CN107816204A CN201710876873.2A CN201710876873A CN107816204A CN 107816204 A CN107816204 A CN 107816204A CN 201710876873 A CN201710876873 A CN 201710876873A CN 107816204 A CN107816204 A CN 107816204A
Authority
CN
China
Prior art keywords
vertical rod
row
balcony
skyscraper
protective frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710876873.2A
Other languages
Chinese (zh)
Inventor
左乾军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201710876873.2A priority Critical patent/CN107816204A/en
Publication of CN107816204A publication Critical patent/CN107816204A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section
    • E04G1/06Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section comprising members with rod-like or tubular portions fitting together end to end, with or without separate connecting pieces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • E04G1/152Platforms made of metal or with metal-supporting frame
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/066Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for overhangs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to protective frame outside a kind of skyscraper staggered floor balcony to also serve as operating platform erection method, the described method comprises the following steps:Two row's preformed holes are set on the floorboard of balcony;The corresponding preformed hole is passed through to be connected with lower floor scaffold interior the row's vertical rod and intermediate row vertical rod of three exclusive scaffolds;Wedging is carried out using timber wedge between interior row's vertical rod and the intermediate row vertical rod and the preformed hole;Bar of sweeping the floor, horizon bar and outer row's vertical rod are set up according to a conventional method;Construct and removed the three exclusive scaffold, waterproof closure is carried out to the preformed hole.Because protective frame also serves as operating platform erection method outside skyscraper staggered floor balcony provided by the invention, set up at staggered floor balcony using three framed bents, can effectively ensure that security protection, while take into account external wall construction.Using setting preformed hole on the floorboard of balcony, the vertical rod of three exclusive scaffolds is connected through preformed hole with lower floor scaffold, optimizes the setting of wall-connecting piece.

Description

The outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method
Technical field
The present invention relates to technical field of building construction, more particularly to a kind of outer protective frame of skyscraper staggered floor balcony are simultaneous Do operation Platforms Construct Method of Super.
Background technology
As the progress of society, skyscraper are more and more.
At present, protecting outside skyscraper and either use floor stand, builder's jack or climbing frame, it is in the main body construction stage, and one As be the protection of double outrigger.But when facade is staggered floor balcony, on staggered floor balcony facade(Particularly outside staggered floor balcony Choose length it is also bigger when), only can guarantee that balcony floor is guaranteed safely using double outrigger, the floor edge of no balcony Gap is excessive, and for operator when facing side operation, safety can not ensure do not possess scope of operation security protection condition in place at all. Operated in the facade of two layers of floor height, either agent structure, or secondary structure, decorations, difficulty of construction, Input for safety can all increase much.
Therefore, the outer protective frame of skyscraper staggered floor balcony in the prior art be present can not ensure no balcony using double outrigger The technological deficiency of the construction safety of floor.
The content of the invention
The embodiment of the present invention provides a kind of outer protective frame of skyscraper staggered floor balcony and also serves as operating platform erection method, to The construction peace that the outer protective frame of skyscraper staggered floor balcony can not ensure no balcony floor using double outrigger in the prior art be present Full technological deficiency.
On the one hand, operating platform is also served as the embodiments of the invention provide protective frame outside a kind of skyscraper staggered floor balcony to set up Method, it the described method comprises the following steps:
(1)Two row's preformed holes are set on the floorboard of balcony;
(2)Interior the row's vertical rod and intermediate row vertical rod of three exclusive scaffolds are connected through the preformed hole with lower floor scaffold;
(3)Wedging is carried out using timber wedge between interior row's vertical rod and the intermediate row vertical rod and the preformed hole;
(4)Bar of sweeping the floor, horizon bar and outer row's vertical rod are set up according to a conventional method;
(5)Construct and removed the three exclusive scaffold, waterproof closure is carried out to the preformed hole.
Optionally, the preformed hole is specially Φ 100mm preformed holes.
Optionally, exterior wall 200mm of the interior row's vertical rod apart from the skyscraper.
Optionally, outer row's vertical rod is apart from the balcony outer edge 600mm.
Optionally, interior row's vertical rod, the intermediate row vertical rod, outer row's vertical rod, bar and the level of sweeping the floor Bar uses the steel pipes of Φ 48 × 3.5.
Optionally, the step pitch of described three exclusive scaffolds is 1.75m, wherein, a height of 2.0m of first step frame.
Optionally, the horizontal spacing of interior row's vertical rod, the intermediate row vertical rod and outer row's vertical rod is specially 0.8- 1.0m;Spacing between interior row's vertical rod and the intermediate row vertical rod between the intermediate row vertical rod and outer row's vertical rod No more than 1.5m;The bar of sweeping the floor is 200mm away from ground.
Optionally, it is described to be specially to preformed hole progress waterproof closure:
Closely knit using the pouring of C35 microdilatancies pea gravel concreten, maintenance is no less than 7 days.
One or more of technical methods provided in an embodiment of the present invention, at least have the following technical effect that and advantage:
Because protective frame also serves as operating platform erection method outside a kind of skyscraper staggered floor balcony provided in an embodiment of the present invention, Set up at staggered floor balcony using three framed bents, can effectively ensure that security protection, while take into account external wall construction.
Further, due to outside skyscraper staggered floor balcony provided in an embodiment of the present invention protective frame also serve as operating platform and take Equipment, method, using two row's preformed holes are set on the floorboard of balcony, interior row's vertical rod and intermediate row by three exclusive scaffolds are stood Bar passes through the corresponding preformed hole to be connected with lower floor scaffold, optimizes the setting of wall-connecting piece, makes scaffold resistance to overturning More there is safety assurance.
Further, because to also serve as operation flat for protective frame outside a kind of skyscraper staggered floor balcony provided in an embodiment of the present invention Platform erection method, after the three exclusive scaffold is removed, preformed hole hangs hole and concrete grouting processing is simple, and quality is easily protected Card.
Brief description of the drawings
Fig. 1 is that a kind of outer protective frame of skyscraper staggered floor balcony provided in an embodiment of the present invention also serves as the operating platform side of setting up The method flow diagram of method;
Fig. 2 also serves as operating platform for the outer protective frame of middle-high building staggered floor of embodiment of the present invention balcony and sets up schematic diagram;
Fig. 3 also serves as operating platform for the outer protective frame of middle-high building staggered floor of embodiment of the present invention balcony and sets up diagrammatic cross-section.
Embodiment
The embodiment of the present invention provides a kind of outer protective frame of skyscraper staggered floor balcony and also serves as operating platform erection method, to The construction peace that the outer protective frame of skyscraper staggered floor balcony can not ensure no balcony floor using double outrigger in the prior art be present Full technological deficiency.
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached in the embodiment of the present invention Figure, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is the present invention Part of the embodiment, rather than whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not having The every other embodiment obtained under the premise of creative work is made, belongs to the scope of protection of the invention.
The embodiments of the invention provide protective frame outside a kind of skyscraper staggered floor balcony to also serve as operating platform erection method, please With reference to figure 1, the described method comprises the following steps:
Step S1:Two row's preformed holes are set on the floorboard of balcony.
Step S2:Interior the row's vertical rod and intermediate row vertical rod of three exclusive scaffolds are passed through into the corresponding preformed hole and lower floor Scaffold connects.
Step S3:Wedge is carried out using timber wedge between interior row's vertical rod and the intermediate row vertical rod and the preformed hole Tightly.
Step S4:Bar of sweeping the floor, horizon bar and outer row's vertical rod are set up according to a conventional method.
Step S5:Construct and removed the three exclusive scaffold, waterproof closure is carried out to the preformed hole.
In specific implementation process, as shown in Figures 2 and 3, the preformed hole 30 on the floorboard of balcony 10 is specially Φ 100mm preformed holes, use during construction and be configured in the form of Φ 100PVC pipes are pre-buried.
In specific implementation process, exterior wall 200mm of the interior row's vertical rod 40 apart from the skyscraper.If the high level The window 20 that floats is provided with the exterior wall of building, then interior row's vertical rod 40 is floatd the outer 200mm of window 20 with regard to distance.
Further, in specific implementation process, balcony 10 outer edge of the outer row's vertical rod 60 apart from the skyscraper 600mm。
In specific implementation process, interior row's vertical rod 40, intermediate row vertical rod 50, outer row's vertical rod 60, sweep the floor bar 70 and level Bar 80 uses Φ 48*3.5 steel pipes.
In specific implementation process, the step pitch of the three exclusive scaffold is 1.75m, wherein, first step frame is a height of 2.0m。
In specific implementation process, the horizontal spacing of interior row's vertical rod 40, intermediate row vertical rod 50 and outer row's vertical rod 60 is specific For 0.8-1.0m;Spacing between interior row's vertical rod 40 and intermediate row vertical rod 50 between intermediate row vertical rod 50 and outer row's vertical rod 60 is not More than 1.5m;Bar 70 of sweeping the floor away from ground is 200mm.
In specific implementation process, between interior row's vertical rod 40 on upper strata and interior row's vertical rod 40 of lower floor, the centre on upper strata Adopted between row's vertical rod 50 and the intermediate row vertical rod 50 of lower floor and between outer row's vertical rod 60 on upper strata and outer row's vertical rod 60 of lower floor Connected with direct fastener, between horizon bar 80 and interior row's vertical rod 40, intermediate row vertical rod 50 and outer row's vertical rod 60 and bar 70 of sweeping the floor It is connected between interior row's vertical rod 40, intermediate row vertical rod 50 and outer row's vertical rod 60 using right-angle coupler.
In specific implementation process, when constructed remove the three exclusive scaffold after, to the preformed hole on balcony 10 30 progress waterproof closure specific methods be:Closely knit using the pouring of C35 microdilatancies pea gravel concreten, maintenance is no less than 7 days.Maintenance Closed-water test is done to the position of preformed hole 30 after end, it is just qualified to close water 24h ne-leakages.
One or more of technical methods provided in an embodiment of the present invention, at least have the following technical effect that and advantage:
Because protective frame also serves as operating platform erection method outside a kind of skyscraper staggered floor balcony provided in an embodiment of the present invention, Set up at staggered floor balcony using three framed bents, can effectively ensure that security protection, while take into account external wall construction.
Further, due to outside skyscraper staggered floor balcony provided in an embodiment of the present invention protective frame also serve as operating platform and take Equipment, method, using two row's preformed holes are set on the floorboard of balcony, interior row's vertical rod and intermediate row by three exclusive scaffolds are stood Bar passes through the corresponding preformed hole to be connected with lower floor scaffold, optimizes the setting of wall-connecting piece, makes scaffold resistance to overturning More there is safety assurance.
Further, because to also serve as operation flat for protective frame outside a kind of skyscraper staggered floor balcony provided in an embodiment of the present invention Platform erection method, after the three exclusive scaffold is removed, preformed hole hangs hole and concrete grouting processing is simple, and quality is easily protected Card.
Obviously, those skilled in the art can carry out the essence of various changes and modification without departing from the present invention to the present invention God and scope.So, if these modifications and variations of the present invention belong to the scope of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to comprising including these changes and modification.

Claims (8)

1. a kind of outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method, it is characterised in that methods described bag Include following steps:
(1)Two row's preformed holes are set on the floorboard of balcony;
(2)Interior the row's vertical rod and intermediate row vertical rod of three exclusive scaffolds are passed through into the corresponding preformed hole and scaffold company of lower floor Connect;
(3)Wedging is carried out using timber wedge between interior row's vertical rod and the intermediate row vertical rod and the preformed hole;
(4)Bar of sweeping the floor, horizon bar and outer row's vertical rod are set up according to a conventional method;
(5)Construct and removed the three exclusive scaffold, waterproof closure is carried out to the preformed hole.
2. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 1 also serves as operating platform erection method, its feature exists In the preformed hole is specially Φ 100mm preformed holes.
3. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 1 also serves as operating platform erection method, its feature exists In exterior wall 200mm of the interior row's vertical rod apart from the skyscraper.
4. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 3 also serves as operating platform erection method, its feature exists In outer row's vertical rod is apart from the balcony outer edge 600mm.
5. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 1 also serves as operating platform erection method, its feature exists In, interior row's vertical rod, the intermediate row vertical rod, outer row's vertical rod, described sweep the floor bar and the horizon bar uses Φ 48* 3.5 steel pipe.
6. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 1 also serves as operating platform erection method, its feature exists In, the step pitch of the three exclusive scaffold is 1.75m, wherein, a height of 2.0m of first step frame.
7. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 1 also serves as operating platform erection method, its feature exists In the horizontal spacing of interior row's vertical rod, the intermediate row vertical rod and outer row's vertical rod is specially 0.8-1.0m;The interior row Spacing between vertical rod and the intermediate row vertical rod between the intermediate row vertical rod and outer row's vertical rod is not more than 1.5m;Institute It is 200mm that bar of sweeping the floor, which is stated, away from ground.
8. the outer protective frame of skyscraper staggered floor balcony as claimed in claim 1 also serves as operating platform erection method, its feature exists In described to be specially to preformed hole progress waterproof closure:
Closely knit using the pouring of C35 microdilatancies pea gravel concreten, maintenance is no less than 7 days.
CN201710876873.2A 2017-09-25 2017-09-25 The outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method Pending CN107816204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710876873.2A CN107816204A (en) 2017-09-25 2017-09-25 The outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710876873.2A CN107816204A (en) 2017-09-25 2017-09-25 The outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method

Publications (1)

Publication Number Publication Date
CN107816204A true CN107816204A (en) 2018-03-20

Family

ID=61607143

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710876873.2A Pending CN107816204A (en) 2017-09-25 2017-09-25 The outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method

Country Status (1)

Country Link
CN (1) CN107816204A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395725A (en) * 2020-04-22 2020-07-10 中建八局第二建设有限公司 Construction method of scaffold with irregular convex-concave facade structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2876236Y (en) * 2006-03-12 2007-03-07 范增林 Suspension arm lifting scaffold
CH702922B1 (en) * 2008-02-27 2011-10-14 Rudolf Wiederkehr Closure component for balcony or facade of building, has dewatering channel element running parallel to hand rail, which is attached at closure component, and fastening elements connected with dewatering channel elements by junction plate
CN203856182U (en) * 2014-05-15 2014-10-01 中航天建设工程有限公司 Novel cantilever scaffold structure
CN204343647U (en) * 2014-11-24 2015-05-20 中国十七冶集团有限公司 A kind of the shaped steel suspension scaffolding bracing frame
CN205558237U (en) * 2016-05-03 2016-09-07 中建八局第一建设有限公司 Encorbelment board position and encorbelment scaffold frame and exempt from back a structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2876236Y (en) * 2006-03-12 2007-03-07 范增林 Suspension arm lifting scaffold
CH702922B1 (en) * 2008-02-27 2011-10-14 Rudolf Wiederkehr Closure component for balcony or facade of building, has dewatering channel element running parallel to hand rail, which is attached at closure component, and fastening elements connected with dewatering channel elements by junction plate
CN203856182U (en) * 2014-05-15 2014-10-01 中航天建设工程有限公司 Novel cantilever scaffold structure
CN204343647U (en) * 2014-11-24 2015-05-20 中国十七冶集团有限公司 A kind of the shaped steel suspension scaffolding bracing frame
CN205558237U (en) * 2016-05-03 2016-09-07 中建八局第一建设有限公司 Encorbelment board position and encorbelment scaffold frame and exempt from back a structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395725A (en) * 2020-04-22 2020-07-10 中建八局第二建设有限公司 Construction method of scaffold with irregular convex-concave facade structure
CN111395725B (en) * 2020-04-22 2021-07-09 中建八局第二建设有限公司 Construction method of scaffold with irregular convex-concave facade structure

Similar Documents

Publication Publication Date Title
CN205077845U (en) Building core section of thick bamboo well hydraulic pressure intelligence operation scaffold that climbs
CN104975719A (en) Novel material distribution device and floor concrete casting construction method of novel material distribution device
CN107419918A (en) A kind of Historical Buildings periphery single-layer frame retains method for dismounting
CN106088447B (en) A kind of exterior wall builder's jack shaped steel hole eye protection brick device and construction method
CN108252504A (en) Tube shear wall concrete structure large form hoisting type construction method and constructing device
CN102400470B (en) Construction method for multi-platform deep foundation of hillside high-rise building
CN105088979B (en) Demolition blasting method for large bridge
CN204753628U (en) Guider that hangs down is transferred to contrary way of doing things steel -pipe column that can have enough to meet need
CN104404979A (en) H-shaped pile slab wall construction method
CN203374008U (en) Elevator shaft titling plane protective structure
CN209585054U (en) One kind is quickly met an urgent need diagonal brace for salvage of foundation pits
CN105350760A (en) Edge-beam-supporting steel-rod-inclined-pulling and wire-rope-unloading overhanging scaffold construction method
CN106337520A (en) The construction technology of large-cell point glass curtain wall
CN107816204A (en) The outer protective frame of skyscraper staggered floor balcony also serves as operating platform erection method
CN210713745U (en) Synchronous construction scaffold system for multiple working faces of super high-rise building
CN208363666U (en) It is a kind of for build face side construction safety protection frame
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform
CN104878775A (en) Turnable top-down method steel pipe column verticality adjusting guide device and construction method thereof
CN205476556U (en) Horizontal protector of construction scaffolding operating layer
CN108104506A (en) It is a kind of to be used for structural demolition and the temporary facility rebuilded and its construction method
CN108019040A (en) A kind of high-rise building transfer floor Bailey bracket platform construction method
CN205382718U (en) Sparse passway for escaping of steel platform die carrier system
CN207988457U (en) It is protected outside skyscraper staggered floor balcony and operating platform sets up structure
CN106760530B (en) A kind of operating platform and its construction method for the dismounting of tower crane wall attaching rod
CN205591519U (en) Elevator well handling frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180320