CN107877680A - A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine - Google Patents

A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine Download PDF

Info

Publication number
CN107877680A
CN107877680A CN201711302622.XA CN201711302622A CN107877680A CN 107877680 A CN107877680 A CN 107877680A CN 201711302622 A CN201711302622 A CN 201711302622A CN 107877680 A CN107877680 A CN 107877680A
Authority
CN
China
Prior art keywords
dabbing
fluting
plate
frame
wet seam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201711302622.XA
Other languages
Chinese (zh)
Inventor
吴秋敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711302622.XA priority Critical patent/CN107877680A/en
Publication of CN107877680A publication Critical patent/CN107877680A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/08Apparatus or processes for treating or working the shaped or preshaped articles for reshaping the surface, e.g. smoothing, roughening, corrugating, making screw-threads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28DWORKING STONE OR STONE-LIKE MATERIALS
    • B28D1/00Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor
    • B28D1/22Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by cutting, e.g. incising
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Abstract

The present invention relates to a kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine, including dabbing fluting frame, the upper end of dabbing fluting frame is symmetrically arranged with dabbing fixed mechanism, dabbing travel mechanism is provided with dabbing fluting frame, dabbing grooving mechanism is provided with dabbing travel mechanism, the dabbing grooving mechanism includes the dabbing mobile rack being engaged on by gear transmission mode in dabbing travel mechanism, dabbing mobile rack is arranged on dabbing movable plate, and dabbing positioning side chain is provided with dabbing movable plate.The present invention can solve to need manually to be constructed by existing dabbing equipment present in existing wet seam dabbing grooving process, it is unstable that manual control dabbing equipment carries out dabbing processing, complicated connecting sewing position needs to carry out repeatedly dabbing, manual control dabbing equipment handles the problem such as not comprehensive, it is possible to achieve the function of the wet intelligent dabbing fluting of seam construction.

Description

A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine
Technical field
The present invention relates to the building wet seam technical field of construction of prestressed concrete beam body, specifically a kind of wet seam Can intelligent dabbing fluting building prestressed concrete construction machine.
Background technology
Wet seam, refer to building prestressed concrete beam body precast block, cantilever, which is abandoned, dresses up large-span continuous beam, is adopted between beam body Beam block is linked to be overall wet seam with cast-in-place concrete.Need to carry out at dabbing connecting sewing position in wet seam work progress Reason, dabbing processing are the important steps in wet seam work progress, and nowadays in the market dabbing equipment is more rich and varied, alleviates The pressure of wet seam dabbing construction, debris during work high above the ground during dabbing can directly be fallen, but existing wet seam dabbing Need manually to be constructed by existing dabbing equipment in grooving process, carrying out the wet seam dabbing construction of different size needs to select The regulation instrument of adaptation is selected, the progress dabbing processing of manual control dabbing equipment is unstable, and complicated connecting sewing position needs to carry out Repeatedly dabbing, the processing of manual control dabbing equipment is not comprehensive, is needed during dabbing in order to ensure wet seam construction quality Need that specified location slot processing, it is necessary to be manually processed using grooving tool, complex operation.
The content of the invention
In order to solve the above problems, the invention provides a kind of wet seam can the building prestressing force of intelligent dabbing fluting mix Native construction machine is coagulated, can solve to need manually by existing dabbing equipment to enter present in existing wet seam dabbing grooving process Row construction, carrying out the wet seam dabbing construction of different size is needed to select the regulation instrument adapted to, and manual control dabbing equipment is carried out Dabbing processing is unstable, and complicated connecting sewing position needs to carry out repeatedly dabbing, and the processing of manual control dabbing equipment is not complete Face, need during dabbing in order to ensure wet seam construction quality needs slot processing, it is necessary to manually make to specified location It is processed with grooving tool, the problem such as complex operation, it is possible to achieve the function of the wet intelligent dabbing fluting of seam construction, Without manual operation, and there is the advantages that labor intensity is small, and operating efficiency is high.
To achieve these goals, the present invention is realized using following technical scheme:A kind of wet seam can intelligent dabbing The building prestressed concrete construction machine of fluting, including dabbing fluting frame, the upper end of dabbing fluting frame are symmetrically arranged with dabbing and consolidated Determine mechanism, be provided with dabbing travel mechanism in dabbing fluting frame, dabbing grooving mechanism be provided with dabbing travel mechanism, dabbing is solid Determine mechanism, dabbing travel mechanism is used in conjunction with each other the work for completing the intelligent dabbing fluting of wet seam construction with dabbing grooving mechanism Skill, the regulation that dabbing fixed mechanism can be adapted to during construction according to the width between connecting sewing, it is ensured that wet The carry out operation that dabbing grooving mechanism can be stablized during seam dabbing is constructed, in order to adjust the effect of wet seam dabbing construction Fruit, dabbing travel mechanism can drive dabbing grooving mechanism to carry out working in reciprocating mode in specified working region, wet so as to improve The effect of seam construction dabbing fluting, without manually carrying out construction processing by existing dabbing equipment, can construct caused Dust damages to staff's body, in the absence of potential safety hazard, reduces the labor intensity of staff, improves work Efficiency.
The dabbing that the dabbing grooving mechanism includes being engaged on by gear transmission mode in dabbing travel mechanism moves tooth Bar, dabbing mobile rack are arranged on dabbing movable plate, and dabbing positioning side chain, dabbing movable plate peace are provided with dabbing movable plate On two blocks of dabbing feeding plates, two blocks of dabbing feeding plates are symmetrically positioned in the front and rear sides of dabbing fluting frame, and dabbing feeding plate leads to Cross sliding matching mode to be connected on dabbing fluting frame, dabbing fluting side chain, two pieces of chisels are installed in the side wall of dabbing feeding plate Hair feeding plate serves support, the effect of auxiliary and guiding during work to dabbing movable plate, on dabbing movable plate Dabbing mobile rack drives dabbing to feed plate and moved left and right by gear-driven mode, and dabbing fluting side chain enters in dabbing To reciprocal working process is carried out in the presence of plate, so as to improve the efficiency of wet seam dabbing processing.
As a preferred technical solution of the present invention, the dabbing fixed mechanism includes being arranged on dabbing fluting frame Dabbing location-plate, dabbing telescopic cylinder is installed in the side wall of dabbing location-plate, the top of dabbing telescopic cylinder is pacified by flange On dabbing expansion plate, dabbing fixed plate is installed on the outside of dabbing fluting frame, it is spacing to be provided with dabbing in dabbing fixed plate Hole, dabbing limited post is provided with the side wall of dabbing expansion plate, dabbing limited post is located in dabbing spacing hole, dabbing limited post Diameter is less than the diameter of dabbing spacing hole, and dabbing limited post is arranged on dabbing working plate, on the outer wall of dabbing working plate in the past It is provided with dabbing locating dowel at equal intervals backward, dabbing locating dowel is cone-shaped structure, according to the condition of construction of wet seam, is passed through Dabbing telescopic cylinder drives the dabbing expansion plate on dabbing limited post to carry out telescopic adjustment, and dabbing spacing hole rises to dabbing limited post The spacing effect with support, the company of being fixed on that the dabbing locating dowel on dabbing expansion plate can be stable during work are arrived On the inwall of seam, without manual operation, the labor intensity of staff is reduced, improves the stability of work.
As a preferred technical solution of the present invention, the dabbing travel mechanism includes being arranged on dabbing fluting frame Two pieces of dabbings move riser, and dabbing movement tooth is provided with equal intervals from left to right by bearing between two pieces of dabbing movement risers Wheel, the front end of dabbing carrier wheel are provided with dabbing sprocket wheel, are connected between two neighboring dabbing sprocket wheel by a linkage, position It is connected in the dabbing carrier wheel of dabbing fluting frame right-hand member by shaft coupling with the output of dabbing mobile motor, dabbing mobile motor Dabbing is arranged on by motor cabinet to move on riser, is opened on two neighboring dabbing carrier wheel by gear transmission mode and dabbing Groove mechanism is connected, and drives dabbing carrier wheel to be rotated by dabbing mobile motor, process of the dabbing carrier wheel in rotation Middle drive dabbing grooving mechanism is moved left and right, so as to ensure that the effect of wet seam dabbing construction without manual operation, reduces The labor intensity of staff, improve the efficiency of work.
As a preferred technical solution of the present invention, the dabbing positioning side chain includes being arranged on dabbing movable plate Dabbing positioning cylinder, the top of dabbing positioning cylinder are arranged in dabbing fixed column by flange, from left past on dabbing fluting frame Right to be provided with dabbing positioning pipe at equal intervals, dabbing positioning pipe cooperates with dabbing fixed column and moved, and in dabbing positioning pipe The radius that the radius of wall is more than dabbing fixed column drives dabbing fixed column and dabbing positioning pipe phase interworking by dabbing positioning cylinder Resultant motion carries out position to dabbing movable plate and fixed, it is ensured that complicated wet seam dabbing construction location can repeat dabbing and open Groove processing, so as to improve the effect of wet seam dabbing construction.
As a preferred technical solution of the present invention, the dabbing fluting side chain includes being arranged on dabbing feeding plate side wall On fluting telescopic cylinder, the top of telescopic cylinder of slotting is arranged on fluting dabbing frame by flange, and fluting dabbing frame is U-shaped Structure, conversion motor is provided with by motor cabinet on dabbing frame of slotting, passes through shaft coupling and conversion on the output shaft of conversion motor Roller is connected, and the lower end of conversion roller is arranged on fluting dabbing frame by bearing, and it is flexible that two conversions are provided with the outside of conversion roller Bar, the top of two conversion expansion links are arranged on dabbing locating rack, are provided with the inwall of dabbing locating rack by motor cabinet Dabbing vibrating motor, automatic dabbing machine is provided with equal intervals on the outer wall of dabbing locating rack, be provided with and turn on the inside of conversion roller Telescopic cylinder is changed, the top for changing telescopic cylinder is arranged on fluting posting by flange, is set in the side wall for posting of slotting Lifting carriage groove is equipped with, fluting lifting motor is provided with by motor cabinet on posting of slotting, the output shaft for lifting motor of slotting It is arranged on by bearing on fluting posting, the output shaft for lifting motor of slotting passes through the upper end of shaft coupling and elevating screw of slotting It is connected, the lower end for elevating screw of slotting is installed on fluting posting by bearing, and fluting lifting is provided with elevating screw of slotting Block, fluting elevator are connected with fluting posting by sliding matching mode, are provided with fluting connecting plate on elevator of slotting, open Groove connecting plate is arranged on fluting sliding panel, and fluting electric rotating machine, fluting rotation are provided with by motor cabinet on sliding panel of slotting Fluting swivel plate is installed on the output shaft of motor, electric groover is installed on swivel plate of slotting, according to specific construction feelings Wet joint construction method corresponding to condition selection drives fluting dabbing frame, it is necessary to when carrying out dabbing processing by telescopic cylinder of slotting The position specified is moved to, automatic dabbing machine is moved on the outer wall of connecting sewing, automatic dabbing machine is in two conversion expansion links Fast and effectively dabbing processing is carried out under the auxiliary to cooperate with dabbing vibrating motor, it is necessary to when carrying out fluting processing, to pass through Conversion motor driving electric groover moves to operating position, and conversion telescopic cylinder control electric groover carries out telescopic adjustment, Fluting electric rotating machine can adjust the fluting direction of electric groover at work, and fluting lifting motor drives fluting elevating screw Rotated, fluting elevating screw driving electric groover carries out elevating movement, it is ensured that electric groover can enter at work Row automation angular adjustment, without manual operation, it is ensured that the effect of wet seam dabbing construction, the work for reducing staff are strong Degree, improve the efficiency of work.
During work, the present invention is placed on existing mobile device first, and existing mobile device drives the present invention mobile To the operating position specified, dabbing fixed mechanism is started working, and according to the condition of construction of wet seam, passes through dabbing telescopic cylinder band Dabbing expansion plate on dynamic dabbing limited post carries out telescopic adjustment, and dabbing spacing hole serves spacing with supporting to dabbing limited post Effect, what the dabbing locating dowel on dabbing expansion plate can be stable during work is fixed on the inwall of connecting sewing, Dabbing travel mechanism drives dabbing carrier wheel to be rotated by dabbing mobile motor, process of the dabbing carrier wheel in rotation Middle drive dabbing grooving mechanism is moved left and right, and dabbing positions side chain and drives dabbing fixed column and chisel by dabbing positioning cylinder Hair positioning pipe cooperates to move and dabbing movable plate progress position is fixed, it is ensured that complicated wet seam dabbing construction location can Repeat dabbing fluting to process, two pieces of dabbings on dabbing grooving mechanism feed plate during work to dabbing movable plate Support, auxiliary and the effect being oriented to, the dabbing mobile rack on dabbing movable plate is served to drive by gear-driven mode Dabbing feeding plate is moved left and right, and dabbing fluting side chain carries out reciprocal working process in the presence of dabbing feeds plate, so as to Improve the efficiency of wet seam dabbing processing, dabbing fluting side chain wet seam construction party according to corresponding to the selection of specific condition of construction Method drives fluting dabbing frame to move to the position specified, makes to dig automatically, it is necessary to when carrying out dabbing processing by telescopic cylinder of slotting Hair machine is moved on the outer wall of connecting sewing, and automatic dabbing machine cooperates with dabbing vibrating motor auxiliary in two conversion expansion links Helping lower progress, fast and effectively dabbing processing, it is necessary to when carrying out fluting processing, is moved by conversion motor driving electric groover To operating position, conversion telescopic cylinder control electric groover carries out telescopic adjustment, and fluting electric rotating machine can be adjusted at work The fluting direction of section electric groover, fluting lifting motor drive fluting elevating screw to be rotated, and fluting elevating screw drives Electric groover carries out elevating movement, it is ensured that electric groover can carry out automation angular adjustment at work, realize wet The function of the intelligent dabbing fluting of seam construction.
The beneficial effects of the invention are as follows:
1st, the present invention can solve to need manually by existing dabbing present in existing wet seam dabbing grooving process Equipment is constructed, and carrying out the wet seam dabbing construction of different size is needed to select the regulation instrument adapted to, and manual control dabbing is set Standby to carry out that dabbing processing is unstable, complicated connecting sewing position needs to carry out repeatedly dabbing, at manual control dabbing equipment Reason it is not comprehensive, needed during dabbing in order to ensure wet seam construction quality need to specified location carry out slot processing, it is necessary to Manually it is processed using grooving tool, the problem such as complex operation, it is possible to achieve the wet intelligent dabbing fluting of seam construction Function, without manual operation, and, operating efficiency high the advantages that small with labor intensity;
2nd, the present invention devises dabbing fixed mechanism, dabbing travel mechanism and dabbing grooving mechanism, and dabbing fixed mechanism exists The regulation that can be adapted to during construction according to the width between connecting sewing, it is ensured that in the process of wet seam dabbing construction The carry out operation that middle dabbing grooving mechanism can be stablized, in order to adjust the effect of wet seam dabbing construction, dabbing travel mechanism exists Dabbing grooving mechanism can be driven to carry out working in reciprocating mode in the working region specified, so as to improve wet seam construction dabbing fluting Effect, without manually carrying out construction processing by existing dabbing equipment, the caused dust that can construct is to staff's body Damage, in the absence of potential safety hazard, reduce the labor intensity of staff, improve the efficiency of work.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the knot that dabbing of the present invention is slotted between frame, dabbing travel mechanism, dabbing fluting side chain and dabbing positioning side chain Structure schematic diagram.
Embodiment
In order that the technical means, the inventive features, the objects and the advantages of the present invention are easy to understand, tie below Conjunction is specifically illustrating, and the present invention is expanded on further.
As shown in Figure 1 to Figure 2, a kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine, bag Dabbing fluting frame 41 is included, the upper end of dabbing fluting frame 41 is symmetrically arranged with dabbing fixed mechanism 42, set in dabbing fluting frame 41 There is dabbing travel mechanism 43, dabbing grooving mechanism 44, dabbing fixed mechanism 42, dabbing movement are provided with dabbing travel mechanism 43 Mechanism 43 is used in conjunction with each other the technique for completing the intelligent dabbing fluting of wet seam construction with dabbing grooving mechanism 44, and dabbing is fixed The regulation that mechanism 42 can be adapted to during construction according to the width between connecting sewing, it is ensured that applied in wet seam dabbing The carry out operation that dabbing grooving mechanism 44 can be stablized during work, in order to adjust the effect of wet seam dabbing construction, dabbing Travel mechanism 43 can drive dabbing grooving mechanism 44 to carry out working in reciprocating mode in specified working region, so as to improve wet seam The effect of dabbing of constructing fluting, without manually carrying out construction processing by existing dabbing equipment, can construct caused dust Staff's body is damaged, in the absence of potential safety hazard, the labor intensity of staff is reduced, improves the effect of work Rate.
The dabbing that the dabbing grooving mechanism 44 includes being engaged on by gear transmission mode in dabbing travel mechanism 43 is moved Carry-over bar 441, dabbing mobile rack 441 are arranged on dabbing movable plate 442, and dabbing positioning is provided with dabbing movable plate 442 Side chain 46, dabbing movable plate 442 are arranged on two pieces of dabbings and fed on plate 443, and two blocks of dabbing feeding plates 443 are symmetrically positioned in dabbing and opened The front and rear sides of truss 41, dabbing feed plate 443 and are connected to by sliding matching mode on dabbing fluting frame 41, dabbing feeding plate Dabbing fluting side chain 45 is installed, two blocks of dabbing feeding plates rise during work to dabbing movable plate 442 in 443 side wall Arrive support, auxiliary and the effect being oriented to, the dabbing mobile rack 441 on dabbing movable plate 442 and pass through gear-driven mode Dabbing feeding plate 443 is driven to be moved left and right, dabbing fluting side chain 45 carries out past be added with the presence of dabbing feeds plate 443 Work processing, so as to improve the efficiency of wet seam dabbing processing.
The dabbing fixed mechanism 42 includes the dabbing location-plate 421 being arranged on dabbing fluting frame 41, dabbing location-plate Dabbing telescopic cylinder 422 is installed, the top of dabbing telescopic cylinder 422 is stretched by flange installed in dabbing in 421 side wall On plate 423, the outside of dabbing fluting frame 41 is provided with dabbing fixed plate 427, and it is spacing to be provided with dabbing in dabbing fixed plate 427 Hole, dabbing limited post 424 is provided with the side wall of dabbing expansion plate 423, dabbing limited post 424 is located in dabbing spacing hole, chisel The diameter of hair limited post 424 is less than the diameter of dabbing spacing hole, and dabbing limited post 424 is arranged on dabbing working plate 425, dabbing It is provided with dabbing locating dowel 426 on the outer wall of working plate 425 at equal intervals from front to back, dabbing locating dowel 426 is coniform knot Structure, according to the condition of construction of wet seam, the dabbing expansion plate 423 on dabbing limited post 424 is driven by dabbing telescopic cylinder 422 Telescopic adjustment is carried out, dabbing spacing hole serves the spacing effect with support to dabbing limited post 424, on dabbing expansion plate 423 Dabbing locating dowel 426 can be stable during work be fixed on the inwall of connecting sewing, without manual operation, reduce The labor intensity of staff, improve the stability of work.
Two pieces of dabbings movement riser 431 that the dabbing travel mechanism 43 slots on frame 41 including being arranged on dabbing, two pieces Dabbing carrier wheel 432, dabbing carrier wheel are provided with by bearing at equal intervals from left to right between dabbing movement riser 431 432 front end is provided with dabbing sprocket wheel 433, is connected between two neighboring dabbing sprocket wheel 433 by a linkage 434, is located at The dabbing carrier wheel 432 of the dabbing fluting right-hand member of frame 41 is connected by shaft coupling with the output of dabbing mobile motor 435, and dabbing is moved Dynamic motor 435 is arranged on dabbing by motor cabinet and moved on riser 431, passes through gear on two neighboring dabbing carrier wheel 432 The kind of drive is connected with dabbing grooving mechanism 44, drives dabbing carrier wheel 432 to be rotated by dabbing mobile motor 435, Dabbing carrier wheel 432 drives dabbing grooving mechanism 44 to be moved left and right during rotation, so as to ensure wet seam chisel The effect of hair construction reduces the labor intensity of staff without manual operation, improves the efficiency of work.
The dabbing positioning side chain 46 includes the dabbing positioning cylinder 461 being arranged on dabbing movable plate 442, dabbing positioning The top of cylinder 461 is arranged in dabbing fixed column 462 by flange, is set at equal intervals from left to right on dabbing fluting frame 41 There is dabbing positioning pipe 463, dabbing positioning pipe 463 cooperates with dabbing fixed column 462 and moved, and the inwall of dabbing positioning pipe 463 Radius be more than the radius of dabbing fixed column 462 and pass through dabbing positioning cylinder 461 and drive dabbing fixed column 462 and dabbing positioning pipe 463 mutual cooperation motions carry out position to dabbing movable plate 442 and fixed, it is ensured that complicated wet seam dabbing construction location can weigh Dabbing fluting processing is carried out again, so as to improve the effect of wet seam dabbing construction.
The dabbing fluting side chain 45 includes the fluting telescopic cylinder 451 being arranged in the dabbing feeding side wall of plate 443, fluting The top of telescopic cylinder 451 is arranged on fluting dabbing frame 452 by flange, 452 U-shaped structure of fluting dabbing frame, grooving chisel Conversion motor 453 is provided with by motor cabinet on hair frame 452, passes through shaft coupling and conversion roller on the output shaft of conversion motor 453 454 are connected, and the lower end of conversion roller 454 is arranged on fluting dabbing frame 452 by bearing, and the outside of conversion roller 454 is provided with two Individual conversion expansion link 455, the top of two conversion expansion links 455 are arranged on dabbing locating rack 456, dabbing locating rack 456 Dabbing vibrating motor 457 is provided with by motor cabinet on inwall, is provided with equal intervals on the outer wall of dabbing locating rack 456 automatic Dabbing machine 458, the inner side of conversion roller 454 are provided with conversion telescopic cylinder 459, and the top of conversion telescopic cylinder 459 passes through flange On fluting posting 4510, lifting carriage groove is provided with the side wall for posting 4510 of slotting, posting 4510 of slotting Upper to be provided with fluting lifting motor 4511 by motor cabinet, the output shaft for lifting motor 4511 of slotting is arranged on fluting by bearing On posting 4510, the output shaft for lifting motor 4511 of slotting is connected by shaft coupling with the upper end for elevating screw 4512 of slotting, The lower end of fluting elevating screw 4512 is installed on fluting posting 4510 by bearing, is provided with out on elevating screw 4512 of slotting Groove elevator 4513, fluting elevator 4513 are connected by sliding matching mode with fluting posting 4510, elevator of slotting Fluting connecting plate 4514 is installed, fluting connecting plate 4514 is arranged on fluting sliding panel 4515, sliding panel of slotting on 4513 Fluting electric rotating machine 4516 is provided with by motor cabinet on 4515, fluting rotation is installed on the output shaft for electric rotating machine 4516 of slotting Flap 4517, slot swivel plate 4517 on electric groover 4518 is installed, according to specific condition of construction selection corresponding to it is wet Joint construction method drives fluting dabbing frame 452 to move to finger, it is necessary to when carrying out dabbing processing by telescopic cylinder 451 of slotting Fixed position, automatic dabbing machine 458 is set to move on the outer wall of connecting sewing, automatic dabbing machine 458 is in two conversion expansion links 455 Fast and effectively dabbing processing is carried out under the auxiliary to cooperate with dabbing vibrating motor 457, it is necessary to when carrying out fluting processing, to lead to Cross the driving electric groover 4518 of conversion motor 453 and move to operating position, conversion telescopic cylinder 459 controls electric groover 4518 carry out telescopic adjustment, and fluting electric rotating machine 4516 can adjust the fluting direction of electric groover 4518, open at work Groove lifting motor 4511 drives fluting elevating screw 4512 to be rotated, the driving electric groover 4518 of elevating screw 4512 of slotting Carry out elevating movement, it is ensured that electric groover 4518 can carry out automation angular adjustment at work, without manual operation, really The effect of moisturizing seam dabbing construction, the labor intensity of staff is reduced, improve the efficiency of work.
During work, the present invention is placed on existing mobile device first, and existing mobile device drives the present invention mobile To the operating position specified, dabbing fixed mechanism 42 is started working, and according to the condition of construction of wet seam, passes through dabbing telescopic cylinder 422 drive the dabbing expansion plate 423 on dabbing limited post 424 to carry out telescopic adjustment, and dabbing spacing hole rises to dabbing limited post 424 The spacing effect with support is arrived, what the dabbing locating dowel 426 on dabbing expansion plate 423 can be stable during work consolidates It is scheduled on the inwall of connecting sewing, dabbing travel mechanism 43 drives dabbing carrier wheel 432 to be revolved by dabbing mobile motor 435 Turn, dabbing carrier wheel 432 drives dabbing grooving mechanism 44 to be moved left and right during rotation, dabbing positioning side chain 46 Dabbing fixed column 462 is driven to cooperate motion to dabbing movable plate with dabbing positioning pipe 463 by dabbing positioning cylinder 461 442 progress positions are fixed, it is ensured that complicated wet seam dabbing construction location can repeat dabbing fluting processing, dabbing fluting Two pieces of dabbings feeding plate in mechanism 44 serves support, auxiliary and guiding during work to dabbing movable plate 442 Act on, the dabbing mobile rack 441 on dabbing movable plate 442 drives dabbing to feed plate 443 and carried out by gear-driven mode Move left and right, dabbing fluting side chain 45 carries out reciprocal working process in the presence of dabbing feeds plate 443, so as to improve wet seam Dabbing processing efficiency, dabbing slot side chain 45 according to specific condition of construction selection corresponding to wet joint construction method, it is necessary to When carrying out dabbing processing, drive fluting dabbing frame 452 to move to the position specified by telescopic cylinder 451 of slotting, make to dig automatically Hair machine 458 is moved on the outer wall of connecting sewing, and automatic dabbing machine 458 is in two conversion expansion links 455 and dabbing vibrating motor 457 Fast and effectively dabbing processing is carried out under the auxiliary of mutual cooperation, it is necessary to when carrying out fluting processing, to drive by conversion motor 453 Electric groover 4518 moves to operating position, and conversion telescopic cylinder 459 controls electric groover 4518 to carry out telescopic adjustment, opened Groove electric rotating machine 4516 can adjust the fluting direction of electric groover 4518 at work, and fluting lifting motor 4511, which drives, to be opened Groove elevating screw 4512 is rotated, and fluting elevating screw 4512 driving electric groover 4518 carries out elevating movement, it is ensured that electricity Dynamic groover 4518 can carry out automation angular adjustment at work, realize the work(of the intelligent dabbing fluting of wet seam construction Can, solve needs manually to be constructed by existing dabbing equipment present in existing wet seam dabbing grooving process, enters The wet seam dabbing construction of row different size needs to select the regulation instrument adapted to, and manual control dabbing equipment carries out dabbing processing not Stable, complicated connecting sewing position needs to carry out repeatedly dabbing, and manual control dabbing equipment handles not comprehensive, dabbing process Middle needs need slot processing, it is necessary to manually using grooving tool enter to specified location in order to ensure wet seam construction quality The problems such as row working process, complex operation, have reached purpose.
The basic principles, principal features and advantages of the present invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, and the description in above-described embodiment and specification simply illustrates the present invention Principle, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, and these change and changed Enter all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its equivalent Define.

Claims (6)

1. a kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine, including dabbing fluting frame (41), It is characterized in that:The upper end of dabbing fluting frame (41) is symmetrically arranged with dabbing fixed mechanism (42), is set in dabbing fluting frame (41) Dabbing travel mechanism (43) is equipped with, dabbing grooving mechanism (44), dabbing fixed mechanism are provided with dabbing travel mechanism (43) (42), dabbing travel mechanism (43) is used in conjunction with each other the intelligent dabbing of the wet seam construction of completion with dabbing grooving mechanism (44) and opened The technique of groove;
The dabbing that the dabbing grooving mechanism (44) includes being engaged on by gear transmission mode in dabbing travel mechanism (43) is moved Carry-over bar (441), dabbing mobile rack (441) are arranged on dabbing movable plate (442), and dabbing movable plate is provided with (442) Dabbing positioning side chain (46), dabbing movable plate (442) are arranged on two pieces of dabbings and fed on plate (443), and two pieces of dabbings feed plate (443) front and rear sides of dabbing fluting frame (41) are symmetrically positioned in, dabbing feeding plate (443) is connected to chisel by sliding matching mode On hair fluting frame (41), dabbing fluting side chain (45) is installed in the side wall of dabbing feeding plate (443);
The dabbing fixed mechanism (42) includes the dabbing location-plate (421) being arranged on dabbing fluting frame (41), dabbing positioning Dabbing telescopic cylinder (422) is installed, the top of dabbing telescopic cylinder (422) is arranged on by flange in the side wall of plate (421) On dabbing expansion plate (423), dabbing fixed plate (427) is installed on the outside of dabbing fluting frame (41), in dabbing fixed plate (427) Dabbing spacing hole is provided with, dabbing limited post (424), dabbing limited post (424) are provided with the side wall of dabbing expansion plate (423) In dabbing spacing hole, dabbing limited post (424) is arranged on dabbing working plate (425), the outer wall of dabbing working plate (425) On be provided with dabbing locating dowel (426) at equal intervals from front to back, dabbing locating dowel (426) is cone-shaped structure.
2. a kind of wet seam according to claim 1 can intelligent dabbing fluting building prestressed concrete construction machine, It is characterized in that:The dabbing travel mechanism (43) includes the two pieces of dabbings movement riser being arranged on dabbing fluting frame (41) (431) dabbing carrier wheel, is provided with by bearing at equal intervals from left to right between two pieces of dabbing movement risers (431) (432), the front end of dabbing carrier wheel (432) is provided with dabbing sprocket wheel (433), leads between two neighboring dabbing sprocket wheel (433) Cross a linkage (434) to be connected, the dabbing carrier wheel (432) positioned at dabbing fluting frame (41) right-hand member passes through shaft coupling and chisel The output of hair mobile motor (435) is connected, and dabbing mobile motor (435) is arranged on dabbing by motor cabinet and moves riser (431) On, it is connected on two neighboring dabbing carrier wheel (432) by gear transmission mode with dabbing grooving mechanism (44).
3. a kind of wet seam according to claim 1 can intelligent dabbing fluting building prestressed concrete construction machine, It is characterized in that:The dabbing positioning side chain (46) includes the dabbing positioning cylinder being arranged on dabbing movable plate (442) (461), the top of dabbing positioning cylinder (461) is arranged in dabbing fixed column (462) by flange, on dabbing fluting frame (41) It is provided with dabbing positioning pipe (463) at equal intervals from left to right.
4. a kind of wet seam according to claim 1 can intelligent dabbing fluting building prestressed concrete construction machine, It is characterized in that:The dabbing fluting side chain (45) includes the fluting telescopic cylinder being arranged in dabbing feeding plate (443) side wall (451), the top of fluting telescopic cylinder (451) is arranged on fluting dabbing frame (452) by flange, dabbing frame (452) of slotting U-shaped structure, conversion motor (453), the output of conversion motor (453) are provided with by motor cabinet on fluting dabbing frame (452) It is connected on axle by shaft coupling with conversion roller (454), the lower end of conversion roller (454) is arranged on fluting dabbing frame by bearing (452) on, two conversion expansion links (455), the top of two conversion expansion links (455) are installed on the outside of conversion roller (454) On dabbing locating rack (456), dabbing vibrating motor is provided with by motor cabinet on the inwall of dabbing locating rack (456) (457) automatic dabbing machine (458), the inner side of conversion roller (454), are provided with the outer wall of dabbing locating rack (456) at equal intervals Conversion telescopic cylinder (459) is installed, the top of conversion telescopic cylinder (459) is arranged on fluting posting (4510) by flange On, lifting carriage groove is provided with the side wall of fluting posting (4510), is installed on fluting posting (4510) by motor cabinet There is fluting lifting motor (4511), the output shaft of fluting lifting motor (4511) is arranged on fluting posting (4510) by bearing On, the output shaft of fluting lifting motor (4511) is connected by shaft coupling with the upper end of fluting elevating screw (4512), and fluting rises The lower end for dropping leading screw (4512) is installed on fluting posting (4510) by bearing, is provided with out on elevating screw (4512) of slotting Groove elevator (4513), fluting elevator (4513) are connected by sliding matching mode with fluting posting (4510), and fluting rises Fluting connecting plate (4514) is installed on drop block (4513), fluting connecting plate (4514) is arranged on fluting sliding panel (4515), Fluting electric rotating machine (4516), the output of fluting electric rotating machine (4516) are provided with by motor cabinet on fluting sliding panel (4515) Fluting swivel plate (4517) is installed on axle, electric groover (4518) is installed on fluting swivel plate (4517).
5. a kind of wet seam according to claim 3 can intelligent dabbing fluting building prestressed concrete construction machine, It is characterized in that:The dabbing positioning pipe (463) cooperates with dabbing fixed column (462) and moved, and dabbing positioning pipe (463) The radius of inwall is more than the radius of dabbing fixed column (462).
6. a kind of wet seam according to claim 1 can intelligent dabbing fluting building prestressed concrete construction machine, It is characterized in that:The diameter of the dabbing limited post (424) is less than the diameter of dabbing spacing hole.
CN201711302622.XA 2017-12-11 2017-12-11 A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine Withdrawn CN107877680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711302622.XA CN107877680A (en) 2017-12-11 2017-12-11 A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711302622.XA CN107877680A (en) 2017-12-11 2017-12-11 A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine

Publications (1)

Publication Number Publication Date
CN107877680A true CN107877680A (en) 2018-04-06

Family

ID=61773684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711302622.XA Withdrawn CN107877680A (en) 2017-12-11 2017-12-11 A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine

Country Status (1)

Country Link
CN (1) CN107877680A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755420A (en) * 2018-05-24 2018-11-06 浙江交工集团股份有限公司 A kind of high leg structure automatically adjusting stability
CN112045872A (en) * 2020-09-27 2020-12-08 金巧蒙 Method for improving installation stability of building exterior wall board
CN111526677B (en) * 2020-04-27 2021-06-11 安徽华安建筑安装工程有限公司 Fixing device for control cabinet and conveying plate for civil engineering tool and using method of fixing device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755420A (en) * 2018-05-24 2018-11-06 浙江交工集团股份有限公司 A kind of high leg structure automatically adjusting stability
CN111526677B (en) * 2020-04-27 2021-06-11 安徽华安建筑安装工程有限公司 Fixing device for control cabinet and conveying plate for civil engineering tool and using method of fixing device
CN112045872A (en) * 2020-09-27 2020-12-08 金巧蒙 Method for improving installation stability of building exterior wall board

Similar Documents

Publication Publication Date Title
CN107877680A (en) A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine
CN207026949U (en) A kind of special-shaped movable corner connectors processing unit (plant)
CN107053443A (en) Block cutting production line
CN210523522U (en) Conveying device for stator and rotor punching sheets
CN206335686U (en) A kind of environmentally friendly cutter device of laying bricks
CN206071622U (en) The heading and anchoring integrated machine of development machine transformation
CN105689693B (en) A kind of casting separator and its method
CN106592402A (en) Road cutting robot and construction method thereof
CN207615576U (en) A kind of pier head machine convenient for feeding
CN115625534A (en) Automatic production line and production process of steel arch for railway tunnel support
CN109382873A (en) A kind of plate drilling equipment that can be recycled waste material and improve surface flatness
CN207672434U (en) A kind of wet seam construction robot of prestressed concrete automating dabbing fluting
CN107988912A (en) It is a kind of can efficiently dabbing fluting the wet seam construction equipment of prestressed concrete beam body
CN205613972U (en) Automatic guide portable swing arm punching press machine people
CN104999550A (en) Cleaning system of steel dies for tubular pile production
CN110748306A (en) Foldable pipe swinging robot for drilling platform surface
CN113000684A (en) End flattening equipment for machining automobile bumper reinforcing pipe and using method thereof
CN202742436U (en) Automatic drilling machine
CN108086644A (en) The building and ornament materials fiber cement outer wall Slate hanging construction robot that can be squeegeeed automatically
CN105109927B (en) Automatic transfer machine structure for cylindrical work
CN209535583U (en) A kind of manual box press material collecting device
CN207578662U (en) A kind of wet seam can intelligent dabbing fluting building prestressed concrete construction machine
CN204160813U (en) The semi-automatic carton nailing machine of full machinery
CN209724216U (en) A kind of screw mandrel regulation type various dimensions mining drilling equipment
CN203794490U (en) Lifting device of tramcar reclaimer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180406