CN107954306A - Precast stair Lift-on/Lift-off System and hanging method - Google Patents

Precast stair Lift-on/Lift-off System and hanging method Download PDF

Info

Publication number
CN107954306A
CN107954306A CN201711163062.4A CN201711163062A CN107954306A CN 107954306 A CN107954306 A CN 107954306A CN 201711163062 A CN201711163062 A CN 201711163062A CN 107954306 A CN107954306 A CN 107954306A
Authority
CN
China
Prior art keywords
hoisting
hoist
hole
lift
precast stair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711163062.4A
Other languages
Chinese (zh)
Inventor
李琰
潘峰
邱迪
沈浅灏
曹刘坤
韩亚明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201711163062.4A priority Critical patent/CN107954306A/en
Publication of CN107954306A publication Critical patent/CN107954306A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of precast stair Lift-on/Lift-off System and hanging method, belong to the lifting field of construction, for solving the pre-buried lifting connector on precast stair in the prior art, the problem of lifting is easily come off in hoisting process with connector and occurs not lifting or even occur lifting accident.The present invention on the precast stair by setting two holes for hoist pair, each pair hole for hoist is to including two vertically arranged holes for hoist, each hoisting steel beam is correspondingly arranged in each hole for hoist to lower section, and opened up on each hoisting steel beam with corresponding hole for hoist to corresponding through hole, drawing-in is connected after corresponding to the correspondence hole for hoist of correspondence hole for hoist centering on the correspondence through hole and precast stair of hoisting steel beam with shoulder pole for hoisting successively respectively at the both ends of every first steel wire rope, the first steel wire rope is enabled to pass through the safely and reliably hoisting prefabricated stair of the vertical hole for hoist and hoisting steel beam on precast stair, improve the security of precast stair lifting, and construction efficiency can be improved.

Description

Precast stair Lift-on/Lift-off System and hanging method
Technical field
The present invention relates to construction to lift field, more particularly to a kind of precast stair Lift-on/Lift-off System and hanging method.
Background technology
With prefabricated concrete structure large-area applications, in prefabrication building course, a large amount of prefabricated components Lifting is needed to install, since a large amount of prefabricated components such as precast stair is made by armored concrete, construction weight is big, and lifting adopts Lifted with large-scale tower crane, sling height is high, has certain danger, and current most of prefabricated part hangings use component , there is suspension centre damage in installation process is lifted, construction weight is big, hoisting height is high, hangs in the mode of interior suspension-center pre-embedded Component is caused to fall after point failure dangerous very big.
Because how to provide a kind of Hoisting Security and lift efficient precast stair Lift-on/Lift-off System and hanging method, it is This area technical problem urgently to be resolved hurrily.
The content of the invention
It is an object of the invention to provide a kind of precast stair Lift-on/Lift-off System and hanging method, by pre- on precast stair Stay vertical hole for hoist and hoisting steel beam is set, can avoid the occurrence of caused by prior art lifting is damaged with connector and hang Dress accident, realizes the safty hoisting construction of precast stair, improves prefabrication construction efficiency and quality, and can be so as to In suspension centre Fast Installation, dismounting, accelerate construction efficiency.
In order to solve the above technical problems, the present invention provides following technical solution:
A kind of precast stair Lift-on/Lift-off System, for hoisting prefabricated stair, including a pair of of hoisting steel beam, at least two first steel Cord, tower crane suspension hook and shoulder pole for hoisting, shoulder pole for hoisting are suspended to the lower section of tower crane suspension hook, are reserved on the precast stair Two holes for hoist pair, each pair hole for hoist including two vertically arranged holes for hoist, each hoisting steel beam to being correspondingly arranged in each hang Hole is filled to lower section, and is opened up on each hoisting steel beam with corresponding hole for hoist to corresponding through hole, the both ends of every first steel wire rope After drawing-in corresponds to the correspondence hole for hoist of correspondence hole for hoist centering on the correspondence through hole and precast stair of hoisting steel beam successively respectively It is connected with shoulder pole for hoisting.
Preferably, in above-mentioned precast stair Lift-on/Lift-off System, the both ends of first steel wire rope are connected to vertically respectively On the shoulder pole for hoisting.
Preferably, in above-mentioned precast stair Lift-on/Lift-off System, the shoulder pole for hoisting lower surface is evenly arranged with four For connecting the hanging ring of first steel wire rope.
Preferably, in above-mentioned precast stair Lift-on/Lift-off System, the tower crane suspension hook passes through described in the second wire rope suspensioning Shoulder pole for hoisting, the quantity of second steel wire rope is two, and the end of second steel wire rope is uniformly connected to the lifting With on shoulder pole, hung in the middle part of second steel wire rope on the tower crane suspension hook.
Preferably, in above-mentioned precast stair Lift-on/Lift-off System, the hole for hoist is to being arranged at the different of precast stair In stairway step section.
The invention also discloses a kind of precast stair hanging method as described above, hung using precast stair as described above Dress system, includes the following steps:
Step 1, factory for prefabrication process precast stair according to design drawing, reserve hole for hoist;
Step 2, the first steel wire rope are installed with hoisting steel beam so that the both ends of the first steel wire rope are respectively from hoisting steel beam It is pierced by corresponding through hole;
Step 3, the both ends of the first steel wire rope are each passed through after the correspondence hole for hoist of precast stair and shoulder pole for hoisting phase Even;
Step 4, tower crane suspension hook is by suspending the hoisting prefabricated stair of shoulder pole for hoisting in midair;
Step 5, precast stair reach designated position;
Step 6, dismounting hoisting steel beam, the first steel wire rope of dismounting and shoulder pole for hoisting;
Step 7, precast stair lifting installation are completed, and carry out next precast stair lifting.
From techniques disclosed above scheme, compared with prior art, beneficial effects of the present invention are as follows:
The present invention carries out research and development optimization for the lifting installation method of the medium-and-large-sized precast stair of prefabricated concrete structure, will The hanging method of original built-in metal suspension centre on precast stair is changed to reserve vertical hole for hoist on precast stair, and utilizes First steel wire rope perforation connection hoisting steel beam realizes the lifting of precast stair, lifts, avoids the occurrence of suitable for large scale prefabricated stair Prior art lifting connector i.e. harm caused by suspension centre damage, realizes the safty hoisting construction of precast stair, improves pre- Assembled architecture construction efficiency and quality processed.Also, it is of the invention by the way of vertical hole for hoist is reserved on precast stair, It can accelerate construction efficiency in order to suspension centre Fast Installation, dismounting.
Brief description of the drawings
Fig. 1 is precast stair top view in one embodiment of the invention.
Fig. 2 is the elevation of the precast stair Lift-on/Lift-off System of one embodiment of the invention.
Fig. 3 is the bottom view of precast stair Lift-on/Lift-off System in one embodiment of the invention.
In figure:1- precast stairs, 2- hoisting steel beams, the first steel wires of 3-, 4- tower cranes suspension hook, 5- shoulder pole for hoisting, 6- second Steel wire rope, 7- holes for hoist, 8- through holes.
Embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and right Claim, advantages and features of the invention will become apparent from.This hair will be described in detail by cited embodiment combination attached drawing below Bright technology contents and feature.Need in addition it illustrate, attached drawing uses using very simplified form and non-accurate ratio Example, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.For sake of convenience, described below " on ", " under " the upper and lower direction with attached drawing is consistent, but this can't be the limitation of technical solution of the present invention.
Please refer to Fig.1 to Fig.3, present embodiment discloses a kind of 1 Lift-on/Lift-off System of precast stair, for hoisting prefabricated stair 1, Including a pair of of hoisting steel beam 2, at least two first steel wire ropes 3, tower crane suspension hook 4 and shoulder pole for hoisting 5, shoulder pole for hoisting 5 are outstanding It is right in reserving two holes for hoist 7 on the lower section of tower crane suspension hook 4, the precast stair 1 to hang, and each pair hole for hoist 7 is to vertical including two The hole for hoist 7 of setting, each hoisting steel beam 2 are correspondingly arranged in each hole for hoist 7 to lower section, and are opened up on each hoisting steel beam 2 Pair that drawing-in successively corresponds to hoisting steel beam 2 is distinguished to corresponding through hole 8, the both ends of every first steel wire rope 3 with correspondence hole for hoist 7 It is connected after answering the correspondence hole for hoist 7 of 7 centering of correspondence hole for hoist on through hole 8 and precast stair 1 with shoulder pole for hoisting 5.
The present invention is by setting two holes for hoist 7 right on the precast stair 1, each pair hole for hoist 7 including two to vertically setting The hole for hoist 7 put, each hoisting steel beam 2 are correspondingly arranged in each hole for hoist 7 to lower section, and opened up on each hoisting steel beam 2 with Correspondence hole for hoist 7 distinguishes the correspondence that drawing-in successively corresponds to hoisting steel beam 2 to corresponding through hole 8, the both ends of every first steel wire rope 3 It is connected after the correspondence hole for hoist 7 of 7 centering of correspondence hole for hoist on through hole 8 and precast stair 1 with shoulder pole for hoisting 5 so that first Steel wire rope 3 can by the vertical hole for hoist 7 on precast stair 1 and hoisting steel beam 2 safely and reliably hoisting prefabricated stair 1, Hoisting Security accident is avoided the occurrence of, improves the safety and stability that precast stair 1 lifts.Also, the present invention is using prefabricated The mode of vertical hole for hoist 7 is reserved on stair 1, easy to suspension centre Fast Installation, dismounting, accelerates construction efficiency.
In order to enable more stable hoisting prefabricated stair 1, it is preferred that in above-mentioned 1 Lift-on/Lift-off System of precast stair, institute The both ends for stating the first steel wire rope 3 are connected on the shoulder pole for hoisting 5 vertically respectively.
Preferably, in above-mentioned 1 Lift-on/Lift-off System of precast stair, 5 lower surface of shoulder pole for hoisting is evenly arranged with four A hanging ring for being used to connect first steel wire rope 3.The hanging ring is uniformly arranged on 5 lower surface of shoulder pole for hoisting, can be with So that the weight of precast stair 1 and hoisting steel beam 2 is uniformly transferred to the shoulder pole for hoisting 5, stress concentration is avoided the occurrence of.
In order to enable tower crane suspension hook 4 more smoothly suspends lifting use shoulder pole in midair, it is preferred that in above-mentioned precast stair 1 In Lift-on/Lift-off System, the tower crane suspension hook 4 passes through shoulder pole for hoisting 5 described in the second steel wire rope 6, the quantity of second steel wire rope 6 For two, the end of second steel wire rope 6 is uniformly connected on the shoulder pole for hoisting 5, the middle part of second steel wire rope 6 Hang on the tower crane suspension hook 4.
Please continue to refer to Fig. 1 to Fig. 3,1 hanging method of precast stair of the invention, using precast stair 1 as described above Lift-on/Lift-off System, includes the following steps:
Step 1, factory for prefabrication process precast stair 1 according to design drawing, reserve hole for hoist 7;
Step 2, the first steel wire rope 3 are installed with hoisting steel beam 2 so that the both ends of the first steel wire rope 3 are respectively from hoisting steel beam It is pierced by 2 correspondence through hole 8;
Step 3, the both ends of the first steel wire rope 3 are each passed through after the correspondence hole for hoist 7 of precast stair 1 and shoulder pole for hoisting 5 It is connected;
Step 4, tower crane suspension hook 4 suspend the hoisting prefabricated stair 1 of shoulder pole for hoisting 5 in midair by the second steel wire rope 6;
Step 5, precast stair 1 reach designated position;
Step 6, dismounting hoisting steel beam 2, the first steel wire rope 3 of dismounting and shoulder pole for hoisting 5;
Step 7, precast stair 1 lift installation and complete, carry out next precast stair 1 and lift.
The present invention cardinal principle be:The vertical hole for hoist 7 that the first steel wire rope 3 passes through is reserved on precast stair 1, the 1 time hoisting steel beam in one steel wire rope, 3 one end and precast stair 2 is connected, and the other end is connected with 4 steel shoulder pole of tower crane suspension hook, utilizes lifting Stress support of the girder steel 2 as carrying 1 weight of precast stair, tower crane lift by crane precast stair 1 to designated position, dismantle hoisting steel beam 2, the first steel wire rope 3 of lifting is removed, completes the lifting installation of precast stair 1.On the one hand, 1 Lift-on/Lift-off System of precast stair of the invention And hanging method, optimization precast stair 1 lift installation method, effectively avoid the weight caused by 1 suspension-center pre-embedded of precast stair damages Big peril, enhancing precast stair 1 lift the security of installation.On the other hand, precast stair 1 of the invention lifting system System and hanging method, by the way of vertical hole for hoist 7 is reserved on precast stair 1, easy to suspension centre Fast Installation, are dismantled, Accelerate construction efficiency.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Scope.

Claims (6)

1. a kind of precast stair Lift-on/Lift-off System, for hoisting prefabricated stair, it is characterised in that including a pair of of hoisting steel beam, at least Two first steel wire ropes, tower crane suspension hook and shoulder pole for hoisting, shoulder pole for hoisting is suspended to the lower section of tower crane suspension hook, described prefabricated Two holes for hoist pair are reserved on stair, each pair hole for hoist is to corresponding to and setting including two vertically arranged holes for hoist, each hoisting steel beam Each hole for hoist is placed in lower section, and is opened up on each hoisting steel beam with corresponding hole for hoist to corresponding through hole, every first steel Distinguish pair that drawing-in successively corresponds to the correspondence hole for hoist centering on the correspondence through hole and precast stair of hoisting steel beam in the both ends of cord It is connected after answering hole for hoist with shoulder pole for hoisting.
2. precast stair Lift-on/Lift-off System as claimed in claim 1, it is characterised in that erect respectively at the both ends of first steel wire rope It is direct-connected to be connected on the shoulder pole for hoisting.
3. precast stair Lift-on/Lift-off System as claimed in claim 2, it is characterised in that the shoulder pole for hoisting lower surface is uniformly set It is equipped with four hanging rings for being used to connect first steel wire rope.
4. precast stair Lift-on/Lift-off System as claimed in claim 1, it is characterised in that the tower crane suspension hook passes through the second steel wire rope Suspend the shoulder pole for hoisting in midair, the quantity of second steel wire rope is two, and the end of second steel wire rope is uniformly connected to On the shoulder pole for hoisting, hung in the middle part of second steel wire rope on the tower crane suspension hook.
5. precast stair Lift-on/Lift-off System as claimed in claim 1, it is characterised in that the hole for hoist is to being arranged at precast stair Different stairway step sections on.
6. a kind of precast stair hanging method, it is characterised in that using the prefabricated building as described in any one in claim 1-5 Terraced Lift-on/Lift-off System, includes the following steps:
Step 1, factory for prefabrication process precast stair according to design drawing, reserve hole for hoist;
Step 2, the first steel wire rope are installed with hoisting steel beam so that the both ends of the first steel wire rope are respectively from the correspondence of hoisting steel beam It is pierced by through hole;
Step 3, the both ends of the first steel wire rope are connected after being each passed through the correspondence hole for hoist of precast stair with shoulder pole for hoisting;
Step 4, tower crane suspension hook is by suspending the hoisting prefabricated stair of shoulder pole for hoisting in midair;
Step 5, precast stair reach designated position;
Step 6, dismounting hoisting steel beam, the first steel wire rope of dismounting and shoulder pole for hoisting;
Step 7, precast stair lifting installation are completed, and carry out next precast stair lifting.
CN201711163062.4A 2017-11-21 2017-11-21 Precast stair Lift-on/Lift-off System and hanging method Pending CN107954306A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711163062.4A CN107954306A (en) 2017-11-21 2017-11-21 Precast stair Lift-on/Lift-off System and hanging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711163062.4A CN107954306A (en) 2017-11-21 2017-11-21 Precast stair Lift-on/Lift-off System and hanging method

Publications (1)

Publication Number Publication Date
CN107954306A true CN107954306A (en) 2018-04-24

Family

ID=61965187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711163062.4A Pending CN107954306A (en) 2017-11-21 2017-11-21 Precast stair Lift-on/Lift-off System and hanging method

Country Status (1)

Country Link
CN (1) CN107954306A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108862015A (en) * 2018-09-17 2018-11-23 五冶集团上海有限公司 A kind of precast beam lifting auxiliary tool and hanging method
CN108868131A (en) * 2018-07-12 2018-11-23 湖北省建工第五建设有限公司 Precast stair supporting apparatus and its application construction method
CN109823964A (en) * 2019-01-31 2019-05-31 浙江省一建建设集团有限公司 A kind of precast stair lifting connection structure and hanging method
CN110759237A (en) * 2018-07-27 2020-02-07 上海公路桥梁(集团)有限公司 Hoisting method
CN110817690A (en) * 2018-08-07 2020-02-21 上海公路桥梁(集团)有限公司 Transmission and hoisting method
CN114457965A (en) * 2020-11-10 2022-05-10 长安大学 Prefabricated staircase with assembled steps and construction method for assembling steps

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4707957A (en) * 1986-08-20 1987-11-24 Shepherd John D Preassembled platform stairway
CN205637624U (en) * 2016-05-11 2016-10-12 中建一局华江建设有限公司 Prefabricated component hoist device
CN206408947U (en) * 2016-12-27 2017-08-15 中铁三局集团有限公司 Prefabricated stair hoisting appliance

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4707957A (en) * 1986-08-20 1987-11-24 Shepherd John D Preassembled platform stairway
CN205637624U (en) * 2016-05-11 2016-10-12 中建一局华江建设有限公司 Prefabricated component hoist device
CN206408947U (en) * 2016-12-27 2017-08-15 中铁三局集团有限公司 Prefabricated stair hoisting appliance

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868131A (en) * 2018-07-12 2018-11-23 湖北省建工第五建设有限公司 Precast stair supporting apparatus and its application construction method
CN110759237A (en) * 2018-07-27 2020-02-07 上海公路桥梁(集团)有限公司 Hoisting method
CN110759237B (en) * 2018-07-27 2022-05-17 上海公路桥梁(集团)有限公司 Hoisting method
CN110817690A (en) * 2018-08-07 2020-02-21 上海公路桥梁(集团)有限公司 Transmission and hoisting method
CN108862015A (en) * 2018-09-17 2018-11-23 五冶集团上海有限公司 A kind of precast beam lifting auxiliary tool and hanging method
CN109823964A (en) * 2019-01-31 2019-05-31 浙江省一建建设集团有限公司 A kind of precast stair lifting connection structure and hanging method
CN109823964B (en) * 2019-01-31 2024-01-05 浙江省一建建设集团有限公司 Prefabricated stair hoisting connection structure and hoisting method
CN114457965A (en) * 2020-11-10 2022-05-10 长安大学 Prefabricated staircase with assembled steps and construction method for assembling steps

Similar Documents

Publication Publication Date Title
CN107954306A (en) Precast stair Lift-on/Lift-off System and hanging method
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN103663101A (en) Method for lifting voltage stabilizer of nuclear power station
CN102756975A (en) Method for hoisting rolling mill housing
CN205397854U (en) Gasifier hoist and mount hoisting device
CN205387439U (en) Mast hoisting accessory
CN207699024U (en) Precast stair Lift-on/Lift-off System
CN105060125B (en) High tower structure of cable crane and its method for dismounting
CN104989111B (en) Steel construction high level construction method for hanging
CN105464456A (en) Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN103011031A (en) Stand column type 360-degree rotary oil tank maintenance platform
CN106144929A (en) One population hoist device and construction method
CN205442393U (en) Posture that falls suspension system
CN203959697U (en) The equalizing bar of hoisting platform truss
CN206680062U (en) A kind of prefabricated part hanging instrument
CN105060124B (en) Intra-frame portal crane system and hoisting use method thereof
CN211444740U (en) Shaft pipeline hoist device
CN103452043B (en) Maintenance system of cable-stayed bridge solid pylon and application of maintenance system
CN110616909B (en) Construction method of suspension track system at bottom of connecting bridge of super high-rise building
CN203187370U (en) Inner mast hoisting device
CN206569910U (en) The vertical hanging apparatus of slender member
CN205663226U (en) Super high -rise building thing top steel construction symmetry is hung and is drawn device
CN217229918U (en) Hoisting connecting device
CN204825670U (en) Inclined to one side hanging beam frame device is prevented turning round by eccentric case roof beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180424

WD01 Invention patent application deemed withdrawn after publication