of crane upper mechanism is from dismantling device, crane and tears method open certainly | |
CN207608203U (en) | A kind of T beams suspender | |
CN206665952U (en) | A kind of novel hanging tool | |
CN108946475A (en) | A kind of overturning Lift-on/Lift-off System and hanging method for horizontal equipment | |
CN101412488B (en) | Air turnover device and method for special-shaped barrel | |
CN108002208A (en) | A kind of T beams suspender and its hanging method | |
CN201385979Y (en) | Rotary lifting bent | |
CN214527651U (en) | Hoisting device for production and processing of mining equipment rack | |
CN207243271U (en) | Handling molten metal crane balance pulley and pulley blocks | |
CN106522097A (en) | Self-adaptive cable cranes for extra large space-cross cable face suspension bridge girder erection | |
CN101402435B (en) | Special sling for inner bore of step and its use method | |
CN110963407B (en) | Hoisting and overturning method for square pyramid equipment | |
CN203513086U (en) | Special lifting appliance for long-bundle-shaped material | |
CN2910879Y (en) | Single hook four points self-balancing sling of lifter | |
CN213569142U (en) | High lifting machine of security for civil engineering | |
CN106480824B (en) | A kind of handling method of cable wire tower | |
CN210117158U (en) | Boom nut mounting device for large-tonnage bridging machine | |
CN209082340U (en) | Large-span steel girder lifting device | |
CN201236098Y (en) | Combined pressure bar sling | |
CN203213018U (en) | Lifting device for rigid hinges and large components | |
CN207618894U (en) | Hydraulic generator rotor rigidity lifting tool | |
CN205241050U (en) | I -shaped wheel lifting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20181224 Address after: 410004 No. 239 Shaoshan South Road, Yuhua District, Changsha City, Hunan Province Applicant after: Hunan Transportation and Water Conservancy Construction Group Co., Ltd. Applicant after: Hunan Road & Bridge Construction Group Co., Ltd. Address before: 410004 No. 239 Shaoshan South Road, Yuhua District, Changsha City, Hunan Province Applicant before: Hunan Road & Bridge Construction Group Co., Ltd. |