CN107905818A - A kind of tunnel concrete lining construction ancillary equipment and construction technology - Google Patents

A kind of tunnel concrete lining construction ancillary equipment and construction technology Download PDF

Info

Publication number
CN107905818A
CN107905818A CN201711305324.6A CN201711305324A CN107905818A CN 107905818 A CN107905818 A CN 107905818A CN 201711305324 A CN201711305324 A CN 201711305324A CN 107905818 A CN107905818 A CN 107905818A
Authority
CN
China
Prior art keywords
template
submounts
subtemplate
tunnel
stent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711305324.6A
Other languages
Chinese (zh)
Other versions
CN107905818B (en
Inventor
李信斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711305324.6A priority Critical patent/CN107905818B/en
Publication of CN107905818A publication Critical patent/CN107905818A/en
Application granted granted Critical
Publication of CN107905818B publication Critical patent/CN107905818B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel concrete lining construction ancillary equipment and construction technology, belongs to tunnel building technology field.The auxiliary construction equipment includes:Template and stent, stent support shuttering make it have pre-set space between tunnel surrounding, and template includes the polylith subtemplate being detachably connected;The total length of polylith subtemplate is arranged to:After pre-set space casting concrete between the subtemplate and tunnel surrounding at template tail end, the concrete in the pre-set space between subtemplate and tunnel surrounding at template head end reaches default curdled appearance;Stent includes two sets of broad-adjustable submounts, and when the reduced width of a set of submounts, it can depart from the support to template and move the distance of at least one sub- template length along the length direction of stent.Tunnel concrete lining construction ancillary equipment provided by the present invention make it that concrete- liner construction is continuous uninterrupted, improves construction efficiency, reasonable arrangement human and material resources.

Description

A kind of tunnel concrete lining construction ancillary equipment and construction technology
Technical field
The present invention relates to tunnel building technology field, more particularly to a kind of tunnel concrete- liner ancillary equipment and construction technology.
Background technology
Tunnel is a kind of important means of transportation, when building subway, Chuan Shan highways, is required for building tunnel.Usually Ensure the safe to use of tunnel, be provided with the concrete- liner formed by concrete along the country rock of tunnel trunk.Pass through concrete- liner pair Tunnel surrounding forms permanent support, avoids tunnel surrounding from collapsing.As it can be seen that it is particularly significant that concrete- liner is built in constructing tunnel.
In the prior art, when building tunnel concrete- liner, using stent and template as ancillary equipment.Specifically, stent Including joist, and it is fixed on the top beam set on joist along length of tunnel direction.Wherein, the radial section shape of joist and template Shape is adapted with the radial cross-sectional shape in tunnel.Illustratively, when tunnel is arch, joist and template are in arcuation.When in use, Diaphragm plate is placed on the top beam of stent, and ensures that template surface forms pre-set space with tunnel surrounding surface., will be mixed during construction Solidifying soil is filled in the pre-set space between template and tunnel surrounding.3~4 days are stood so that concrete reaches default solidification afterwards It is required that form first segment concrete- liner.Template is dismantled afterwards, and mobile stent, builds according to above-mentioned technique close to first segment concrete- liner Second segment concrete- liner.And so on, until building and the isometric concrete- liner in tunnel.
In the implementation of the present invention, inventor has found that the prior art has at least the following problems:
For construction technology of the prior art there are low construction efficiency, personnel, equipment arrange the problem of unreasonable.It is specific next Say, in the prior art, within the period for standing concrete, other operations can not be carried out again, can just start to collect after the standing Middle construction.So not only delay the construction period, influence construction efficiency, while concentrate input human and material resources, easily cause job placement It is chaotic.
The content of the invention
In order to solve concrete- liner construction technology in the prior art, there are low construction efficiency, personnel, equipment arrangement are unreasonable Defect, an embodiment of the present invention provides a kind of tunnel concrete lining construction ancillary equipment and technique.The technical solution is specific as follows:
In a first aspect, an embodiment of the present invention provides a kind of tunnel concrete lining construction ancillary equipment, including:Template and branch Frame, the stent support the template it is had pre-set space between tunnel surrounding,
The total length of the polylith subtemplate is arranged to:When to the subtemplate at the template tail end and the tunnel After pre-set space casting concrete between road country rock, between the subtemplate and the tunnel surrounding at the template head end Pre-set space in concrete reach default curdled appearance;
The stent includes two sets of width and adjustable for height submounts, when the width and height of a set of submounts contract Hour, it can depart from the support to the template and move at least one subtemplate length along the length direction of the stent Distance.
Alternatively, it is connected between multiple subtemplates by connection component.
Alternatively, the submounts include:The joist of the arch formed by two Curved beams;
It is fixed on by height difference block on the joist outer surface, the top beam set along the length of tunnel direction;
The telescopic crossbeam that both ends are connected with two Curved beams inner sides respectively;And
It is arranged on the telescopic pillar of the joist lower end.
Alternatively, the submounts further include:One end connects the crossbeam lower surface, the other end is connected in the Curved beam The raker beam on surface.
Alternatively, the top beam of two sets of submounts distributes alternately.
Alternatively, the stent further includes while connects the propulsion assembly of two sets of submounts.
Alternatively, an advance distance of the propulsion assembly is the length of at least one subtemplate.
A kind of second aspect, there is provided tunnel concrete lining construction work of the concrete- liner construction equipment provided using first aspect Skill, the technique include:
Stent, be placed in tunnel by step 1, and template is placed on the bracket, the template and the tunnel There is pre-set space between country rock;
Step 2, by the template head end into the template tail end corresponding pre-set space casting concrete;
Step 3, after the pre-set space casting concrete at the template tail end, respectively move two cover branch Frame, so that the head end of the stent departs from the support to the template, the tail end of the stent is at least one beyond the template The length of the template;
The subtemplate at step 4, the dismounting template head end, and the subtemplate under being disassembled is installed on institute State the end that stent exceeds the template;
Step 5, the casting concrete into the pre-set space for the subtemplate newly installed;
Step 6, repeating said steps 3~5 to the completion concrete- liner.
Alternatively, it is described to move two sets of submounts respectively and include:
Step 301, the width and height for reducing a set of submounts, to depart from the support to the template;Edge afterwards Move the distance of at least one subtemplate length of submounts in the length of tunnel direction;Recover the submounts to institute State the support of template;
Step 302, according to the step 301 move the another set of submounts.
Alternatively, the step 301 includes:
Crossbeam, pillar and the raker beam of a set of submounts are shunk, so that the top beam of the submounts departs to institute State the support of template;
The propulsion assembly promotes, and makes described in tail end one of the tail end of the submounts beyond the another set of submounts The distance of subtemplate;
The crossbeam, pillar and the raker beam of the submounts are extended, to recover support of the top beam to the template.
The beneficial effect that technical solution provided in an embodiment of the present invention is brought is:
The present invention implements provided ancillary equipment, wherein when the pre-set space to template tail end virgin's template pours coagulation After soil, the concrete segment in the pre-set space of template head end virgin's template reaches default curdled appearance.Thus by dismounting template The subtemplate of head end, and new installation position is formed after mobile stent, installation is disassembled subtemplate again afterwards, completes this and continuously applies Work.So so that tunnel concrete lining cutting building course is continuously uninterrupted so that working procedure is more reasonable, substantially increases construction Efficiency, avoids low construction efficiency in the prior art, and human and material resources arrange the defects of unreasonable.
Brief description of the drawings
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the present invention, for For those of ordinary skill in the art, without creative efforts, other can also be obtained according to these attached drawings Attached drawing.
Fig. 1 is a kind of side structure schematic diagram of tunnel concrete lining construction ancillary equipment provided in an embodiment of the present invention;
Fig. 2 is the section structure signal of stent in a kind of tunnel concrete lining construction ancillary equipment provided in an embodiment of the present invention Figure;
Fig. 3 is the knot of subtemplate connection component in a kind of tunnel concrete lining construction ancillary equipment provided in an embodiment of the present invention Structure schematic diagram.
Mark in attached drawing is respectively:
1st, template;
11st, subtemplate;
12nd, connection component;
121st, the first fixing bolt;
122nd, the second fixing bolt;
123rd, connection sheet;
124th, nut;
2nd, stent;
21st, submounts;
211st, joist;
212nd, top beam;
213rd, crossbeam;
214th, pillar;
215th, raker beam;
X, Curved beam;
22nd, propulsion assembly.
Embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention Formula is described in further detail.
First, the term position appeared in the embodiment of the present invention is explained, illustrated.In embodiments of the present invention, Concrete- liner is built since the one end in tunnel, then head end is known as close to the one end for building concrete- liner first with template 1 and stent 2, Tail end is known as close to rear one end for building concrete- liner with template 1 and stent 2.Also, the direction of advance of stent 2 is directed toward tail by head end End.
Involved " length " refers to the size along length of tunnel direction in the embodiment of the present invention, and " width " refers to along tunnel The size of width, " height " refer to the size along tunnel radial direction.
The tunnel concrete lining construction ancillary equipment and technique provided below for the embodiment of the present invention carries out detailed Explanation.
Referring to Fig. 1, Fig. 2, an embodiment of the present invention provides a kind of tunnel concrete lining construction ancillary equipment, including:Template 1 with Stent 2,2 support shuttering 1 of stent make it have pre-set space between tunnel surrounding.Wherein, template 1 includes what is be detachably connected Polylith subtemplate 11;The total length of polylith subtemplate 11 is arranged to:When to the subtemplate 11 and tunnel surrounding at 1 tail end of template Between pre-set space casting concrete after, in the pre-set space between subtemplate 11 and tunnel surrounding at 1 head end of template Concrete reaches default curdled appearance.
Stent 2 includes two sets of width, adjustable for height submounts 21, when the width and reduced height of a set of submounts 21 When, it can depart from the support to template 1 and move the distance of at least one 11 length of subtemplate along the length direction of stent 2.
The operation principle for the tunnel concrete- liner ancillary equipment that the embodiment of the present invention is provided is as follows:
When in use, laying bracket 2 in tunnel, and template 1 is placed on stent 2, and adjust two sets of submounts 21 Width effective support is formed to template, form pre-set space between template 1 and tunnel surrounding at this time.The backward pre-set space Casting concrete, forms concrete segment.Since the total length of subtemplate 11 meets the following conditions:When to the son at 1 tail end of template After pre-set space casting concrete between template 11 and tunnel surrounding, subtemplate 11 at 1 head end of template and tunnel surrounding it Between pre-set space in concrete segment reach default curdled appearance.In other words, by the institute of subtemplate 11 positioned at 1 head end of template The concrete segment of support has reached default solidification and has required, therefore the subtemplate 11 of 1 head end of template can be removed.At this time, first contract The width and height of small a set of submounts, disengage it from the support to template, and the tail end of its towards template is moved at least one The distance of a sub- template length, increases the width of the set submounts afterwards, its recovery is supported template;Reduce again afterwards The width of another set of submounts, disengages it from the support to template, and the tail end of its towards template is moved an at least submodule The distance of plate length, is further added by support of the width recovery of the set submounts to template.Pass through the alternating of above-mentioned two sets of subtemplates Walking, makes the overall distance that at least one subtemplate length is moved towards the direction of template tail end of stent 2, so that stent 2 One end depart from support to 1 head end subtemplate 11 of template, the other end of stent 2 forms new at the tail end close to template 1 The installation space of subtemplate 11.In this way, the subtemplate 11 of 1 head end of detachable template, and the subtemplate 11 under being disassembled is pacified At the new installation space formed mounted in stent 2.And then the new subtemplate 11 installed in 1 tail end of stent and tunnel surrounding it Between form pre-set space again, so can form new concrete segment to the pre-set space casting concrete.And complete After new concrete segment, the 11 corresponding concrete segment of subtemplate of 1 first section of template has equally reached default curdled appearance at this time, because This can continue aforesaid operations until completing and the isometric concrete segment in tunnel, i.e. completion tunnel concrete- liner.
Tunnel concrete lining construction ancillary equipment provided in an embodiment of the present invention, using by multiple subtemplates being detachably connected 11 templates 1 formed, and the stent 2 formed by two submounts 21 that can be walked relatively, realize the continuous of concrete- liner and apply Work.Especially by the subtemplate 11 of dismounting 1 first section of template, and new installation position is formed after mobile stent 2, quilt is installed again afterwards Subtemplate 11 is dismantled, completes the continuous construction.Therefore overall tunnel concrete- liner building course is continuously uninterrupted, and procedure arrangement closes Reason, substantially increases construction efficiency, avoids low construction efficiency in the prior art, and human and material resources arrange the defects of unreasonable.
Furthermore, it is necessary to explanation, in the prior art, also there are adjacent concrete section seam crossing stability difference ask Topic, it is specific as follows:
Required since a section concrete section needs standing 3~4 days in the completed with reaching default solidification, afterwards again adjacent Build another section concrete section in position.At this time, two section concrete sections formed when the interval long period, its curdled appearance difference compared with Greatly, therefore easily there is internal stress in the intersegmental junction of adjacent concrete.The stability of concrete segment junction is so reduced, And then the quality of finally formed tunnel concrete- liner is influenced, damage the safety in utilization of tunnel concrete- liner.
And in embodiments of the present invention, by the tunnel concrete lining construction ancillary equipment, when building concrete- liner, except head Secondary primary concreting and the isometric concrete segment of template 1, build the length for only carrying out a subtemplate 11 every time afterwards.Cause This, substantially reduces molding time interval between adjacent concrete section so that adjacent concrete segment is more easy to connect, Jin Erke The seam stability of concrete segment connecting place is effectively improved, and then ensures the quality of built tunnel concrete- liner, improving it makes Use security.
Further, done as described in detail below for the quantity of subtemplate 11.
In embodiments of the present invention, the length of concrete segment of the minimum number of subtemplate 11 with completion can be poured daily It is related.For example, using one day 3 classes of working system, per tour can complete the concrete segment of 2 cross-talk template, 11 length, and mixed Solidifying soil section reaches default solidification and requires the 4 day time of needs;Then the minimum number for the subtemplate 11 that template 1 is included is:3×2×4 =24.During first casting concrete section, succession pours the concrete segment of 24 cross-talk template, 11 length, only needs to install during being somebody's turn to do Subtemplate 11, without dismantling subtemplate 11.After the 24th cross-talk template 11 has been poured, completion pours for the first time.At this time, template 1 is first First subtemplate, the 11 corresponding concrete segment of section has reached default solidification and has required, therefore dismountable first subtemplate 11. Stent 2 is moved afterwards, is removed and is reinstalled first the 24th subtemplate 11 of formation of subtemplate 11, and after reinstalling Subtemplate 11 at placing concrete.Obviously, the time needed for a series of this operation, more than pouring corresponding to a subtemplate 11 Concrete segment needed for time.Therefore at this time, second original subtemplate 11 be first present subtemplate 11 pair The concrete segment answered also has reached default solidification and has required, dismountable subtemplate 11.And then circulate and carry out above-mentioned steps, to completion tunnel Road concrete- liner.
Certainly, the concrete segment of 2 cross-talk template, 11 length can be completed according to the working system of 2 classes of productions in one day, per tour, Then the minimum number for the subtemplate 11 that template 1 is included is:2 × 2 × 4=16.In embodiments of the present invention, for subtemplate 11 Particular number do not limit, can according to mentioned above principle with regard to real work arrangement set.
Further, it is connected between connected subtemplate 11 by connection component 12.On 11 connection components 12 of subtemplate Specific implementation form, the embodiment of the present invention is not specifically limited.
Illustratively, referring to Fig. 3, connection component 12 includes the first fixing bolt 121 being arranged on one piece of subtemplate 11, with And the second fixing bolt 122 on adjacent subtemplate 11 is arranged on, while connect the first fixing bolt 121 and the second fixing bolt 122 connection sheet 123, and the nut being adapted with the first fixing bolt 121, the second fixing bolt 122.In use, by son The one of bolt is connected with template 11 facing to tunnel internal, is not connected with the one of bolt facing to tunnel surrounding.In two pieces of connection During subtemplate 11, connection sheet 123 is connected into the first fixing bolt 121 and the second fixing bolt 122 at the same time, is fixed afterwards first Attaching nut 124 on 121 and second fixing bolt 122 of bolt, to be fixedly connected with piece 123, completes the connection of adjacent subtemplate 11. During dismounting, nut 124 is screwed off, removes connecting plate 123.
Other can realize that the mode that adjacent subtemplate 11 is detachably connected can be applied in the embodiment of the present invention.
The continuous of template 1 when building concrete- liner is realized by the subtemplate 11 being detachably connected to advance, and then is improved Construction effect.When template 1 is advanced, two sets of submounts 21 in stent 2 are also required to one side support shuttering 1, one side advanced in unison, It will be described in detail below for the structure of stent 2.
Wherein, referring to Fig. 2, and Fig. 1 is combined, submounts 21 include:By two Curved beam X-shapeds into arch joist 211; Top beam 212 on 211 outer surface of joist is fixed on by height difference block;Both ends are connected scalable with two Curved beams inner sides respectively Crossbeam 213;And it is arranged on the telescopic pillar 214 of 211 lower end of joist.Wherein, the flexible of crossbeam 213 can make two Distance increase or diminution between Curved beam X adjacent end portions;And top beam 212 is set along length of tunnel direction.
In movement wherein a set of submounts 21, the pillar 214 of the submounts 21 is shunk, so that the height of the submounts 2 Reduce the distance of a height difference block;Shrinking the crossbeam 213 of the submounts 21 makes two Curved beam X close, and then is used to support tunnel The top beam 212 of template 1 departs from 1 inner surface of template at road gusset.At this time, the top beam 212 of submounts 21 to be moved no longer supports Template 1, can smoothly advance pre-determined distance.After submounts 21 advance, elongate struts 214 and crossbeam 213 so that top beam 212 support shuttering 1 again.At this time another set of submounts 21 are moved according still further to above-mentioned steps.
In submounts 21 provided in an embodiment of the present invention, by two Curved beam X-shapeds into joist 211 so that its On the premise of satisfaction is adapted with tunnel cross sectional shape, it can depart from top beam 212 to contract and template 1 supported.And lead to Downward, the inward displacement headspace that height difference block is top beam 212 are crossed, realizes the smooth walking of submounts 21.
Preferably, the top beam 212 of two sets of submounts 21 distributes alternately.So when a set of submounts 21 move, its top beam 212 When departing from the support to template 1, another set of submounts 21 can keep uniform to template 1, comprehensive supporting, avoid the occurrence of supporting Weak link causes template 1 to cave in.
Further, which further includes:Table in 213 lower surface of one end connecting cross beam, other end connection Curved beam X The telescopic raker beam 215 in face.In embodiments of the present invention, raker beam 215 be crossbeam 213 stretch, contracting when floor stringer.Due to The overall dimensions of stent 2 are larger, thus by raker beam 215 can ensure joist shrink when uniform force, avoid the occurrence of deflection.
Further, advance for the ease of the opposite of submounts 21, stent 2 further includes while connects two sets of submounts 21 The propulsion assembly 22 of joist 211.Also, the distance once promoted of propulsion assembly 22 is the length of a subtemplate 11.Change speech It, a submounts 21 are opposite with respect to another submounts 21 to walk once, the length for the subtemplate 11 that as advances.So In mobile stent 2, pull by the once promotion of propulsion assembly 22 and once and realize two sets of one submodules of advance of submounts 21 The length of plate 11.Also, the new installation space that the advance of stent 2 is formed also has the length of a subtemplate 11, Jin Erbao The stability of the new installation subtemplate 11 of card.
In embodiments of the present invention, for propulsion assembly 22, telescopic crossbeam 213, pillar 214 and raker beam 215 Specific implementation be not specifically limited, such as use hydraulically extensible cylinder.
The tunnel concrete lining construction ancillary equipment provided by the embodiment of the present invention, it is continuous to realize concrete- liner construction Change, significantly improve construction efficiency, it is more reasonable to human and material resources utilization.
Second aspect of the embodiment of the present invention provides a kind of tunnel concrete lining construction technique, the above-mentioned first party of the technology utilization The ancillary equipment that face is provided carries out.Specifically, which includes:
Stent 2, be placed in tunnel by step 1, template 1 is placed on stent 2, between template 1 and the country rock in tunnel With pre-set space;
Step 2, by 1 head end of template into 1 tail end of template corresponding pre-set space casting concrete;
Step 3, after the pre-set space casting concrete at 1 tail end of template, respectively move two sets of submounts 21, with Make support of the head end disengaging of stent 2 to template 1, the tail end of stent 2 exceeds the length of at least one template 1 of template 1;
Subtemplate 11 at step 4, dismounting 1 head end of template, and the subtemplate 11 under being disassembled exceeds installed in stent 2 The end of template 1;
Step 5, the casting concrete into the pre-set space for the subtemplate 11 newly installed;
Repeat step 3~5 to complete concrete- liner.
The tunnel concrete lining construction technique provided by the embodiment of the present invention so that overall concrete- liner construction technology is continuous Uninterruptedly, construction efficiency, while reasonable arrangement human and material resources are substantially increased, avoid concentrating construction, construction in the prior art not The defects of coherent.
Further, moving two sets of submounts 21 in step 3 respectively includes:
Step 301, the width and height for reducing a set of submounts 21, to depart from the support to template 1;Grown afterwards along tunnel Spend the distance of direction movement at least one 11 length of subtemplate of submounts 21;Recover support of the submounts 21 to template 1;
Step 302, according to step 301 move another set of submounts 21.More specifically, above-mentioned steps 301 further include:
First, the crossbeam 213, pillar 214 and raker beam 215 of a set of submounts 21 are shunk, so that the top of submounts 21 Beam 212 departs from the support to template 1.Secondly, propulsion assembly 22 promotes, and the tail end of submounts 21 is exceeded another set of submounts 21 One subtemplate 11 of tail end distance.Finally, crossbeam 213, pillar 214 and the raker beam 215 of submounts 21 are extended, to recover Support of the top beam 212 to template 1.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent replacement, improvement and so on, should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of tunnel concrete lining construction ancillary equipment, including:Template (1) and stent (2), the stent (2) support the mould Plate (1) makes it have pre-set space between tunnel surrounding, it is characterised in that
The template (1) includes the polylith subtemplate (11) being detachably connected;
The total length of the polylith subtemplate (11) is arranged to:When to the subtemplate (11) at the template (1) tail end After pre-set space casting concrete between the tunnel surrounding, the subtemplate (11) at template (1) head end with The concrete in pre-set space between the tunnel surrounding reaches default curdled appearance;
The stent (2) includes two sets of width and adjustable for height submounts (21), when the width of a set of submounts (21) During with reduced height, its can depart from the support to the template (1) and along the stent (2) length direction move it is at least one The distance of subtemplate (11) length.
2. ancillary equipment according to claim 1, it is characterised in that pass through connection group between multiple subtemplates (11) Part (12) is connected.
3. ancillary equipment according to claim 1, it is characterised in that the submounts (21) include:
The joist (211) of the arch formed by two Curved beams (X);
It is fixed on by height difference block on the joist (211) outer surface, the top beam (212) set along the length of tunnel direction;
The telescopic crossbeam (213) that both ends are connected with two Curved beams (X) inner sides respectively;And
It is arranged on the telescopic pillar (214) of the joist (211) lower end.
4. ancillary equipment according to claim 3, it is characterised in that the submounts (21) further include:One end connects institute State crossbeam (213) lower surface, the other end connects the raker beam (215) of Curved beam (X) inner surface.
5. ancillary equipment according to claim 3, it is characterised in that the top beam of two sets of submounts (21) (212) distribute alternately.
6. ancillary equipment according to claim 3, it is characterised in that the stent (2) further includes while connects two sets of institutes State the propulsion assembly (22) of submounts (21).
7. ancillary equipment according to claim 6 a, it is characterised in that advance distance of the propulsion assembly (22) is The length of at least one subtemplate (11).
8. a kind of tunnel concrete lining construction technique, utilizes the concrete- liner construction auxiliary equipment any one of claim 1~7 Implement, it is characterised in that the technique includes:
Stent (2), be placed in tunnel by step 1, template (1) is placed on the stent (2), the template (1) and institute Stating between the country rock in tunnel has pre-set space;
Step 2, by the template (1) head end into the template (1) tail end corresponding pre-set space casting concrete;
Step 3, after the pre-set space casting concrete at the template (1) tail end, respectively move two cover branch Frame (21), so that the head end of the stent (2) departs from the support to the template (1), the tail end of the stent (2) is beyond described The length of at least one template (1) of template (1);
The subtemplate (11) at step 4, dismounting template (1) head end, and the subtemplate (11) under being disassembled Exceed the end of the template (1) installed in the stent (2);
Step 5, the casting concrete into the pre-set space for the subtemplate (11) newly installed;
Repeating said steps 3~5 are to completing the concrete- liner.
9. technique according to claim 8, it is characterised in that described to move two sets of submounts (21) respectively and include:
Step 301, the width and height for reducing a set of submounts (21), to depart from the support to the template (1);Afterwards The distance of at least one subtemplate (11) length of the submounts (21) is moved along the length of tunnel direction;Described in recovery Support of the submounts (21) to the template (1);
Step 302, according to the step 301 move the another set of submounts (21).
10. technique according to claim 9, it is characterised in that the step 301 includes:
The crossbeam (213), pillar (214) and raker beam (215) of a set of submounts (21) are shunk, so that the submounts (21) top beam (212) departs from the support to the template (1);
The propulsion assembly (22) promotes, and the tail end of the submounts (21) is exceeded the tail end of the another set of submounts (21) The distance of one subtemplate (11);
The crossbeam (213), pillar (214) and raker beam (215) of the submounts (3121) are extended, to recover the top beam (212) to the support of the template (1).
CN201711305324.6A 2017-12-11 2017-12-11 Tunnel concrete lining construction auxiliary equipment and construction process Active CN107905818B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711305324.6A CN107905818B (en) 2017-12-11 2017-12-11 Tunnel concrete lining construction auxiliary equipment and construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711305324.6A CN107905818B (en) 2017-12-11 2017-12-11 Tunnel concrete lining construction auxiliary equipment and construction process

Publications (2)

Publication Number Publication Date
CN107905818A true CN107905818A (en) 2018-04-13
CN107905818B CN107905818B (en) 2019-12-27

Family

ID=61864896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711305324.6A Active CN107905818B (en) 2017-12-11 2017-12-11 Tunnel concrete lining construction auxiliary equipment and construction process

Country Status (1)

Country Link
CN (1) CN107905818B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111271098A (en) * 2020-01-16 2020-06-12 国家能源集团宁夏煤业有限责任公司 Construction method for gob-side entry retaining under metal false roof beside coal pillar
CN112065458A (en) * 2020-09-08 2020-12-11 中建钢构天津有限公司 Novel steel skeleton structure formwork-free rapid environment-friendly tunnel construction method

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100953494B1 (en) * 2009-09-23 2010-04-16 진명구 Front mold for tunnel of concrete working
CN102454410A (en) * 2010-10-26 2012-05-16 李信斌 Timbering equipment for coal mines
CN202544887U (en) * 2012-04-26 2012-11-21 李信斌 Tunnel self-moving supporting shed
CN202673316U (en) * 2012-06-26 2013-01-16 李信斌 Step-shaped tunnel self-moving supporting shed
CN104234723A (en) * 2014-07-23 2014-12-24 中建三局集团有限公司 Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section
CN104533447A (en) * 2014-12-19 2015-04-22 郑州煤矿机械集团股份有限公司 Coal face gob-side entry retaining supporting method
CN104594918A (en) * 2014-12-31 2015-05-06 上海市机械施工集团有限公司 Split integrated underground passage steel mold plate trolley and construction method thereof
CN105041339A (en) * 2015-07-28 2015-11-11 上海市机械施工集团有限公司 Clutch type formwork trolley, trolley assembly and underground passage concrete construction method
CN105673045A (en) * 2015-12-30 2016-06-15 中铁十二局集团有限公司 Large reverse slop and small cross-section tunnel double chassis direct connection lining construction method
CN106013233A (en) * 2016-07-14 2016-10-12 中国建筑第八工程局有限公司 Slippage system used for underground pipe rack cast-in-place construction and construction method of slippage system
CN107255034A (en) * 2017-08-11 2017-10-17 中铁隧道集团有限公司 All-hydraulic voluntarily formwork jumbo carries out split and passes through formula concrete placings construction method
CN107387122A (en) * 2017-08-17 2017-11-24 中铁上海工程局集团有限公司 A kind of formwork jumbo and its construction method for the construction of piping lane tunneling boring
CN107448211A (en) * 2016-06-01 2017-12-08 湖南五新机械有限公司 Tunnel efficient construction method and its automatically walk shifting formwork transposition framework trestle used

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100953494B1 (en) * 2009-09-23 2010-04-16 진명구 Front mold for tunnel of concrete working
CN102454410A (en) * 2010-10-26 2012-05-16 李信斌 Timbering equipment for coal mines
CN202544887U (en) * 2012-04-26 2012-11-21 李信斌 Tunnel self-moving supporting shed
CN202673316U (en) * 2012-06-26 2013-01-16 李信斌 Step-shaped tunnel self-moving supporting shed
CN104234723A (en) * 2014-07-23 2014-12-24 中建三局集团有限公司 Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section
CN104533447A (en) * 2014-12-19 2015-04-22 郑州煤矿机械集团股份有限公司 Coal face gob-side entry retaining supporting method
CN104594918A (en) * 2014-12-31 2015-05-06 上海市机械施工集团有限公司 Split integrated underground passage steel mold plate trolley and construction method thereof
CN105041339A (en) * 2015-07-28 2015-11-11 上海市机械施工集团有限公司 Clutch type formwork trolley, trolley assembly and underground passage concrete construction method
CN105673045A (en) * 2015-12-30 2016-06-15 中铁十二局集团有限公司 Large reverse slop and small cross-section tunnel double chassis direct connection lining construction method
CN107448211A (en) * 2016-06-01 2017-12-08 湖南五新机械有限公司 Tunnel efficient construction method and its automatically walk shifting formwork transposition framework trestle used
CN106013233A (en) * 2016-07-14 2016-10-12 中国建筑第八工程局有限公司 Slippage system used for underground pipe rack cast-in-place construction and construction method of slippage system
CN107255034A (en) * 2017-08-11 2017-10-17 中铁隧道集团有限公司 All-hydraulic voluntarily formwork jumbo carries out split and passes through formula concrete placings construction method
CN107387122A (en) * 2017-08-17 2017-11-24 中铁上海工程局集团有限公司 A kind of formwork jumbo and its construction method for the construction of piping lane tunneling boring

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111271098A (en) * 2020-01-16 2020-06-12 国家能源集团宁夏煤业有限责任公司 Construction method for gob-side entry retaining under metal false roof beside coal pillar
CN111271098B (en) * 2020-01-16 2021-06-08 国家能源集团宁夏煤业有限责任公司 Construction method for gob-side entry retaining under metal false roof beside coal pillar
CN112065458A (en) * 2020-09-08 2020-12-11 中建钢构天津有限公司 Novel steel skeleton structure formwork-free rapid environment-friendly tunnel construction method
CN112065458B (en) * 2020-09-08 2022-09-16 中建钢构天津有限公司 Novel steel skeleton structure formwork-free rapid environment-friendly tunnel construction method

Also Published As

Publication number Publication date
CN107905818B (en) 2019-12-27

Similar Documents

Publication Publication Date Title
CN104963290B (en) Flat vertical curve combination section variable cross-section cast-in-situ box girder formwork erecting structure and construction method
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN105350454B (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN106638304A (en) UHPC-common-concrete-lamination composite bridge-deck-slab construction and constructing method thereof
CN104032668B (en) Half-through steel purlin-Combined concrete continuous steel frame bridge
CN110700105B (en) Synchronous construction method for high pier column and tie beam and template used in same
CN215164794U (en) Three-dimensional retractable template suitable for assembled bent cap
CN108755421A (en) Capping beam construction device and construction method
CN107905818A (en) A kind of tunnel concrete lining construction ancillary equipment and construction technology
CN102251481B (en) Railway pier layered construction method and construction device
CN204875533U (en) Flat cast -in -place case roof beam of curve combination section variable cross section mode structure of indulging
CN110792028B (en) Construction method of cable-stayed bridge without back cables
CN214497202U (en) Strutting arrangement is used in construction of steel-concrete composite beam decking
CN107142834B (en) A kind of Through Steel pipe concrete tie-rod arch bridge abutment steel pipe location structure and its construction method
CN212641878U (en) Prestressed concrete superimposed sheet bottom plate
CN110847052B (en) Porous large-section cast-in-situ box girder and construction method
CN210561618U (en) Concrete pavement pouring formwork system
CN107190898A (en) Exempt from formwork super thick floor and its construction method
CN109837924B (en) Construction method for intersection part of lattice column and main body structure of foundation pit support
CN107366427B (en) A kind of city cast-in-situ hollow Sandwich Plates concrete construction method
CN206070404U (en) Oblique formwork support structure at the section haunch of box culvert top
CN206553938U (en) Bridge pier integral formwork support one-shot forming structure
CN109972537B (en) Construction method of composite reinforced structure of double-arch bridge
CN212358013U (en) Cable tower operation platform template separation lift system
CN211849006U (en) Hollow slab beam transverse splicing auxiliary construction device capable of being rapidly spliced in modular mode

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant