CN107881985A - A kind of river course groynes structure and its construction method - Google Patents

A kind of river course groynes structure and its construction method Download PDF

Info

Publication number
CN107881985A
CN107881985A CN201711211111.7A CN201711211111A CN107881985A CN 107881985 A CN107881985 A CN 107881985A CN 201711211111 A CN201711211111 A CN 201711211111A CN 107881985 A CN107881985 A CN 107881985A
Authority
CN
China
Prior art keywords
groynes
hollow shell
river course
shell pill
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711211111.7A
Other languages
Chinese (zh)
Inventor
陈海琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Institute of Industry Technology
Original Assignee
Nanjing Institute of Industry Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Institute of Industry Technology filed Critical Nanjing Institute of Industry Technology
Priority to CN201711211111.7A priority Critical patent/CN107881985A/en
Publication of CN107881985A publication Critical patent/CN107881985A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

This application discloses a kind of river course groynes structure, including groynes body, the groynes body includes dam root and dam body from dam root to river course that extended from the soil body for the side for being arranged on river course, and stone is filled with around dam body;Groynes body includes concrete bodies and the spaced hollow shell pill of outer rim along concrete bodies, and the stake bottom of hollow shell pill is less than the bottom surface of concrete bodies, and through hole is offered on the pile lining of hollow shell pill, and the through hole is in the straight hole shape tilted down from inside to outside;Connection beam is set between adjacent hollow shell pill.Disclosed herein as well is the construction method of above-mentioned river course groynes structure.River course groynes structure has stronger anti-impact force, reduces width of the groynes body along river direction, reduces the expenditure of construction of groynes.

Description

A kind of river course groynes structure and its construction method
Technical field
The present invention relates to hydraulic engineering field, it is more particularly related to a kind of river course groynes structure and its construction Method.
Background technology
Groynes is the river regulating structure that or oblique orthogonal with riverbank is stretched into river course, and the end on dam connects with embankment is in " T " font, the structure and form of construction work of existing groynes still use traditional dam construction method, in order to meet needs, dam Body is larger along the width of water (flow) direction, and the expenditure of construction made is higher, and construction speed is slower.
The content of the invention
To reduce the expenditure of construction of groynes and improving construction speed, the application first proposed a kind of groynes structure, specifically Technical scheme it is as follows:
A kind of river course groynes structure, including groynes body, the groynes body include the soil body for being arranged on the side in river course Interior dam root and the dam body extended from dam root into river course, are filled with stone around dam body;Groynes body include concrete bodies, With the spaced hollow shell pill of outer rim along concrete bodies, the stake bottom of hollow shell pill is less than the bottom surface of concrete bodies, hollow Through hole is offered on the pile lining of pile tube, the through hole is in the straight hole shape tilted down from inside to outside;Adjacent hollow shell pill it Between connection beam is set.
Further, pea gravel concreten is filled with the centre bore of hollow shell pill, pea gravel concreten via through holes are connected to mixed On the solidifying soil body.Preferably, the stake bottom of hollow shell pill is less than the bottom surface 4-6 rice of concrete bodies.
In the groynes structure of the application, using hollow shell pill as the supporter around groynes body, and in hollow shell pill Pea gravel concreten is inside poured into a mould, part pea gravel concreten can overflow from the through hole on pile lining, the microlith coagulation that this part is overflowed Soil can be connected on concrete bodies, made to contact even closer between hollow shell pill and concrete bodies, also enhanced groynes body Anti-impact force, width of the groynes body along river direction can be efficiently reduced., can on the basis of groynes body width is reduced The matrix of groynes body is efficiently reduced, reduces the expenditure of construction of groynes.Hollow shell pill is connected as an entirety by linking beam, is protected The intensity of groynes body is demonstrate,proved.
The application also provides a kind of construction method of above-mentioned groynes structure, specifically comprises the following steps:
(1) according to setting position sinking hollow shell pill, in the lateral surface sinking steel sheet pile of hollow shell pill, steel sheet pile is mutually twisted Cofferdam is formed, excavation pit and is completed in the range of cofferdam institute corral;
(2) connection beam is installed between adjacent hollow shell pill;
(3) pea gravel concreten is poured into a mould into the centre bore of hollow shell pill, and makes pea gravel concreten from the through hole on pile lining Extrusion;
(4) concrete is poured into a mould in foundation ditch, while stone is put into concrete, until the designed elevation of groynes body, its In in the soil body of the side in river course groynes body form dam root, groynes body in river course forms dam body;
(5) steel sheet pile is extracted before concrete solidifies completely;
(6) to surrounding's throwing stone of dam body.
Preferably, the steel sheet pile is U-shaped steel sheet pile.
Preferably, the hollow shell pill is concrete tubular pile.
Preferably, the stake bottom of the steel sheet pile is less than bottom of foundation ditch 3-4 rice.
Using steel sheet pile as cofferdam in this method, the cofferdam formed by steel sheet pile has good water resistance, In work progress, outside body of water can be effectively prevented from and entered in foundation ditch.At present in the work progress of groynes, still more generally Using first excavating foundation ditch, then after the inwall installation form of foundation ditch, the cast of concrete is carried out, and in this application, steel sheet pile The cofferdam formed also has the function that template, eliminates and sets up template in addition, can reduce operating expenses.
Brief description of the drawings
Fig. 1 is the sketch of groynes structure.
Fig. 2 be Fig. 1 in A-A to view.
Fig. 3 is to complete the schematic diagram after hollow shell pill and steel sheet pile sinking.
Fig. 4 is to complete foundation ditch to excavate and the schematic diagram after connection beam installation.
Fig. 5 is to complete the schematic diagram after being poured into a mould in the centre bore of hollow shell pill.
Fig. 6 is to complete concrete cast, and pulls out the schematic diagram after steel sheet pile.
Specific embodiment
Fig. 1 and Fig. 2, a kind of river course groynes structure, including groynes body 10 are referred to, groynes body 10 includes being arranged on river Dam root 12 in the soil body 11 of the side in road and the dam body 14 extended from dam root 12 into river course 30, are filled with around dam body 14 Stone 15.
Groynes body 10 includes concrete bodies 40 and the spaced hollow shell pill 13 of outer rim along concrete bodies 40, empty The stake bottom of heart pile tube 13 is less than the bottom surface of concrete bodies 40, through hole 21 is offered on the pile lining of hollow shell pill 40, through hole 21 is in The straight hole shape tilted down from inside to outside.
Connection beam 22 is set between adjacent hollow shell pill 13.
Pea gravel concreten 26 is filled with the centre bore 23 of hollow shell pill 13, the via through holes 21 of pea gravel concreten 26 are connected to On concrete bodies 40.
In the present embodiment, the stake bottom of hollow shell pill 13 is less than 5 meters of the bottom surface of concrete bodies 40.In other embodiments, The stake bottom of hollow shell pill 13 may also be below the bottom surface 4-6 rice of concrete bodies 40.
The construction method of above-mentioned river course groynes structure is described below in conjunction with Fig. 3-Fig. 6, comprised the following steps:
(1) Fig. 3 is referred to, according to setting position sinking hollow pipe 13, in the lateral surface sinking steel sheet pile of hollow shell pill 13, steel plate The stake bottom of stake is less than bottom of foundation ditch 3-4 rice, steel sheet pile is mutually twisted to form cofferdam 17, is opened in the range of the corral of 17, cofferdam Dig foundation ditch and complete.
(2) Fig. 4 is referred to, connection beam 22 is installed between adjacent hollow shell pill 13 and completed.
(3) Fig. 5 is referred to, pea gravel concreten 26 is poured into a mould into the centre bore 23 of hollow shell pill 13, and make pea gravel concreten 26 Extruded from the through hole 21 on pile lining, the pea gravel concreten of extrusion forms a small concrete block 24.
(4) Fig. 6 is referred to, concrete 14 is poured into a mould in foundation ditch, while stone is put into concrete, until setting for groynes body Absolute altitude is counted, wherein groynes body forms dam root in the soil body of the side in river course, the groynes body in river course forms dam Body;
(5) steel sheet pile is extracted before concrete solidifies completely;
(6) to surrounding's throwing stone of dam body.
In the present embodiment, steel sheet pile specifically uses U-shaped steel sheet pile.Hollow shell pill is concrete tubular pile.

Claims (7)

1. a kind of river course groynes structure, including groynes body, it is characterised in that the groynes body includes being arranged on the one of river course Dam root in the soil body of side and the dam body extended from dam root into river course, are filled with stone around dam body;
Groynes body includes concrete bodies and the spaced hollow shell pill of outer rim along concrete bodies, the stake bottom of hollow shell pill Less than the bottom surface of concrete bodies, through hole is offered on the pile lining of hollow shell pill, the through hole is in what is tilted down from inside to outside Straight hole shape;
Connection beam is set between adjacent hollow shell pill.
2. groynes structure in river course according to claim 1, it is characterised in that filled with thin in the centre bore of hollow shell pill Stone concrete, pea gravel concreten via through holes are connected on concrete bodies.
3. groynes structure in river course according to claim 1, it is characterised in that the stake bottom of hollow shell pill is less than concrete bodies Bottom surface 4-6 rice.
4. the construction method of the river course groynes structure described in a kind of claim 2, it is characterised in that comprise the following steps:
(1) according to setting position sinking hollow shell pill, in the lateral surface sinking steel sheet pile of hollow shell pill, steel sheet pile is mutually twisted to be formed Cofferdam, excavation pit and completed in the range of cofferdam institute corral;
(2) connection beam is installed between adjacent hollow shell pill;
(3) pea gravel concreten is poured into a mould into the centre bore of hollow shell pill, and pea gravel concreten is extruded from the through hole on pile lining;
(4) concrete is poured into a mould in foundation ditch, while stone is put into concrete, until the designed elevation of groynes body, its middle position Dam root is formed in groynes body in the soil body of the side in river course, the groynes body in river course forms dam body;
(5) steel sheet pile is extracted before concrete solidifies completely;
(6) to surrounding's throwing stone of dam body.
5. construction method according to claim 4, it is characterised in that the steel sheet pile is U-shaped steel sheet pile.
6. construction method according to claim 4, it is characterised in that the hollow shell pill is concrete tubular pile.
7. construction method according to claim 4, it is characterised in that the stake bottom of the steel sheet pile is less than bottom of foundation ditch 3-4 Rice.
CN201711211111.7A 2017-11-28 2017-11-28 A kind of river course groynes structure and its construction method Pending CN107881985A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711211111.7A CN107881985A (en) 2017-11-28 2017-11-28 A kind of river course groynes structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711211111.7A CN107881985A (en) 2017-11-28 2017-11-28 A kind of river course groynes structure and its construction method

Publications (1)

Publication Number Publication Date
CN107881985A true CN107881985A (en) 2018-04-06

Family

ID=61775615

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711211111.7A Pending CN107881985A (en) 2017-11-28 2017-11-28 A kind of river course groynes structure and its construction method

Country Status (1)

Country Link
CN (1) CN107881985A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118563710A (en) * 2024-08-01 2024-08-30 浙江江南春建设集团有限公司 Anti-impact T-dam structure and construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002242164A (en) * 2001-02-20 2002-08-28 Nippon Steel Metal Prod Co Ltd Civil engineering structure such as sediment control weir and levee or the like using steel sheet pile and thinning member or the like and construction method therefor
JP2005200933A (en) * 2004-01-15 2005-07-28 Komiyama Doboku:Kk Comb dam
CN101666098A (en) * 2009-08-03 2010-03-10 天津大学 Sheet-cell conduit frame prefabricated part pilling structure and dock using same
CN201459674U (en) * 2009-09-01 2010-05-12 黄河水利委员会黄河水利科学研究院 PHC tubular pile dam
CN101775788A (en) * 2010-02-10 2010-07-14 王军 Block stone-reinforced concrete piling composite groyne bank protection structure
JP2013002086A (en) * 2011-06-14 2013-01-07 Kenji Ishikura Pile frame structure and structure of the same
CN204000840U (en) * 2014-07-10 2014-12-10 安徽省金田建筑设计咨询有限责任公司 Concrete floral tube slip casting uplift pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002242164A (en) * 2001-02-20 2002-08-28 Nippon Steel Metal Prod Co Ltd Civil engineering structure such as sediment control weir and levee or the like using steel sheet pile and thinning member or the like and construction method therefor
JP2005200933A (en) * 2004-01-15 2005-07-28 Komiyama Doboku:Kk Comb dam
CN101666098A (en) * 2009-08-03 2010-03-10 天津大学 Sheet-cell conduit frame prefabricated part pilling structure and dock using same
CN201459674U (en) * 2009-09-01 2010-05-12 黄河水利委员会黄河水利科学研究院 PHC tubular pile dam
CN101775788A (en) * 2010-02-10 2010-07-14 王军 Block stone-reinforced concrete piling composite groyne bank protection structure
JP2013002086A (en) * 2011-06-14 2013-01-07 Kenji Ishikura Pile frame structure and structure of the same
CN204000840U (en) * 2014-07-10 2014-12-10 安徽省金田建筑设计咨询有限责任公司 Concrete floral tube slip casting uplift pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118563710A (en) * 2024-08-01 2024-08-30 浙江江南春建设集团有限公司 Anti-impact T-dam structure and construction method

Similar Documents

Publication Publication Date Title
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN101255691B (en) Construction method for complete casing tube thin wall filling pile and movable internal mold
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN104988907A (en) Construction method of concrete pile
CN108330764B (en) Shallow layer solidified pile bearing type embankment and construction method
CN208136652U (en) Shallow-layer solidifies Piled Embankments
CN203403404U (en) High-efficiency cast-in-place pile device
CN107905221A (en) A kind of method for being accurately positioned percussive drilling bored concrete pile
CN108193642A (en) A kind of revetment reinforces facility and its construction method
CN103696416A (en) Novel foundation treatment method
CN202323865U (en) Novel revetment combined structure
CN109184221A (en) Anchor rib construction method is planted after a kind of concrete
CN110485444B (en) Construction method for seepage prevention and reinforcement of deepwater cofferdam
CN203834468U (en) Internal expansion type miniature concrete pile
CN107587502A (en) A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method
CN107881985A (en) A kind of river course groynes structure and its construction method
CN103343534A (en) Closed precipitation method for foundation pit construction
CN205776282U (en) A kind of immersed tube tunnel rebuilds cofferdam structure
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN106638646A (en) Secondary bottom sealing structure of open caisson and construction method
CN110144881A (en) One kind is drowned oneself type precast hollow friction pile and its construction method
CN207109804U (en) A kind of quick spreading structure configuration of soft soil foundation bored concrete pile
CN206655217U (en) Precast concrete drainage pile
CN207538090U (en) A kind of externally reinforced structure of Urban underground Tunnel
CN110219256A (en) A kind of channel complexity Construction of Supporting method for passing through box culvert

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180406