CN107905221A - A kind of method for being accurately positioned percussive drilling bored concrete pile - Google Patents

A kind of method for being accurately positioned percussive drilling bored concrete pile Download PDF

Info

Publication number
CN107905221A
CN107905221A CN201711215718.2A CN201711215718A CN107905221A CN 107905221 A CN107905221 A CN 107905221A CN 201711215718 A CN201711215718 A CN 201711215718A CN 107905221 A CN107905221 A CN 107905221A
Authority
CN
China
Prior art keywords
stake holes
hole
mud
casing
accurately positioned
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711215718.2A
Other languages
Chinese (zh)
Inventor
刘平
周波
万飞
冉鹏
陈彦君
房志华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd
Chongqing Construction Engineering Group Co Ltd
Chongqing Communications Construction Group Co Ltd
Original Assignee
CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd, Chongqing Construction Engineering Group Co Ltd filed Critical CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd
Priority to CN201711215718.2A priority Critical patent/CN107905221A/en
Publication of CN107905221A publication Critical patent/CN107905221A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Earth Drilling (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of method for being accurately positioned percussive drilling bored concrete pile, including:Hole position is measured, buries casing, slurrying, drilling, examines hole, first time borehole cleaning, the making and fixing of reinforcing steel bar cage, installs conduit, second of borehole cleaning, the perfusion of concrete.A kind of method for being accurately positioned percussive drilling bored concrete pile in the present invention, can be accurately positioned stake holes, easy to the construction of drilling machine by designing fender pile;Embedded casing not only protects aperture to prevent ground stone from falling into hole, while ensures mud water level, prevents the hole that collapses;Twice borehole cleaning can effective cleaning hole bottom heavy quarrel, the pile body after perfusion is not easy broken pile and folder mud, ensure that pile quality.

Description

A kind of method for being accurately positioned percussive drilling bored concrete pile
Technical field
The present invention relates to technical field of civil engineering, more particularly to a kind of method for being accurately positioned percussive drilling bored concrete pile.
Background technology
Bored concrete pile refers to pass through means shapes in foundation soil such as machine drilling, steel pipe soil compaction or manpower excavation in engineering site Into stake holes, and steel reinforcement cage, concrete perfusion and the stake made are placed in it, different according to forming hole method, bored concrete pile can divide again For several classes such as driven cast-in-place pile, cast-in-situ bored pile and digging hole filling pile.Wherein cast-in-situ bored pile is most widely used, existing brill Hole method for filling positions the shortcomings that not accurate enough, operation is not sufficiently stable due to existing in boring procedure, causes the stake after perfusion Body easily goes out the perfusion bad phenomenons such as broken pile, undergauge, folder mud, influences pile quality.
The content of the invention
To solve in the prior art, the skill such as position inaccurate, fluctuation of service during drilling existing for drill-pouring piling method Art problem, technical scheme are as follows:
A kind of method for being accurately positioned percussive drilling bored concrete pile in the present invention, including:
Step S101, measure hole position, using the position of total powerstation positioning stake holes, draws cross tailor's tack to put according to the position of stake holes Four control fender piles, draw bored concrete pile contour line on the basis of four control fender piles;
Step S102, bury casing, casing waste pit is dug according to bored concrete pile contour line, will cheat bottom it is smooth after be put into shield Cylinder, is backfilled after the stack shell of casing is vertical with clay;
Step S103, slurrying, digs mud pit, mud is using water, high viscosity using excavator in the range of stake holes It is prepared by clay and additive;
Step S104, drilling, lifting drilling machine make the center of cross hairs in drill central alignment procedures S101, and drilling machine is first with small Stroke perforate, after drilling depth exceedes drill bit overall height, adds stroke normally to be impacted, and mud is injected stake holes during drilling It is interior;
Step S105, examines hole, detects hole depth, aperture and the gradient of stake holes;
Step S106, first time borehole cleaning, continues to inject mud into stake holes, by flushing repeatedly for the low stroke of impact cone, Bottom hole is set to sink quarrel as mud is easily discharged out of the hole using mud endless form;
Step S107, the making and fixing of reinforcing steel bar cage, steel reinforcement cage are hung steel reinforcement cage with crane by steel bar meter field sectional making Enter in stake holes, fixed under every after complete section steel reinforcement cage with steel pipe or the lumps of wood, then hang another section steel reinforcement cage with crane and welded, Whole steel reinforcement cages are hung in stake holes successively;
Step S108, is installed conduit, is hung in conduit in stake holes using crane;
Step S109, mud, is pressed into conduit by second of borehole cleaning using pump, then from bottom hole along conduit outside displacement it is heavy Quarrel;
Step S110, the perfusion of concrete, by conduit into stake holes concrete perfusion.
Further, it is further comprising the steps of before the step S101:
Step S100, smooth location, makes the place of stake holes to the height of design requirement.
Further, in the step S102, casing is one-piece steel casing, and the wall thickness of casing is 4mm, casing Internal diameter is more than the aperture 20cm of stake holes, and during shield-tube embedment, construction ground 0.3m is higher by the top of casing.
Further, it is further comprising the steps of in the step S103:
Step S1031, the shape of mud pit is rectangle, is separated in mud pit long side direction, forms pulping pond and sinks Shallow lake pond;
Step S1032, sedimentation basin are connected by mud ditch with casing;
Step S1033, the top in pulping pond install iron sheet case using steel pipe frame, and iron sheet case elevation of bottom is higher than stake holes absolute altitude Mud in mud pit, is extracted into iron sheet case by least 50cm using slush pump, then uses more rubber-plastic flexible pipes from iron sheet tank wall It is connected with stake holes to be drilled.
Further, it is further comprising the steps of in the step S104:
Take in batches jump hole apply, bore pile hole construction when applied by every two piles, adjacent two pile driving constructions interval time is not When small less than 36.
Further, in the step S108, conduit uses diameterThe seamless steel pipe of wall thickness 6mm.
Further, it is further comprising the steps of in the step S105:
Step S1051, using the aperture of cage inspection hole device detection stake holes;
Step S1052, using the oblique instrument of side wall or the gradient of drilling rod normal line method detection stake holes;
Step S1053, using the hole depth of lining rope detection stake holes.
A kind of method for being accurately positioned percussive drilling bored concrete pile in the present invention, compared with prior art, its advantage For:
A kind of method for being accurately positioned percussive drilling bored concrete pile in the present invention, stake can be accurately positioned by designing fender pile Hole, easy to the construction of drilling machine;Embedded casing not only protects aperture to prevent ground stone from falling into hole, while ensures mud water level, Prevent the hole that collapses;Twice borehole cleaning can effective cleaning hole bottom heavy quarrel, the pile body after perfusion is not easy broken pile and folder mud, ensure that pile body Quality.
Brief description of the drawings
Fig. 1 is a kind of flow diagram for the method for being accurately positioned percussive drilling bored concrete pile in the present invention.
Embodiment
Below in conjunction with the attached drawing of the present invention, technical scheme is clearly and completely described.Based on this hair Embodiment in bright, the every other implementation that those of ordinary skill in the art are obtained without creative efforts Example, belongs to the scope of protection of the invention.
As shown in Figure 1, a kind of method for being accurately positioned percussive drilling bored concrete pile in the present invention, including:
Step S101, measure hole position, using the position of total powerstation positioning stake holes, draws cross tailor's tack to put according to the position of stake holes Four control fender piles, draw bored concrete pile contour line on the basis of four control fender piles, and accurate in place so as to drilling machine, fender pile will be done Work is protected well, is prevented disturbed in work progress.
Step S102, bury casing, casing waste pit is dug according to bored concrete pile contour line, will cheat bottom it is smooth after be put into shield Cylinder, is backfilled after the stack shell of casing is vertical with clay, and compaction in layers, and with filling out with observation casing, casing position is inclined when preventing from banketing Move, after shield-tube embedment is good, reinforcing rib and lifting lug are welded at top and outputs the mouth of a river
Step S103, slurrying, digs mud pit, mud pit is set using sunk type using excavator in the range of stake holes Put, to prevent mud leakage after the completion of excavation, tunnel waterproof roll shop fixtures is used after bottom cushion pours, and roll up in waterproof 5cm thickness fish tail and waterproof layers are poured above material.Mud is prepared using water, high viscosity clay and additive, mud have floating outstanding boring mud, Drill bit, lubrication drilling tool are cooled down, increases the effect of hydrostatic pressure.
Step S104, drilling, lifting drilling machine make the center of cross hairs in drill central alignment procedures S101, and drilling machine is first with small Stroke perforate, after drilling depth exceedes drill bit overall height, adds stroke normally to be impacted, and mud is injected stake holes during drilling Interior, mud forms mudcake in hole wall and forms retaining wall effect, separates seepage flow inside and outside hole, the effect in the hole that prevents from collapsing.
Step S105, examines hole, detects hole depth, aperture and the gradient of stake holes.
Step S106, first time borehole cleaning, continues to inject mud into stake holes, by flushing repeatedly for the low stroke of impact cone, Bottom hole is set to sink quarrel as mud is easily discharged out of the hole using mud endless form.
Step S107, the making and fixing of reinforcing steel bar cage, steel reinforcement cage are hung steel reinforcement cage with crane by steel bar meter field sectional making Enter in stake holes, fixed under every after complete section steel reinforcement cage with steel pipe or the lumps of wood, then hang another section steel reinforcement cage with crane and welded, Whole steel reinforcement cages are hung in stake holes successively.
Step S108, is installed conduit, is hung in conduit in stake holes using crane.
Step S109, second of borehole cleaning, after in first time, borehole cleaning reaches requirement, due to steel reinforcement cage to be placed and conduit, extremely The time slot of pour concrete is longer, and bottom hole can produce heavy quarrel again, so after placement steel reinforcement cage and conduit are ready, recycles conduit Carry out second of borehole cleaning, mud be pressed into conduit using pump, then from bottom hole along conduit outside the heavy quarrel of displacement, be concrete perfusion Create good condition.
Step S110, the perfusion of concrete, by conduit into stake holes concrete perfusion.
Further, it is further comprising the steps of before the step S101:
Step S100, smooth location, makes the place of stake holes to the height of design requirement.
Further, in the step S102, casing is one-piece steel casing, and the wall thickness of casing is 4mm, casing Internal diameter is more than the aperture 20cm of stake holes, and during shield-tube embedment, construction ground 0.3m is higher by the top of casing.
Further, it is further comprising the steps of in the step S103:
Step S1031, the shape of mud pit is rectangle, is separated in mud pit long side direction, forms pulping pond and sinks Shallow lake pond;
Step S1032, sedimentation basin are connected by mud ditch with casing;
Step S1033, the top in pulping pond install iron sheet case using steel pipe frame, and iron sheet case elevation of bottom is higher than stake holes absolute altitude Mud in mud pit, is extracted into iron sheet case by least 50cm using slush pump, then uses more rubber-plastic flexible pipes from iron sheet tank wall It is connected with stake holes to be drilled.
Further, it is further comprising the steps of in the step S104:
Take in batches jump hole apply, bore pile hole construction when applied by every two piles, adjacent two pile driving constructions interval time is not When small less than 36.
Further, in the step S108, conduit uses diameterThe seamless steel pipe of wall thickness 6mm.
Further, it is further comprising the steps of in the step S105:
Step S1051, using the aperture of cage inspection hole device detection stake holes;
Step S1052, using the oblique instrument of side wall or the gradient of drilling rod normal line method detection stake holes;
Step S1053, using the hole depth of lining rope detection stake holes.
The above description is merely a specific embodiment, but protection scope of the present invention is not limited thereto, any Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained Cover within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (7)

  1. A kind of 1. method for being accurately positioned percussive drilling bored concrete pile, it is characterised in that including:
    Step S101, measure hole position, using the position of total powerstation positioning stake holes, draws cross tailor's tack to put four according to the position of stake holes Fender pile is controlled, bored concrete pile contour line is drawn on the basis of four control fender piles;
    Step S102, bury casing, casing waste pit is dug according to bored concrete pile contour line, will cheat bottom it is smooth after be put into casing, protect Cylinder stack shell it is vertical after backfilled with clay;
    Step S103, slurrying, digs mud pit, mud is using water, high viscosity clay using excavator in the range of stake holes Prepared with additive;
    Step S104, drilling, lifting drilling machine make the center of cross hairs in drill central alignment procedures S101, and drilling machine is first with small stroke Perforate, after drilling depth exceedes drill bit overall height, adds stroke normally to be impacted, by mud injection stake holes during drilling;
    Step S105, examines hole, detects hole depth, aperture and the gradient of stake holes;
    Step S106, first time borehole cleaning, continues to inject mud into stake holes, by flushing repeatedly for the low stroke of impact cone, utilizes Mud endless form makes bottom hole sink quarrel as mud is easily discharged out of the hole;
    Steel reinforcement cage is hung in stake by step S107, the making and fixing of reinforcing steel bar cage, steel reinforcement cage by steel bar meter field sectional making with crane In hole, fixed under every after complete section steel reinforcement cage with steel pipe or the lumps of wood, then hang another section steel reinforcement cage with crane and welded, successively Whole steel reinforcement cages are hung in stake holes;
    Step S108, is installed conduit, is hung in conduit in stake holes using crane;
    Step S109, mud, is pressed into conduit by second of borehole cleaning using pump, then from bottom hole along conduit outside the heavy quarrel of displacement;
    Step S110, the perfusion of concrete, by conduit into stake holes concrete perfusion.
  2. A kind of 2. method for being accurately positioned percussive drilling bored concrete pile according to claim 1, it is characterised in that the step It is further comprising the steps of before S101:
    Step S100, smooth location, makes the place of stake holes to the height of design requirement.
  3. 3. a kind of method for being accurately positioned percussive drilling bored concrete pile according to claim 1, it is characterised in that in the step In rapid S102, casing is one-piece steel casing, and the wall thickness of casing is 4mm, and the internal diameter of casing is more than the aperture 20cm of stake holes, shield When cylinder is embedded, construction ground 0.3m is higher by the top of casing.
  4. A kind of 4. method for being accurately positioned percussive drilling bored concrete pile according to claim 1, it is characterised in that the step It is further comprising the steps of in S103:
    Step S1031, the shape of mud pit is rectangle, is separated in mud pit long side direction, forms pulping pond and sedimentation basin;
    Step S1032, sedimentation basin are connected by mud ditch with casing;
    Step S1033, the top in pulping pond install iron sheet case using steel pipe frame, and iron sheet case elevation of bottom is higher than stake holes absolute altitude at least Mud in mud pit, is extracted into iron sheet case by 50cm using slush pump, then iron sheet tank wall is used more rubber-plastic flexible pipes with treating Bore stake holes connection.
  5. A kind of 5. method for being accurately positioned percussive drilling bored concrete pile according to claim 1, it is characterised in that the step It is further comprising the steps of in S104:
    Take in batches jump hole apply, bore pile hole construction when applied by every two piles, adjacent two pile driving constructions interval time is not less than 36 it is small when.
  6. 6. a kind of method for being accurately positioned percussive drilling bored concrete pile according to claim 1, it is characterised in that in the step In rapid S108, conduit uses diameterThe seamless steel pipe of wall thickness 6mm.
  7. A kind of 7. method for being accurately positioned percussive drilling bored concrete pile according to claim 1, it is characterised in that the step It is further comprising the steps of in S105:
    Step S1051, using the aperture of cage inspection hole device detection stake holes;
    Step S1052, using the oblique instrument of side wall or the gradient of drilling rod normal line method detection stake holes;Step S1053, is detected using lining rope The hole depth of stake holes.
CN201711215718.2A 2017-11-28 2017-11-28 A kind of method for being accurately positioned percussive drilling bored concrete pile Pending CN107905221A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711215718.2A CN107905221A (en) 2017-11-28 2017-11-28 A kind of method for being accurately positioned percussive drilling bored concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711215718.2A CN107905221A (en) 2017-11-28 2017-11-28 A kind of method for being accurately positioned percussive drilling bored concrete pile

Publications (1)

Publication Number Publication Date
CN107905221A true CN107905221A (en) 2018-04-13

Family

ID=61847924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711215718.2A Pending CN107905221A (en) 2017-11-28 2017-11-28 A kind of method for being accurately positioned percussive drilling bored concrete pile

Country Status (1)

Country Link
CN (1) CN107905221A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797569A (en) * 2018-06-26 2018-11-13 江苏地基工程有限公司 A kind of control method that drilled pile novel energy-conserving pile crown is superfilled
CN108978644A (en) * 2018-07-28 2018-12-11 江苏地基工程有限公司 Energy saving and environment friendly bored pile construction method
CN109797757A (en) * 2019-01-16 2019-05-24 包头市公路工程股份有限公司 Retaining wall engineering method in the construction of highway engineering Bridge Bored Pile
CN111236220A (en) * 2020-01-19 2020-06-05 中交第三航务工程局有限公司江苏分公司 Construction process of punching cast-in-place pile of mixed foundation in sea-filling area
CN111851478A (en) * 2020-07-13 2020-10-30 深圳市工勘岩土集团有限公司 Pile-forming construction method for light corrugated steel pile casing isolation non-filling karst cave filling pile
CN113404040A (en) * 2021-07-06 2021-09-17 中铁二十局集团第六工程有限公司 Construction method of bored pile foundation
CN114541436A (en) * 2022-04-02 2022-05-27 中铁二院昆明勘察设计研究院有限责任公司 Rectangular anti-slide pile forming method for soft soil section

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56142921A (en) * 1980-04-03 1981-11-07 Taisei Corp Construction work of foundation of structure
CN103615001A (en) * 2013-11-27 2014-03-05 宁波盛宏建设工程有限公司 Bored pile construction method for reinforcing cage framework layered installation
CN107130592A (en) * 2017-04-10 2017-09-05 贾茂来 A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56142921A (en) * 1980-04-03 1981-11-07 Taisei Corp Construction work of foundation of structure
CN103615001A (en) * 2013-11-27 2014-03-05 宁波盛宏建设工程有限公司 Bored pile construction method for reinforcing cage framework layered installation
CN107130592A (en) * 2017-04-10 2017-09-05 贾茂来 A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘爱华: "陇南卵石层地层冲击钻孔灌注桩施工技术要点讨论", 《科技资讯》 *
张继莹 等: "旋挖钻机钻孔灌注桩施工工艺", 《科技信息》 *
李长平: "班多水电站专用公路桥梁工程冲击钻孔灌注桩施工工艺", 《科技信息》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797569A (en) * 2018-06-26 2018-11-13 江苏地基工程有限公司 A kind of control method that drilled pile novel energy-conserving pile crown is superfilled
CN108978644A (en) * 2018-07-28 2018-12-11 江苏地基工程有限公司 Energy saving and environment friendly bored pile construction method
CN108978644B (en) * 2018-07-28 2020-09-29 江苏地基工程有限公司 Energy-saving and environment-friendly construction method for cast-in-situ bored pile
CN109797757A (en) * 2019-01-16 2019-05-24 包头市公路工程股份有限公司 Retaining wall engineering method in the construction of highway engineering Bridge Bored Pile
CN111236220A (en) * 2020-01-19 2020-06-05 中交第三航务工程局有限公司江苏分公司 Construction process of punching cast-in-place pile of mixed foundation in sea-filling area
CN111851478A (en) * 2020-07-13 2020-10-30 深圳市工勘岩土集团有限公司 Pile-forming construction method for light corrugated steel pile casing isolation non-filling karst cave filling pile
CN113404040A (en) * 2021-07-06 2021-09-17 中铁二十局集团第六工程有限公司 Construction method of bored pile foundation
CN114541436A (en) * 2022-04-02 2022-05-27 中铁二院昆明勘察设计研究院有限责任公司 Rectangular anti-slide pile forming method for soft soil section

Similar Documents

Publication Publication Date Title
CN107905221A (en) A kind of method for being accurately positioned percussive drilling bored concrete pile
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN110424381A (en) A kind of process for rotary digging drilling hole stake
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN108166483A (en) Bored pile construction method
CN111827275A (en) Karst area pile foundation construction system and construction method
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN110106872A (en) A kind of super thick mud head of district casing concrete pouring of punched hole piles method
CN110042842A (en) A kind of open cut construction method of deep foundation ditch for wearing river
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
CN104480929B (en) A kind of pile wall interaction construction method that interlocking pile is applied to permanent outer wall of basement
CN115341533B (en) Drilling construction method for easy-collapse stratum cast-in-situ pile
CN113668527A (en) Construction method for inserting long steel pile casing under rotary digging pile construction of deep rockfill silt stratum
CN110158579A (en) A kind of bored pile construction method
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN113737780A (en) Underwater rock-socketed concrete pile and construction method thereof
CN109339079A (en) A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum
CN103374900A (en) Gravity wharf built on silt foundation and method for constructing gravity wharf
CN110485444B (en) Construction method for seepage prevention and reinforcement of deepwater cofferdam
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN209066468U (en) A kind of base pit dewatering device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180413

RJ01 Rejection of invention patent application after publication