CN107916941A - Bore quick-fried combined construction method in a kind of double main holes of three hole vcehicular tunnels and middle drift TBM - Google Patents
Bore quick-fried combined construction method in a kind of double main holes of three hole vcehicular tunnels and middle drift TBM Download PDFInfo
- Publication number
- CN107916941A CN107916941A CN201711360326.5A CN201711360326A CN107916941A CN 107916941 A CN107916941 A CN 107916941A CN 201711360326 A CN201711360326 A CN 201711360326A CN 107916941 A CN107916941 A CN 107916941A
- Authority
- CN
- China
- Prior art keywords
- hole
- middle drift
- tbm
- main
- main hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 78
- 238000000034 method Methods 0.000 claims abstract description 60
- 238000005422 blasting Methods 0.000 claims abstract description 33
- 238000005553 drilling Methods 0.000 claims abstract description 33
- 238000009412 basement excavation Methods 0.000 claims abstract description 20
- 238000004880 explosion Methods 0.000 claims abstract description 7
- 239000000463 material Substances 0.000 claims description 20
- 238000009423 ventilation Methods 0.000 claims description 5
- 238000005520 cutting process Methods 0.000 claims description 4
- 238000009826 distribution Methods 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 238000005266 casting Methods 0.000 claims description 2
- 239000011799 hole material Substances 0.000 description 132
- 230000004888 barrier function Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 229910052760 oxygen Inorganic materials 0.000 description 2
- 239000001301 oxygen Substances 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 230000018199 S phase Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 230000001627 detrimental effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/006—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/10—Making by using boring or cutting machines
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a kind of three hole vcehicular tunnels, including two main holes, middle drift is equipped between two main holes, the middle drift is connected between two main holes by several Lateral Holes respectively, the middle drift is a passage at least meeting one way traffic, also disclose a kind of double main holes of middle drift TBM and bore quick-fried combined construction methods, including during producing in TBM, assemble, debugging, the Portal Section of main hole and middle drift is constructed using drilling and blasting method;The working face that TBM marches to the middle drift starts TBM drivings, and two main holes continue construction of explosion;Construct the preliminary bracing of the middle drift;Construct to the inverted arch of the middle drift;The Lateral Hole is excavated using drilling and blasting method, into the main hole after excavate main hole back work face;The initialization face in main hole and main hole back work face are excavated in the same direction;The excavation of the middle drift is completed using TBM methods, the excavation in the main hole is completed using drilling and blasting method.
Description
Technical field
The present invention relates to technical field of tunnel construction, more particularly to a kind of double main holes of three hole vcehicular tunnels and middle drift TBM-
Bore quick-fried combined construction method.
Background technology
Existing two hole vcehicular tunnel, when being constructed using central drift method, is considered, middle drift design area for cost of investment
It is often smaller, so cause that middle drift material channel is narrow, material organizational stress is big, delayed construction speed.And due to general
The escape and rescue scarce capacity of logical two hole tunnels, once there is accident, is highly detrimental to escape and rescue.
Three hole vcehicular tunnels are excavated according to traditional drilling and blasting method, and construction speed is slow, completion time of project length, work efficiency
It is low, in tunnel piercing construction location apart from hole remotely, construction exist very big safety risks.Tunnel boring machine method is to excavate
A kind of method in tunnel, tunnel and other underground spaces.Abbreviation TBM (tunnel boring manchine) method, it utilizes spy
The Large Cutting equipment of system, then rock shearing attrition crushing is transported rubble by supporting transporting equipment.TBM methods exist
Speed of application under normal circumstances is significantly faster than drilling and blasting method, and not only construction quality is good, and mechanization degree is high, easy for construction, has
Beneficial to environmental protection and save labour., should be not as flexible as drilling and blasting method but TBM methods are poor to the adaptability of unfavorable geological condition
It is relatively weak to the ability of complex geological condition especially soft rock environment., should therefore, it is necessary to a set of scientific and reasonable construction method
Construction method has the advantages of drilling and blasting method and TBM methods concurrently, to ensure quickly and safely to excavate three hole vcehicular tunnels.
The content of the invention
It is an object of the invention to overcome the above-mentioned deficiency in the presence of the prior art, there is provided a kind of three hole vcehicular tunnels and
Middle drift TBM- bores quick-fried combined construction method in double main holes, it uses the arrangement and method for construction of " long tunnel hand-to-hand fight in tights ", has drilling and blasting method and TBM methods concurrently
The advantages of, time availability is high, can greatly speed up Tunnel Construction Schedule, and can form main hole material channel early, mitigate thing
Expect organizational stress.
In order to realize foregoing invention purpose, the present invention provides following technical scheme:
A kind of three hole vcehicular tunnels, including two main holes, are equipped with middle drift, the middle drift between two main holes
It is connected respectively between two main holes by several Lateral Holes, the middle drift is at least to meet one way traffic
One passage.
Parallel longitudinal setting of the middle drift along main hole, middle drift cross sectional dimensions are less than the cross sectional dimensions in main hole, lead to
The middle drift and Lateral Hole set is crossed, on the one hand during constructing tunnel, can quickly open up main hole back work face, can
Construction speed is greatly speeded up, and main hole material channel can be formed early, mitigates material organizational stress, solves main hole material channel
Narrow, the problem of material organizational stress is big.On the other hand, after the completion of constructing tunnel, middle drift can be used as operation phase escape and rescue
Passage, solves the problems, such as common two hole tunnels escape and rescue scarce capacity, can also be used as Emergency Vehicle Lane.
Preferably, the hole cross-sectional area of the middle drift is the 40%-70% in each main hole.
Preferably, the main hole excavates to be formed using drilling and blasting method, and the middle drift excavates to be formed using TBM methods.Utilize TBM
The advanced advantage of method progress, can get through multiple main hole back work faces, and each working face in main hole is constructed at the same time, realize " long
Tunnel hand-to-hand fight in tights ", can greatly speed up construction speed.
Preferably, the main hole and middle drift are equipped with equipped with supporting, lining cutting and drainage system.Both can connect integral
Formula structure, in case of emergency, can also come into operation as independent structure.
A kind of middle drift TBM- bores quick-fried combined construction methods in double main holes, using any above-mentioned three hole vcehicular tunnel of one kind,
Comprise the following steps:
Step 1:During TBM productions, assembling, debugging, the Portal Section of main hole and middle drift is applied using drilling and blasting method
Work;
Step 2:After TBM assembly and adjustments, stop the construction of explosion of the middle drift, TBM marches to the middle drift
Working face start TBM driving, two main holes continue construction of explosion;
Step 3:Construct the preliminary bracing of the middle drift;
Step 4:Construct to the inverted arch of the middle drift;
Step 5:After TBM drive end units are by Lateral Hole and reserved enough construction spaces, excavated using drilling and blasting method described in
Lateral Hole, into the main hole after the main hole back work face of drill-blast tunnelling;
Step 6:The initialization face and back work face in main hole are excavated in the same direction;
Step 7:The excavation of the middle drift is completed using TBM methods, the excavation in the main hole is completed using drilling and blasting method.
The construction method carries out middle drift excavation using TBM methods, while the excavation in double main holes is carried out using drilling and blasting method, passes through
Each garage's transverse passage-way opens up main hole back work face, and each working face in main hole excavates in the same direction at the same time, and when tunnel can
Realize " long tunnel hand-to-hand fight in tights ", progress steadily promotes in the construction period, and time availability is higher, and duration controllability is strong, and personnel equipment throws
Enter low, and main hole material channel can be formed early, substantially reduce material organizational stress in middle drift.During the construction method solves
The technical barrier of the double main hole drilling and blasting methods combination rapid constructions of pilot tunnel TBM-, the advantages of having drilling and blasting method and TBM methods concurrently, be later speciality
Tunnel bores quick-fried joint construction using the double main holes of middle drift TBM- and provides optimal construction scheme, and it is total to substantially reduce construction
Duration.
Preferably, middle drift is leading, the working face dislocation construction of two main holes and middle drift, between two working faces
The spacing that staggers is more than twice of the main hole excavation width.
Preferably, in the step 4, the inverted arch of middle drift is lifted in concentration pre-casting, the scene of being transported to again outside place.
Preferably, it is pre- in the rear progress inverted arch of TBM machines support boots by itself lifting system of TBM machines in the step 4
The lifting of clamp dog.
Preferably, excavation forms the main hole section of standard after the step 5 enters main hole, and opens up the main hole working face of auxiliary,
After completing main hole back work face, Lateral Hole and main hole junction are digged, main hole is formed and widens section, main hole is finally completed and adds
Wide Band Oxygen Sensors Second Lining Construction.
Preferably, constructed using the trolley of fast demountable to each working face in main hole, using Mobile distribution
The supply configuration of the power supply for construction and construction ventilation in main hole is carried out with Dynamic Construction Design of ventilation, is shifted easy to equipment, accelerates to apply
Work process.
Preferably, method of tunnel drilling and blasting is slagged tap by the middle drift, then by Lateral Hole, then branches to main hole and hole
Outside, material is then transported into by opposite direction.Middle drift, Lateral Hole, main hole cooperatively form material channel, can substantially reduce material group
Active pressure.
Preferably, when excavating the middle drift using TBM methods, slagged tap using belt feeder, wherein just branch work progress
In, be used to hanging and fix the embedded hanging part of belt feeder vault is pre-buried, and the belt feeder using guide chain hang on it is described in
The vault center of pilot tunnel.
Compared with prior art, the beneficial effect of a kind of three hole vcehicular tunnel of the present invention:
By the middle drift and Lateral Hole of setting, on the one hand during constructing tunnel, it is auxiliary can quickly to open up main hole
Working face is helped, construction speed can be greatly speeded up, and main hole material channel can be formed early, mitigates material organizational stress, solves
The problem of main hole material channel is narrow, material organizational stress is big.On the other hand, after the completion of constructing tunnel, middle drift can be used as fortune
Battalion's phase escape and rescue passage, solves the problems, such as common two hole tunnels escape and rescue scarce capacity.
Compared with prior art, the beneficial of quick-fried combined construction method is bored in a kind of double main holes of middle drift TBM- of the present invention
Effect:
The construction method carries out middle drift excavation using TBM methods, while the excavation in double main holes is carried out using drilling and blasting method, passes through
Each garage's transverse passage-way opens up main hole back work face, and each working face in main hole excavates in the same direction at the same time, and when tunnel can
Realize " long tunnel hand-to-hand fight in tights ", progress steadily promotes in the construction period, and time availability is higher, and duration controllability is strong, and personnel equipment throws
Enter low, and main hole material channel can be formed early, substantially reduce material organizational stress in middle drift.During the construction method solves
The technical barrier of the double main hole drilling and blasting methods combination rapid constructions of pilot tunnel TBM-, the advantages of having drilling and blasting method and TBM methods concurrently, be later speciality
Tunnel bores quick-fried joint construction using the double main holes of middle drift TBM- and provides optimal construction scheme, and it is total to substantially reduce construction
Duration.
Brief description of the drawings:
Fig. 1 is a kind of structure diagram of three hole vcehicular tunnel of the present invention.
Fig. 2 is the schematic diagram that quick-fried combined construction method is bored in a kind of double main holes of middle drift TBM- of the present invention.
Fig. 3 is the schematic diagram of slagging tap that quick-fried combined construction method is bored in a kind of double main holes of middle drift TBM- of the present invention.
Marked in figure:The main holes of 1-, 2- middle drifts, 3- Lateral Holes.
Embodiment
With reference to test example and embodiment, the present invention is described in further detail.But this should not be understood
Following embodiment is only limitted to for the scope of the above-mentioned theme of the present invention, it is all that this is belonged to based on the technology that present invention is realized
The scope of invention.
Embodiment 1
As shown in Figure 1, a kind of three hole vcehicular tunnels, including two main holes 1, led in being equipped between two main holes 1
Hole 2, the middle drift 2 are connected between two main holes 1 by several Lateral Holes 3 respectively, and the middle drift 2 is
At least meet a passage of one way traffic.The main hole 1 excavates to be formed using drilling and blasting method, and the middle drift 2 is opened using TBM methods
Dig and formed, the main hole 1 and middle drift 2 are equipped with equipped with supporting, lining cutting and drainage system.
The middle drift 2 is longitudinally disposed along main hole 1, and 2 cross sectional dimensions size of middle drift is less than the cross section ruler in main hole 1
It is very little, by the middle drift 2 and Lateral Hole 3 of setting, on the one hand during constructing tunnel, it can quickly open up main hole backman
Make face, construction speed can be greatly speeded up, and main 1 material channel of hole can be formed early, mitigate material organizational stress, solve main hole
The problem of 1 material channel is narrow, material organizational stress is big.On the other hand, after the completion of constructing tunnel, middle drift 2 can be used as operation
Phase escape and rescue passage, solves the problems, such as common two hole tunnels escape and rescue scarce capacity.
Embodiment 2
As shown in Figure 1-Figure 3, quick-fried combined construction method is bored in a kind of double main holes of middle drift TBM-, uses three hole of one kind
Vcehicular tunnel, comprises the following steps:
Step 1:During TBM productions, assembling, debugging, the Portal Section of main hole 1 and middle drift 2 is applied using drilling and blasting method
Work, wherein middle drift 2 are leading, the working face dislocation construction of two main holes 1 and middle drift 2, stagger between two working faces
Spacing is more than twice of main 1 excavation width of hole.
Step 2:After TBM assembly and adjustments, stop the construction of explosion of the middle drift 2, TBM march to it is described in lead
The working face in hole 2 starts TBM drivings, and two main holes 1 continue construction of explosion.
Step 3:Construct the preliminary bracing of the middle drift 2.
Step 4:Construct to the inverted arch of the middle drift 2, the inverted arch of specially middle drift 2 is concentrated in advance outside place
System, supporting afterbody after inverted arch prefabricated section is transported to TBM by precasting yard with large-tonnage fork truck, by itself lifting system of TBM machines
The lifting of inverted arch prefabricated section is carried out at the rear of TBM machines support boots.
Step 5:Using the advanced advantage of TBM progresses, TBM drive end units pass through Lateral Hole 3 and reserved enough construction skies
Between after, the Lateral Hole 3 is excavated using drilling and blasting method, into the main hole back work face of drill-blast tunnelling behind the main hole 1.Specially
3 drilling and blasting method excavation construction of Lateral Hole, into main hole 1 after excavate and form the main hole section of standard, and open up the main hole working face of auxiliary,
After completing main hole back work face, Lateral Hole 3 and main 1 junction of hole are digged, main hole is formed and widens section, and carry out main hole and add
Wide Band Oxygen Sensors Second Lining Construction.
Step 6:As shown in Fig. 2, the working face in main hole 1 and back work face are excavated in the same direction.
Step 7:The excavation of the middle drift 2 is completed using TBM methods, the excavation in the main hole 1 is completed using drilling and blasting method.
Wherein, constructed using the trolley of fast demountable to each working face in main hole, using Mobile distribution and
Dynamic Construction Design of ventilation carries out the supply configuration of the power supply for construction and construction ventilation in main hole.Using TBM methods excavate it is described in lead
During hole 2, slagged tap using belt feeder, wherein just in branch work progress, it is pre-buried for hanging and fixing belt feeder in vault
Embedded hanging part, and the belt feeder hangs on the vault center of the middle drift 2 using guide chain.
As shown in figure 3, method of tunnel drilling and blasting is slagged tap by the middle drift 2, then by Lateral Hole 3, then master is branched to
Outside hole 1 and hole, material is then transported into by opposite direction, and middle drift 2, Lateral Hole 3, main hole 1 cooperatively form material channel, can be significantly
Reduce material organizational stress.
The construction method carries out middle drift excavation using TBM methods, while the excavation in double main holes is carried out using drilling and blasting method, passes through
Each garage's transverse passage-way opens up main hole back work face, and each working face in main hole excavates in the same direction at the same time, and when tunnel can
Realize " long tunnel hand-to-hand fight in tights ", progress steadily promotes in the construction period, and time availability is higher, and duration controllability is strong, and personnel equipment throws
Enter low, and main hole material channel can be formed early, substantially reduce material organizational stress in middle drift.During the construction method solves
The technical barrier of the double main hole drilling and blasting methods combination rapid constructions of pilot tunnel TBM-, the advantages of having drilling and blasting method and TBM methods concurrently, be later speciality
Tunnel bores quick-fried joint construction using the double main holes of middle drift TBM- and provides optimal construction scheme, and it is total to substantially reduce construction
Duration.
Above example only not limits technical solution described in the invention to illustrate the present invention, although this explanation
Book is with reference to above-mentioned each embodiment to present invention has been detailed description, but the present invention is not limited to above-mentioned specific implementation
Mode, therefore any modify to the present invention or equivalent substitution;And the technical side of all spirit and scope for not departing from invention
Case and its improvement, it should all cover among scope of the presently claimed invention.
Claims (10)
1. a kind of three hole vcehicular tunnels, it is characterised in that including two main holes (1), in being equipped between two main holes (1)
Pilot tunnel (2), the middle drift (2) are connected between two main holes (1) by several Lateral Holes (3) respectively, institute
It is a passage at least meeting one way traffic to state middle drift (2).
2. a kind of three hole vcehicular tunnel according to claim 1, it is characterised in that the main hole (1) is opened using drilling and blasting method
Dig and formed, the middle drift (2) excavates to be formed using TBM methods.
3. a kind of three hole vcehicular tunnel according to claim 1, it is characterised in that the main hole (1) and middle drift (2) are equal
Equipped with equipped with supporting, lining cutting and drainage system.
4. a kind of middle drift TBM- bores quick-fried combined construction method in double main holes, it is characterised in that using such as any institutes of claim 1-3
The three hole vcehicular tunnel of one kind stated, comprises the following steps:
Step 1:During TBM productions, assembling, debugging, the Portal Section of main hole (1) and middle drift (2) is applied using drilling and blasting method
Work;
Step 2:After TBM assembly and adjustments, stop the construction of explosion of the middle drift (2), TBM marches to the middle drift
(2) working face starts TBM drivings, and two main holes (1) continue construction of explosion;
Step 3:Construct the preliminary bracings of the middle drift (2);
Step 4:Construct to the inverted arch of the middle drift (2);
Step 5:After TBM drive end units are by Lateral Hole (3) and reserved enough construction spaces, excavated using drilling and blasting method described in
Lateral Hole (3), into the main hole (1) the main hole back work face of drill-blast tunnelling afterwards;
Step 6:The initialization face and back work face of main hole (1) are excavated in the same direction;
Step 7:The excavation of the middle drift (2) is completed using TBM methods, the excavation of the main hole (1) is completed using drilling and blasting method.
5. a kind of middle drift TBM- according to claim 4 bores quick-fried combined construction method in double main holes, it is characterised in that two
The dislocation of the working face of the main hole (1) and middle drift (2) is constructed, and the spacing that staggers between two working faces is more than the main hole (1)
Twice of excavation width.
6. a kind of middle drift TBM- according to claim 4 bores quick-fried combined construction method in double main holes, it is characterised in that described
In step 4, the inverted arch of middle drift (2) is lifted in concentration pre-casting, the scene of being transported to again outside place.
7. a kind of middle drift TBM- according to claim 4 bores quick-fried combined construction method in double main holes, it is characterised in that described
Step 5 enters main hole (1), and excavation forms the main hole section of standard afterwards, and opens up the main hole working face of auxiliary, completes main hole back work
Behind face, Lateral Hole (3) and main hole (1) junction are digged, main hole is formed and widens section, finally completing main hole, to widen section secondary
Lining construction.
8. boring quick-fried combined construction method according to a kind of double main holes of any middle drift TBM- of claim 4-7, its feature exists
In being constructed to each working face in main hole using the trolley of fast demountable, led to using Mobile distribution and Dynamic Construction
Wind design carries out the supply configuration of the power supply for construction and construction ventilation in main hole.
9. boring quick-fried combined construction method according to a kind of double main holes of any middle drift TBM- of claim 4-7, its feature exists
In, method of tunnel drilling and blasting is slagged tap by the middle drift (2), then by Lateral Hole (3), then is branched to outside main hole (1) and hole,
Material is then transported into by opposite direction.
10. boring quick-fried combined construction method according to a kind of double main holes of any middle drift TBM- of claim 4-7, its feature exists
In, when excavating middle drift (2) using TBM methods, slagged tap using belt feeder, wherein just in branch work progress, in vault
The pre-buried embedded hanging part for being used to hanging and fixing belt feeder, and the belt feeder hangs on the middle drift (2) using guide chain
Vault center.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711360326.5A CN107916941A (en) | 2017-12-15 | 2017-12-15 | Bore quick-fried combined construction method in a kind of double main holes of three hole vcehicular tunnels and middle drift TBM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711360326.5A CN107916941A (en) | 2017-12-15 | 2017-12-15 | Bore quick-fried combined construction method in a kind of double main holes of three hole vcehicular tunnels and middle drift TBM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107916941A true CN107916941A (en) | 2018-04-17 |
Family
ID=61893370
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711360326.5A Pending CN107916941A (en) | 2017-12-15 | 2017-12-15 | Bore quick-fried combined construction method in a kind of double main holes of three hole vcehicular tunnels and middle drift TBM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107916941A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108999615A (en) * | 2018-08-13 | 2018-12-14 | 中铁二局工程有限公司 | A kind of building structure and method reducing double-shielded TBM card machine risk |
CN109017816A (en) * | 2018-06-11 | 2018-12-18 | 中铁工程设计咨询集团有限公司 | A kind of three layer of three vertical group hole underground station |
CN113863939A (en) * | 2021-09-27 | 2021-12-31 | 中铁二院工程集团有限责任公司 | Rapid construction method for adopting TBM (tunnel boring machine) to lead double-hole cross tunneling in complex stratum |
CN114251099A (en) * | 2021-11-25 | 2022-03-29 | 中交二公局东萌工程有限公司 | Blasting excavation method for crossed caverns |
CN114320423A (en) * | 2022-01-12 | 2022-04-12 | 中交二公局东萌工程有限公司 | Roadway type construction ventilation method for advanced double main holes of parallel middle-guide tunnel |
CN114575858A (en) * | 2022-03-14 | 2022-06-03 | 中交一公局集团有限公司 | Combined tunneling method for double-lane single-width main tunnel and single-lane rescue channel of highway tunnel |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296963A (en) * | 2011-08-01 | 2011-12-28 | 湖南省交通规划勘察设计院 | Construction method for ultra-long deep-buried road tunnel |
CN102305095A (en) * | 2011-08-01 | 2012-01-04 | 湖南省交通规划勘察设计院 | Flat guide ventilation operation system of extra-long deeply-buried road tunnel |
CN102720520A (en) * | 2012-07-02 | 2012-10-10 | 西南交通大学 | Method for ventilating drainage tunnel of extremely-long double-hole tunnel of expressway during construction |
CN103244127A (en) * | 2013-04-22 | 2013-08-14 | 中交路桥北方工程有限公司 | Method for quickening construction of multiple-arch tunnel |
CN207568616U (en) * | 2017-12-15 | 2018-07-03 | 中交二公局东萌工程有限公司 | A kind of three hole vcehicular tunnels |
-
2017
- 2017-12-15 CN CN201711360326.5A patent/CN107916941A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296963A (en) * | 2011-08-01 | 2011-12-28 | 湖南省交通规划勘察设计院 | Construction method for ultra-long deep-buried road tunnel |
CN102305095A (en) * | 2011-08-01 | 2012-01-04 | 湖南省交通规划勘察设计院 | Flat guide ventilation operation system of extra-long deeply-buried road tunnel |
CN102720520A (en) * | 2012-07-02 | 2012-10-10 | 西南交通大学 | Method for ventilating drainage tunnel of extremely-long double-hole tunnel of expressway during construction |
CN103244127A (en) * | 2013-04-22 | 2013-08-14 | 中交路桥北方工程有限公司 | Method for quickening construction of multiple-arch tunnel |
CN207568616U (en) * | 2017-12-15 | 2018-07-03 | 中交二公局东萌工程有限公司 | A kind of three hole vcehicular tunnels |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109017816A (en) * | 2018-06-11 | 2018-12-18 | 中铁工程设计咨询集团有限公司 | A kind of three layer of three vertical group hole underground station |
CN108999615A (en) * | 2018-08-13 | 2018-12-14 | 中铁二局工程有限公司 | A kind of building structure and method reducing double-shielded TBM card machine risk |
CN113863939A (en) * | 2021-09-27 | 2021-12-31 | 中铁二院工程集团有限责任公司 | Rapid construction method for adopting TBM (tunnel boring machine) to lead double-hole cross tunneling in complex stratum |
CN114251099A (en) * | 2021-11-25 | 2022-03-29 | 中交二公局东萌工程有限公司 | Blasting excavation method for crossed caverns |
CN114251099B (en) * | 2021-11-25 | 2024-04-16 | 中交二公局东萌工程有限公司 | Blasting excavation method for cross grotto |
CN114320423A (en) * | 2022-01-12 | 2022-04-12 | 中交二公局东萌工程有限公司 | Roadway type construction ventilation method for advanced double main holes of parallel middle-guide tunnel |
CN114575858A (en) * | 2022-03-14 | 2022-06-03 | 中交一公局集团有限公司 | Combined tunneling method for double-lane single-width main tunnel and single-lane rescue channel of highway tunnel |
CN114575858B (en) * | 2022-03-14 | 2024-04-16 | 中交一公局集团有限公司 | Combined tunneling method for highway tunnel double-lane single-frame positive tunnel and single-lane rescue channel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107916941A (en) | Bore quick-fried combined construction method in a kind of double main holes of three hole vcehicular tunnels and middle drift TBM | |
US10494924B2 (en) | Longwall mine construction method N00 | |
CN103382844B (en) | A kind of tracked hydraulic sectional shelf-unit temporary lining and permanent support parallel operations piercing technique and equipment | |
CN104653187B (en) | Water-rich sand layer geology large cross-section tunnel excavation method | |
CN103643979B (en) | Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support | |
CN207568616U (en) | A kind of three hole vcehicular tunnels | |
CN107060795B (en) | A kind of underground mine TBM assembly construction methods | |
EA037982B1 (en) | Method for pillarless mining with self-preserving development without roadway development at mining area | |
CN101220746A (en) | TBM pilot tunnel expansion digging method for 20km double-line double-cavity ultra-long tunnel construction | |
CN108691550A (en) | A kind of vertical shaft shield machine constructed upwards by underground and its construction method | |
CN109403986A (en) | The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel | |
CN105697029B (en) | A kind of single-track railway tunnel Drillhole excavation trolley | |
CN106150509A (en) | A kind of double track tunnel is non-bores quick-fried mechanized construction method | |
CN104373147B (en) | Folding extension type roadway hydraulic bracket | |
CN103174448A (en) | In-time supporting method for roadway fully-mechanized excavating operation | |
CN204113319U (en) | A kind of folding telescopic alley hydraulic support | |
CN103939115B (en) | A kind of method of half shallow mining method hangar tunnel and structure | |
CN111764955A (en) | Coal roadway advance region pre-extraction method based on directional extraction drilling cross-roadway arrangement | |
CN206592127U (en) | Great burying TBM construction tunnel rock burst processing structures | |
CN108222945A (en) | Utilize the construction method of main and auxiliary layering sap excavating extra-large cross-section Underground Subway Station | |
US20190376257A1 (en) | Grooving Device for Underground Structures and Its Construction Method | |
WO2021003771A1 (en) | Design method for mine without leaving coal pillar and without roadway tunneling | |
CN209354152U (en) | Plain type hard rock TBM | |
CN205189880U (en) | Shield constructs to be assembled section of jurisdiction and crosses undercut tunnel construction structures | |
RU2490454C1 (en) | Method for open-underground mining of thick steep coal bed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |