CN107762238A - A kind of king-post prestressed strand lifts position control method - Google Patents

A kind of king-post prestressed strand lifts position control method Download PDF

Info

Publication number
CN107762238A
CN107762238A CN201710952262.1A CN201710952262A CN107762238A CN 107762238 A CN107762238 A CN 107762238A CN 201710952262 A CN201710952262 A CN 201710952262A CN 107762238 A CN107762238 A CN 107762238A
Authority
CN
China
Prior art keywords
steel
strand wires
anchor
steel strand
shu
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710952262.1A
Other languages
Chinese (zh)
Other versions
CN107762238B (en
Inventor
陈敦刚
席军现
李廷钰
高建斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201710952262.1A priority Critical patent/CN107762238B/en
Publication of CN107762238A publication Critical patent/CN107762238A/en
Application granted granted Critical
Publication of CN107762238B publication Critical patent/CN107762238B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/16Prestressed structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/121Construction of stressing jacks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/341Arrangements for casting in situ concrete towers or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of king-post prestressed strand to lift position control method, comprises the following steps:Shu Pingtai is compiled in selection, and according to the length of steel beam, the conduit for compiling beam is set on Shu Pingtai is compiled;Steel strand wires are penetrated in conduit by root;Beam is compiled to steel beam lower end;Beam is compiled to steel Shu Shangduan again, and 1# anchor slabs are installed, steel strand wires are locked on 1# anchor slabs using steel strand wires card;2# anchor slabs are worn again in steel bunchy top portion, using anchor ear by 1#, 2# anchor slab banding;Steel strand wires are sent into reserving hole channel;The anchor ear for anchoring two anchor slabs is released, takes 2# anchor slabs away, completes the installation of steel beam;Stretch-draw jack is installed on the 1# anchor slabs left, use 10% 20% initial tensioning forces of tension stress, complete unblock and adjustment steel Shu Shunzhi degree, the loose degree of card temporary locking, subsequently into the tensioning construction stage, the present invention has the advantages of simple to operate, saving time, operating efficiency is high.

Description

A kind of king-post prestressed strand lifts position control method
Technical field
The invention belongs to king-post pre-stress construction field, and in particular to a kind of king-post prestressed strand lifts location control side Method.
Background technology
Prestressing force is in order to improve structure military service performance, in the precharge pressure that construction period is previously applied to structure, structure Tension caused by precharge pressure can completely or partially offset load during one's term of military service, avoids structure from destroying.It is usually used in concrete knot Structure.Prestressed reinforced concrete construction, it is before structure bearing load, pressure is applied to it in advance, makes it in outer load action Concrete in tension zone internal force produce compression, to offset or reduce tension caused by external load, structure is normally made Do not produce crack in the case of or split must be than later.
At present, large-sized prestress king-post steel strand wires because joint length it is big, lashing is mostly carried out using special strand pulling machine, led to Cross strand pulling machine machine driving, roller clamping steel strand wires are transmitted, i.e., drive double driving wheels to rotate using reductor, steel hinge line from The insertion of one end incoming line, driving wheel, which with double driven pulleys is pushed down steel hinge line and moved forward along conduit, penetrates reserving hole channel, until from hole The road other end passes the size for reaching tensioning needs.When king-post takes subsection tension size shorter, also matched somebody with somebody sometimes using crane After closing hanging object snap ring locking steel strand wires, steel strand wires bunchy is sling into cooperation steel strand wires are slowly manually sent into reserving hole channel, until Steel strand wires pass from duct lower end, then first steel beam lower end is baffled, steel strand wires are consolidated using 8# galvanized wires or steel wire rope in upper end It is fixed, then galvanized wire or steel wire rope are released, after installation anchor slab makes jack and possesses the ability for locking steel beam, release the gear of steel beam lower end Plate, steel beam lower end anchor slab and jack are installed, complete the preparation before the lashing and tensioning of steel strand wires.
However, when pre-stress construction place is narrow, pulling anchor cable stage must be by carrying out to the built-in fitting at tensioning port Processing, could be that suitable space is vacateed in tensioning, and require just to can guarantee that tensioning is normally carried out using the jack of small volume, Therefore, carrying out lashing operation in prestressed pore passage arrangement strand pulling machine suitable for reading can not realize.If steel strand wires are sling using crane Afterwards, manually it is sent into hole by root, and is glided in the baffled stop steel beam in duct bottom, taking the measure, not only difficulty of construction is big, And easily cause steel beam to be dropped because of deadweight, need to do over again lashing again, and construction quality risk be present, and steel Shu Zichong compared with Greatly, portion is baffled under prestress and when coordinating duct top and galvanized wire or steel wire rope fixation steel beam, steel beam easily occurs and crashes into Phenomenon in hole, and steel beam relative position produces dislocation, it is necessary to repeatedly adjust steel beam, and many troubles are caused to pre-stress construction, In addition, during prestressed cable tensioning, increased to eliminate steel strand wires straight and slackness caused by internal cause deadweight in duct is sagging Loss of prestress, also need after carrying out single top prestretching, then carry out the tensioning of whole beam, construction is complicated time-consuming.
The content of the invention
In view of the shortcomings of the prior art, it is an object of the invention to provide a kind of king-post prestressed strand to lift location control side Method, the control method, comprises the following steps:
Step 1:Platform of the smooth location as steel strands-woven bundle is selected, according to the length of steel beam, on Shu Pingtai is compiled Two blocks of steel plates that can be moved are set, and a steel pipe is welded as the conduit for compiling beam on steel plate, by steel plate Position adjustment, to be adapted to compile different segment length steel beam the needs of beam;
Step 2:Steel strand wires are penetrated in the conduit that beam is compiled for steel beam top and bottom by root, so as in conduit outlet Steel strand wires are arranged on the steel plate at end;
Step 3:When compiling beam in steel beam lower end, steel beam is divided into three kinds of dislocation and placed, adjacent dislocation difference is 30cm, is used The steel strand wires colligation of equal length together, and long 30cm steel strand wires is wrapped 30cm shorter than its steel strand wires by galvanized wire, Cone-shaped is formed in the bottom of steel beam;
Step 4:A guiding cap is hinged with steel beam lower end, in order to which steel beam passes through duct;
Step 5:When steel Shu Shangduan compiles beam, the steel strand wires of most long beam are first arranged on to several center hole portions of 1# anchor slabs Position, then vice-minister's beam of steel strand wires is faced into centre bore installation beam arrangement, most short steel strand wires are finally arranged in the periphery hole position of anchor slab Put;
Step 6:After the completion of 1# anchor slab lashings, steel strand wires are locked on 1# anchor slabs using steel strand wires card;
Step 7:After completing the locking of upper end steel strand wires, 2# anchor slabs are worn again at the top of steel Shu Shangduan, then using anchor ear by 1# Anchor slab, 2# anchor slabs hoop are together;
Step 8:Along steel beam length direction at interval of 4m-6m, steel beam is bundled with galvanized wire, prevents that steel beam is adjacent in lifting Steel strand wires produce gap and displacement;
Step 9:The steel Shu Caiyong cranes for completing top and bottom volume beam are sling, steel strand wires are sent into reserving hole channel simultaneously The galvanized wire every 4m-6m colligation steel beams is released, until steel strand wires lower end passes from duct lower end;
Step 10:Steel Shu Shangduan close to duct it is suitable for reading when, 1# anchor slabs that steel Shu Shangduan is installed, 2# anchor slabs center with it is reserved Duct center alignment, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11:The anchor ear for anchoring two anchor slabs is released, takes 2# anchor slabs away, completes the installation of steel beam;
Step 12:Directly stretch-draw jack is installed on the 1# anchor slabs left, uses the tension stress of jack 10%-20% initial tensioning forces, complete the unblock of card temporary locking and the adjustment of steel Shu Shunzhi degree, loose degree, Ran Houjin Enter the tensioning construction stage.
Further, in step 1, the length of steel pipe is 50cm and identical with reserving hole channel internal diameter, is easy to compile beam, So that steel beam compiles Shu Haohou, can be sent into duct.
Further, in step 1, the size of steel plate is 200cm*200cm*2cm.
Further, in step 3, during steel strand wires colligation, the colligation galvanized wire coiling of use is no less than 2 circles.
Further, in step 4,4-5 layers are swathed using adhesive tape outside guiding cap, so that lashing head is in flexible shape.
Further, galvanized wire is 16# galvanized wire.
Further, in step 8, along steel beam length direction at interval of 5m, steel is tied in using galvanized wire and is held together, So that steel beam is integrally bonded in hoisting process.
Further, in step 9, by steel strand wires uniformly, be sent into reserving hole channel in order.
Further, in step 12, using 20% initial tensioning force of the tension stress of jack, complete card and face Shi Suoding unblock and adjustment steel Shu Shunzhi degree, loose degree.
Control method of the present invention has the beneficial effect that:
1st, control method of the present invention completes single steel strand on Shu Pingtai is compiled and integrally compiles beam so that steel strand wires arrange Neatly, smooth-going, colligation are firm, avoid the generation that Gang Jiao Xian Chan are twisted or turned round fried dough twist phenomenon.
2nd, control method of the present invention takes whole strand pricking technique, improves straight degree and relaxation of the steel strand wires in duct Degree, reduces stress loss of the prestressed strand in tensioning, reduces the stress-deviation between steel strand wires.
3rd, control method of the present invention has the advantages of saving time, simple to operate, operating efficiency is high.
4th, control method of the present invention takes double anchor slabs to be transferred after adding anchor ear, card locking steel strand wires using crane, both Debunching, steel strand wires gliding dislocations of the steel beam in hoisting process are prevented, in turn simplify steel beam in decentralization to the locking behind aperture Work.
5th, control method of the present invention avoids the generation that steel beam falls with shifting phenomena so that steel stranded wire penetrating adapter is determined Position is more accurate, and safely and controllably.
Embodiment
With reference to embodiments of the invention, technical scheme is clearly and completely described, it is clear that institute The embodiment of description is only part of the embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, The every other embodiment that those of ordinary skill in the art are obtained, belongs to the scope of protection of the invention.
Embodiment 1
The control method, comprises the following steps:
Step 1:Platform of the smooth location as steel strands-woven bundle is selected, according to the length of steel beam, on Shu Pingtai is compiled Two blocks of steel plates that can be moved are set, and a steel pipe is welded as the conduit for compiling beam on steel plate, by steel plate Position adjustment, to be adapted to compile different segment length steel beam the needs of beam;
Step 2:Steel strand wires are penetrated in the conduit that beam is compiled for steel beam top and bottom by root, so as in conduit outlet Steel strand wires are arranged on the steel plate at end;
Step 3:When compiling beam in steel beam lower end, steel beam is divided into three kinds of dislocation and placed, adjacent dislocation difference is 30cm, is used The steel strand wires colligation of equal length together, and long 30cm steel strand wires is wrapped 30cm shorter than its steel strand wires by galvanized wire, Cone-shaped is formed in the bottom of steel beam;
Step 4:A guiding cap is hinged with steel beam lower end, in order to which steel beam passes through duct;
Step 5:When steel Shu Shangduan compiles beam, the steel strand wires of most long beam are first arranged on to several center hole portions of 1# anchor slabs Position, then vice-minister's beam of steel strand wires is faced into centre bore installation beam arrangement, most short steel strand wires are finally arranged in the periphery hole position of anchor slab Put;
Step 6:After the completion of 1# anchor slab lashings, steel strand wires are locked on 1# anchor slabs using steel strand wires card;
Step 7:After completing the locking of upper end steel strand wires, 2# anchor slabs are worn again at the top of steel Shu Shangduan, then using anchor ear by 1# Anchor slab, 2# anchor slabs hoop are together;
Step 8:Along steel beam length direction at interval of 4m-6m, steel beam is bundled with galvanized wire, prevents that steel beam is adjacent in lifting Steel strand wires produce gap and displacement;
Step 9:The steel Shu Caiyong cranes for completing top and bottom volume beam are sling, steel strand wires are sent into reserving hole channel simultaneously The galvanized wire every 4m-6m colligation steel beams is released, until steel strand wires lower end passes from duct lower end;
Step 10:Steel Shu Shangduan close to duct it is suitable for reading when, 1# anchor slabs that steel Shu Shangduan is installed, 2# anchor slabs center with it is reserved Duct center alignment, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11:The anchor ear for anchoring two anchor slabs is released, takes 2# anchor slabs away, completes the installation of steel beam;
Step 12:Directly stretch-draw jack is installed on the 1# anchor slabs left, uses the tension stress of jack 10%-20% initial tensioning forces, complete the unblock of card temporary locking and the adjustment of steel Shu Shunzhi degree, loose degree, Ran Houjin Enter the tensioning construction stage.
Further, in step 1, the length of steel pipe is 50cm and identical with reserving hole channel internal diameter, is easy to compile beam, So that steel beam compiles Shu Haohou, can be sent into duct.
Further, in step 1, the size of steel plate is 200cm*200cm*2cm.
Further, in step 3, during steel strand wires colligation, the colligation galvanized wire coiling of use is no less than 2 circles.
Further, in step 4,4-5 layers are swathed using adhesive tape outside guiding cap, so that lashing head is in flexible shape.
Further, galvanized wire is 16# galvanized wire.
Further, in step 8, along steel beam length direction at interval of 5m, steel is tied in using galvanized wire and is held together, So that steel beam is integrally brought into close contact in hoisting process.
Further, in step 9, by steel strand wires uniformly, be sent into reserving hole channel in order.
Further, in step 12, using 20% initial tensioning force of the tension stress of jack, complete card and face Shi Suoding unblock and adjustment steel Shu Shunzhi degree, loose degree.
Embodiment 2
Construction Gereral Situation:
It is located at humane road and Jialuhe River intersection, overall length of bridge 526.0m, the wide 55m of bridge floor in certain Chinese bridge.It is wherein main Bridge long 190m, wide 55m, main bridge be double rope faces without dorsal funciculus single pylon cable stayed bridge, king-tower is prestressed concrete inclined pylon, and upper king-post strut is high 60m, 30 are tilted backwards, cross section is single box single chamber;The high 12.5m of lower king-post strut, cross section are single box double room, and short transverse is in line Property gradual change, wide tower is 4m.
The high 12.51m of king-tower lower king-post strut, it is divided into two sections of constructions, first paragraph completes the construction of lower king-post strut base, and second segment construction is surplus Remaining chamber part;Points of 10 sections constructions of king-tower, each section with steel box girder segment synchronous construction.Completed in king-post concreting And after reaching 100% intensity, prestressed cable in tensioning king-tower, then it is connected to form what is mutually balanced each other by suspension cable with steel box-girder Overall, therefore, king-post quality control for prestress stretching construction is to ensure the basis of leaning tower and steel case and monolithic stability, leaning tower and steel box-girder Monolithic stability is the key of bridge construction success or failure.
The problem of being run into construction:
Because king-tower prestressed concrete is single box single chamber structure, chamber side wall thickness only 1m, therefore, pre-stress construction place Narrow, pulling anchor cable stage could must be that suitable space is vacateed in tensioning by handling the built-in fitting at tensioning port, and It is required that it just can guarantee that tensioning is normally carried out using the jack of small volume, therefore, in prestressed pore passage arrangement strand pulling machine suitable for reading Carrying out lashing operation can not realize.During upper tower hypomere construction, because steel strand wires are shorter, after using crane, steel strand wires are sling, manually It is sent into hole by root, and is glided in the baffled stop steel beam in duct bottom, taking the measure, not only difficulty of construction is big, and easily Steel beam is caused to be dropped because of deadweight, need to do over again lashing again, and construction quality risk be present;During upper midsection construction, take When stating method lashing, because steel Shu Zichong is larger, portion is baffled under prestress and coordinates duct top and galvanized wire or steel wire rope to consolidate When determining steel beam, steel beam repeatedly occurs and crashes into phenomenon in hole, and steel beam relative position has dislocation, it is necessary to repeatedly adjust steel beam, gives Pre-stress construction causes many troubles.During prestressed cable tensioning, to eliminate steel strand wires caused by internal cause deadweight in duct is sagging Straight and slackness increases loss of prestress, also needs after carrying out single top prestretching, then carry out the tensioning of whole beam.
Solution method:
Using control method of the present invention, comprise the following steps:
Step 1:Platform of the smooth location as steel strands-woven bundle is selected, according to the length of steel beam, on Shu Pingtai is compiled Two blocks of steel plates that can be moved are set, and welds a steel pipe on steel plate and is as the conduit for compiling beam, the size of steel plate 200cm*200cm*2cm, the length of steel pipe are 50cm and identical with reserving hole channel internal diameter;
Step 2:Steel strand wires are penetrated in the conduit that beam is compiled for steel beam top and bottom by root;
Step 3:When compiling beam in steel beam lower end, steel beam is divided into three kinds of dislocation and placed, adjacent dislocation difference is 30cm, is used 16# galvanized wires by the steel strand wires colligation of equal length together, no less than 2 enclose by the colligation galvanized wire coiling of use, and by long 30cm's Steel strand wires wrap 30cm shorter than its steel strand wires, and cone-shaped is formed in the bottom of steel beam;
Step 4:A guiding cap is hinged with steel beam lower end, guiding cap outside swathes 5 layers using adhesive tape;
Step 5:When steel Shu Shangduan compiles beam, the steel strand wires of most long beam are first arranged on to several center hole portions of 1# anchor slabs Position, then vice-minister's beam of steel strand wires is faced into centre bore installation beam arrangement, most short steel strand wires are finally arranged in the periphery hole position of anchor slab Put;
Step 6:After the completion of 1# anchor slab lashings, steel strand wires are locked on 1# anchor slabs using steel strand wires card;
Step 7:After completing the locking of upper end steel strand wires, 2# anchor slabs are worn again at the top of steel Shu Shangduan, then using anchor ear by 1# Anchor slab, 2# anchor slabs hoop are together;
Step 8:Along steel beam length direction at interval of 5m, steel beam is bundled with 16# galvanized wires;
Step 9:The steel Shu Caiyong cranes for completing top and bottom volume beam are sling, steel strand wires are sent into reserving hole channel simultaneously The 16# galvanized wires every 5m colligation steel beams are released, until steel strand wires lower end passes from duct lower end;
Step 10:Steel Shu Shangduan close to duct it is suitable for reading when, 1# anchor slabs that steel Shu Shangduan is installed, 2# anchor slabs center with it is reserved Duct center alignment, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11:The anchor ear for anchoring two anchor slabs is released, takes 2# anchor slabs away, completes the installation of steel beam;
Step 12:Directly stretch-draw jack is installed on the 1# anchor slabs left, uses the tension stress of jack 20% initial tensioning force, the unblock of card temporary locking and the adjustment of steel Shu Shunzhi degree, loose degree are completed, answered subsequently into pre- The power stretching construction stage.
The effect reached:
In the construction of king-tower upper king-post strut 3-10 section steel beam, crane is sent after adding anchor ear, card locking steel strand wires using double anchor slabs Anchor technique, it is therefore prevented that debunching, steel strand wires gliding dislocations of the steel beam in hoisting process, avoid again in installation 1-3 section steel beams because of peace Fill anchor slab when temporary fixing lifting galvanized wire or steel wire rope and cause steel beam fall and shift phenomenon generation so that steel stranded wire penetrating adapter Positioning more precisely and it is safe, controllable, construction efficiency is substantially accelerated.
The present invention is not limited to above-mentioned embodiment, in the case of without departing substantially from substantive content of the present invention, art technology Any deformation, improvement, the replacement that personnel are contemplated that each fall within protection scope of the present invention.

Claims (9)

1. a kind of king-post prestressed strand lifts position control method, it is characterised in that comprises the following steps:
Step 1:Platform of the smooth location as steel strands-woven bundle is selected, according to the length of steel beam, is set on Shu Pingtai is compiled Two blocks of steel plates that can be moved, and a steel pipe is welded as the conduit for compiling beam on steel plate;
Step 2:Steel strand wires are penetrated in the conduit that beam is compiled for steel beam top and bottom by root;
Step 3:When compiling beam in steel beam lower end, steel beam is divided into three kinds of dislocation and placed, adjacent dislocation difference is 30cm, using galvanized wire By the steel strand wires colligation of equal length together, and by long 30cm steel strand wires 30cm shorter than its steel strand wires are wrapped, in steel The bottom of beam forms cone-shaped;
Step 4:A guiding cap is hinged with steel beam lower end;
Step 5:When steel Shu Shangduan compiles beam, the steel strand wires of most long beam are first arranged on to several centre bore positions of 1# anchor slabs, then Vice-minister's beam of steel strand wires is faced into centre bore installation beam arrangement, most short steel strand wires are finally arranged in the periphery hole site of anchor slab;
Step 6:After the completion of 1# anchor slab lashings, steel strand wires are locked on 1# anchor slabs using steel strand wires card;
Step 7:After completing the locking of upper end steel strand wires, 2# anchor slabs are worn again at the top of steel Shu Shangduan, then using anchor ear by 1# anchors Plate, 2# anchor slabs hoop are together;
Step 8:Along steel beam length direction at interval of 4m-6m, steel beam is bundled with galvanized wire;
Step 9:The steel Shu Caiyong cranes for completing top and bottom volume beam are sling, steel strand wires are sent into reserving hole channel and released Every the galvanized wire of 4m-6m colligation steel beams, until steel strand wires lower end passes from duct lower end;
Step 10:Steel Shu Shangduan close to duct it is suitable for reading when, 1# anchor slabs, 2# anchor slabs center and reserving hole channel that steel Shu Shangduan is installed Center alignment, anchor slab is uniformly placed on the platform suitable for reading of duct;
Step 11:The anchor ear for anchoring two anchor slabs is released, takes 2# anchor slabs away, completes the installation of steel beam;
Step 12:Stretch-draw jack directly is installed on the 1# anchor slabs left, uses the 10%- of the tension stress of jack 20% initial tensioning force, the unblock of card temporary locking and the adjustment of steel Shu Shunzhi degree, loose degree are completed, answered subsequently into pre- The power stretching construction stage.
2. control method according to claim 1, it is characterised in that in step 1, the length of steel pipe for 50cm and It is identical with reserving hole channel internal diameter.
3. control method according to claim 1, it is characterised in that in step 1, the size of steel plate is 200cm* 200cm*2cm。
4. control method according to claim 1, it is characterised in that in step 3, during steel strand wires colligation, use is tied up Galvanized wire coiling is pricked no less than 2 circles.
5. control method according to claim 1, it is characterised in that in step 4, twined outside guiding cap using adhesive tape Wrap up in 4-5 layers.
6. control method according to claim 1, it is characterised in that in step 8, along steel beam length direction at interval of Steel is tied in and is held together by 5m using galvanized wire.
7. according to the control method described in any one of claim 1,4,6, it is characterised in that galvanized wire is 16# galvanized wire.
8. control method according to claim 1, it is characterised in that in step 9, steel strand wires are sent into uniformly, in order Reserving hole channel.
9. control method according to claim 1, it is characterised in that, should using the tensioning of jack in step 12 20% initial tensioning force of power, complete unblock and adjustment steel Shu Shunzhi degree, the loose degree of card temporary locking.
CN201710952262.1A 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method Active CN107762238B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710952262.1A CN107762238B (en) 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710952262.1A CN107762238B (en) 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method

Publications (2)

Publication Number Publication Date
CN107762238A true CN107762238A (en) 2018-03-06
CN107762238B CN107762238B (en) 2019-05-10

Family

ID=61269308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710952262.1A Active CN107762238B (en) 2017-10-13 2017-10-13 A kind of king-post prestressed strand lifting position control method

Country Status (1)

Country Link
CN (1) CN107762238B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518977A (en) * 2018-12-26 2019-03-26 中国核工业二四建设有限公司 A kind of inverted U prestress wire anti-slip device and method
CN111517170A (en) * 2020-04-07 2020-08-11 福建福清核电有限公司 Wiring device of inverted U-shaped prestress braiding

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009057713A (en) * 2007-08-30 2009-03-19 Kyushu Electric Power Co Inc Wind power generation hybrid tower, and its construction method
CN101798874A (en) * 2010-03-08 2010-08-11 东南大学 Pre-stress construction method of parallel steel stranded wire assembled cable in annular sealed steel pipe
CN203613812U (en) * 2013-11-29 2014-05-28 甘肃路桥建设集团有限公司 Pre-stressed steel strand blanking and binding rack
CN204919354U (en) * 2015-08-17 2015-12-30 北京奇力建通工程技术有限公司 A construction equipment that is arranged in construction of taking one's place of cable -stay bridge cable wire
CN105672138A (en) * 2016-03-31 2016-06-15 中铁四局集团第一工程有限公司 Through type stayed cable installation circulation system and cable threading construction method thereof
CN106948263A (en) * 2017-05-10 2017-07-14 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009057713A (en) * 2007-08-30 2009-03-19 Kyushu Electric Power Co Inc Wind power generation hybrid tower, and its construction method
CN101798874A (en) * 2010-03-08 2010-08-11 东南大学 Pre-stress construction method of parallel steel stranded wire assembled cable in annular sealed steel pipe
CN203613812U (en) * 2013-11-29 2014-05-28 甘肃路桥建设集团有限公司 Pre-stressed steel strand blanking and binding rack
CN204919354U (en) * 2015-08-17 2015-12-30 北京奇力建通工程技术有限公司 A construction equipment that is arranged in construction of taking one's place of cable -stay bridge cable wire
CN105672138A (en) * 2016-03-31 2016-06-15 中铁四局集团第一工程有限公司 Through type stayed cable installation circulation system and cable threading construction method thereof
CN106948263A (en) * 2017-05-10 2017-07-14 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518977A (en) * 2018-12-26 2019-03-26 中国核工业二四建设有限公司 A kind of inverted U prestress wire anti-slip device and method
CN109518977B (en) * 2018-12-26 2024-01-30 中国核工业二四建设有限公司 Anti-slip device and method for inverted U-shaped prestress steel strand
CN111517170A (en) * 2020-04-07 2020-08-11 福建福清核电有限公司 Wiring device of inverted U-shaped prestress braiding

Also Published As

Publication number Publication date
CN107762238B (en) 2019-05-10

Similar Documents

Publication Publication Date Title
US9657494B2 (en) Method for producing a tower construction from reinforced concrete
CN110804952B (en) Suspension bridge beam prefabrication and assembly construction process
CN101597960B (en) Large-tonnage jack tension construction technology for non-bonded prestressed silo
US7814724B2 (en) Method for building over an opening via incremental launching
CN108570935A (en) Bent cap, box beam, plate-beam construction method in bridges in highway engineering
CN102354926A (en) Large-section conductor tension stringing construction method
CN111764517A (en) Large-span truss string guiding traction high-altitude cable loading method
CN107762238A (en) A kind of king-post prestressed strand lifts position control method
CN112554067A (en) Method for constructing bracket-free tied arch by means of arch first and beam second
CN106087759A (en) A kind of prestressed strand threader and the threading method of prestressed strand
CN210714046U (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN117144804A (en) Stay cable hanging method under synchronous construction condition of tower beams and cables of low-tower cable-stayed bridge
CN110541599A (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN116516836A (en) Continuous pushing method for bridge approach non-guide girder large-span steel girder
CN107938517B (en) A kind of cable-stayed bridge prestressed concrete beam ring anchor construction method
CN210458987U (en) Soft temporary pocket hoisting device is changed to jib
CN210368674U (en) Bridge cantilever pouring construction device based on inclined pull buckle hanging
CN211116420U (en) Precast concrete fan tower section of thick bamboo and tower section of thick bamboo component
CN211338564U (en) Tower top main cable saddle mounting system
CN107419670A (en) Hybrid structure of arch and beam formula continuous rigid frame bridge winds up walking cradle construction device and method
CN114541283A (en) Structure and method for solving continuous downwarping problem of large-span PC beam bridge
CN215289717U (en) Lifting device for temporary tie bars of tied arch bridge constructed based on arch-first beam-after-beam method
CN116872353B (en) Device and process for rapidly forming pretensioned prestressing I-beam
CN219508376U (en) Device for erecting super-long and super-heavy stay cable
CN220434257U (en) Integral traction device for high-altitude prestress horizontal steel beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant