CN207452739U - A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system - Google Patents

A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system Download PDF

Info

Publication number
CN207452739U
CN207452739U CN201721559527.3U CN201721559527U CN207452739U CN 207452739 U CN207452739 U CN 207452739U CN 201721559527 U CN201721559527 U CN 201721559527U CN 207452739 U CN207452739 U CN 207452739U
Authority
CN
China
Prior art keywords
ring
steel strand
strand wires
anchor
mid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721559527.3U
Other languages
Chinese (zh)
Inventor
肖军良
阮坤
张波
谢井丽
任家栋
曾令华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Road and Bridge Corp
CCCC Second Highway Engineering Co Ltd
Original Assignee
China Road and Bridge Corp
CCCC Second Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Road and Bridge Corp, CCCC Second Highway Engineering Co Ltd filed Critical China Road and Bridge Corp
Application granted granted Critical
Publication of CN207452739U publication Critical patent/CN207452739U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system, it is characterised in that:Including the steel strand wires (1) being embedded in described two beam sections of mid-span closure segment and the ring shape anchorage (2) for connecting the steel strand wires (1) one end jointly, the ordinary connector anchorage (3) for fixing the steel strand wires (1) other end;Wherein, the ring shape anchorage (2) includes a ring anchor body (21), be provided with penetrating anchor hole (22) on ring anchor body (21), it is described be anchored twocouese in hole (22) and wear connect the steel strand wires (1);The ring shape anchorage (2) is movably placed in a ring anchor stretching notch (4).The utility model connects steel strand wires using two-way ring anchor, implements two dimension prestressing, reduces construction risk, reduce the risk of prestressed failure, improve the durability of structure.

Description

A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system
Technical field
The utility model is related to a kind of cable-stayed bridge prestressed Construction Technologies, and in particular to a kind of cable-stayed bridge beams of concrete mid-span Closure segment pre-stress system.
Background technology
The prestressed application of beams of concrete, in the latter stage fifties, China is for the first time using bar reinforcement electrothermal way to circular reservoir (tank) applies prestressing force;The mid-1960s start using wrapping wire prestressing force, with the appearance of the round buildings such as large silo, around Silk prestressing force has been difficult to meet the requirements.China's Zhujiang Cement life clinker warehouse successfully uses large-tonnage steel strand bundle for the first time.Later, Have to bond and be widely used in silo, cistern, sewage digesting pool, nuclear plant safety with soap-free emulsion polymeization annular post-tensioned pre-stressed technology In the unique constructions such as shell, television tower.
For cable-stayed bridge, with progress of the epoch, a series of higher rachis face cable-stayed bridge of quality index is had devised, Rachis face cable-stayed bridge generally use concrete box girder is as girder, and concrete box girder is in addition to bearing bending stress, it is also necessary to Bear the pulling force from suspension cable.The longitudinal prestressing that cable-stayed bridge needs is big, and end bay closure segment and mid-span closure segment generally use Steel strand wires apply prestressing force and close up, and ordinary connector connection may be employed in closure segment prestressing force, and mid-span closure segment is generally adopted at present With prestress anchoraging mode is applied on tooth plate, construction is complicated, and quality is difficult to control.In addition, existing anchorage style is all one As be all single-ended or both ends tensioning in steel strand wires, the beam at both ends can not be tied down simultaneously with same anchorage, leaned in opposite directions Hold together.
Utility model content
For this purpose, the utility model puts forth effort on the deficiency for solving the above-mentioned prior art, provide in a kind of cable-stayed bridge beams of concrete Across closure segment pre-stress system can reduce the risk of beam body cracking and prestressed failure using the pre-stress system, improve beam Body structure durability.
Technical solution adopted in the utility model is as follows:A kind of cable-stayed bridge beams of concrete mid-span closure segment prestressing force system System, it is characterised in that:It is including the steel strand wires being embedded in described two beam sections of mid-span closure segment and described for connecting jointly The ring shape anchorage of steel strand wires one end, the ordinary connector anchorage for fixing the steel strand wires other end;
Wherein, the ring shape anchorage includes a ring anchor body, and penetrating anchor hole, the anchor are provided on ring anchor body It connects twocouese in hole and wears and connect the steel strand wires;
The ring shape anchorage is movably placed in a ring anchor stretching notch.
Preferably, the bellmouth for being anchored hole and being made of one section of straight hole section and one section of taper hole section, and in the ring anchor Twocouese opens up on body.
The anchor hole in all directions, around the center symmetric setting of the ring anchor body.
The anchor hole number in all directions is consistent.
Preferably, the ring anchor stretching notch surrounds a square groove, upper opening by steel plate, and the ring shape anchorage activity is put In the square groove;Reinforced steel bar ring is welded on the surrounding outer wall of the square groove;The square groove is reserved upwards in steel strand wires connection side There is threading hole, steel strand wires confinement ring is welded in threading outer end of hole.
The ring anchor stretching notch is embedded in any one of described two beam sections of mid-span closure segment.
Preferably, when there is multigroup mid-span closure segment side by side, the ring anchor stretching notch is disposed alternately at each mid-span and closes up In the beam section of section.
The utility model uses ring anchor prestress anchoraging mode in prestressed concrete cable-stayed bridge construction, instead of tradition Closure segment tooth plate anchorage style, reduce beam body cracking and prestressed failure risk, improve girder construction durability.It avoids The construction of tooth block and the processing of tooth block abnormal formwork, reduce difficulty of construction.Tensioning is easy, directly can carry out tensioning work in bridge floor Make, reduce the operation difficulty and construction risk in beam bottom application work.
Description of the drawings
Fig. 1 is layout drawing of the steel strand prestress system provided by the utility model in cable-stayed bridge main-beam mid-span closure segment;
Fig. 2 is that schematic diagram is seen in the side of ring shape anchorage;
Fig. 3 is the A-A sectional views in Fig. 2;
Fig. 4 is ring anchor stretching notch, ring shape anchorage, the scheme of installation of steel strand wires;
Fig. 5 is the schematic top plan view of ring anchor stretching notch;
Fig. 6 is the schematic side view of ring anchor stretching notch.
Specific embodiment
The utility model is described in detail with reference to the accompanying drawings and examples.
Cable-stayed bridge beams of concrete mid-span closure segment pre-stress system provided by the utility model, it is pre- suitable for beams of concrete It buries steel strand wires and applies prestressed situation, entire pre-stress system includes steel strand wires pre-buried in mid-span closure segment and for leading The anchorage of drawing steel stranded wire.
As shown in Figure 1, in the 1# beam sections and 2# beam sections of mid-span closure segment, steel strand wires 1, two sections of steel strand wires 1 are all embedded with This one end to connect is connected by a special ring shape anchorage 2, and the one end being away from each other is each via an ordinary connector anchor Tool 3 is connected on end bay beam.
A kind of special new ring shape anchorage 2 of the utility model, as shown in Figure 2 and Figure 3, ring shape anchorage 2 include a ring anchor body 21, it is provided on ring anchor body 21 and is anchored hole 22, the whole thickness side for being anchored hole 22 and running through the ring anchor body 21 To.
The bellmouth that hole 22 can be made of one section of straight hole section 221 and one section of taper hole section 222 is anchored, it further, can Being anchored hole both ends, technique reaming 223 is set.Straight hole section 221 and 222 natural sparse model of taper hole section, the taper of taper hole section 222 is 1: 10~1:30, preferably 1:20, small end is connected in straight hole section 221.In general, entirely it is being anchored on hole length, 221 He of straight hole section Taper hole section 222 about respectively accounts for half length or taper hole section is less than straight hole section.
It can also be an isodiametric cylindrical hole to be anchored hole 22.
This ring shape anchorage provided by the utility model, feature are exactly the ring anchor anchor in prestress wire anchor Connection of the tool available for two-way steel strand wires, so it is penetrating on ring anchor body 21 to be anchored hole 22, opening direction is also both sides To, i.e., steel strand wires can both be penetrated from the front of ring anchor, can also be penetrated from the back side of ring anchor (front, the back side refer both to thickness Direction), the steel strand wires of both direction mutually can draw close two closure segments by the prestressing force of active force application each other.So for ring anchor On anchor hole 22, should have twocouese arrangement, wherein taper hole section 222 should be opened in the steel strand wires traversing through end on anchorage, be pierced by End, taper hole section 222 is gradual reaming shape, until end face.
Twocouese can set multiple anchor holes 22 on ring anchor body 21, such as in one embodiment, can set two-way 8 Hole is anchored as a, unidirectional 4.It is preferred that the anchor hole number of twocouese is preferably consistent, also, the anchor in each direction Connecing hole will be centrosymmetrically arranged compared with ring anchor body 21.
For the blowing angle in hole 22 is anchored, the axis for being anchored hole 22 can be with the center of 21 thickness direction of ring anchor body Line is parallel (be known as parallel hole), can also (being known as oblique hole) angled with the center line of 21 thickness direction of ring anchor body, The anchor hole of twocouese both can be oblique hole simultaneously, can also be parallel hole simultaneously, can be oblique hole with a direction, another Direction is parallel hole, as long as both direction is non-interference in tensioning phase.
Unidirectional anchor hole will be symmetrically distributed on the ring anchor body 21 as far as possible, the inclined direction including oblique hole Also it is symmetrical, it could so cause ring anchor body uniform force, the pulling force of each steel strand wires could uniformly.
It further, can be in the end face a of steel strand wires traversing through end (this one end for having bellmouth) for slanting anchor hole On, a gradient is repaired, makes the central axis on the inclined-plane and slanting anchor hole, it is therefore an objective to ensure the axial symmetry of bellmouth itself Property, in order to install steel strand wires ring folder.
Elastic ring folder can also be set for clamping steel strand wires by being anchored in hole;In the end in hole installation can also be set to press Head.
Due to realize two-way steel strand wires prestress application, so the utility model uses the ring shape anchorage in cable-stayed bridge master In beam mid-span closure segment pre-stress construction, ring anchor is not fixed, and with prestressed application, ring anchor can move, so must Ring anchor stretching notch 4 must be set to provide the ionized space, while protection ring anchor.It is also that this practicality is new to set ring anchor stretching notch 4 One feature of type.
Ring anchor stretching notch 4 is embedded in can in which section of mid-span closure segment.Further, for being arranged side by side The situation of multigroup closure segment is preferably arranged alternately ring anchor stretching notch 4 on each group closure segment, as shown in Figure 1, the 1st group of ring Anchor stretching notch can be arranged in 1# beam sections, and the 2nd group of ring anchor stretching notch should be then arranged in 2# beam sections, the 3rd group of ring anchor Stretching notch is arranged on again in 1# beam sections, and so on, it can so ensure that the steel strand wires tie point of entire middle bridge is in not Same section meets girder construction design requirement.
Ring anchor stretching notch 4 and steel strand wires 1, the link position relation of ring shape anchorage 2 are as shown in figure 4, self structure such as figure 5th, shown in Fig. 6, ring anchor stretching notch 4 is made of steel plate, and size needs are determined according to ring anchor size and ring anchor amount of movement.Ring anchor Stretching notch 4 surrounds a square groove 41 (square or rectangular all right) by four steel plates, is used to accommodate ring shape anchorage 2 in slot;Square groove 41 Surrounding outer wall on weld several reinforced steel bar rings 42, for strengthening bonding strength in concrete, prevent notch from deforming;Square groove 41 are reserved with threading hole upwards in steel strand wires connection side, and confinement ring 43 (as shown in Figure 4), steel strand wires are welded in threading outer end of hole 1 enters from outside through confinement ring 43 and threading hole in notch, is connected with anchorage.
Pre-buried ring anchor stretching notch 4, the ring shape anchorage 2 for putting on steel strand wires are placed in ring anchor in beams of concrete beam body during construction In stretching notch 4,2 twocouese of ring shape anchorage connection steel strand wires 1, the steel strand wires one end in each direction is connected on ring shape anchorage 2, The other end is pierced by ring anchor stretching notch and is connected in the beam body poured;Then no matter draw either party to steel strand wires, all The beam body at both ends can be made mutually to draw close.
The utility model is special to be used for cable-stayed bridge mid-span closure segment beams of concrete prestress system, and construction technology main points are as follows:
1st, pre-buried ring anchor stretching notch.The first pre-buried ring anchor stretching notch as described above before prestressed girder pours.
2nd, prestressed pipeline.Prestress pipe is engaged in the confinement ring on the outside of ring anchor stretching notch, prestressed pipe Road installation is conventionally constructed, and does not do excessive limitation herein.
3rd, middle bridge closure segment is poured.Middle two beam section of bridge is all poured into a mould into concrete formation, wherein reserving ring anchor tensioning The position of notch and the position of prestress pipe not pour into a mould.Notch is clogged with geotextiles during casting beams section concrete, is prevented Concrete blocks notch.
4th, steel strand wires and anchorage installation.It is two-way on ring shape anchorage to wear steel strand wires, it can be using a direction steel strand wires as anchor Fixed end steel strand wires (do not do tensioning work), and other direction steel strand wires are as stretching end steel strand wires (doing tensioning work), anchored end steel For twisted wire according to design length blanking, stretching end steel strand wires need additional increase tensioning active length.
During construction, first in the fixed beam on the outside of closure segment beam, steel strand wires are anchored with ordinary connector anchorage, then by steel Twisted wire is pierced into from prestress pipe in ring anchor stretching notch;Stretching end and anchored end steel strand wires are all worn into ring anchor stretching notch It crosses on ring shape anchorage, stretching end steel strand wires and anchored end steel strand wires are walked in opposite directions on ring shape anchorage, are pierced into respectively corresponding It is anchored in hole;Then the ring anchor for putting on steel strand wires is positioned in ring anchor stretching notch.
Ring shape anchorage installation site can increase certain surplus capacity (see Fig. 4) further along according to the anchorage amount of movement L estimated, rich Surplus is substantially met by 10cm or so consideration, about 10-15cm.Ring anchor measurement amount of movement theoretically can be considered fixing end steel strand wires Elongation, steel strand wires elongation can be checked by measuring ring anchor amount of movement.
5th, tensioning.After stretching end steel strand wires are pierced by ring anchor, tensioner is sequentially passed through, force can tense steel strand wires. It is that stretching force and elongation are double using the steel strand tension on the basis of ring shape anchorage provided by the utility model using dual control technique Control, wherein elongation need control anchored end steel strand wires elongation (Lm), also for anchorage amount of movement (intermediate plate indent due to It is smaller negligible);Additionally need control stretching end steel strand wires elongation (Lz).The elongation (Lm) of anchored end steel strand wires can lead to The amount of movement for crossing directly measurement anchorage is recorded and calculated, and stretching end steel strand wires elongation (Lz) can be by measuring indirectly The overhangs (Ld) of very heavy top steel strand wires calculates, and above-mentioned several amounts are calculated by following expression:
Ld=Lm+Lz
According to theoretical elongation calculation formula, elongation and stretching force per beam steel strand wires are linear relationship.It may be employed Linear regression analysis carries out elongation statistical analysis, and calculates actual elongation by equation of linear regression.

Claims (7)

1. a kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system, it is characterised in that:It is closed including being embedded in the mid-span The steel strand wires (1) that hold together in two beam sections of section and for connecting the ring shape anchorage (2) of the steel strand wires (1) one end jointly, being used for The ordinary connector anchorage (3) of fixed steel strand wires (1) other end;
Wherein, the ring shape anchorage (2) includes a ring anchor body (21), and penetrating anchor hole is provided on ring anchor body (21) (22), twocouese is worn and connects the steel strand wires (1) in anchor hole (22);
The ring shape anchorage (2) is movably placed in a ring anchor stretching notch (4).
2. cable-stayed bridge beams of concrete mid-span closure segment pre-stress system according to claim 1, it is characterised in that:The anchor The bellmouth that hole (22) is made of one section of straight hole section (221) and one section of taper hole section (222) is connect, and in the ring anchor body (21) Upper twocouese opens up.
3. cable-stayed bridge beams of concrete mid-span closure segment pre-stress system according to claim 1 or 2, it is characterised in that:Respectively The anchor hole (22) on direction, around the center symmetric setting of the ring anchor body (21).
4. cable-stayed bridge beams of concrete mid-span closure segment pre-stress system according to claim 1 or 2, it is characterised in that:Respectively Anchor hole (22) quantity on direction is consistent.
5. cable-stayed bridge beams of concrete mid-span closure segment pre-stress system according to claim 1, it is characterised in that:The ring Anchor stretching notch (4) surrounds a square groove, upper opening by steel plate, and the ring shape anchorage (2) is movably placed in the square groove;Institute It states and is welded with reinforced steel bar ring on the surrounding outer wall of square groove;The square groove is reserved with threading hole upwards in steel strand wires connection side, is threading Outer end of hole is welded with steel strand wires confinement ring.
6. cable-stayed bridge beams of concrete mid-span closure segment pre-stress system according to claim 1 or 5, it is characterised in that:Institute Ring anchor stretching notch (4) is stated to be embedded in any one of described two beam sections of mid-span closure segment.
7. cable-stayed bridge beams of concrete mid-span closure segment pre-stress system according to claim 6, it is characterised in that:When side by side When having multigroup mid-span closure segment, the ring anchor stretching notch (4) is disposed alternately in the beam section of each mid-span closure segment.
CN201721559527.3U 2017-10-01 2017-11-21 A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system Active CN207452739U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710924553 2017-10-01
CN201710924553X 2017-10-01

Publications (1)

Publication Number Publication Date
CN207452739U true CN207452739U (en) 2018-06-05

Family

ID=61929370

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201711162764.0A Active CN107938517B (en) 2017-10-01 2017-11-21 A kind of cable-stayed bridge prestressed concrete beam ring anchor construction method
CN201721559527.3U Active CN207452739U (en) 2017-10-01 2017-11-21 A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201711162764.0A Active CN107938517B (en) 2017-10-01 2017-11-21 A kind of cable-stayed bridge prestressed concrete beam ring anchor construction method

Country Status (1)

Country Link
CN (2) CN107938517B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523093A (en) * 2020-11-24 2021-03-19 中铁大桥局集团有限公司 Prestressed lengthening device and method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201165726Y (en) * 2008-01-11 2008-12-17 河南红桥锚机有限公司 Ring anchor
KR101387595B1 (en) * 2012-11-29 2014-04-23 지에스건설 주식회사 Tention typed multi-span cable-stayed bridge construction method using hybrid decksegment
CN103882812B (en) * 2014-04-03 2016-01-20 重庆建工桥梁工程有限责任公司 Across the construction method of girder in stayed-cable bridge
CN104775365B (en) * 2015-02-28 2017-04-05 张跃平 A kind of construction method of cable-stayed bridge
CN106351128B (en) * 2016-11-28 2019-04-09 中交路桥华南工程有限公司 The construction method of cable-stayed bridge end bay girder

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523093A (en) * 2020-11-24 2021-03-19 中铁大桥局集团有限公司 Prestressed lengthening device and method
CN112523093B (en) * 2020-11-24 2022-03-18 中铁大桥局集团有限公司 Prestressed lengthening device and method

Also Published As

Publication number Publication date
CN107938517A (en) 2018-04-20
CN107938517B (en) 2019-09-24

Similar Documents

Publication Publication Date Title
CN101982629B (en) Assembly-type self-compaction steel tube and concrete composite structure
CN206109970U (en) Prefabricated assembled pier suitable for well meizoseismal area
CN101787733A (en) Prefabricated vertical member
CN101560772B (en) Prestressed grid anchorage technology for side slope governance
CN109057148A (en) Ultra-high performance concrete is without regular reinforcement Prestressed U type beam and its construction method
CN108678225A (en) The built-in steel plate combined shear wall of built-in presstressed reinforcing steel steel pipe concrete frame and the practice
CN201133085Y (en) Structure for enhancing external prestressing force effect
CN113638304A (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN207452739U (en) A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system
CN107034785A (en) Rope construction method is changed in a kind of interchangeable anchorage prestress anchoraging device and its installation
CN102808371B (en) The integral precast overlapping Continuous Bridge of a kind of simple-supported thencontinuous and construction method
CN1978802A (en) Super-length prestressed ground beam construction method
CN207793884U (en) The steel frame construction of Sarasota upper king-post strut
CN106087692A (en) A kind of Simply supported non-uniform T negative moment of girder section structure and construction method
CN109457608A (en) A kind of construction method of prefabricated steel reinforced concrete combined bridge deck
CN219410510U (en) Steel-ultra-high performance concrete composite structure
CN102808372B (en) The integral precast overlapping bridge of a kind of freely-supported and construction method
CN104652430A (en) Composite reinforcement partially prestressed concrete solid square pile and manufacturing method thereof
CN111519530A (en) Pier head type tunnel anchor and construction method
CN209580015U (en) A kind of fiber grating post-tensioned prestressing tensioning Precise control device
CN208362941U (en) One kind reinforcing the old hollow slab bridge construction of single hole by real abdomen Bars In Poured Concrete Slab
CN216108007U (en) Concrete beam type bridge and cast-in-situ hidden cover beam thereof
CN214423122U (en) Combined type suspender structure of tied-rod arch bridge
CN106087881B (en) A kind of precast concrete box-structure and cast-in-place concrete convolution Sluice Pier structure and its construction technology
CN111719407B (en) Stay cable and concrete bridge tower anchoring structure of pre-buried steel plate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant