CN107764235A - 用于高层建筑施工的高程竖向传递测量方法 - Google Patents
用于高层建筑施工的高程竖向传递测量方法 Download PDFInfo
- Publication number
- CN107764235A CN107764235A CN201610664591.1A CN201610664591A CN107764235A CN 107764235 A CN107764235 A CN 107764235A CN 201610664591 A CN201610664591 A CN 201610664591A CN 107764235 A CN107764235 A CN 107764235A
- Authority
- CN
- China
- Prior art keywords
- elevation
- measurement
- mark
- control
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C5/00—Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
Abstract
本发明公开了一种用于高层建筑施工的高程竖向传递测量方法,本方法首先引测拟建建筑物的首层控制标高,在距离拟建建筑物最近的塔吊塔身上标注所述控制标高并作出标记;采用钢卷尺以该标记为基准,沿塔身向上一次测量到顶,标注拟建建筑物各施工层的控制标高,并且作出各施工层的控制标高标记;截取60cm长尺身,将尺身零刻度对准塔吊塔身的各施工层控制标高标记并且垂直粘贴;各施工层施工过程的高程测量、控制、检查时,在各楼层架设水准仪,以对应层尺身为标靶,照准尺身刻度,即可直接读取后视点数据,实现高程竖向传递测量。本方法使测量人员无需反复登塔操作,有效提高了测量效率,降低测量人员的作业强度,并且提高了测量精度。
Description
技术领域
本发明涉及一种用于高层建筑施工的高程竖向传递测量方法。
背景技术
随着基础建设的发展,建筑行业的发展十分迅猛,其中高层建筑的施工项目越来越多;高层建筑施工的高程竖向传递及检查控制工作十分频繁,也十分重要,稍有不慎就将导致无法弥补的损失。
就目前来说,高层建筑施工的高程竖向传递测量方法有多种,其中最常用的方法为首先将高程引测到塔吊底层塔身上;再使用钢卷尺沿塔吊塔身往上量取各施工楼层所需高程,并做好标记;然后测量人员拿着塔尺爬到塔吊上取好后视点,往施工楼层引测高程或用于检查控制。由于正在施工的楼层随时需要用到高程测量及检查,又没有位置稳定可引测标记的部位,因此测量人员每次都需拿着塔尺爬上塔吊读取后视点数据。如此既降低了高程竖向传递测量的效率,又增加了测量人员的劳动强度,并且提高了测量误差。
发明内容
本发明所要解决的技术问题是提供一种用于高层建筑施工的高程竖向传递测量方法,本方法在高程竖向传递测量时测量人员无需反复登塔操作,即一次准备,可以多次使用,有效提高了工作效率,降低测量人员的作业强度,并且提高了测量精度。
为解决上述技术问题,本发明用于高层建筑施工的高程竖向传递测量方法包括如下步骤:
步骤一、引测拟建建筑物的首层控制标高,在距离拟建建筑物最近的塔吊塔身上标注所述控制标高,并且作出标记;
步骤二、采用钢卷尺以所述控制标高的标记为基准,沿塔吊塔身向上一次测量到顶,标注拟建建筑物各施工层的控制标高,并且作出各施工层的控制标高标记;
步骤三、截取60cm长尺身,尺身刻度取整数,将尺身零刻度对准塔吊塔身的各施工层控制标高标记并且垂直粘贴;
步骤四、各施工层施工过程的高程测量、控制、检查时,在各楼层架设水准仪,以粘贴于塔吊塔身的对应层尺身为标靶,照准尺身刻度,即可直接读取后视点数据,实现高程竖向传递测量。
进一步,各施工层的控制标高采用结构1米线。
由于本发明用于高层建筑施工的高程竖向传递测量方法采用了上述技术方案,即本方法首先引测拟建建筑物的首层控制标高,在距离拟建建筑物最近的塔吊塔身上标注所述控制标高并作出标记;采用钢卷尺以该标记为基准,沿塔身向上一次测量到顶,标注拟建建筑物各施工层的控制标高,并且作出各施工层的控制标高标记;截取60cm长尺身,将尺身零刻度对准塔吊塔身的各施工层控制标高标记并且垂直粘贴;各施工层施工过程的高程测量、控制、检查时,在各楼层架设水准仪,以对应层尺身为标靶,照准尺身刻度,即可直接读取后视点数据,实现高程竖向传递测量。本方法在高程竖向传递测量时测量人员无需反复登塔操作,即一次准备,可以多次使用,有效提高了工作效率,降低测量人员的作业强度,并且提高了测量精度。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为本发明用于高层建筑施工的高程竖向传递测量方法示意图;
图2为本方法中粘贴塔吊塔身的尺身示意图。
具体实施方式
实施例如图1和图2所示,本发明用于高层建筑施工的高程竖向传递测量方法包括如下步骤:
步骤一、引测拟建建筑物的首层控制标高,在距离拟建建筑物1最近的塔吊2塔身上标注所述控制标高,并且作出标记;
步骤二、采用钢卷尺以所述控制标高的标记为基准,沿塔吊2塔身向上一次测量到顶,标注拟建建筑物1各施工层的控制标高,并且作出各施工层的控制标高标记;
步骤三、截取60cm长尺身3,尺身3刻度取整数,将尺身3零刻度对准塔吊2塔身的各施工层控制标高标记并且垂直粘贴;
步骤四、各施工层施工过程的高程测量、控制、检查时,在各楼层架设水准仪4,以粘贴于塔吊2塔身的对应层尺身3为标靶,照准尺身3刻度,即可直接读取后视点数据,实现高程竖向传递测量。
优选的,各施工层的控制标高采用结构一米线。结构一米线是指从楼板面向上1米的标高。
本方法操作简单方便,随用随取,测量人员无需每次拿着塔尺爬上塔吊取后视点读数;降低了测量误差,提高精度。并且塔吊结构相对比较稳定,在施工楼层里架设水准仪每次都可以读取到设置于塔吊上的后视点,后视点位置固定,测量的数据误差就越小,从而提高了拟建建筑物的施工质量。同时采用本方法大大减少了测量的准备工作,一次准备,可多次使用,降低了测量人员的劳动强度,提高工作效率。
Claims (2)
1.一种用于高层建筑施工的高程竖向传递测量方法,其特征在于本方法包括如下步骤:
步骤一、引测拟建建筑物的首层控制标高,在距离拟建建筑物最近的塔吊塔身上标注所述控制标高,并且作出标记;
步骤二、采用钢卷尺以所述控制标高的标记为基准,沿塔吊塔身向上一次测量到顶,标注拟建建筑物各施工层的控制标高,并且作出各施工层的控制标高标记;
步骤三、截取60cm长尺身,尺身刻度取整数,将尺身零刻度对准塔吊塔身的各施工层控制标高标记并且垂直粘贴;
步骤四、各施工层施工过程的高程测量、控制、检查时,在各楼层架设水准仪,以粘贴于塔吊塔身的对应层尺身为标靶,照准尺身刻度,即可直接读取后视点数据,实现高程竖向传递测量。
2.根据权利要求1所述的用于高层建筑施工的高程竖向传递测量方法,其特征在于:各施工层的控制标高采用结构1米线。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610664591.1A CN107764235B (zh) | 2016-08-15 | 2016-08-15 | 用于高层建筑施工的高程竖向传递测量方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610664591.1A CN107764235B (zh) | 2016-08-15 | 2016-08-15 | 用于高层建筑施工的高程竖向传递测量方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107764235A true CN107764235A (zh) | 2018-03-06 |
CN107764235B CN107764235B (zh) | 2020-04-14 |
Family
ID=61259680
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610664591.1A Active CN107764235B (zh) | 2016-08-15 | 2016-08-15 | 用于高层建筑施工的高程竖向传递测量方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107764235B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110160488A (zh) * | 2019-05-13 | 2019-08-23 | 北京铁科工程检测有限公司 | 一种异形钢索塔高程的测量方法及测量装置 |
CN113356608A (zh) * | 2021-07-26 | 2021-09-07 | 何相昆 | 一种房建工程施工用规避墙体间距误差的标高方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050060901A1 (en) * | 2003-09-19 | 2005-03-24 | Todd Cook | Laser sighting device and method |
JP2007276947A (ja) * | 2006-04-06 | 2007-10-25 | Chugoku Electric Power Co Inc:The | レーザ受光装置及びこれを用いた警報装置 |
JP2012194070A (ja) * | 2011-03-16 | 2012-10-11 | Chugoku Electric Power Co Inc:The | 鉄塔レベル測定補助具 |
CN103308030A (zh) * | 2012-12-14 | 2013-09-18 | 北京市测绘设计研究院 | 超高层标高高精度自动传递工艺方法 |
CN104677345A (zh) * | 2013-12-03 | 2015-06-03 | 黑龙江融德建筑技术开发有限公司 | 一种竖向标高传递装置 |
-
2016
- 2016-08-15 CN CN201610664591.1A patent/CN107764235B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050060901A1 (en) * | 2003-09-19 | 2005-03-24 | Todd Cook | Laser sighting device and method |
JP2007276947A (ja) * | 2006-04-06 | 2007-10-25 | Chugoku Electric Power Co Inc:The | レーザ受光装置及びこれを用いた警報装置 |
JP2012194070A (ja) * | 2011-03-16 | 2012-10-11 | Chugoku Electric Power Co Inc:The | 鉄塔レベル測定補助具 |
CN103308030A (zh) * | 2012-12-14 | 2013-09-18 | 北京市测绘设计研究院 | 超高层标高高精度自动传递工艺方法 |
CN104677345A (zh) * | 2013-12-03 | 2015-06-03 | 黑龙江融德建筑技术开发有限公司 | 一种竖向标高传递装置 |
Non-Patent Citations (1)
Title |
---|
唐春平等: "《建筑工程测量》", 30 April 2016 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110160488A (zh) * | 2019-05-13 | 2019-08-23 | 北京铁科工程检测有限公司 | 一种异形钢索塔高程的测量方法及测量装置 |
CN110160488B (zh) * | 2019-05-13 | 2021-08-31 | 北京铁科工程检测有限公司 | 一种异形钢索塔高程的测量方法及测量装置 |
CN113356608A (zh) * | 2021-07-26 | 2021-09-07 | 何相昆 | 一种房建工程施工用规避墙体间距误差的标高方法 |
Also Published As
Publication number | Publication date |
---|---|
CN107764235B (zh) | 2020-04-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102322896B (zh) | 隧道tsp几何参数全方位测量装置与方法 | |
CN102997846A (zh) | 基于工作空间测量定位系统的飞机全机水平测量方法 | |
CN103115605A (zh) | 一种基于联系三角形的地铁竖井定向测量方法 | |
CN102607516B (zh) | 测量核电工程中的基准的高程的方法 | |
CN105974398A (zh) | 一种雷达激光靶校准前调平方法 | |
CN104880204A (zh) | 利用gps及自动跟踪与测量系统对高精度激光测距仪的校准方法 | |
CN107764235A (zh) | 用于高层建筑施工的高程竖向传递测量方法 | |
CN204831204U (zh) | 一种水稻植株高度测量装置 | |
CN104535974A (zh) | 一种飞机雷达系统校靶装置及其使用方法 | |
CN201081728Y (zh) | 一种便携式卫星天线辅助寻星装置 | |
CN201892537U (zh) | 模板垂直度检测尺 | |
CN102022997A (zh) | 一种跨障碍对线路视距和高差的测量方法 | |
CN106767670B (zh) | 光电吊舱安装偏角辅助标校装置 | |
CN204988223U (zh) | 一种钢构件制作尺寸精度的检测装置 | |
CN105157668B (zh) | 火箭瞄准系统通过基准棱镜获取基准方位的方法 | |
CN103912458B (zh) | 一种风力发电机组风向标精确对风的安装工装及对风方法 | |
CN102967237A (zh) | 一种用于悬索桥主缆索股架设多功能测量仪 | |
CN108343448A (zh) | 一种隧道任意断面姿态确定的方法 | |
CN102322854B (zh) | 隧道监控量测点及tsp炮孔布设装置与方法 | |
CN105486282A (zh) | 一种测量导管架平台结构倾斜角度的装置及测量方法 | |
CN105021094A (zh) | 一种小展弦比导弹水平测量方法 | |
CN110207570A (zh) | 一种架空导线型号测量工具 | |
CN109443139A (zh) | 导流罩线型检验方法 | |
CN202964636U (zh) | 一种余量线划制工装 | |
CN202177380U (zh) | 隧道监控量测点及tsp炮孔布设装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |