CN107965141A - The stair tread formwork that both sides are provided with shear wall installs device and erection method - Google Patents

The stair tread formwork that both sides are provided with shear wall installs device and erection method Download PDF

Info

Publication number
CN107965141A
CN107965141A CN201810024338.9A CN201810024338A CN107965141A CN 107965141 A CN107965141 A CN 107965141A CN 201810024338 A CN201810024338 A CN 201810024338A CN 107965141 A CN107965141 A CN 107965141A
Authority
CN
China
Prior art keywords
steel pipe
stair
shear wall
marking time
upper strata
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810024338.9A
Other languages
Chinese (zh)
Inventor
冯波
雷秀清
冯永峰
邵艳丽
王鹏
焦鹏飞
时彩峰
武喆广
张峰
杨志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Sanjian Group Co Ltd
Original Assignee
Shanxi Sanjian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Sanjian Group Co Ltd filed Critical Shanxi Sanjian Group Co Ltd
Priority to CN201810024338.9A priority Critical patent/CN107965141A/en
Publication of CN107965141A publication Critical patent/CN107965141A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/062Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for stairs or steps

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Moulds, Cores, Or Mandrels (AREA)
  • Steps, Ramps, And Handrails (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The stair tread formwork that shear wall is provided with the invention discloses a kind of both sides installs device and erection method, solves the problems, such as that stair step structure size deviation existing for existing template is excessive and construction procedure is cumbersome.Including left side shear wall(10), right side shear wall(11)With lower floor's stair step(1), in upper strata stair bottom plate(4)Top surface on be provided with stop sleeve(17), in left side shear wall(10)With right side shear wall(11)Between compartment of terrain apical grafting have transverse horizontal supporting steel pipe(9), in transverse horizontal supporting steel pipe(9)Upper compartment of terrain is welded with inclined shore steel pipe(8), in inclined shore steel pipe(8)On be welded with tooth form reinforcing bar of marking time(7), in tooth form reinforcing bar of marking time(7)On be provided with supporting rod(16), supporting rod(16)It is actively socketed on stop sleeve(17)In, in tooth form reinforcing bar of marking time(7)On be plugged with template of marking time(12).Instinct invents the production quality for improving stair step.

Description

The stair tread formwork that both sides are provided with shear wall installs device and erection method
Technical field
The present invention relates to a kind of high-rise stair formwork erection device, more particularly to one kind is in shear wall structure cantilever stair The more stair template of index bed install device and erection method.
Background technology
Stair step in general shear wall structure building has two kinds of forms, and a kind of is that side of marking time has the building of shear wall Ladder, another kind are the stair for having shear wall in both sides of marking time;The process that performs for having the stair step of shear wall to both sides is: On the stair that lower first floor ladder concrete strength reaches after installing upper strata frame body requirement, the stair template branch of last layer is set up Frame, then installs the bottom plate of this floor ladder, binds stair reinforcing bar, and according to absolute altitude and size of marking time, even partition stair are stepped on Step, independently installs template of marking time, and a steel pipe is crimped in the upper end for template of respectively marking time, and consolidated with steel pipe with the silk template that will mark time is tied up It is scheduled on together, marks time during casting concrete bulge phenomenon occur in order to prevent, is carried out in the lower end of template with the lumps of wood Apical grafting is fixed, and finally carries out concreting, and it is that substep carries out that the template of this construction method, which is set up, the time length set up, Be especially in the presence of stair tread formwork can not fixation the defects of, bulge phenomenon often occurs in casting process, due to The support of whole formwork erection system is by two steel pipe banding fixeds set along stair direction, two in casting process Steel pipe is easily distorted dislocation, be easy to cause the stair step torsional deformation poured.
The content of the invention
The stair tread formwork that shear wall is provided with the present invention provides a kind of both sides installs device and erection method, solves Stair step structure size deviation existing for existing template is excessive and the cumbersome technical problem of construction procedure.
The present invention is to solve above technical problem by the following technical programs:
The stair tread formwork that a kind of both sides are provided with shear wall installs device, including left side shear wall, right side shear wall and under Floor ladder rung, chock is provided with lower floor's stair step, and upper former supporting frame is provided with chock, in upper strata mould Upper strata stair bottom plate is provided with plate bracing frame body, upper strata stair bottom plate is arranged on upper strata half space and stops with lower floor Between ceasing platform, stop sleeve is provided with the top surface of upper strata stair bottom plate, shear wall and right side shear wall in left side Between compartment of terrain apical grafting have transverse horizontal supporting steel pipe, compartment of terrain is welded with inclined shore steel on transverse horizontal supporting steel pipe Pipe, tooth form reinforcing bar of marking time is welded with inclined shore steel pipe, supporting rod is provided with tooth form reinforcing bar marking time, supporting rod activity It is socketed in stop sleeve, template of marking time is plugged with tooth form reinforcing bar marking time.
Level(l)ing bubble is provided with transverse horizontal supporting steel pipe, hanging ring is provided with inclined shore steel pipe;In transverse direction The both ends of horizontal support steel pipe are both provided with nut, and screw rod is bolted with nut, and U-shaped is connected with the outboard end of screw rod Support.
A kind of both sides are provided with the stair tread formwork erection method of shear wall, comprise the following steps:
The first step, pad sets chock in lower floor's stair step, upper former supporting frame is set on chock, in upper former branch Upper strata stair bottom plate is set on support body, stop sleeve is set on the top surface of upper strata stair bottom plate;
Second step, absolute altitude and axis position according to the top half spaces of upper strata stair and the lower part half space of lower floor's stair Put, determine the first step step of this floor ladder rung and the absolute altitude of final step step and axial location size, cross machine water Flat supporting steel pipe and inclined shore steel pipe, by spaced transverse horizontal supporting steel pipe and spaced inclined shore steel pipe Assembly is simultaneously welded into rectangular general frame;
3rd step, tooth form reinforcing bar of marking time by this floor ladder rung making of design requirement, and it is welded to inclined shore steel pipe On, marking time supporting rod is welded on tooth form reinforcing bar;
Nut is set at the both ends of transverse horizontal supporting steel pipe, screw rod is bolted with nut, U is connected on the outboard end of screw rod Shape support;
4th step, the top that general frame is lifted into upper strata stair bottom plate, by adjusting screw rod, support transverse horizontal The both ends apical grafting of steel pipe is between left side shear wall and right side shear wall, and the supporting rod grafting that will be welded on tooth form reinforcing bar of marking time In stop sleeve;The position of transverse horizontal supporting steel pipe is adjusted by level(l)ing bubble, until whole template system acceptance(check).
The present invention sets up cope plate of marking time by overall, overcomes the defects of scene overlap joint error is big, tooth of particularly marking time The setting of shape reinforcing bar enormously simplify the program of setting up for template of marking time, accurate positioning, by being set on transverse horizontal supporting steel pipe The level(l)ing bubble put can accurately realize the installation positioning of integral mold plate, avoid the inclination and dislocation of template, improve stair step Production quality.
Brief description of the drawings
Fig. 1 is the structure diagram of the present invention;
Fig. 2 is structure diagram of the present invention in overlook direction;
Fig. 3 is the structure diagram of the overall cope plate of marking time of the present invention;
The entirety that Fig. 4 is the present invention is marked time structure diagram of the cope plate in overlook direction;
Fig. 5 is the fiting relation figure between tooth form reinforcing bar 7 of marking time, template of marking time 12 and the stop sleeve 17 of the present invention;
Fig. 6 is the end construction schematic diagram of transverse horizontal supporting steel pipe 9.
Embodiment
The present invention is described in detail below in conjunction with the accompanying drawings:
The stair tread formwork that a kind of both sides are provided with shear wall installs device, including left side shear wall 10, right side shear wall 11 With lower floor stair step 1, chock 2 is provided with lower floor's stair step 1, upper former supporting frame is provided with chock 2 3, upper strata stair bottom plate 4 is provided with upper former supporting frame 3, upper strata stair bottom plate 4 is arranged on upper strata and stops Cease between platform 5 and lower floor's half space 6, stop sleeve 17 is provided with the top surface of upper strata stair bottom plate 4, in left side Compartment of terrain apical grafting has transverse horizontal supporting steel pipe 9 between shear wall 10 and right side shear wall 11, on transverse horizontal supporting steel pipe 9 Compartment of terrain is welded with inclined shore steel pipe 8, and tooth form reinforcing bar 7 of marking time is welded with inclined shore steel pipe 8, in tooth form reinforcing bar of marking time Supporting rod 16 is provided with 7, supporting rod 16 is actively socketed in stop sleeve 17, is marked time marking time to be plugged with tooth form reinforcing bar 7 Template 12.
Level(l)ing bubble 19 is provided with transverse horizontal supporting steel pipe 9, hanging ring 18 is provided with inclined shore steel pipe 8; Nut 14 is both provided with the both ends of transverse horizontal supporting steel pipe 9, screw rod 13 is bolted with nut 14, in the outside of screw rod 13 U-shaped support 15 is connected with end.
A kind of both sides are provided with the stair tread formwork erection method of shear wall, comprise the following steps:
The first step, pad sets chock 2 in lower floor's stair step 1, upper former supporting frame 3 is set on chock 2, in upper strata mould Upper strata stair bottom plate 4 is set on plate bracing frame body 3, stop sleeve 17 is set on the top surface of upper strata stair bottom plate 4;
Second step, absolute altitude and axis position according to the top half spaces 5 of upper strata stair and the lower part half space 6 of lower floor's stair Put, determine the first step step of this floor ladder rung and the absolute altitude of final step step and axial location size, cross machine water Flat supporting steel pipe 9 and inclined shore steel pipe 8, by spaced transverse horizontal supporting steel pipe 9 and spaced inclined shore Steel pipe 8 is assembled and is welded into rectangular general frame;
3rd step, tooth form reinforcing bar 7 of marking time by this floor ladder rung making of design requirement, and it is welded to inclined shore steel pipe On 8, supporting rod 16 is welded on tooth form reinforcing bar 7 marking time;
Nut 14 is set at the both ends of transverse horizontal supporting steel pipe 9, screw rod 13 is bolted with nut 14, in the outside of screw rod 13 U-shaped support 15 is connected on end;
4th step, the top that general frame is lifted into upper strata stair bottom plate 4, by adjusting screw rod 13, make transverse horizontal The both ends apical grafting of supporting steel pipe 9 will weld on tooth form reinforcing bar 7 of marking time between left side shear wall 10 and right side shear wall 11 Supporting rod 16 is plugged in stop sleeve 17;The position of transverse horizontal supporting steel pipe 9 is adjusted by level(l)ing bubble 19, until whole Template system acceptance(check).

Claims (3)

1. the stair tread formwork that a kind of both sides are provided with shear wall installs device, including left side shear wall(10), right side shearing Wall(11)With lower floor's stair step(1), in lower floor's stair step(1)On be provided with chock(2), in chock(2)On be provided with Layer template support frame body(3), in upper former supporting frame(3)On be provided with upper strata stair bottom plate(4), upper strata stair bottom Template die plate(4)It is arranged on upper strata half space(5)With lower floor's half space(6)Between, it is characterised in that in upper strata stair bottom plate Template(4)Top surface on be provided with stop sleeve(17), in left side shear wall(10)With right side shear wall(11)Between compartment of terrain Apical grafting has transverse horizontal supporting steel pipe(9), in transverse horizontal supporting steel pipe(9)Upper compartment of terrain is welded with inclined shore steel pipe(8), In inclined shore steel pipe(8)On be welded with tooth form reinforcing bar of marking time(7), in tooth form reinforcing bar of marking time(7)On be provided with supporting rod(16), Supporting rod(16)It is actively socketed on stop sleeve(17)In, in tooth form reinforcing bar of marking time(7)On be plugged with template of marking time(12).
2. the stair tread formwork that a kind of both sides according to claim 1 are provided with shear wall installs device, its feature exists In in transverse horizontal supporting steel pipe(9)On be provided with level(l)ing bubble(19), in inclined shore steel pipe(8)On be provided with hanging ring (18);In transverse horizontal supporting steel pipe(9)Both ends be both provided with nut(14), in nut(14)In be bolted with screw rod(13), In screw rod(13)Outboard end on be connected with U-shaped support(15).
3. a kind of both sides are provided with the stair tread formwork erection method of shear wall, comprise the following steps:
The first step, in lower floor's stair step(1)Upper pad sets chock(2), in chock(2)Upper setting upper former supporting frame(3), In upper former supporting frame(3)Upper setting upper strata stair bottom plate(4), in upper strata stair bottom plate(4)Top surface on Stop sleeve is set(17);
Second step, the top half space according to upper strata stair(5)And the lower part half space of lower floor's stair(6)Absolute altitude and axis Line position, determines the first step step of this floor ladder rung and the absolute altitude of final step step and axial location size, and processing is horizontal To horizontal support steel pipe(9)With inclined shore steel pipe(8), by spaced transverse horizontal supporting steel pipe(9)With interval setting Inclined shore steel pipe(8)Assembly is simultaneously welded into rectangular general frame;
3rd step, tooth form reinforcing bar of marking time by this floor ladder rung making of design requirement(7), and it is welded to inclined shore steel Pipe(8)On, in tooth form reinforcing bar of marking time(7)Upper welding supporting rod(16);
In transverse horizontal supporting steel pipe(9)Both ends set nut(14), in nut(14)In be bolted with screw rod(13), in screw rod (13)Outboard end on connect U-shaped support(15);
General frame, is lifted into upper strata stair bottom plate by the 4th step(4)Top, by adjusting screw rod(13), make transverse direction Horizontal support steel pipe(9)Both ends apical grafting in left side shear wall(10)With right side shear wall(11)Between, and the tooth form steel that will mark time Muscle(7)The supporting rod of upper welding(16)It is plugged on stop sleeve(17)In;Pass through level(l)ing bubble(19)Adjust transverse horizontal support Steel pipe(9)Position, until whole template system acceptance(check).
CN201810024338.9A 2018-01-10 2018-01-10 The stair tread formwork that both sides are provided with shear wall installs device and erection method Pending CN107965141A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810024338.9A CN107965141A (en) 2018-01-10 2018-01-10 The stair tread formwork that both sides are provided with shear wall installs device and erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810024338.9A CN107965141A (en) 2018-01-10 2018-01-10 The stair tread formwork that both sides are provided with shear wall installs device and erection method

Publications (1)

Publication Number Publication Date
CN107965141A true CN107965141A (en) 2018-04-27

Family

ID=61993438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810024338.9A Pending CN107965141A (en) 2018-01-10 2018-01-10 The stair tread formwork that both sides are provided with shear wall installs device and erection method

Country Status (1)

Country Link
CN (1) CN107965141A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962962A (en) * 2021-03-15 2021-06-15 山西三建集团有限公司 Building method of modularly assembled cast-in-place concrete stair template system
TWI745011B (en) * 2020-08-06 2021-11-01 李松霖 Stair construction structure
CN118148355A (en) * 2024-05-09 2024-06-07 山西三建集团有限公司 Template construction equipment and method for aluminum film closed type stairs

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669865A (en) * 2013-12-20 2014-03-26 广东省第四建筑工程公司 Stair construction method through shaped supports
CN203640278U (en) * 2013-12-20 2014-06-11 茂名市建筑集团有限公司 Stair construction die shelf
CN104878924A (en) * 2015-05-29 2015-09-02 成都市第二建筑工程公司 Stair step concrete pouring-molded template and stair cast-in-situ construction method
CN207920076U (en) * 2018-01-10 2018-09-28 山西三建集团有限公司 The stair tread formwork that both sides are provided with shear wall installs device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669865A (en) * 2013-12-20 2014-03-26 广东省第四建筑工程公司 Stair construction method through shaped supports
CN203640278U (en) * 2013-12-20 2014-06-11 茂名市建筑集团有限公司 Stair construction die shelf
CN104878924A (en) * 2015-05-29 2015-09-02 成都市第二建筑工程公司 Stair step concrete pouring-molded template and stair cast-in-situ construction method
CN207920076U (en) * 2018-01-10 2018-09-28 山西三建集团有限公司 The stair tread formwork that both sides are provided with shear wall installs device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI745011B (en) * 2020-08-06 2021-11-01 李松霖 Stair construction structure
CN112962962A (en) * 2021-03-15 2021-06-15 山西三建集团有限公司 Building method of modularly assembled cast-in-place concrete stair template system
CN118148355A (en) * 2024-05-09 2024-06-07 山西三建集团有限公司 Template construction equipment and method for aluminum film closed type stairs

Similar Documents

Publication Publication Date Title
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN105863253B (en) Integral formwork support is asynchronous to pour staircase wall column formwork system and construction method
CN205604088U (en) But bent cap quick adjustment support
CN107965141A (en) The stair tread formwork that both sides are provided with shear wall installs device and erection method
CN105804395B (en) Stair continuously poured in one molding construction method based on monoblock type typified form
CN108265885A (en) The construction method of tall and big nonopiate high inclination-angle abnormal shape concrete batter post
CN106638947A (en) Prefabricated frame structure and cascaded prefabrication construction method thereof
CN114770706B (en) Light T-beam prefabrication equipment and prefabrication installation construction method
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
CN108914780A (en) A kind of bridge tall pier and thin wall hydraulic sliding mould construction method
CN110700570A (en) Construction method of cast-in-place concrete curved surface inclined cylinder structure
CN115369749A (en) Pier column-beam-bent cap beam integrated public rail double-layer viaduct and construction method
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN205894670U (en) Template structure for concrete joint construction between floors
CN114717968A (en) Construction method for main tower of cable-stayed bridge
CN105735638B (en) A kind of bracket is poured with arcuate die processing method and its bracket casting method
CN207920076U (en) The stair tread formwork that both sides are provided with shear wall installs device
CN102936958A (en) Construction method for positioning upper reinforcements of concrete floor slab by using tool type supports
CN105735474A (en) Single-layer steel pipe column construction method for core tube beam column
CN113123597A (en) Assembled laminated slab splicing seam suspension type formwork structure and construction method thereof
CN210947781U (en) Slip form construction horizontal reinforcement auxiliary positioning instrument
CN112458905A (en) Splicing adjustment method for prefabricated capping beam and prefabricated stand column
CN107142834A (en) A kind of Through Steel pipe concrete tie-rod arch bridge abutment steel pipe location structure and its construction method
CN206553938U (en) Bridge pier integral formwork support one-shot forming structure
CN110080271A (en) The construction method of the pre-buried quality control of foundation bolt embedded part

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180427

WD01 Invention patent application deemed withdrawn after publication