CN107762238B - A kind of king-post prestressed strand lifting position control method - Google Patents

A kind of king-post prestressed strand lifting position control method Download PDF

Info

Publication number
CN107762238B
CN107762238B CN201710952262.1A CN201710952262A CN107762238B CN 107762238 B CN107762238 B CN 107762238B CN 201710952262 A CN201710952262 A CN 201710952262A CN 107762238 B CN107762238 B CN 107762238B
Authority
CN
China
Prior art keywords
steel
strand wires
anchor slab
steel strand
shu
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710952262.1A
Other languages
Chinese (zh)
Other versions
CN107762238A (en
Inventor
陈敦刚
席军现
李廷钰
高建斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201710952262.1A priority Critical patent/CN107762238B/en
Publication of CN107762238A publication Critical patent/CN107762238A/en
Application granted granted Critical
Publication of CN107762238B publication Critical patent/CN107762238B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/16Prestressed structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/121Construction of stressing jacks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/341Arrangements for casting in situ concrete towers or the like

Abstract

The present invention relates to a kind of king-post prestressed strands to lift position control method, includes the following steps: that Shu Pingtai is compiled in selection, according to the length of steel beam, the conduit of beam is compiled in setting on compiling Shu Pingtai;Steel strand wires are penetrated in conduit by root;Beam is compiled to steel beam lower end;Beam is compiled to steel Shu Shangduan again, and 1# anchor slab is installed, steel strand wires are locked on 1# anchor slab using steel strand wires card;2# anchor slab is worn again in steel bunchy top portion, using anchor ear by 1#, 2# anchor slab banding;Steel strand wires are sent into reserving hole channel;The anchor ear for anchoring two anchor slabs is released, takes 2# anchor slab away, completes the installation of steel beam;Stretch-draw jack is installed on the 1# anchor slab left, use the 10%-20% initial tensioning force of tension stress, complete unlock and adjustment the steel Shu Shunzhi degree, loose degree of card temporary locking, subsequently into the tensioning construction stage, the present invention has the advantages that easy to operate, the saving time, work efficiency is high.

Description

A kind of king-post prestressed strand lifting position control method
Technical field
The invention belongs to king-post pre-stress construction fields, and in particular to a kind of king-post prestressed strand lifting location control side Method.
Background technique
Prestressing force is in order to improve structure military service performance, in the precharge pressure that construction period is previously applied to structure, structure Precharge pressure can completely or partially offset tensile stress caused by load during one's term of military service, and structure is avoided to destroy.It is usually used in concrete knot Structure.Prestressed reinforced concrete construction is to apply pressure before structure bearing load to it in advance, make it in outer load action Concrete in tension zone internal force generate compression, to offset or reduce external load generation tensile stress, make structure normally It does not generate crack in the case where or splits than later.
Currently, large-sized prestress king-post steel strand wires because joint length is big, mostly carry out lashing using special strand pulling machine, lead to Cross strand pulling machine machine driving, idler wheel clamping steel strand wires are transmitted, i.e., drive double driving wheels to rotate using speed reducer, steel hinge line from The insertion of one end incoming line, driving wheel and double driven wheels, which are pushed down steel hinge line and moved forward, penetrates reserving hole channel along conduit, until from hole The road other end is pierced by the size for reaching tensioning needs.When king-post takes subsection tension size shorter, also matched sometimes using crane After closing hanging object snap ring locking steel strand wires, steel strand wires bunchy is sling into cooperation, steel strand wires are slowly manually sent into reserving hole channel, until Steel strand wires are pierced by from duct lower end, then first steel beam lower end is baffled, upper end using 8# galvanized wire or wirerope is consolidated steel strand wires It is fixed, then galvanized wire or wirerope are released, after installation anchor slab makes jack and has the ability of locking steel beam, release the gear of steel beam lower end Plate installs steel beam lower end anchor slab and jack, the lashing for completing steel strand wires and the preparation before tensioning.
However, pulling anchor cable stage must be by carrying out the built-in fitting at tensioning port when pre-stress construction place is narrow Processing could be that suitable space is vacateed in tensioning, and requires just to can guarantee that tensioning is normally carried out using the jack of small volume, Therefore, carrying out lashing operation in prestressed pore passage arrangement strand pulling machine suitable for reading cannot achieve.If steel strand wires sling using crane Afterwards, it is manually sent into hole by root, and glides in the baffled blocking steel beam in duct lower part, taking the measure, not only difficulty of construction is big, And easily cause steel beam to drop because of self weight, need to do over again lashing again, and there are construction quality risk, and steel Shu Zichong compared with Greatly, portion is baffled under prestress and when cooperating the fixed steel beam of duct top and galvanized wire or wirerope, is easy to happen steel beam and crashes into Phenomenon in hole, and steel beam relative position generates dislocation, needs repeatedly to adjust steel beam, causes many troubles to pre-stress construction, In addition to this, when prestressed cable tensioning, for eliminate steel strand wires in duct because be self-possessed it is sagging caused by straight and slackness increase Loss of prestress also needs after carrying out single top prestretching, then carries out the tensioning of whole beam, and construction is complicated time-consuming.
Summary of the invention
In view of the deficiencies of the prior art, the object of the present invention is to provide a kind of king-post prestressed strands to lift location control side Method, the control method, includes the following steps:
Step 1: select a smooth location as the platform of steel strands-woven bundle, according to the length of steel beam, on compiling Shu Pingtai Two blocks of steel plates that can be moved are set, and weld a steel pipe on the steel plate as the conduit for compiling beam, by steel plate Position adjustment, to be suitble to compile different segment length steel beam the needs of beam;
Step 2: steel strand wires are penetrated by root in the conduit for being used for steel beam top and bottom volume beam, so as in conduit outlet Steel strand wires are arranged on the steel plate at end;
Step 3: when beam is compiled in steel beam lower end, being divided into three kinds of dislocation for steel beam and place, and adjacent dislocation difference is 30cm, uses Galvanized wire binds the steel strand wires of equal length together, and the steel strand wires of long 30cm are wrapped to the steel strand wires of 30cm shorter than its, Cone-shaped is formed in the lower end of steel beam;
Step 4: it is hinged with a guiding cap in steel beam lower end, in order to which steel beam passes through duct;
Step 5: when steel Shu Shangduan compiles beam, the steel strand wires of longest beam are first mounted on to several center hole portions of 1# anchor slab Position, then vice-minister's beam of steel strand wires is faced into centre bore mounting arrangements, most short steel strand wires are finally arranged in the periphery hole site of anchor slab;
Step 6: after the completion of 1# anchor slab lashing, steel strand wires are locked on 1# anchor slab using steel strand wires card;
Step 7: it after completing the locking of upper end steel strand wires, wears 2# anchor slab again at the top of steel Shu Shangduan, then uses anchor ear by 1# Anchor slab, 2# anchor slab hoop are together;
Step 8: along steel beam length direction at interval of 4m-6m, bundling steel beam with galvanized wire, prevents steel beam adjacent in lifting Steel strand wires generate gap and displacement;
Step 9: the steel Shu Caiyong crane for completing top and bottom volume beam is sling, steel strand wires are sent into reserving hole channel simultaneously The galvanized wire every 4m-6m binding steel beam is released, until steel strand wires lower end is pierced by from duct lower end;
Step 10: when steel Shu Shangduan is suitable for reading close to duct, 1# anchor slab that steel Shu Shangduan is installed, 2# anchor slab center and reserved The alignment of duct center, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11: releasing the anchor ear for anchoring two anchor slabs, takes 2# anchor slab away, completes the installation of steel beam;
Step 12: directly installing stretch-draw jack on the 1# anchor slab left, uses the tension stress of jack 10%-20% initial tensioning force, complete card temporary locking unlock and steel Shu Shunzhi degree, loose degree adjustment, then into Enter the tensioning construction stage.
Further, in step 1, the length of steel pipe is 50cm and identical as reserving hole channel internal diameter, convenient for compiling beam, So that steel beam compiles Shu Haohou, can be sent into duct.
Further, in step 1, the size of steel plate is 200cm*200cm*2cm.
Further, in step 3, when steel strand wires are bound, the binding galvanized wire coiling of use is no less than 2 circles.
Further, in step 4,4-5 layers are swathed using adhesive tape outside guiding cap, so that lashing head is in flexible shape.
Further, galvanized wire is the galvanized wire of 16#.
Further, in step 8, along steel beam length direction at interval of 5m, steel is tied in using galvanized wire and is held together, So that steel beam is integrally bonded in hoisting process.
Further, in step 9, by steel strand wires uniformly, be orderly sent into reserving hole channel.
Further, it in step 12, using 20% initial tensioning force of the tension stress of jack, completes card and faces The unlock of Shi Suoding and adjustment steel Shu Shunzhi degree, loose degree.
Control method of the present invention has the beneficial effect that
1, control method of the present invention completes single steel strand on compiling Shu Pingtai and integrally compiles beam, so that steel strand wires arrange Neatly, smoothly, binding securely, avoid Gang Jiao Xian Chan twist or turn round fried dough twist phenomenon generation.
2, control method of the present invention takes whole strand pricking technique, improves straight degree and relaxation of the steel strand wires in duct Degree, reduces stress loss of the prestressed strand in tensioning, reduces the stress-deviation between steel strand wires.
3, control method of the present invention has the advantages that the saving time, easy to operate, work efficiency is high.
4, control method of the present invention is transferred after taking double anchor slabs to add anchor ear, card locking steel strand wires using crane, both Debunching, steel strand wires gliding dislocations of the steel beam in hoisting process are prevented, in turn simplify steel beam in decentralization to the locking behind aperture Work.
5, control method of the present invention avoids the generation that steel beam falls with shifting phenomena, so that steel stranded wire penetrating adapter is determined Position is more accurate, and safely and controllably.
Specific embodiment
Below with reference to the embodiment of the present invention, technical solution of the present invention is clearly and completely described, it is clear that institute The embodiment of description is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, Those of ordinary skill in the art's every other embodiment obtained, shall fall within the protection scope of the present invention.
Embodiment 1
The control method, includes the following steps:
Step 1: select a smooth location as the platform of steel strands-woven bundle, according to the length of steel beam, on compiling Shu Pingtai Two blocks of steel plates that can be moved are set, and weld a steel pipe on the steel plate as the conduit for compiling beam, by steel plate Position adjustment, to be suitble to compile different segment length steel beam the needs of beam;
Step 2: steel strand wires are penetrated by root in the conduit for being used for steel beam top and bottom volume beam, so as in conduit outlet Steel strand wires are arranged on the steel plate at end;
Step 3: when beam is compiled in steel beam lower end, being divided into three kinds of dislocation for steel beam and place, and adjacent dislocation difference is 30cm, uses Galvanized wire binds the steel strand wires of equal length together, and the steel strand wires of long 30cm are wrapped to the steel strand wires of 30cm shorter than its, Cone-shaped is formed in the lower end of steel beam;
Step 4: it is hinged with a guiding cap in steel beam lower end, in order to which steel beam passes through duct;
Step 5: when steel Shu Shangduan compiles beam, the steel strand wires of longest beam are first mounted on to several center hole portions of 1# anchor slab Position, then vice-minister's beam of steel strand wires is faced into centre bore mounting arrangements, most short steel strand wires are finally arranged in the periphery hole site of anchor slab;
Step 6: after the completion of 1# anchor slab lashing, steel strand wires are locked on 1# anchor slab using steel strand wires card;
Step 7: it after completing the locking of upper end steel strand wires, wears 2# anchor slab again at the top of steel Shu Shangduan, then uses anchor ear by 1# Anchor slab, 2# anchor slab hoop are together;
Step 8: along steel beam length direction at interval of 4m-6m, bundling steel beam with galvanized wire, prevents steel beam adjacent in lifting Steel strand wires generate gap and displacement;
Step 9: the steel Shu Caiyong crane for completing top and bottom volume beam is sling, steel strand wires are sent into reserving hole channel simultaneously The galvanized wire every 4m-6m binding steel beam is released, until steel strand wires lower end is pierced by from duct lower end;
Step 10: when steel Shu Shangduan is suitable for reading close to duct, 1# anchor slab that steel Shu Shangduan is installed, 2# anchor slab center and reserved The alignment of duct center, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11: releasing the anchor ear for anchoring two anchor slabs, takes 2# anchor slab away, completes the installation of steel beam;
Step 12: directly installing stretch-draw jack on the 1# anchor slab left, uses the tension stress of jack 10%-20% initial tensioning force, complete card temporary locking unlock and steel Shu Shunzhi degree, loose degree adjustment, then into Enter the tensioning construction stage.
Further, in step 1, the length of steel pipe is 50cm and identical as reserving hole channel internal diameter, convenient for compiling beam, So that steel beam compiles Shu Haohou, can be sent into duct.
Further, in step 1, the size of steel plate is 200cm*200cm*2cm.
Further, in step 3, when steel strand wires are bound, the binding galvanized wire coiling of use is no less than 2 circles.
Further, in step 4,4-5 layers are swathed using adhesive tape outside guiding cap, so that lashing head is in flexible shape.
Further, galvanized wire is the galvanized wire of 16#.
Further, in step 8, along steel beam length direction at interval of 5m, steel is tied in using galvanized wire and is held together, So that steel beam integrally fits closely in hoisting process.
Further, in step 9, by steel strand wires uniformly, be orderly sent into reserving hole channel.
Further, it in step 12, using 20% initial tensioning force of the tension stress of jack, completes card and faces The unlock of Shi Suoding and adjustment steel Shu Shunzhi degree, loose degree.
Embodiment 2
Construction Gereral Situation:
It is located at humane road and Jialuhe River intersection, overall length of bridge 526.0m, the wide 55m of bridge floor in certain Chinese bridge.Wherein lead The long 190m of bridge, wide 55m, main bridge is double rope faces without dorsal funciculus single pylon cable stayed bridge, and king-tower is prestressed concrete inclined pylon, and upper king-post strut is high 60m tilts backwards 30, and cross section is single box single chamber;The high 12.5m of lower king-post strut, cross section are single box double room, and short transverse is in line Property gradual change, tower width is 4m.
The high 12.51m of king-tower lower king-post strut is divided into two sections of constructions, and first segment completes the construction of lower king-post strut pedestal, and second segment construction is surplus Remaining chamber part;Points of 10 sections constructions of king-tower, each segment with steel box girder segment synchronous construction.It is completed in king-post concreting And after reaching 100% intensity, then prestressed cable in tensioning king-tower is connect to be formed by suspension cable with steel box-girder and mutually be balanced each other Whole, therefore, king-post quality control for prestress stretching construction is to guarantee the basis of leaning tower and steel case and monolithic stability, leaning tower and steel box-girder Monolithic stability is the key that bridge construction success or failure.
The problem of being encountered in construction:
Because king-tower prestressed concrete is single box single chamber structure, chamber side wall thickness only 1m, therefore, pre-stress construction place Narrow, pulling anchor cable stage could must be that suitable space is vacateed in tensioning by handling the built-in fitting at tensioning port, and It is required that the jack using small volume just can guarantee that tensioning is normally carried out, therefore, in prestressed pore passage arrangement strand pulling machine suitable for reading Carrying out lashing operation cannot achieve.When upper tower lower section is constructed, because steel strand wires are shorter, after being sling steel strand wires using crane, manually It is sent into hole by root, and glides in the baffled blocking steel beam in duct lower part, taking the measure, not only difficulty of construction is big, but also easily Steel beam is caused to drop because of self weight, need to do over again lashing again, and there are construction quality risks;When upper midsection is constructed, take When stating method lashing, because steel Shu Zichong is larger, portion is baffled under prestress and cooperates duct top and galvanized wire or wirerope solid When determining steel beam, steel beam repeatedly occurs and crashes into phenomenon in hole, and steel beam relative position has dislocation, needs repeatedly to adjust steel beam, give Pre-stress construction causes many troubles.When prestressed cable tensioning, for eliminate steel strand wires in duct because be self-possessed it is sagging caused by Straight and slackness increases loss of prestress, also needs after carrying out single top prestretching, then carry out the tensioning of whole beam.
Solution:
Using control method of the present invention, include the following steps:
Step 1: select a smooth location as the platform of steel strands-woven bundle, according to the length of steel beam, on compiling Shu Pingtai Two blocks of steel plates that can be moved are set, and weld a steel pipe on the steel plate as the conduit for compiling beam, the size of steel plate is 200cm*200cm*2cm, the length of steel pipe are 50cm and identical as reserving hole channel internal diameter;
Step 2: steel strand wires are penetrated by root in the conduit for being used for steel beam top and bottom volume beam;
Step 3: when beam is compiled in steel beam lower end, being divided into three kinds of dislocation for steel beam and place, and adjacent dislocation difference is 30cm, uses Together by the steel strand wires binding of equal length, the binding galvanized wire coiling of use is no less than 2 circles to 16# galvanized wire, and by long 30cm's Steel strand wires wrap the steel strand wires of 30cm shorter than its, form cone-shaped in the lower end of steel beam;
Step 4: it is hinged with a guiding cap in steel beam lower end, uses adhesive tape to swathe 5 layers outside guiding cap;
Step 5: when steel Shu Shangduan compiles beam, the steel strand wires of longest beam are first mounted on to several center hole portions of 1# anchor slab Position, then vice-minister's beam of steel strand wires is faced into centre bore mounting arrangements, most short steel strand wires are finally arranged in the periphery hole site of anchor slab;
Step 6: after the completion of 1# anchor slab lashing, steel strand wires are locked on 1# anchor slab using steel strand wires card;
Step 7: it after completing the locking of upper end steel strand wires, wears 2# anchor slab again at the top of steel Shu Shangduan, then uses anchor ear by 1# Anchor slab, 2# anchor slab hoop are together;
Step 8: along steel beam length direction at interval of 5m, steel beam is bundled with 16# galvanized wire;
Step 9: the steel Shu Caiyong crane for completing top and bottom volume beam is sling, steel strand wires are sent into reserving hole channel simultaneously The 16# galvanized wire every 5m binding steel beam is released, until steel strand wires lower end is pierced by from duct lower end;
Step 10: when steel Shu Shangduan is suitable for reading close to duct, 1# anchor slab that steel Shu Shangduan is installed, 2# anchor slab center and reserved The alignment of duct center, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11: releasing the anchor ear for anchoring two anchor slabs, takes 2# anchor slab away, completes the installation of steel beam;
Step 12: directly installing stretch-draw jack on the 1# anchor slab left, uses the tension stress of jack 20% initial tensioning force completes the unlock of card temporary locking and the adjustment of steel Shu Shunzhi degree, loose degree, subsequently into answering in advance The power stretching construction stage.
The effect reached:
In the 3-10 sections of steel beam constructions of king-tower upper king-post strut, crane after anchor ear, card locking steel strand wires is added to send using double anchor slabs Anchor technique, it is therefore prevented that debunching, steel strand wires gliding dislocations of the steel beam in hoisting process, and avoid that 1-3 sections of steel Shu Yinan are being installed Temporary fixing lifting galvanized wire or wirerope when filling anchor slab and the phenomenon that cause steel beam to fall and shift so that steel stranded wire penetrating adapter Positioning is more accurate and safety, controllable, construction efficiency is obviously accelerated.
Present invention is not limited to the embodiments described above, without departing substantially from substantive content of the present invention, art technology Any deformation, improvement, the replacement that personnel are contemplated that each fall within protection scope of the present invention.

Claims (9)

1. a kind of king-post prestressed strand lifts position control method, which comprises the steps of:
Step 1: a smooth location is selected to be arranged on compiling Shu Pingtai as the platform of steel strands-woven bundle according to the length of steel beam Two blocks of steel plates that can be moved, and a steel pipe is welded on the steel plate as the conduit for compiling beam;
Step 2: steel strand wires are penetrated by root in the conduit for being used for steel beam top and bottom volume beam;
Step 3: when beam is compiled in steel beam lower end, being divided into three kinds of dislocation for steel beam and place, and adjacent dislocation difference is 30cm, using galvanized wire Together by the steel strand wires binding of equal length, and by the steel strand wires of long 30cm the steel strand wires for wrapping 30cm shorter than its, in steel The lower end of beam forms cone-shaped;
Step 4: a guiding cap is hinged in steel beam lower end;
The steel strand wires of longest beam: when steel Shu Shangduan compiles beam, being first mounted on several centre bore positions of 1# anchor slab by step 5, then Vice-minister's beam of steel strand wires is faced into centre bore mounting arrangements, most short steel strand wires are finally arranged in the periphery hole site of anchor slab;
Step 6: after the completion of 1# anchor slab lashing, steel strand wires are locked on 1# anchor slab using steel strand wires card;
Step 7: it after completing the locking of upper end steel strand wires, wears 2# anchor slab again at the top of steel Shu Shangduan, then uses anchor ear by 1# anchor Plate, 2# anchor slab hoop are together;
Step 8: along steel beam length direction at interval of 4m-6m, steel beam is bundled with galvanized wire;
Step 9: the steel Shu Caiyong crane for completing top and bottom volume beam is sling, steel strand wires are sent into reserving hole channel and are released Every the galvanized wire of 4m-6m binding steel beam, until steel strand wires lower end is pierced by from duct lower end;
Step 10: when steel Shu Shangduan is suitable for reading close to duct, 1# anchor slab, 2# anchor slab center and reserving hole channel that steel Shu Shangduan is installed Center alignment, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11: releasing the anchor ear for anchoring two anchor slabs, takes 2# anchor slab away, completes the installation of steel beam;
Step 12: stretch-draw jack directly is installed on the 1# anchor slab left, uses the 10%- of the tension stress of jack 20% initial tensioning force completes the unlock of card temporary locking and the adjustment of steel Shu Shunzhi degree, loose degree, subsequently into answering in advance The power stretching construction stage.
2. control method according to claim 1, which is characterized in that in step 1, the length of steel pipe be 50cm and It is identical as reserving hole channel internal diameter.
3. control method according to claim 1, which is characterized in that in step 1, the size of steel plate is 200cm* 200cm*2cm。
4. control method according to claim 1, which is characterized in that in step 3, when steel strand wires are bound, use is tied up It pricks galvanized wire coiling and is no less than 2 circles.
5. control method according to claim 1, which is characterized in that in step 4, twined outside guiding cap using adhesive tape Wrap up in 4-5 layers.
6. control method according to claim 1, which is characterized in that in step 8, along steel beam length direction at interval of Steel is tied in using galvanized wire and is held together by 5m.
7. according to claim 1,4,6 described in any item control methods, which is characterized in that galvanized wire is the galvanized wire of 16#.
8. control method according to claim 1, which is characterized in that in step 9, steel strand wires uniformly, are orderly sent into Reserving hole channel.
9. control method according to claim 1, which is characterized in that in step 12, answered using the tensioning of jack 20% initial tensioning force of power completes unlock and adjustment the steel Shu Shunzhi degree, loose degree of card temporary locking.
CN201710952262.1A 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method Active CN107762238B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710952262.1A CN107762238B (en) 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710952262.1A CN107762238B (en) 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method

Publications (2)

Publication Number Publication Date
CN107762238A CN107762238A (en) 2018-03-06
CN107762238B true CN107762238B (en) 2019-05-10

Family

ID=61269308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710952262.1A Active CN107762238B (en) 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method

Country Status (1)

Country Link
CN (1) CN107762238B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518977B (en) * 2018-12-26 2024-01-30 中国核工业二四建设有限公司 Anti-slip device and method for inverted U-shaped prestress steel strand

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009057713A (en) * 2007-08-30 2009-03-19 Kyushu Electric Power Co Inc Wind power generation hybrid tower, and its construction method
CN101798874A (en) * 2010-03-08 2010-08-11 东南大学 Pre-stress construction method of parallel steel stranded wire assembled cable in annular sealed steel pipe
CN203613812U (en) * 2013-11-29 2014-05-28 甘肃路桥建设集团有限公司 Pre-stressed steel strand blanking and binding rack
CN204919354U (en) * 2015-08-17 2015-12-30 北京奇力建通工程技术有限公司 A construction equipment that is arranged in construction of taking one's place of cable -stay bridge cable wire
CN105672138A (en) * 2016-03-31 2016-06-15 中铁四局集团第一工程有限公司 Through type stayed cable installation circulation system and cable threading construction method thereof
CN106948263A (en) * 2017-05-10 2017-07-14 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009057713A (en) * 2007-08-30 2009-03-19 Kyushu Electric Power Co Inc Wind power generation hybrid tower, and its construction method
CN101798874A (en) * 2010-03-08 2010-08-11 东南大学 Pre-stress construction method of parallel steel stranded wire assembled cable in annular sealed steel pipe
CN203613812U (en) * 2013-11-29 2014-05-28 甘肃路桥建设集团有限公司 Pre-stressed steel strand blanking and binding rack
CN204919354U (en) * 2015-08-17 2015-12-30 北京奇力建通工程技术有限公司 A construction equipment that is arranged in construction of taking one's place of cable -stay bridge cable wire
CN105672138A (en) * 2016-03-31 2016-06-15 中铁四局集团第一工程有限公司 Through type stayed cable installation circulation system and cable threading construction method thereof
CN106948263A (en) * 2017-05-10 2017-07-14 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate

Also Published As

Publication number Publication date
CN107762238A (en) 2018-03-06

Similar Documents

Publication Publication Date Title
CN101597960B (en) Large-tonnage jack tension construction technology for non-bonded prestressed silo
WO2018006558A1 (en) Confined high-strength concrete support system applicable to underground tunnel
CN203377546U (en) High speed railway spanning construction apparatus
CN108570935A (en) Bent cap, box beam, plate-beam construction method in bridges in highway engineering
CN110804952B (en) Suspension bridge beam prefabrication and assembly construction process
CN102354926A (en) Large-section conductor tension stringing construction method
CN109750791B (en) Assembled large cantilever steel structure
CN102290742A (en) Tension stringing construction technology
CN208668765U (en) Precast prestressed beam and assembled composite frame structure
CN101705660B (en) Reaction frame prestress anchoring system and method for vertical rotating steel pipe arch on concrete bridge
CN111907378A (en) Passenger-cargo collinear carrier cable and contact line synchronous replacement construction process
CN108457422A (en) Precast prestressed beam, assembled composite frame structure and its installation method
CN107762238B (en) A kind of king-post prestressed strand lifting position control method
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN113756201A (en) T-structure continuous beam prestressed steel strand pulling method and pulling device thereof
CN112554067A (en) Method for constructing bracket-free tied arch by means of arch first and beam second
CN106087759A (en) A kind of prestressed strand threader and the threading method of prestressed strand
CN210714046U (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN208934432U (en) It is a kind of circle concrete tube chamber structure without support prestressed reinforcement equipment
CN110777667A (en) Hoisting method for preventing deformation of steel pipe arch
CN110541599A (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN210458987U (en) Soft temporary pocket hoisting device is changed to jib
CN201260052Y (en) On-tower hydraulic line tightening system
CN207452739U (en) A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system
CN205975368U (en) Prestressed steel beam threading device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant