JP2002242164A - Civil engineering structure such as sediment control weir and levee or the like using steel sheet pile and thinning member or the like and construction method therefor - Google Patents

Civil engineering structure such as sediment control weir and levee or the like using steel sheet pile and thinning member or the like and construction method therefor

Info

Publication number
JP2002242164A
JP2002242164A JP2001043828A JP2001043828A JP2002242164A JP 2002242164 A JP2002242164 A JP 2002242164A JP 2001043828 A JP2001043828 A JP 2001043828A JP 2001043828 A JP2001043828 A JP 2001043828A JP 2002242164 A JP2002242164 A JP 2002242164A
Authority
JP
Japan
Prior art keywords
steel sheet
sheet pile
concrete
anchor
foundation beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001043828A
Other languages
Japanese (ja)
Other versions
JP4421124B2 (en
Inventor
Kiyoshi Sano
佐野  清
Keiichi Iwatsuri
敬一 岩釣
Kengo Hori
堀  謙吾
Yoshikatsu Akiyama
祥克 秋山
Hiroyuki Handa
博幸 半田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INBAKKUSU KK
Nippon Steel Metal Products Co Ltd
Original Assignee
INBAKKUSU KK
Nippon Steel Metal Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INBAKKUSU KK, Nippon Steel Metal Products Co Ltd filed Critical INBAKKUSU KK
Priority to JP2001043828A priority Critical patent/JP4421124B2/en
Publication of JP2002242164A publication Critical patent/JP2002242164A/en
Application granted granted Critical
Publication of JP4421124B2 publication Critical patent/JP4421124B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a civil engineering structure and a construction method by using steel sheet piles at upstream side and thinning members or the like at downstream side as exterior wall members respectively and concrete is filled up inside the space between the exterior walls. SOLUTION: An end portion of a joint member is connected to a foundation beam determining the bottom position of the steel sheet pile, a bottom end of the steel sheet pile is inserted to the inside a channel of a foundation beam, and the steel sheet pile is supported by struts from the inner side. A waling member is jointed to the steel sheet pile, and anchors are attached to the waling members. Column members having channels are arranged on the foundation ground, a supporting plate for the column member is connected by the end of a tie member and connected to the foundation beam. Both ends of the thinning members or the like are inserted to the channel portion of the column member and piled up. An anchor member is attached to an anchor hooking plate, and concrete is poured to the inner side of the exterior wall members.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、上流側に鋼矢板
を、下流側に間伐材等をそれぞれ外壁材として用い、そ
の内側にコンクリートを充填してなる砂防堰堤等の土木
構造物及びその構築工法の技術分野に属する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a civil engineering structure, such as a sabo dam, which is constructed by using a steel sheet pile on the upstream side and a thinned material on the downstream side as an outer wall material and filling the inside thereof with concrete. Belongs to the technical field of construction methods.

【0002】[0002]

【従来の技術】従来、上流側の外壁材を鋼矢板で構成
し、下流側の外壁材を間伐材等で構成して、前記両外壁
材の内側にコンクリートを充填してなる砂防堰堤等の土
木構造物は皆無に等しい。しかし、鋼矢板を用いた砂防
堰堤等の土木構造物の構造としては、例えば、
2. Description of the Related Art Conventionally, an outer wall material on the upstream side is made of steel sheet piles, and an outer wall material on the downstream side is made of thinned wood or the like. There are no civil structures. However, as the structure of civil engineering structures such as sabo dams using steel sheet piles, for example,

【0003】(I)鋼矢板を上流側及び下流側の外壁材
として用い、その内側にコンクリートを打設してなる砂
防堰堤等の土木構造物(特公平4−33921号公報、
特開平7−3750号公報)。
(I) Civil structures such as sabo dams in which steel sheet piles are used as outer wall materials on the upstream and downstream sides and concrete is cast inside the piles (Japanese Patent Publication No. 4-33921,
JP-A-7-3750).

【0004】(II)鋼板を上流側及び下流側の外壁材と
して用い、その内側にコンクリートを打設してなる砂防
堰堤等の土木構造物(特公昭61−3929号公報、実
開昭60−40530号公報)。
(II) Civil structures, such as sabo dams, in which a steel sheet is used as an outer wall material on the upstream and downstream sides and concrete is cast inside the material (Japanese Patent Publication No. 61-3929, Japanese Utility Model Application No. 60-160). No. 40530).

【0005】(III)鋼矢板を千鳥状に組み立て上流側
及び下流側の外壁材として用い、その内側にコンクリー
トを打設してなる砂防堰堤等の土木構造物(特公平4−
2727号公報、特公平4−44644号公報)。など
が公知に属する。
(III) Steel sheet piles are assembled in a zigzag pattern and used as outer wall materials on the upstream and downstream sides, and concrete is cast on the inside thereof.
No. 2727, Japanese Patent Publication No. 4-44464). Etc. belong to the public domain.

【0006】上記(I)〜(III)いずれの土木構造物
も、基礎地盤上に直接鋼矢板等を構築して外壁材を完成
し、又は基礎地盤上に基礎フレーム等の骨組みを構築
し、その骨組みに鋼矢板等を接合して外壁材を完成し
て、前記外壁材の内側へコンクリートを打設して土木構
造物を完成する構築工法が採用されている。
[0006] In any of the above civil structures (I) to (III), a steel sheet pile or the like is constructed directly on the foundation ground to complete an outer wall material, or a framework such as a foundation frame is constructed on the foundation ground. A construction method has been adopted in which a steel sheet pile or the like is joined to the frame to complete an outer wall material, and concrete is cast inside the outer wall material to complete a civil engineering structure.

【0007】[0007]

【本発明が解決しようとする課題】上述した従来技術の
ように基礎地盤上に直接鋼矢板を構築すると、一段目の
鋼矢板の配置や、鋼矢板の傾斜角度等を設計した通りに
構築することが困難である。即ち、外壁材を正確に定形
化する(コンクリート型枠としての形を作り保持す
る。)ことが困難である。
When the steel sheet pile is constructed directly on the foundation ground as in the above-mentioned prior art, the arrangement of the first-stage steel sheet pile, the inclination angle of the steel sheet pile, etc. are constructed as designed. It is difficult. That is, it is difficult to accurately shape the outer wall material (make and hold the shape as a concrete formwork).

【0008】また、コンクリートの打設を一気に完了さ
せるため、向かい合う外壁材同士はコンクリートの打設
圧に耐えるようにタイロッド等の連結部材で連結するな
どの補強工作を行い、外壁材の変形(いわゆる孕み)を
防ぐ強固な構成とする必要がある。
Further, in order to complete the casting of the concrete at a stretch, the opposing outer wall materials are connected to each other by a connecting member such as a tie rod so as to withstand the concrete driving pressure, and the outer wall materials are deformed (so-called deformation). It is necessary to have a strong configuration that prevents

【0009】そのため、基礎地盤上に基礎フレーム等の
骨組みを構築し、その骨組みに鋼矢板を接合して外壁材
を完成させることも行われるが、この場合には部材点数
が多くなってコストが嵩む。しかも前記部材点数の増加
に伴い組立作業が煩雑となる。
[0009] Therefore, a framework such as a foundation frame is constructed on the foundation ground, and a steel sheet pile is joined to the framework to complete the outer wall material. However, in this case, the number of members increases and the cost increases. Bulky. In addition, as the number of members increases, the assembling work becomes complicated.

【0010】従って、本発明の目的は、少ない部材点
数、少ない工数で外壁材の定形化(特に第一段目)を容
易に行うことができ、コストの削減と作業能率の向上が
可能で、しかも自然と調和して景観性が高い鋼矢板及び
間伐材等を用いた砂防堰堤等の土木構造物及びその構築
工法を提供することである。
Therefore, an object of the present invention is to make it possible to easily form the outer wall material (especially, the first step) with a small number of members and a small number of man-hours, and to reduce costs and improve work efficiency. Moreover, it is an object of the present invention to provide a civil engineering structure such as a sabo dam using a steel sheet pile and a thinned wood material having a high scenic nature in harmony with nature and a construction method thereof.

【0011】[0011]

【課題を解決するための手段】上記従来技術を解決する
ための手段として、請求項1に記載した発明に係る鋼矢
板及び間伐材等を用いた砂防堰堤等の土木構造物は、上
流側の外壁材を鋼矢板で構成し、下流側の外壁材を間伐
材等で構成して、前記両外壁材をコンクリート型枠とし
て用い、その内側へコンクリートを打設して構築された
砂防堰堤等の土木構造物であって、上流側の外壁材の下
端位置を定める基礎梁が基礎地盤上に上向きの溝形断面
材として配置され、前記基礎梁には、同基礎梁と後記の
下流側の柱材の支持プレートとを連結するつなぎ材の一
方の端部が接合されており、前記基礎梁の溝内へ鋼矢板
の下端を挿入してあり、前記鋼矢板は、内側からサポー
ト材で支持された支柱で支保されており、前記鋼矢板に
水平方向の腹起こし材が接合され、その腹起こし材にア
ンカー材が取り付けられていること、前記つなぎ材によ
り基礎梁と連結される支持プレートが下端部に設けら
れ、上方へ間隔を開けて複数のアンカー引掛用プレート
が設けられた、H型鋼等の溝部を有する柱材が基礎地盤
上に間隔を開けて配置され、前記支持プレートには、つ
なぎ材の他方の端部が接合されて上流側の基礎梁と連結
されており、下流側の外壁材である間伐材等の両端が、
隣接する柱材の溝部へ挿入され、柱材の上端部近傍まで
ほぼ水平に積み重ねられており、前記柱材のアンカー引
掛用プレートに腹起こし材が接合され、前記アンカー引
掛用プレート又は腹起こし材の少なくとも一方にアンカ
ー材が取り付けられていること、前記の両外壁材の内側
へコンクリートが打設されていることを特徴とする。
As means for solving the above-mentioned prior art, a civil engineering structure such as a sabo dam using steel sheet pile and thinned wood according to the first aspect of the present invention is provided on the upstream side. The outer wall material is made of steel sheet pile, the outer wall material on the downstream side is made of thinned wood, etc., and the both outer wall materials are used as concrete formwork, and concrete is poured into the inside thereof, such as a sabo dam and the like. In a civil engineering structure, a foundation beam for determining a lower end position of an outer wall material on an upstream side is disposed as an upwardly-facing groove-shaped section material on a foundation ground, and the foundation beam includes the same foundation beam and a downstream column described below. One end of a tie connecting the support plate of the material is joined, the lower end of the steel sheet pile is inserted into the groove of the foundation beam, and the steel sheet pile is supported by the support material from the inside. The steel sheet piles are supported by horizontal pillars. The anchoring material is attached to the protruding material, and a supporting plate connected to the foundation beam by the connecting material is provided at a lower end portion, and a plurality of anchor hooking plates are spaced apart upward. Are provided at intervals on the foundation ground, and the other end of the joining material is joined to the support plate and connected to the upstream foundation beam. Both ends of the thinning material, which is the outer wall material on the downstream side,
It is inserted into the groove of the adjacent column material, is stacked substantially horizontally up to the vicinity of the upper end of the column material, and the buckling material is joined to the anchor hooking plate of the column material, and the anchor hooking plate or the buckling material is joined. Characterized in that an anchor material is attached to at least one of them, and concrete is cast inside the both outer wall materials.

【0012】請求項2記載の発明は、請求項1に記載し
た発明に係る鋼矢板及び間伐材等を用いた砂防堰堤等の
土木構造物において、前記コンクリートの骨材がクラッ
シャーランであることを特徴とする。
According to a second aspect of the invention, in the civil engineering structure such as a sabo dam using the steel sheet pile and the thinned wood according to the first aspect of the invention, the concrete aggregate is a crusher run. And

【0013】請求項3に記載した発明に係る鋼矢板及び
間伐材等を用いた砂防堰堤等の土木構造物の構築工法
は、上流側の外壁材を鋼矢板で構成し、下流側の外壁材
を間伐材等で構成して、前記両外壁材をコンクリート型
枠として用い、その内側へコンクリートを打設して砂防
堰堤等の土木構造物を構築する工法であって、上流側の
外壁材の下端位置を定める基礎梁を基礎地盤上に上向き
の溝形断面材として配置し、前記基礎梁に、同基礎梁と
後記の下流側の柱材の支持プレートとを連結するつなぎ
材の一方の端部を接合し、前記基礎梁の溝内へ鋼矢板の
下端を挿入する段階と、前記鋼矢板を、内側からサポー
ト材で支持された支柱で支保し、前記鋼矢板に水平方向
の腹起こし材を接合する段階と、前記つなぎ材により基
礎梁と連結する支持プレートを下端部に設け、上方へ間
隔を開けて複数のアンカー引掛用プレートを設けた、H
型鋼等の溝部を有する柱材を、基礎地盤上に間隔を開け
て配置し、その支持プレートに、つなぎ材の他方の端部
を接合し上流側の基礎梁と連結する段階と、下流側の外
壁材である間伐材等の両端を、隣接する柱材の溝部へ挿
入し、上流側の背が低い鋼矢板の上端部近傍まで積み重
ねる段階と、前記アンカー引掛用プレートに腹起こし材
を接合する段階と、前記の両外壁材の内側へ、各外壁材
が自立する高さまでコンクリートを打設し、打設したコ
ンクリートの上部を振動ローラー等で転圧し、前記上流
側の腹起こし材、及び下流側のアンカー引掛用プレート
又は腹起こし材の少なくとも一方にアンカー材を取り付
けて、打設したコンクリートが強度を発現するまで養生
する段階と、前記外壁材の構築と、コンクリートの打設
と転圧、及びアンカー材の取付け、並びにコンクリート
の養生を行う工程を、前記土木構造物の高さまで繰り返
す段階とから成ることを特徴とする。
According to a third aspect of the present invention, there is provided a method for constructing a civil engineering structure such as a sabo dam using a steel sheet pile and a thinned material, etc., wherein an upstream outer wall material is constituted by a steel sheet pile, and a downstream outer wall material. Is a method of constructing a civil engineering structure such as a sabo dam by using both outer wall materials as a concrete formwork, casting concrete inside the outer wall material, etc. A foundation beam for determining the lower end position is arranged on the foundation ground as an upward channel-shaped cross-section member, and one end of a linking material connecting the foundation beam and a support plate of a downstream column member described below to the foundation beam. Joining the lower portion of the steel sheet pile into the groove of the foundation beam, supporting the steel sheet pile with a column supported from the inside by a support material, and horizontally bending the steel sheet pile in a horizontal direction. Joining, and supporting to connect to the foundation beam by the connecting member Rates provided at the lower end, provided with a plurality of anchors hooking plate spaced upwardly, H
A column member having a groove portion such as a shape steel is arranged on the foundation ground at an interval, and the other end of the connecting member is joined to the support plate and connected to the upstream foundation beam; Inserting both ends of the thinning material or the like as the outer wall material into the groove of the adjacent pillar material, stacking the steel sheet pile near the upper end portion of the upstream short sheet pile, and joining the protruding material to the anchor hooking plate Step and inside of both outer wall materials, concrete is poured to a height at which each outer wall material is self-supporting, the upper part of the poured concrete is rolled with a vibrating roller or the like, and the upstream side bellows material, and downstream Attach the anchor material to at least one of the side anchor hooking plate or the bulging material, cure the cast concrete until the strength develops, and the construction of the outer wall material, concrete placement and compaction, And Ann Mounting of chromatography material, and a step of performing curing of the concrete, characterized in that it consists of a step repeated until the height of the civil engineering structures.

【0014】請求項4に記載した発明に係る鋼矢板及び
間伐材等を用いた砂防堰堤等の土木構造物の構築工法
は、上流側の外壁材をモジュール長さ及び略1/2モジ
ュール長さに加工した鋼矢板で構成し、下流側の外壁材
を間伐材等で構成して、前記両外壁材をコンクリート型
枠として用い、その内側へコンクリートを打設して砂防
堰堤等の土木構造物を構築する工法であって、上流側の
外壁材の下端位置を定める基礎梁を基礎地盤上に上向き
の溝形断面材として配置し、前記基礎梁に、同基礎梁と
後記の下流側の柱材の支持プレートとを連結するつなぎ
材の一方の端部を接合する段階と、前記基礎梁の上に、
長手方向に間隔を開けて、支柱を一定の内向き傾斜角度
で立て、各支柱は内側からサポート材により支持させる
段階と、前記支柱をガイドにしてその外側に、上記モジ
ュール長さ及び略1/2モジュール長さに加工した一段
目の鋼矢板をそれぞれ互い違いの配置に接合し、それぞ
れの下端を前記基礎梁の溝内へ挿入することによって各
鋼矢板の継目を上下方向に段違いの千鳥状配置に形成
し、前記一段目の背が低い鋼矢板の基礎梁近傍に腹起こ
し材を取り付ける段階と、前記つなぎ材により基礎梁と
連結する支持プレートを下端部に設け、アンカー引掛用
プレートを上流側の鋼矢板とほぼ等しい高さに設け、モ
ジュール長さに加工したH型鋼等の溝部を有する一段目
の柱材を、基礎地盤上に間隔を開けて配置し、その支持
プレートに、前記つなぎ材の他方の端部を接合し、上流
側の基礎梁と連結する段階と、下流側の外壁材である間
伐材等の両端を、隣接する柱材の溝部へそれぞれ挿入
し、上流側の一段目の背が低い鋼矢板とほぼ等しい高さ
まで略水平に積み重ね、前記高さの近傍に設けたアンカ
ー引掛用プレートに腹起こし材を取り付ける段階と、上
流側の一段目の背が低い鋼矢板の上端部近傍まで第一段
目のコンクリートを打設し、打設したコンクリートの上
部を振動ローラー等で転圧し、前記アンカー引掛用プレ
ート又は腹起こし材の少なくとも一方にアンカー材を水
平方向に取り付けて前記打設コンクリートの天端へ置
き、同コンクリートが強度を発現するまで養生する段階
と、上流側の一段目の背が低い鋼矢板の上方に前記モジ
ュール長さの鋼矢板を接合して立て、前記鋼矢板の中部
に二段目の腹起こし材をボルト接合する段階と、下流側
の外壁材である間伐材等を上流側の一段目の背が高い鋼
矢板とほぼ等しい高さまで略水平に積み重ね、前記高さ
の近傍に設けたアンカー引掛用プレートに腹起こし材を
取り付ける段階と、上流側の一段目の背が高い鋼矢板の
上端部近傍まで第二段目のコンクリートを打設して転圧
し、前記背が高い鋼矢板とほぼ等しい高さに設けた下流
側のアンカー引掛用プレート及び上流側の二段目の腹起
こし材にアンカー材を水平方向に取り付けて前記打設コ
ンクリートの天端へ置き、同コンクリートが強度を発現
するまで養生する段階と、以下、上流側の外壁材である
鋼矢板を接合して立て、腹起こし材の取付けを行うと共
に、下流側の柱材を継ぎ足し、間伐材等の積み重ね、及
び腹起こし材の取付けを行い、コンクリートを打設して
転圧し、アンカー材の取付け、及び打設コンクリートの
養生を行う工程を、当該土木構造物の高さまで繰り返す
段階とから成ることを特徴とする。
In the construction method of civil engineering structure such as a sabo dam using steel sheet pile and thinned wood according to the invention as set forth in claim 4, the outer wall material on the upstream side has a module length and a half module length. The outer wall material on the downstream side is made of thinned wood, etc., and the outer wall materials are used as concrete formwork, and concrete is poured into the inside thereof and civil engineering structures such as sabo dams are constructed. A foundation beam that determines the lower end position of the outer wall material on the upstream side is disposed as an upward groove-shaped cross section on the foundation ground, and the foundation beam and the downstream column described below are arranged on the foundation beam. Joining one end of a tie connecting the support plate of the material, and on the foundation beam,
At intervals in the longitudinal direction, the columns are erected at a constant inward inclination angle, and each column is supported by a support material from the inside, and the module length and approximately 1 / The first-stage steel sheet pile processed into a length of 2 modules is joined in a staggered arrangement, and the lower end of each is inserted into the groove of the foundation beam, so that the seams of the steel sheet piles are staggered in the vertical direction. And a step of attaching an uprighting material near the foundation beam of the first-stage short steel sheet pile, and a support plate connected to the foundation beam by the connecting material is provided at a lower end, and an anchor hooking plate is provided on the upstream side. The first column material having a groove portion, such as an H-shaped steel, which is provided at a height substantially equal to that of the steel sheet pile of the above and is processed into a module length, is arranged at intervals on the foundation ground, and the support plate is provided with Joining the other end of the lumber and connecting it to the upstream foundation beam, and inserting both ends of the thinning material, etc., which is the outer wall material on the downstream side, into the grooves of the adjacent pillars, respectively, Stacking substantially horizontally up to a height substantially equal to the height of the first-stage low steel sheet pile, attaching the buckling material to the anchor hooking plate provided near the height, and the first-stage short steel sheet pile on the upstream side The first-stage concrete is poured to the vicinity of the upper end of the concrete, and the upper part of the poured concrete is rolled with a vibrating roller or the like, and the anchor material is horizontally attached to at least one of the anchor hooking plate and the belly material. Placing the concrete on the top of the cast concrete, curing the concrete until the concrete develops its strength, and joining the steel sheet pile of the module length above the first short steel sheet pile on the upstream side. And said At the stage of bolting the second-stage uplifting material to the middle of the sheet pile, and thinning materials etc., which are outer wall materials on the downstream side, are stacked substantially horizontally to a height almost equal to the tall steel sheet pile on the upstream side, Attach the buckling material to the anchor hooking plate provided near the height, and place the second stage concrete near the upper end of the first stage tall steel sheet pile on the upstream side and roll it. Anchor material is attached horizontally to the downstream anchor hooking plate and the upstream second-stage flared material provided at a height substantially equal to the tall steel sheet pile, and then to the top of the cast concrete. Laying the concrete until the concrete develops its strength, and then joining the steel sheet pile, which is the outer wall material on the upstream side, to stand up, attach the uprighting material, add the pillar material on the downstream side, and thin the tree. Stacking of materials, etc., and provocation Repeating the steps of attaching the stiffener, casting and rolling concrete, attaching the anchor material and curing the cast concrete to the height of the civil engineering structure.

【0015】請求項5記載の発明は、請求項3又は4に
記載した発明に係る鋼矢板及び間伐材等を用いた砂防堰
堤等の土木構造物の構築工法において、前記コンクリー
トの骨材がクラッシャーランであることを特徴とする。
According to a fifth aspect of the present invention, in the method for constructing a civil engineering structure such as a sabo dam using the steel sheet pile and the thinned wood according to the third or fourth aspect of the present invention, the concrete aggregate is crusher run. It is characterized by being.

【0016】請求項6記載の発明は、請求項3〜5のい
ずれか一に記載した鋼矢板及び間伐材等を用いた砂防堰
堤等の土木構造物の構築工法において、上流側の鋼矢板
の頂部には、堤冠材を設けることを特徴とする。
According to a sixth aspect of the present invention, there is provided a method of constructing a civil engineering structure such as a sabo dam using the steel sheet pile and the thinned wood according to any one of the third to fifth aspects. It is characterized by providing a bank material on the top.

【0017】[0017]

【本発明の実施の形態、及び実施例】先ずは請求項4〜
6に記載した発明に係る鋼矢板及び間伐材等を用いた砂
防堰堤等の土木構造物の構築工法の実施形態を、図1〜
図13に基づいて説明する。
Embodiments and Examples of the Invention First, claims 4 to
6 shows an embodiment of a construction method of a civil engineering structure such as a sabo dam using steel sheet pile and thinned wood according to the invention described in FIG.
This will be described with reference to FIG.

【0018】この構築工法は、図1〜図3に示すよう
に、上流側の外壁材3をモジュール長さ及び略1/2モ
ジュール長さに加工した鋼矢板5で構成し、下流側の外
壁材3を間伐材6で構成して、一定の間隔を開けて構築
し、前記外壁材3、3をコンクリート型枠として用い、
その内側へコンクリート4を打設して砂防堰堤1を構築
する。
In this construction method, as shown in FIGS. 1 to 3, the upstream outer wall material 3 is constituted by a steel sheet pile 5 processed into a module length and approximately 1/2 module length, and a downstream outer wall material is formed. The lumber 3 is composed of the thinned lumber 6 and is constructed at regular intervals, and the outer wall materials 3 and 3 are used as concrete forms,
The concrete 4 is cast inside the dam, and the sabo dam 1 is constructed.

【0019】先ず、前記砂防堰堤1を構築する第一の工
程が完了した状態を、図4に示している。
First, FIG. 4 shows a state where the first step of constructing the sabo dam 1 is completed.

【0020】上流側の基礎地盤2において、前記上流側
の外壁材3の下端位置を定める基礎梁7を、予め土工に
より地固めを行って整地された基礎地盤2上に、上向き
の溝形断面材として配置し、前記基礎梁7に、同基礎梁
7と後記の下流側の柱材8の支持プレート9とを連結す
るつなぎ材11の一方の端部を接合する。前記つなぎ材
11は、軸材方向に複数本連結され、前記上流側の基礎
梁7と下流側の柱材8の支持プレート9とを一定の間隔
に保持させる。
In the upstream foundation ground 2, a foundation beam 7 that defines the lower end position of the upstream outer wall material 3 is placed on the foundation ground 2, which has been previously solidified by earthwork, and has an upward groove-shaped section material. And one end of a connecting member 11 for connecting the foundation beam 7 and a support plate 9 of a downstream column member 8 described later is joined to the foundation beam 7. A plurality of the connecting members 11 are connected in the direction of the shaft member, and maintain the upstream base beam 7 and the support plate 9 of the downstream column member 8 at a constant interval.

【0021】具体的に説明すると、上流側の外壁材3
は、図1及び図2等に示すように、隣り合う鋼矢板を相
互に接合できるように両端にジョイント部を有する公知
の鋼矢板を使用し、構築作業に至便のモジュール長さ及
び略1/2モジュール長さに加工して用い、もって各々
の継目が互い違いに高低に変化する、所謂段違いの千鳥
状配置となるように組み立てる。したがって、隣り合う
鋼矢板5、5相互を容易に、且つ緊密に接合することが
でき、鋼矢板5…の定形化が容易で構築作業が簡易であ
る。そのため、作業効率の向上が可能でコストの削減に
寄与する。
More specifically, the outer wall material 3 on the upstream side
As shown in FIGS. 1 and 2 and the like, a known steel sheet pile having joint portions at both ends so that adjacent steel sheet piles can be joined to each other is used. It is used after being processed into two module lengths, so that each seam alternately changes in height, so-called staggered staggered arrangement. Therefore, the adjacent steel sheet piles 5, 5 can be easily and tightly joined to each other, so that the steel sheet piles 5,... Therefore, work efficiency can be improved, which contributes to cost reduction.

【0022】その一段目の鋼矢板5…の下端位置を定め
る基礎梁7は、図5に示すように、外壁材3の長さ(堰
堤の長さ)の応じて複数本をボルト12と接合プレート
13とで長く連結して構成され、同基礎梁7を基礎地盤
2上に配置する。そして、前記基礎梁7の長手方向に一
定の間隔(2m程度)を開けて、つなぎ材11を配置
し、その一方の端部を基礎梁7にボルト接合している。
As shown in FIG. 5, a plurality of the foundation beams 7 for determining the lower end positions of the first-stage steel sheet piles 5 are joined to the bolts 12 according to the length of the outer wall material 3 (the length of the bank). The foundation beam 7 is arranged on the foundation ground 2 by being long connected to the plate 13. A connecting member 11 is arranged at a predetermined interval (about 2 m) in the longitudinal direction of the foundation beam 7, and one end thereof is bolted to the foundation beam 7.

【0023】その基礎梁7の上に、長手方向に間隔(2
m程度)を開けて、支柱14を一定の傾斜角度(約1.
4rad)で立て、各支柱14は基端を前記つなぎ材11
へボルト止めしたサポート材15により内側から支持さ
せる。支柱14は1m程度の高さを有する山形鋼で構成
され、図2及び図9に示すように、前記基礎梁7とつな
ぎ材11との接合部位に、下端を上記基礎梁7の溝7a
内へ挿入して立て、上端部近傍をサポート材15とボル
ト止めして一定の内向き傾斜角度に支持させている。
On the foundation beam 7, an interval (2
m), and the support column 14 is tilted at a constant inclination angle (approximately 1.
4 rad), and each strut 14 has its base end connected to the connecting material 11.
It is supported from the inside by the support material 15 which is bolted to the side. The column 14 is made of angle steel having a height of about 1 m. As shown in FIGS. 2 and 9, the lower end of the column 14 is provided at the joint 7 between the foundation beam 7 and the connecting member 11.
The support member 15 is bolted to the vicinity of the upper end with the support member 15 so as to be supported at a constant inward inclination angle.

【0024】前記支柱14をガイドにしてその外側に、
図5及び図9に示すように、上記のモジュール長さ及び
略1/2モジュール長さに加工した一段目の鋼矢板5と
5’を互い違いの配置に接合し、それぞれの下端を前記
基礎梁7の溝部7aへ挿入することによって、一段目の
鋼矢板5及び5’を外壁材として立てる。したがって、
一段目の鋼矢板5及び5’の下端位置及び傾斜角度を容
易に定めることができ、作業効率の向上が可能でコスト
の削減に寄与する。
Using the support 14 as a guide, on the outside thereof,
As shown in FIGS. 5 and 9, the first-stage steel sheet piles 5 and 5 ′ processed into the above-described module length and approximately モ ジ ュ ー ル module length are joined in a staggered arrangement, and each lower end is connected to the foundation beam. 7, the first-stage steel sheet piles 5 and 5 'are erected as outer wall materials. Therefore,
The lower end position and the inclination angle of the first-stage steel sheet piles 5 and 5 'can be easily determined, and the work efficiency can be improved and the cost can be reduced.

【0025】次に、図5及び図10に示すように、前記
一段目の鋼矢板5及び5’の内側面の基礎梁近傍に共通
の腹起こし材16を配置し、内側面が腹起こし材16と
当たっている鋼矢板(本実施形態では背が低い鋼矢板
5’)と腹起こし材16とをボルト12で接合する。そ
の場合、腹起こし材16へ当たらない背が高い鋼矢板5
の内側面と腹起こし材16とは支柱14を挟み込み、鋼
矢板5…がコンクリート4を打設した際のコンクリート
圧により外側へ倒れない構造としている。
Next, as shown in FIGS. 5 and 10, a common flaring material 16 is arranged near the foundation beam on the inner surface of the first-stage steel sheet piles 5 and 5 '. The steel sheet pile (in this embodiment, the short steel sheet pile 5 ′) which is in contact with 16 is connected to the belly material 16 with the bolt 12. In this case, the tall steel sheet pile 5 which does not hit the belly material 16
Are sandwiched between the inner side surface and the belly material 16 so as to sandwich the column 14, so that the steel sheet piles 5 do not fall outward due to the concrete pressure when the concrete 4 is cast.

【0026】一方、下流側の基礎地盤2には、図3及び
図4に示すように、前記つなぎ材11により基礎梁7と
連結する支持プレート9を下端部に設け、アンカー引掛
用プレート10を上流側の鋼矢板とほぼ等しい高さ、即
ち、本実施形態では、中間部及び上端部に設け、上流側
の鋼矢板5のモジュール長さとほぼ等しい長さ(例え
ば、1m程度)に加工したH形鋼等の溝部8aを有する
一段目の柱材8を、前記基礎地盤2上に間隔を開けて配
置する。前記支持プレート9は、鉛直部と水平部とで構
成され、前記アンカー引掛用プレート10も、鉛直部と
水平部とで構成されて、その鉛直部には、アンカー材1
7のフック部を挿入する孔が設けられている。その支持
プレート9の水平部に、前記つなぎ材11の他方の端部
をボルト接合し、上流側の基礎梁7と連結する。
On the other hand, as shown in FIGS. 3 and 4, a support plate 9 which is connected to the foundation beam 7 by the connecting member 11 is provided at a lower end of the downstream foundation ground 2 and an anchor hooking plate 10 is provided. The height H is substantially equal to the height of the steel sheet pile on the upstream side, that is, in the present embodiment, is provided at the intermediate portion and the upper end portion, and is processed to a length substantially equal to the module length of the steel sheet pile 5 on the upstream side (for example, about 1 m). First-stage column members 8 having grooves 8a such as shaped steel are arranged on the foundation ground 2 at intervals. The support plate 9 is composed of a vertical portion and a horizontal portion, and the anchor hooking plate 10 is also composed of a vertical portion and a horizontal portion.
A hole for inserting the hook portion 7 is provided. The other end of the connecting member 11 is bolted to the horizontal portion of the support plate 9 and connected to the upstream foundation beam 7.

【0027】上記間伐材6の両端を、図3及び図6
(A)に示すように、隣接する柱材8、8の溝部8a、
8aにそれぞれ挿入し、上流側の一段目の背が低い鋼矢
板5’とほぼ等しい高さまで略水平に積み重ね、図6
(B)に示すように、前記高さの近傍位置、即ち、柱材
8の中間部に設けたアンカー引掛用プレート10の水平
部に、一段目の腹起こし材16をボルト12で接合す
る。したがって、前記間伐材6の両端を隣接する柱材
8、8の溝部8a、8aにそれぞれ挿入するだけで同間
伐材6…を略水平に積み重ねて壁を作ることができ、間
伐材6…の定形化が容易である。しかも、前記間伐材6
…の下端位置及び傾斜角度も容易に定めることができ構
築作業が簡易である。そのため、作業効率の向上が可能
でコストの削減に寄与する。
The two ends of the thinned wood 6 are connected to each other as shown in FIGS.
As shown in (A), the groove portions 8a of the adjacent column members 8, 8,
8a, and stacked substantially horizontally to a height substantially equal to the height of the first-stage short steel sheet pile 5 'on the upstream side, and FIG.
As shown in (B), the first-stage bulging material 16 is joined to the position near the height, that is, the horizontal portion of the anchor hooking plate 10 provided at the intermediate portion of the column member 8 with the bolt 12. Therefore, the wall can be formed by stacking the thinned materials 6 approximately horizontally by simply inserting the both ends of the thinned materials 6 into the grooves 8a, 8a of the adjacent pillars 8, 8, respectively. Easy to shape. Moreover, the thinned wood 6
Can be easily determined, and the construction work is simple. Therefore, work efficiency can be improved, which contributes to cost reduction.

【0028】その後、上流側の一段目の背が低い鋼矢板
5’の上端部近傍まで第一段目のコンクリート4を打設
し、前記打設したコンクリート4の上部を振動ローラー
等で転圧する。このコンクリート4が強度を発現する前
に、アンカー引掛用プレート10の鉛直部の孔へアンカ
ー材17のフック部を挿入し、前記アンカー材17はコ
ンクリート4の天端へ置く(又は寝かせる)形で略水平
方向に取り付ける。そして、前記第一段目のコンクリー
ト4が強度を発現するまで養生し、砂防堰堤1を構築す
る第一の工程が完了する。
After that, the first-stage concrete 4 is poured to the vicinity of the upper end of the first-stage short steel sheet pile 5 ′ on the upstream side, and the upper portion of the concrete 4 is compacted by a vibrating roller or the like. . Before the concrete 4 develops strength, the hook portion of the anchor member 17 is inserted into the hole of the vertical portion of the anchor hooking plate 10, and the anchor member 17 is placed (or laid down) on the top end of the concrete 4. Install in a substantially horizontal direction. Then, the first concrete 4 is cured until the concrete 4 exhibits the strength, and the first step of constructing the sabo dam 1 is completed.

【0029】前記第一の工程では、上流側の外壁材3に
おいて、下流側の支持プレート9とつなぎ材11で連結
した基礎梁7、サポート材15により支保された支柱1
4、及び腹起こし材16のそれぞれが、鋼矢板5及び
5’を支持する働きをなし、更に、鋼矢板5及び5’自
身の剛性、及び隣り合う鋼矢板5、5’相互の接合力等
が、コンクリート4を打設した際のコンクリート圧に耐
える強度を発揮する。
In the first step, in the outer wall material 3 on the upstream side, the foundation beam 7 connected to the support plate 9 on the downstream side by the linking material 11 and the column 1 supported by the support material 15 are provided.
Each of the steel sheet piles 5 and 5 'serves to support the steel sheet piles 5 and 5', and furthermore, the rigidity of the steel sheet piles 5 and 5 'itself, and the joining strength between the adjacent steel sheet piles 5 and 5'. However, it exhibits the strength to withstand the concrete pressure when the concrete 4 is cast.

【0030】一方、下流側の外壁材3において、上流側
の基礎梁7とつなぎ材11により連結した支持プレート
9、及び腹起こし材16が、間伐材6を挿入する柱材8
を支持する働きをなし、更に柱材8及び間伐材6自身の
剛性が、コンクリート4を打設した際のコンクリート圧
に耐える強度を発揮する。
On the other hand, in the downstream outer wall member 3, the support plate 9 connected to the upstream foundation beam 7 by the linking member 11 and the belly raising member 16 form the column member 8 into which the thinning material 6 is inserted.
In addition, the rigidity of the pillar 8 and the thinned wood 6 themselves exerts a strength to withstand the concrete pressure when the concrete 4 is cast.

【0031】したがって、上流側及び下流側の外壁材
3、3同士をタイロッド等の連結部材で連結して補強す
る工作の必要はない。なお、前記コンクリート4の骨材
には、クラッシャーランを用いる(請求項5記載の発
明)。前記クラッシャーランは、道路の路盤材などに使
用する道路用砕石である。具体的には、破砕機で破砕し
た後、ふるいにかけずそのまま使用する砕石であって、
全国どこでも安価に入手できる。そのため、材料調達を
容易に行うことができコストの削減と作業効率の向上が
可能である。
Therefore, there is no need to reinforce the upstream and downstream outer wall members 3, 3 by connecting them with connecting members such as tie rods. A crusher run is used as the aggregate of the concrete 4 (the invention according to claim 5). The crusher run is crushed stone for roads used for roadbed materials of roads and the like. Specifically, crushed stone that is used as it is without sieving after crushing with a crusher,
It is available at low cost anywhere in the country. Therefore, material procurement can be easily performed, and cost reduction and work efficiency can be improved.

【0032】つづいて、砂防堰堤1を構築する第二の工
程が完了した状態を、図7に示している。
FIG. 7 shows a state in which the second step of constructing the sabo dam 1 has been completed.

【0033】上流側の外壁材3において、図8に示すよ
うに、上流側の一段目の背が低い鋼矢板5’の上方へモ
ジュール長さの鋼矢板5を接合して立て、前記鋼矢板5
の中部を二段目の腹起こし材16とボルト12で接合す
る。その場合、一段目の背が高い鋼矢板5の内側面と前
記腹起こし材16とで支柱14を挟み込む。
As shown in FIG. 8, on the upstream outer wall material 3, a steel sheet pile 5 having a module length is joined and erected above the shortest steel sheet pile 5 'at the first stage on the upstream side. 5
Is joined to the second-stage belly-raising material 16 with the bolts 12. In this case, the support 14 is sandwiched between the inner surface of the first-stage tall steel sheet pile 5 and the belly-raising member 16.

【0034】下流側の外壁材3としては、間伐材6を上
流側の一段目の背が高い鋼矢板5とほぼ等しい高さ、即
ち、一段目の柱材8の上端部近傍まで略水平に間伐材6
を積み重ねる(図7を参照)。なお、本実施形態の場
合、前記高さの近傍位置、即ち柱材8の上端部に設けた
アンカー引掛用プレート10に、後記二段目の柱材8の
支持プレート9を接合するため、前記アンカー引掛用プ
レート10に、腹起こし材を設けない。
As the outer wall material 3 on the downstream side, the thinned wood 6 is set to a height almost equal to the height of the tall steel sheet pile 5 on the upstream side, that is, almost horizontally to the vicinity of the upper end of the column material 8 on the first stage. Thinned wood 6
Are stacked (see FIG. 7). In the case of the present embodiment, the support plate 9 of the second-stage pillar 8 is joined to a position near the height, that is, the anchor hooking plate 10 provided at the upper end of the pillar 8. The buckling material is not provided on the anchor hooking plate 10.

【0035】その後、上流側の一段目の背が高い鋼矢板
5の上端部近傍まで第二段目のコンクリート4を打設し
て、第一の工程と略同様に振動ローラー等で、前記打設
コンクリート4を転圧する。このコンクリート4が強度
を発現する前に下流側のアンカー引掛用プレート10の
孔及び上流側の二段目の腹起こし材16に予めあけてお
いた孔へアンカー材17のフック部を挿入し、前記アン
カー材17をコンクリート4の天端へ置く(又は寝かせ
る)形で略水平方向に取り付ける。そして、前記第二段
目のコンクリート4が強度を発現するまで養生し、砂防
堰堤1を構築する第二の工程が完了する。
Thereafter, the second-stage concrete 4 is cast near the upper end of the tall steel sheet pile 5 at the first stage on the upstream side, and the above-described striking is performed by a vibrating roller or the like in substantially the same manner as in the first step. The concrete 4 is compacted. Before the concrete 4 develops the strength, the hook portion of the anchor member 17 is inserted into the hole of the anchor hooking plate 10 on the downstream side and the hole previously formed in the second-stage belly-raising member 16 on the upstream side, The anchor member 17 is attached to the top end of the concrete 4 (or laid down) in a substantially horizontal direction. The second step of curing the second-stage concrete 4 until the concrete 4 develops strength and constructing the sabo dam 1 is completed.

【0036】前記第二の工程では、既に第一段目のコン
クリート4が強度を発現し一体化された各部材の強度と
剛性、及び二段目のコンクリート4に埋め込まれ一体化
されたアンカー材17の定着力、上流側における二段目
の鋼矢板5自身の剛性、隣り合う鋼矢板5、5相互の接
合力等、並びに下流側における柱材8及び間伐材6自身
の剛性がコンクリート4の打設圧に十分に耐え得る強度
を発揮しており、何の問題もない。
In the second step, the strength and rigidity of each member in which the first-stage concrete 4 has already developed and integrated, and the anchor material embedded and integrated in the second-stage concrete 4 17, the rigidity of the second-stage steel sheet pile 5 itself on the upstream side, the joining strength between the adjacent steel sheet piles 5, 5, and the rigidity of the column material 8 and the thinned material 6 itself on the downstream side It has sufficient strength to withstand the casting pressure and has no problem.

【0037】更に、砂防堰堤1を構築する第三の工程が
完了した状態を、図11に示している。
FIG. 11 shows a state in which the third step of constructing the sabo dam 1 has been completed.

【0038】上流側の外壁材3において、図示は省略し
たが、一段目の背が高い鋼矢板5の上方にモジュール長
さの鋼矢板5を接合して立て、前記二段目の鋼矢板5の
上部を三段目の腹起こし材16とボルト12で接合す
る。
In the upstream outer wall material 3, although not shown, a steel sheet pile 5 having a module length is joined and erected above the tall steel sheet pile 5 in the first stage, and the steel sheet pile 5 in the second stage is set up. Is joined with the third-stage belly-raising material 16 and the bolt 12.

【0039】下流側の外壁材3において、一段目の柱材
8の上方に二段目の柱材8を継ぎ足す。その場合、前記
二段目の柱材8の下端部に設けた支持プレート9に二段
目の腹起こし材16を設置する。具体的には、図12
(A)、(B)に示すように、前記アンカー引掛用プレ
ート10の水平部と支持プレート9の水平部と腹起こし
材16とを共通のボルト12で接合する。
In the outer wall material 3 on the downstream side, a second column member 8 is added above the first column member 8. In this case, the second-stage upset member 16 is installed on the support plate 9 provided at the lower end of the second-stage column member 8. Specifically, FIG.
As shown in (A) and (B), the horizontal part of the anchor hooking plate 10, the horizontal part of the support plate 9, and the belly material 16 are joined by a common bolt 12.

【0040】そして、前記二段目の背が低い鋼矢板5と
ほぼ等しい高さまで略水平に間伐材6を積み重ね、前記
二段目の背が低い鋼矢板5とほぼ等しい高さ、即ち、二
段目の柱材8の中間部に設けたアンカー引掛用プレート
10の水平部に三段目の腹起こし材16をボルト12で
接合する。
Then, the thinned wood 6 is stacked substantially horizontally to a height almost equal to the height of the second-stage steel sheet pile 5, and the height of the second-stage short steel sheet pile 5 is almost equal to that of the second-stage short steel sheet pile 5. The third-stage belly-raising member 16 is joined to the horizontal portion of the anchor hooking plate 10 provided at the intermediate portion of the column member 8 with the bolt 12.

【0041】その後、上流側の二段目の背が低い鋼矢板
5の上端部近傍まで第三段目のコンクリート4を打設
し、第二の工程と略同様に、前記打設コンクリート4の
転圧、アンカー材17の取付け、及び打設コンクリート
4の養生を行い、砂防堰堤1を構築する第三の工程が完
了する。
Thereafter, the third-stage concrete 4 is poured to the vicinity of the upper end of the second-stage short steel sheet pile 5 on the upstream side, and substantially the same as in the second step. Rolling, mounting of the anchor member 17 and curing of the cast concrete 4 are performed, and the third step of constructing the sabo dam 1 is completed.

【0042】前記第三の工程では、第二の工程と同じ
く、コンクリート4の打設圧に十分に耐え得る強度を発
揮し、何の問題もない。
In the third step, as in the second step, a strength sufficient to withstand the casting pressure of the concrete 4 is exhibited, and there is no problem.

【0043】以下、上流側の鋼矢板5を接合して立て、
腹起こし材16の取付けを行うと共に、下流側の柱材8
を継ぎ足し、間伐材6の積み重ね、及び腹起こし材16
の取付けを行い、コンクリート4を打設して転圧し、ア
ンカー材17の取付け、及び打設コンクリート4の養生
を行う工程を、当該砂防堰堤1の高さまで繰り返す。
Hereinafter, the steel sheet piles 5 on the upstream side are joined and erected,
Attach the bulging material 16 and the column material 8 on the downstream side.
Are added, the thinning material 6 is piled up, and
The steps of installing the concrete 4, casting and rolling the concrete 4, attaching the anchor material 17, and curing the cast concrete 4 are repeated up to the height of the sabo dam 1.

【0044】したがって、従来のように外壁材3の変形
を防止するために型枠構造に大きな剛性と強度を確保す
る工作を施す面倒がなく、部材点数を削減でき、組立作
業が容易で、作業効率を向上することができる。また、
部材点数の削減によりコストの削減も図れる。
Accordingly, there is no need to perform a work for securing a large rigidity and strength to the formwork structure in order to prevent the deformation of the outer wall material 3 as in the prior art, the number of members can be reduced, the assembling work is easy, and the work is easy. Efficiency can be improved. Also,
The cost can be reduced by reducing the number of members.

【0045】しかも前工程で打設され強度を発現したコ
ンクリート4を足場代わりにして、次工程の柱材8の設
置、間伐材6の積み重ね、及び鋼矢板5の組立てその他
を行うことができ、外壁材3の内外に別途足場を構築す
る必要がないから、組立作業の容易化に寄与する。
Moreover, the concrete 4 which has been cast in the previous process and has developed strength can be used as a scaffold, and the column 8 in the next process, the thinning material 6 can be stacked, the steel sheet pile 5 can be assembled, and so on. Since it is not necessary to separately construct a scaffold inside and outside the outer wall material 3, this contributes to facilitation of the assembling work.

【0046】また、下流側の外壁材3として、間伐材6
を用いることにより自然と調和し、景観性を高めること
ができる。
As the outer wall material 3 on the downstream side, a thinning material 6
By using, it can be in harmony with nature and enhance the landscape.

【0047】最後に、図13に拡大して示したように、
前記所定の高さまで達した鋼矢板5の頂部に堤冠材18
を挿入し砂防堰堤1を完成する(請求項6記載の発
明)。したがって、この砂防堰堤1を越流する流水や土
砂が直接外壁材3の頂部に衝突して傷つけることを防止
できる。
Finally, as shown enlarged in FIG.
At the top of the steel sheet pile 5 which has reached the predetermined height, an embankment material 18 is provided.
To complete the sabo dam 1 (the invention according to claim 6). Therefore, it is possible to prevent running water or earth and sand flowing over the sabo dam 1 from directly colliding with and damaging the top of the outer wall material 3.

【0048】上述のようにして構築される砂防堰堤1
は、モジュール長さの柱材8及び鋼矢板5に限らない
で、請求項3記載の発明に係る構築工法によっても、全
く同様に構築される。即ち、上流側の外壁材3の下端位
置を定める基礎梁7を基礎地盤2上に上向きの溝形断面
材として配置し、前記基礎梁7に、同基礎梁7と後記の
下流側の柱材8の支持プレート9とを連結するつなぎ材
11の一方の端部を接合し、前記基礎梁7の溝7a内へ
鋼矢板5の下端を挿入する。前記鋼矢板5を、内側から
サポート材15で支持された支柱14で支保させて、同
鋼矢板5に水平方向の腹起こし材16を接合する。
Sabo dam 1 constructed as described above
Is constructed not only by the column member 8 and the steel sheet pile 5 having the module length but also by the construction method according to the third aspect of the present invention. That is, a foundation beam 7 for determining the lower end position of the outer wall material 3 on the upstream side is arranged as an upward groove-shaped section material on the foundation ground 2, and the foundation beam 7 and the downstream column material described later are provided on the foundation beam 7. One end of the connecting member 11 connecting the supporting plate 9 to the supporting plate 9 is joined, and the lower end of the steel sheet pile 5 is inserted into the groove 7a of the foundation beam 7. The steel sheet pile 5 is supported by a support 14 supported by a support member 15 from the inside, and a horizontal bent member 16 is joined to the steel sheet pile 5.

【0049】前記つなぎ材11により基礎梁7と連結す
る支持プレート9を下端部に設け、上方へ間隔を開けて
複数のアンカー引掛用プレート10…を設けた、H型鋼
等の溝部8aを有する柱材8を、基礎地盤2上に間隔を
開けて配置し、その支持プレート9に、つなぎ材11の
他方の端部を接合し上流側の基礎梁7と連結する。間伐
材6の両端を、隣接する柱材8の溝部8aへ挿入し、上
流側の背が低い鋼矢板5の上端部近傍まで積み重ねる。
そして、前記アンカー引掛用プレート10に腹起こし材
16を接合する。
A column having a groove 8a made of H-shaped steel, provided with a support plate 9 connected to the foundation beam 7 at the lower end by the connecting member 11, and provided with a plurality of anchor hooking plates 10 spaced apart upward. The members 8 are arranged at intervals on the foundation ground 2, and the other end of the tether 11 is joined to the support plate 9 and connected to the upstream foundation beam 7. Both ends of the thinned wood 6 are inserted into the grooves 8a of the adjacent column members 8 and stacked up to near the upper end of the short steel sheet pile 5 on the upstream side.
Then, the belly material 16 is joined to the anchor hooking plate 10.

【0050】その後、前記の両外壁材3、3の内側へ、
各外壁材3、3が自立する高さまでコンクリート4を打
設し、打設したコンクリート4の上部を振動ローラー等
で転圧し、前記上流側の腹起こし材16、及び下流側の
アンカー引掛用プレート10又は腹起こし材16の少な
くとも一方にアンカー材17を取り付けて、打設したコ
ンクリート4が強度が発現するまで養生する。
Thereafter, the inside of both outer wall members 3, 3 is
Concrete 4 is cast to a height at which each of the outer wall materials 3 is self-supporting, and the upper portion of the cast concrete 4 is rolled by a vibrating roller or the like, and the upstream flaring material 16 and the downstream anchor catching plate are provided. Anchor material 17 is attached to at least one of 10 or belly material 16 and the cast concrete 4 is cured until the strength is developed.

【0051】以下、前記外壁材3、3の構築と、コンク
リート4の打設と転圧、及びアンカー材17の取付け、
並びにコンクリート4の養生を行う工程を、前記砂防堰
堤1の高さまで繰り返すことによって、請求項1に記載
したような砂防堰堤1を構築できる。なお、前記砂防堰
堤1のコンクリート4の骨材も、クラッシャーランが用
いられる(請求項2記載の発明)。
Hereinafter, the construction of the outer wall members 3 and 3, the placing and compaction of the concrete 4, the attachment of the anchor members 17,
By repeating the step of curing the concrete 4 up to the height of the sabo dam 1, the sabo dam 1 as described in claim 1 can be constructed. The crusher run is also used for the aggregate of the concrete 4 of the sabo dam 1 (the invention according to claim 2).

【0052】なお、上記実施形態では、外壁材3として
間伐材6及び鋼矢板5を用いているが、これに限らな
い。即ち、下流側の外壁材3は、間伐材6のように長尺
材であれば良く、鋼製部材でも良い。また、矩形の鋼製
部材でも同様に実施できる。更に、上流側の外壁材3
は、軽量鋼矢板あるいはライナープレートでも実施でき
る。
In the above embodiment, the thinning material 6 and the steel sheet pile 5 are used as the outer wall material 3, but the invention is not limited to this. That is, the outer wall material 3 on the downstream side may be a long material like the thinned wood 6 and may be a steel member. In addition, the present invention can be similarly applied to a rectangular steel member. Furthermore, the outer wall material 3 on the upstream side
Can also be implemented with lightweight steel sheet piles or liner plates.

【0053】また、上記実施形態では、土木構造物の用
途を砂防堰堤としているが、土留め擁壁としても好適に
実施することができる。
Further, in the above embodiment, the civil engineering structure is used as a sabo dam, but it can be suitably implemented as an earth retaining wall.

【0054】更に、上記実施形態では、柱材8のモジュ
ール長さを鋼矢板5のモジュール長さとほぼ等しくして
いるが、この限りではない。即ち、柱材8のモジュール
長さは自由に定められる。その場合、柱材8の高さに応
じて、上流側の鋼矢板5を接合して立て、腹起こし材1
6の取付けを行うと共に、間伐材6の積み重ね、及び腹
起こし材16の取付けを行い、コンクリート4を打設し
て転圧し、アンカー材17の取付け、及び打設コンクリ
ート4の養生を行う工程を繰り返した後、第二の工程を
行い一段目の柱材8の上端部近傍まで砂防堰堤1を構築
する。更に、次段の柱材8の継ぎ足し等を行う第三の工
程に移行する。そのため、柱材8を鋼矢板5の略1/2
モジュール長さを一単位として連続する長さに構成する
と、上流側の鋼矢板5の長さと整合性がとれ、構築作業
の容易化に寄与する。
Further, in the above embodiment, the module length of the column member 8 is made substantially equal to the module length of the steel sheet pile 5, but this is not restrictive. That is, the module length of the pillar 8 is freely determined. In that case, according to the height of the column member 8, the steel sheet pile 5 on the upstream side is joined and erected, and
6, the steps of stacking the thinned wood 6 and attaching the belly raising material 16, casting the concrete 4 and rolling, attaching the anchor material 17, and curing the cast concrete 4. After the repetition, the second step is performed to construct the sabo dam 1 up to near the upper end of the first column 8. Further, the process shifts to a third step of adding the column member 8 at the next stage. Therefore, the column member 8 is made to be approximately 略 of the steel sheet pile 5.
When the module length is configured as a continuous length as one unit, consistency with the length of the steel sheet pile 5 on the upstream side is obtained, which contributes to facilitation of construction work.

【0055】[0055]

【本発明の奏する効果】請求項1〜6に記載した発明に
係る鋼矢板及び間伐材等を用いた砂防堰堤等の土木構造
物及びその構築工法は、外壁材が自立し得る高さずつ複
数回に分けてコンクリートを打設するため、タイロッド
等の連結部材及び骨組み等を必要とせず、少ない部材点
数、少ない工数で砂防堰堤を構築することができ、コス
トの削減と作業効率の向上が可能である。
[Effects of the present invention] The civil engineering structure such as a sabo dam using the steel sheet pile and the thinned wood according to the inventions according to the first to sixth aspects and the construction method thereof have a plurality of heights at which the outer wall material can stand on its own. Since concrete is cast in different times, connecting members such as tie rods and frameworks are not required, and sabo dams can be constructed with fewer members and fewer man-hours, which can reduce costs and improve work efficiency. It is.

【0056】更に、上流側の外壁材において、外壁材
(特に一段目の鋼矢板)の下端に基礎梁を配置し、同鋼
矢板をサポート材により支保された支柱により支持して
いるので、外壁材の下端位置及び傾斜角度等を容易に定
めることができる。
Further, in the outer wall material on the upstream side, a foundation beam is arranged at the lower end of the outer wall material (particularly, the first-stage steel sheet pile), and the steel sheet pile is supported by the columns supported by the support material. The lower end position and the inclination angle of the material can be easily determined.

【0057】一方、下流側の外壁材においては、外壁
材、即ち間伐材等の両端を柱材の溝部に挿入するだけ
で、同外壁材の下端位置及び傾斜角度を容易に定めるこ
とができる。したがって、上流側及び下流側の外壁材の
定型化を容易に行うことができる。
On the other hand, in the outer wall material on the downstream side, the lower end position and the inclination angle of the outer wall material can be easily determined only by inserting both ends of the outer wall material, that is, the thinned material, into the groove of the pillar material. Therefore, the outer wall material on the upstream side and the downstream side can be easily standardized.

【0058】また、下流側の外壁材に間伐材等を用いる
ことにより自然と調和し、景観性を高めることができ
る。
Further, by using a thinned wood or the like as the outer wall material on the downstream side, it is possible to enhance the landscape in harmony with nature.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る鋼矢板及び間伐材等を用いた砂防
堰堤を示した立面図である。
FIG. 1 is an elevational view showing a sabo dam using a steel sheet pile, a thinned material and the like according to the present invention.

【図2】上流側の外壁材の構造を示した斜視図である。FIG. 2 is a perspective view showing a structure of an outer wall material on an upstream side.

【図3】砂防堰堤を下流側から見た正面図である。FIG. 3 is a front view of the sabo dam viewed from the downstream side.

【図4】鋼矢板及び間伐材等を用いた砂防堰堤等の土木
構造物の構築工法の第一の工程が完了した状態を示した
立面図である。
FIG. 4 is an elevation view showing a state where a first step of a construction method of a civil engineering structure such as a sabo dam using steel sheet pile and thinned wood has been completed.

【図5】一段目の鋼矢板の接合、腹起こし材の取付け、
コンクリートの打設、及びアンカー材を取り付けた工程
を示した正面図である。
FIG. 5: joining of the first-stage steel sheet piles, attachment of the material for raising the belly,
It is the front view which showed the process of placing concrete and attaching an anchor material.

【図6】Aは、アンカー引掛用プレート近傍を拡大して
示した平面図である。Bは、アンカー引掛用プレート近
傍を拡大して示した正面図である。
FIG. 6A is an enlarged plan view showing the vicinity of an anchor hooking plate. B is an enlarged front view showing the vicinity of the anchor hooking plate.

【図7】鋼矢板及び間伐材等を用いた砂防堰堤等の土木
構造物の構築工法の第二の工程が完了した状態を示した
立面図である。
FIG. 7 is an elevational view showing a state in which a second step of a construction method of a civil engineering structure such as a sabo dam using steel sheet pile and thinned wood has been completed.

【図8】二段目の鋼矢板の接合、腹起こし材の取付け、
コンクリートの打設、及びアンカー材を取り付けた工程
を示した正面図である。
FIG. 8 shows the joining of the second-stage steel sheet pile, the attachment of the belly-raising material,
It is the front view which showed the process of placing concrete and attaching an anchor material.

【図9】図8のA−A矢視断面図である。FIG. 9 is a sectional view taken along the line AA of FIG. 8;

【図10】図8のB−B矢視断面図である。FIG. 10 is a sectional view taken along the line BB of FIG. 8;

【図11】鋼矢板及び間伐材等を用いた砂防堰堤等の土
木構造物の構築工法の第三の工程が完了した状態を示し
た立面図である。
FIG. 11 is an elevation view showing a state in which a third step of a construction method of a civil engineering structure such as a sabo dam using steel sheet pile and thinned wood has been completed.

【図12】Aは、支持プレートとアンカー引掛用プレー
トとの接合部近傍を拡大して示した平面図である。B
は、支持プレートとアンカー引掛用プレートとの接合部
近傍を拡大して示した正面図である。
FIG. 12A is an enlarged plan view showing the vicinity of a joint between a support plate and an anchor hooking plate. B
FIG. 4 is an enlarged front view showing the vicinity of a joint between a support plate and an anchor hooking plate.

【図13】上流側の鋼矢板の頂部を示した拡大図であ
る。
FIG. 13 is an enlarged view showing the top of the steel sheet pile on the upstream side.

【符号の説明】[Explanation of symbols]

1 砂防堰堤 2 基礎地盤 3 外壁材 4 コンクリート 5 鋼矢板 6 間伐材 7 基礎梁 7a 溝 8 柱材 8a 溝部 9 支持プレート 10 アンカー引掛用プレート 11 つなぎ材 14 支柱 15 サポート材 16 腹起こし材 17 アンカー材 18 堤冠材 DESCRIPTION OF SYMBOLS 1 Sabo dam 2 Foundation ground 3 Exterior wall material 4 Concrete 5 Steel sheet pile 6 Thinned material 7 Foundation beam 7a Groove 8 Column material 8a Groove 9 Support plate 10 Anchor hooking plate 11 Connecting material 14 Prop 15 Support material 16 Flap material 17 Anchor material 18 Embankment material

───────────────────────────────────────────────────── フロントページの続き (72)発明者 堀 謙吾 神奈川県川崎市川崎区出来野3−2−405 (72)発明者 秋山 祥克 埼玉県川越市脇田町33−1 株式会社イン バックス内 (72)発明者 半田 博幸 埼玉県東松山市松風台3−28 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Kengo Hori 3-2-405 Takino, Kawasaki-ku, Kawasaki City, Kanagawa Prefecture Inventor Hiroyuki Handa 3-28 Shofudai, Higashimatsuyama-shi, Saitama

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】上流側の外壁材を鋼矢板で構成し、下流側
の外壁材を間伐材等で構成して、前記両外壁材をコンク
リート型枠として用い、その内側へコンクリートを打設
して構築された砂防堰堤等の土木構造物であって、 上流側の外壁材の下端位置を定める基礎梁が基礎地盤上
に上向きの溝形断面材として配置され、前記基礎梁に
は、同基礎梁と後記の下流側の柱材の支持プレートとを
連結するつなぎ材の一方の端部が接合されており、前記
基礎梁の溝内へ鋼矢板の下端を挿入してあり、前記鋼矢
板は、内側からサポート材で支持された支柱で支保され
ており、前記鋼矢板に水平方向の腹起こし材が接合さ
れ、その腹起こし材にアンカー材が取り付けられている
こと、 前記つなぎ材により基礎梁と連結される支持プレートが
下端部に設けられ、上方へ間隔を開けて複数のアンカー
引掛用プレートが設けられた、H型鋼等の溝部を有する
柱材が基礎地盤上に間隔を開けて配置され、前記支持プ
レートには、つなぎ材の他方の端部が接合されて上流側
の基礎梁と連結されており、下流側の外壁材である間伐
材等の両端が、隣接する柱材の溝部へ挿入され、柱材の
上端部近傍までほぼ水平に積み重ねられており、前記柱
材のアンカー引掛用プレートに腹起こし材が接合され、
前記アンカー引掛用プレート又は腹起こし材の少なくと
も一方にアンカー材が取り付けられていること、 前記の両外壁材の内側へコンクリートが打設されている
ことを特徴とする、鋼矢板及び間伐材等を用いた砂防堰
堤等の土木構造物。
An outer wall material on the upstream side is made of steel sheet pile, an outer wall material on the downstream side is made of thinned wood or the like, and both outer wall materials are used as a concrete formwork, and concrete is poured into the inside thereof. And a foundation beam that determines the lower end position of the outer wall material on the upstream side is arranged as an upward grooved section material on the foundation ground, and the foundation beam includes One end of a connecting member that connects the beam and a support plate of a downstream column member described later is joined, and a lower end of a steel sheet pile is inserted into a groove of the foundation beam, and the steel sheet pile is A supporting member supported by a support material from the inside, a horizontal flared material is joined to the steel sheet pile, and an anchor material is attached to the flared material, and a foundation beam is provided by the connecting material. A support plate connected to the lower end is provided. A column member having grooves, such as H-section steel, provided with a plurality of anchor hooking plates spaced apart upward is arranged on the foundation ground at intervals, and the other end of the linking material is provided on the support plate. Part is joined and connected to the upstream foundation beam, and both ends of the thinning material, etc., which are the outer wall material on the downstream side, are inserted into the groove of the adjacent column material, and almost horizontally until near the upper end of the column material Stacked, the belly material is joined to the anchor hooking plate of the column material,
An anchor material is attached to at least one of the anchor hooking plate and the bulging material, and concrete is cast inside the both outer wall materials. Civil engineering structures such as sabo dams used.
【請求項2】前記コンクリートの骨材がクラッシャーラ
ンであることを特徴とする、請求項1に記載した鋼矢板
及び間伐材等を用いた砂防堰堤等の土木構造物。
2. The civil engineering structure such as a sabo dam using the steel sheet pile and the thinned wood according to claim 1, wherein the concrete aggregate is a crusher run.
【請求項3】上流側の外壁材を鋼矢板で構成し、下流側
の外壁材を間伐材等で構成して、前記両外壁材をコンク
リート型枠として用い、その内側へコンクリートを打設
して砂防堰堤等の土木構造物を構築する工法であって、 上流側の外壁材の下端位置を定める基礎梁を基礎地盤上
に上向きの溝形断面材として配置し、前記基礎梁に、同
基礎梁と後記の下流側の柱材の支持プレートとを連結す
るつなぎ材の一方の端部を接合し、前記基礎梁の溝内へ
鋼矢板の下端を挿入する段階と、 前記鋼矢板を、内側からサポート材で支持された支柱で
支保し、前記鋼矢板に水平方向の腹起こし材を接合する
段階と、 前記つなぎ材により基礎梁と連結する支持プレートを下
端部に設け、上方へ間隔を開けて複数のアンカー引掛用
プレートを設けた、H型鋼等の溝部を有する柱材を、基
礎地盤上に間隔を開けて配置し、その支持プレートに、
つなぎ材の他方の端部を接合し上流側の基礎梁と連結す
る段階と、 下流側の外壁材である間伐材等の両端を、隣接する柱材
の溝部へ挿入し、上流側の背が低い鋼矢板の上端部近傍
まで積み重ねる段階と、 前記アンカー引掛用プレートに腹起こし材を接合する段
階と、 前記の両外壁材の内側へ、各外壁材が自立する高さまで
コンクリートを打設し、打設したコンクリートの上部を
振動ローラー等で転圧し、前記上流側の腹起こし材、及
び下流側のアンカー引掛用プレート又は腹起こし材の少
なくとも一方にアンカー材を取り付けて、打設したコン
クリートが強度を発現するまで養生する段階と、 前記外壁材の構築と、コンクリートの打設と転圧、及び
アンカー材の取付け、並びにコンクリートの養生を行う
工程を、前記土木構造物の高さまで繰り返す段階とから
成ることを特徴とする、鋼矢板及び間伐材等を用いた砂
防堰堤等の土木構造物の構築工法。
3. The outer wall material on the upstream side is made of steel sheet pile, the outer wall material on the downstream side is made of thinned wood or the like, and both outer wall materials are used as a concrete formwork, and concrete is poured into the inside thereof. A method of constructing a civil engineering structure such as a sabo dam by arranging a foundation beam that determines the lower end position of the outer wall material on the upstream side as a groove-shaped cross section material facing upward on the foundation ground, and Joining one end of a linking material connecting a beam and a support plate of a downstream column member described below, and inserting a lower end of a steel sheet pile into a groove of the foundation beam; A supporting plate supported by a support material from above, and joining a horizontal flared material to the steel sheet pile, and a support plate connected to a foundation beam by the connecting material is provided at a lower end portion, and an interval is provided upward. H-shaped steel, etc. with multiple anchor hooking plates The column member having a groove, spaced placed on foundation ground, to the support plate,
Joining the other end of the joining material and connecting it to the upstream foundation beam; inserting both ends of the thinning material, which is the outer wall material on the downstream side, into the groove of the adjacent column material, Stacking up to the vicinity of the upper end of the low steel sheet pile, joining the buckling material to the anchor hooking plate, and placing concrete inside the both outer wall materials to a height at which each outer wall material is self-supporting, The upper part of the cast concrete is rolled with a vibrating roller or the like, and an anchor material is attached to at least one of the upstream flaring material and the downstream anchor hooking plate or the flaring material, and the poured concrete has strength. Curing until the manifestation of, and constructing the outer wall material, placing and compacting concrete, and attaching anchor material, and curing the concrete, the process of curing the concrete up to the height of the civil engineering structure A method for constructing civil engineering structures such as sabo dams using steel sheet piles and thinned wood, etc., comprising repeating the steps.
【請求項4】上流側の外壁材をモジュール長さ及び略1
/2モジュール長さに加工した鋼矢板で構成し、下流側
の外壁材を間伐材等で構成して、前記両外壁材をコンク
リート型枠として用い、その内側へコンクリートを打設
して砂防堰堤等の土木構造物を構築する工法であって、 上流側の外壁材の下端位置を定める基礎梁を基礎地盤上
に上向きの溝形断面材として配置し、前記基礎梁に、同
基礎梁と後記の下流側の柱材の支持プレートとを連結す
るつなぎ材の一方の端部を接合する段階と、 前記基礎梁の上に、長手方向に間隔を開けて、支柱を一
定の内向き傾斜角度で立て、各支柱は内側からサポート
材により支持させる段階と、 前記支柱をガイドにしてその外側に、上記モジュール長
さ及び略1/2モジュール長さに加工した一段目の鋼矢
板をそれぞれ互い違いの配置に接合し、それぞれの下端
を前記基礎梁の溝内へ挿入することによって各鋼矢板の
継目を上下方向に段違いの千鳥状配置に形成し、前記一
段目の背が低い鋼矢板の基礎梁近傍に腹起こし材を取り
付ける段階と、 前記つなぎ材により基礎梁と連結する支持プレートを下
端部に設け、アンカー引掛用プレートを上流側の鋼矢板
とほぼ等しい高さに設け、モジュール長さに加工したH
型鋼等の溝部を有する一段目の柱材を、基礎地盤上に間
隔を開けて配置し、その支持プレートに、前記つなぎ材
の他方の端部を接合し、上流側の基礎梁と連結する段階
と、 下流側の外壁材である間伐材等の両端を、隣接する柱材
の溝部へそれぞれ挿入し、上流側の一段目の背が低い鋼
矢板とほぼ等しい高さまで略水平に積み重ね、前記高さ
の近傍に設けたアンカー引掛用プレートに腹起こし材を
取り付ける段階と、 上流側の一段目の背が低い鋼矢板の上端部近傍まで第一
段目のコンクリートを打設し、打設したコンクリートの
上部を振動ローラー等で転圧し、前記アンカー引掛用プ
レート又は腹起こし材の少なくとも一方にアンカー材を
水平方向に取り付けて前記打設コンクリートの天端へ置
き、同コンクリートが強度を発現するまで養生する段階
と、 上流側の一段目の背が低い鋼矢板の上方に前記モジュー
ル長さの鋼矢板を接合して立て、前記鋼矢板の中部に二
段目の腹起こし材をボルト接合する段階と、 下流側の外壁材である間伐材等を上流側の一段目の背が
高い鋼矢板とほぼ等しい高さまで略水平に積み重ね、前
記高さの近傍に設けたアンカー引掛用プレートに腹起こ
し材を取り付ける段階と、 上流側の一段目の背が高い鋼矢板の上端部近傍まで第二
段目のコンクリートを打設して転圧し、前記背が高い鋼
矢板とほぼ等しい高さに設けた下流側のアンカー引掛用
プレート及び上流側の二段目の腹起こし材にアンカー材
を水平方向に取り付けて前記打設コンクリートの天端へ
置き、同コンクリートが強度を発現するまで養生する段
階と、 以下、上流側の外壁材である鋼矢板を接合して立て、腹
起こし材の取付けを行うと共に、下流側の柱材を継ぎ足
し、間伐材等の積み重ね、及び腹起こし材の取付けを行
い、コンクリートを打設して転圧し、アンカー材の取付
け、及び打設コンクリートの養生を行う工程を、当該土
木構造物の高さまで繰り返す段階とから成ることを特徴
とする、鋼矢板及び間伐材等を用いた砂防堰堤等の土木
構造物の構築工法。
4. The outer wall material on the upstream side has a module length of about 1
A steel sheet pile processed to a length of / 2 module, the outer wall material on the downstream side is made of thinned wood, etc., and both outer wall materials are used as concrete formwork, and concrete is poured into the inside thereof to make a sabo dam. A method of constructing a civil engineering structure such as the above, wherein a foundation beam that determines the lower end position of the outer wall material on the upstream side is arranged on the foundation ground as a groove-shaped cross-section facing upward, and the foundation beam is referred to as the foundation beam later. Joining one end of a tie connecting the support plate of the downstream pillar to the base beam, at intervals in the longitudinal direction on the foundation beam, the pillar at a constant inward inclination angle Standing, supporting each pillar with a support material from the inside, and alternately disposing the first-stage steel sheet pile processed into the above module length and approximately モ ジ ュ ー ル module length on the outside using the pillar as a guide. Joined to each under Forming the seam of each steel sheet pile in a staggered arrangement with a step difference in the vertical direction by inserting the steel sheet pile into the groove of the foundation beam, and attaching a flared material near the foundation beam of the first-stage short steel sheet pile. A support plate connected to the foundation beam by the connecting member is provided at a lower end portion, and an anchor hooking plate is provided at substantially the same height as the steel sheet pile on the upstream side, and is processed into a module length.
A step of arranging first-stage column members having grooves, such as mold steel, on the foundation ground with a space therebetween, joining the other end of the linking material to the support plate, and connecting to the upstream-side foundation beam. Inserting both ends of the thinning material, etc., which is the outer wall material on the downstream side, into the grooves of the adjacent column members, respectively, and stacking them substantially horizontally to a height almost equal to the height of the first-stage short steel sheet pile on the upstream side, Attaching the buckling material to the anchor hooking plate provided in the vicinity of the sea, and placing the first-stage concrete near the upper end of the first-stage short steel sheet pile on the upstream side, and placing the concrete The upper part of the concrete is rolled with a vibrating roller or the like, and the anchor material is horizontally attached to at least one of the anchor hooking plate or the belly material and placed on the top of the cast concrete, and cured until the concrete develops strength. And joining the steel sheet pile of the module length above the shortest steel sheet pile of the first stage on the upstream side, and bolting the second-stage flared material to the center of the steel sheet pile. The thinning material or the like, which is the outer wall material on the downstream side, is stacked substantially horizontally to a height substantially equal to the height of the tall steel sheet pile of the first stage on the upstream side. Attachment stage, The second stage concrete is cast to near the upper end of the first stage tall steel sheet pile on the upstream side and compacted, and the downstream side provided at a height substantially equal to the tall steel sheet pile Anchor hooking plate and an anchor material is horizontally attached to the second-stage uplifting material on the upstream side and placed on the top of the cast concrete, and the concrete is cured until it develops strength. Steel sheet pile as the outer wall material on the upstream side Joining and standing, attaching the bulging material, adding the pillar material on the downstream side, stacking thinning materials, installing the bulging material, casting concrete, rolling and installing the anchor material And a step of curing the cast concrete to the height of the civil engineering structure, the method comprising the steps of: constructing a civil engineering structure such as a sabo dam using steel sheet pile and thinned wood.
【請求項5】前記コンクリートの骨材がクラッシャーラ
ンであることを特徴とする、請求項3又は4に記載した
鋼矢板及び間伐材等を用いた砂防堰堤等の土木構造物の
構築工法。
5. The construction method of a civil engineering structure such as a sabo dam using a steel sheet pile and a thinned wood material according to claim 3, wherein the concrete aggregate is a crusher run.
【請求項6】上流側の鋼矢板の頂部には、堤冠材を設け
ることを特徴とする、請求項3〜5のいずれか一に記載
した鋼矢板及び間伐材等を用いた砂防堰堤等の土木構造
物の構築工法。
6. A sabo dam using a steel sheet pile and a thinned wood material according to any one of claims 3 to 5, wherein a bank crown material is provided on the top of the steel sheet pile on the upstream side. Construction method of civil engineering structure.
JP2001043828A 2001-02-20 2001-02-20 Civil engineering structures such as sabo dams, etc. using long materials such as steel sheet piles and thinned wood, and construction methods Expired - Fee Related JP4421124B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001043828A JP4421124B2 (en) 2001-02-20 2001-02-20 Civil engineering structures such as sabo dams, etc. using long materials such as steel sheet piles and thinned wood, and construction methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001043828A JP4421124B2 (en) 2001-02-20 2001-02-20 Civil engineering structures such as sabo dams, etc. using long materials such as steel sheet piles and thinned wood, and construction methods

Publications (2)

Publication Number Publication Date
JP2002242164A true JP2002242164A (en) 2002-08-28
JP4421124B2 JP4421124B2 (en) 2010-02-24

Family

ID=18905933

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001043828A Expired - Fee Related JP4421124B2 (en) 2001-02-20 2001-02-20 Civil engineering structures such as sabo dams, etc. using long materials such as steel sheet piles and thinned wood, and construction methods

Country Status (1)

Country Link
JP (1) JP4421124B2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017106271A (en) * 2015-12-11 2017-06-15 Jfe建材株式会社 Construction method for sand control weir
CN107881985A (en) * 2017-11-28 2018-04-06 南京工业职业技术学院 A kind of river course groynes structure and its construction method
US20180305883A1 (en) * 2015-10-13 2018-10-25 John Jarvie Earth retention levee system
CN109295931A (en) * 2018-10-19 2019-02-01 沙洲职业工学院 A kind of antidetonation dam body hydro-structure and its method of construction
JP2021095802A (en) * 2019-12-19 2021-06-24 日鉄建材株式会社 Reinforcement method and reinforcement structure for existing steel sheet pile
CN113026672A (en) * 2020-12-31 2021-06-25 贵阳市水利水电勘测设计研究院有限公司 Construction method for construction engineering dam on karst landform
CN114687280A (en) * 2022-04-08 2022-07-01 中铁大桥局集团有限公司 Construction method and construction system of shoal foundation
CN115506387A (en) * 2022-10-19 2022-12-23 中国电建集团成都勘测设计研究院有限公司 A stagnant water cofferdam structure for rebuilding and enlarging pump floodgate engineering

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180305883A1 (en) * 2015-10-13 2018-10-25 John Jarvie Earth retention levee system
US10494783B2 (en) * 2015-10-13 2019-12-03 Armour Wall Group Pty Ltd Earth retention levee system
JP2017106271A (en) * 2015-12-11 2017-06-15 Jfe建材株式会社 Construction method for sand control weir
CN107881985A (en) * 2017-11-28 2018-04-06 南京工业职业技术学院 A kind of river course groynes structure and its construction method
CN109295931A (en) * 2018-10-19 2019-02-01 沙洲职业工学院 A kind of antidetonation dam body hydro-structure and its method of construction
JP2021095802A (en) * 2019-12-19 2021-06-24 日鉄建材株式会社 Reinforcement method and reinforcement structure for existing steel sheet pile
CN113026672A (en) * 2020-12-31 2021-06-25 贵阳市水利水电勘测设计研究院有限公司 Construction method for construction engineering dam on karst landform
CN114687280A (en) * 2022-04-08 2022-07-01 中铁大桥局集团有限公司 Construction method and construction system of shoal foundation
CN115506387A (en) * 2022-10-19 2022-12-23 中国电建集团成都勘测设计研究院有限公司 A stagnant water cofferdam structure for rebuilding and enlarging pump floodgate engineering

Also Published As

Publication number Publication date
JP4421124B2 (en) 2010-02-24

Similar Documents

Publication Publication Date Title
JP4328114B2 (en) Bridge construction method
CN103741604A (en) Fully prefabricated reinforced concrete bridge assembly structure and connecting method for same
CN105568854B (en) Shaped form fish-bellied type cast-in-situ steel reinforced concrete box girder construction method waterborne
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR20120096605A (en) Bracket support type downward construction system and method
CN203684108U (en) Fully-precast assembly type reinforced concrete bridge assembling structure
JP4343606B2 (en) Bridge construction method
JP2002242164A (en) Civil engineering structure such as sediment control weir and levee or the like using steel sheet pile and thinning member or the like and construction method therefor
CN104929047A (en) V-shaped pier outer support construction method
CN106758839A (en) A kind of strutting system and its installation method of the cast-in-place segmental construction of pier top
KR20090109678A (en) System and method for underground downward construction using concrete filled tube
JP2002242210A (en) Earth retaining wall and construction method therefor
JP4183389B2 (en) Construction method for civil engineering structures using steel sheet piles
CN116464060A (en) Construction method for accelerating high-span region structure at high-low span position of basement bottom plate
CN215052133U (en) Steel case roof beam is alternately construction supporting structure from top to bottom
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
JP2009046942A (en) Foundation block for retaining wall
JP4060135B2 (en) Civil engineering structure
CN113774925A (en) Construction method of horizontal internal support conversion structure of deep foundation pit fender post
JP2004300914A (en) Structure of bridge pier
JP4108456B2 (en) Civil engineering structure with planting part and its construction method
JP2004324340A (en) Steel shell for footing foundation, structure of bridge, construction method of bridge, and construction method of grade separation viaduct
JP2001311247A (en) Construction method for concrete structure
JP4060137B2 (en) Civil engineering structures and construction methods
JP3133598B2 (en) Construction method of small and medium-sized building with basement floor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080122

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090622

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090818

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091013

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091110

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091202

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121211

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4421124

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121211

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131211

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees