CN107756014A - The self installation mold and its installation method of horizontal equipment - Google Patents

The self installation mold and its installation method of horizontal equipment Download PDF

Info

Publication number
CN107756014A
CN107756014A CN201610694659.0A CN201610694659A CN107756014A CN 107756014 A CN107756014 A CN 107756014A CN 201610694659 A CN201610694659 A CN 201610694659A CN 107756014 A CN107756014 A CN 107756014A
Authority
CN
China
Prior art keywords
horizontal equipment
mold
installation
horizontal
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610694659.0A
Other languages
Chinese (zh)
Inventor
王志远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Engineering Group Co Ltd
Sinopec Heavy Lifting Transporting Engineering Co Ltd
Original Assignee
Sinopec Engineering Group Co Ltd
Sinopec Heavy Lifting Transporting Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Engineering Group Co Ltd, Sinopec Heavy Lifting Transporting Engineering Co Ltd filed Critical Sinopec Engineering Group Co Ltd
Priority to CN201610694659.0A priority Critical patent/CN107756014A/en
Publication of CN107756014A publication Critical patent/CN107756014A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/04Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes for assembling or disassembling parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention discloses the self installation mold and its installation method of a kind of horizontal equipment.Self installation is included with mold:Supporter;Rolling rod, rolling are connected to below supporter, supporter can be driven to vertically move;Micro-adjusting mechanism, it is arranged on supporter, the adjustment casing transverse shifting above micro-adjusting mechanism can be driven;Jack, it is arranged at by adjusting casing above micro-adjusting mechanism;Saddle, it is supported on jack;Layering branch backing plate is provided between adjustment casing and saddle.Rolling bar and micro-adjusting mechanism are finely adjusted to equipment, and jack and layering branch backing plate are engaged, and can reach that falling head is controllable, facilitates equipment effect in place.

Description

The self installation mold and its installation method of horizontal equipment
Technical field
The present invention relates to equipment installing area, more particularly, to the self installation mold and its peace of a kind of horizontal equipment Dress method.
Background technology
In equipment installing area, the transport mold of horizontal equipment does not have the function of self installation at present, and only serving to set Effect of the standby horizontal transport to installation site.Equipment conveying is lifted equipment using crane gears such as chain blocks to after installation site From transport mold, equipment in place after transport mold is removed, the method will set suspension centre in framework, by frame structure and by force The influence of degree.Difficulty is adjusted using crane gears such as chain blocks, one time falling head is uncontrollable, and equipment is difficult in place.
Therefore, it is necessary to develop it is a kind of framework is not limited, falling head is controllable, facilitates equipment self installation in place to use Mold and its installation method.
The information of background of invention part is merely intended to deepen the understanding of the general background technology to the present invention, without It should be considered as recognizing or imply information structure prior art known to those skilled in the art in any form.
The content of the invention
The present invention proposes the self installation mold and its installation method of a kind of horizontal equipment, solves current horizontal equipment The problem of crane gear adjustment is difficult during installation, a falling head is uncontrollable, equipment is difficult in place.
According to an aspect of the invention, it is proposed that the self installation mold of horizontal equipment a kind of, including:
Supporter;
Rolling bar, rolling are connected to below the supporter, and the supporter can be driven to vertically move;
Micro-adjusting mechanism, it is arranged on the supporter, the adjustment casing above the micro-adjusting mechanism can be driven laterally to move It is dynamic;
Jack, it is arranged at by the adjustment casing above the micro-adjusting mechanism;
Saddle, it is supported on the jack.
Preferably, layering branch backing plate is provided between the adjustment casing and the saddle, the layering branch backing plate includes The size identical cuboid of multiple stackings.
Preferably, the end set of the adjustment casing has adjustment hanger.
Preferably, a part for the upper surface of the saddle is in cambered surface.
Preferably, the side of the saddle is set fluted, and the jack is contained in the groove.
Preferably, the length of the saddle is consistent with the length of the adjustment casing, the width of the saddle and the tune The width of whole box body is consistent.
Preferably, the rolling bar includes the multiple cylinders be arrangeding in parallel.
Preferably, the micro-adjusting mechanism includes the multiple cylinders be arrangeding in parallel.
According to another aspect of the invention, it is proposed that the self installation method of horizontal equipment a kind of, described in methods described uses Self installation mold, wherein horizontal equipment to be installed is mounted on the basis of outside basis and inner side in framework, it is described horizontal The self installation method of equipment comprises the following steps:
Step 1:Between outer side base plinth and inner side basis, at close outside basis, first set horizontal equipment oneself is set Installation mold, whipline suspension hook is connected to the outer end of horizontal equipment to be installed, will be to be installed by main hoisting crane suspension hook Horizontal equipment is sling and is moved in framework, until the inner of horizontal equipment to be installed is located at the self installation of first set horizontal equipment With on the saddle of mold;
Step 2:Main hoisting crane suspension hook is removed, is sling horizontal equipment to be installed by whipline suspension hook, mobile first The self installation mold of horizontal equipment is covered, horizontal equipment to be installed is moved to lower portion, until first set horizontal equipment Self installation mold will contact inner side basis;
Step 3:Locate between outer side base plinth and inner side basis, close to outside basis, second set of horizontal equipment of installation oneself Installation mold, and remove the self installation mold of first set horizontal equipment;
Step 4:Treated by the self installation mold of whipline suspension hook and second set of horizontal equipment to lower portion movement Horizontal equipment is installed, until whipline suspension hook is stopped by framework;
Step 5:3rd set of horizontal equipment is installed between the self installation mold of outer side base plinth and second set of horizontal equipment Self installation mold, remove whipline suspension hook;
Step 6:The self installation mold of mobile second set of horizontal equipment and the installation clamping fixture of the 3rd set of horizontal equipment, will be treated Installation horizontal equipment is moved to the surface on outside basis and inner side basis;
Step 7:The self installation mold of second set of horizontal equipment of regulation and the installation clamping fixture of the 3rd set of horizontal equipment it is micro- Regulating mechanism, the installation bolt hole of horizontal equipment to be installed is set to be aligned with the installation bolt on outside basis and inner side basis;
Step 8:Pass through the thousand of the self installation mold of second set of horizontal equipment and the installation clamping fixture of the 3rd set of horizontal equipment Jin top lifts the height of horizontal equipment to be installed, then extract out second set of horizontal equipment self installation mold and the 3rd set it is horizontal One cuboid of the layering branch backing plate of the installation clamping fixture of equipment, reduce the height of the jack so as to be installed horizontal to set It is standby to fall back on the layering branch backing plate;
Step 9:Repeating said steps 8, until the installation bolt fully enters installation bolt hole.
It is according to a kind of self installation of horizontal equipment of the present invention with mold and its installation method advantage:Can will be horizontal Equipment level is transported into lower portion, and does not borrow other crane gears such as chain block, using being arranged on self installation tire Hydraulic jack can be in place by equipment on tool, and regulates and controls falling head each time, this installation method using branch backing plate is layered Suitable for the installation of all horizontal equipments, and do not influenceed by frame structure where equipment to be installed, versatility is good.
Methods and apparatus of the present invention has other characteristics and advantage, and these characteristics and advantage are attached from what is be incorporated herein It will be apparent in figure and subsequent specific embodiment, or by the accompanying drawing and subsequent specific implementation being incorporated herein Stated in detail in example, these the drawings and specific embodiments are provided commonly for explaining the certain principles of the present invention.
Brief description of the drawings
Exemplary embodiment of the present is described in more detail in conjunction with the accompanying drawings, it is of the invention above-mentioned and its Its purpose, feature and advantage will be apparent, wherein, in exemplary embodiments of the present invention, identical reference number leads to Chang represents same parts.
Fig. 1 shows the schematic diagram of the self installation mold of horizontal equipment according to an embodiment of the invention.
Fig. 2 shows the schematic diagram that the self installation of horizontal equipment according to an embodiment of the invention is worked with mold.
Fig. 3 a, Fig. 3 b, Fig. 3 c, Fig. 3 d, Fig. 3 e and Fig. 3 f show horizontal equipment according to an embodiment of the invention Each step of self installation method operation chart.
Description of reference numerals:
1st, rolling bar;2nd, supporter;3rd, casing is adjusted;4th, jack;5th, saddle;6th, micro-adjusting mechanism;7th, it is layered branch backing plate;
31st, hanger is adjusted;51st, cambered surface;52nd, groove;
8th, main hoisting crane suspension hook;9th, whipline suspension hook;10th, horizontal equipment to be installed;11st, first set horizontal equipment from Installation mold;12-1, outside basis;12-2, inner side basis;13rd, framework;14th, the self installation tire of second set of horizontal equipment Tool;15th, the self installation mold of the 3rd set of horizontal equipment.
Embodiment
The present invention is more fully described below with reference to accompanying drawings.Although showing the preferred embodiments of the present invention in accompanying drawing, However, it is to be appreciated that the present invention is may be realized in various forms without should be limited by embodiments set forth here.Conversely, there is provided These embodiments are in order that the present invention is more thorough and complete, and can will fully convey the scope of the invention to ability The technical staff in domain.
The one side of exemplary embodiment provides a kind of self installation mold of horizontal equipment, and it includes:
Supporter;
Rolling bar, rolling are connected to below supporter, supporter can be driven to vertically move;
Micro-adjusting mechanism, it is arranged on supporter, the adjustment casing transverse shifting above micro-adjusting mechanism can be driven;
Jack, it is arranged at by adjusting casing above micro-adjusting mechanism;
Saddle, it is supported on jack.
Wherein, rolling bar is the walking mechanism of self installation mold, under the traction of chain block, enables a device to longitudinal shifting Dynamic (i.e. horizontal arrow direction in Fig. 2).Supporter can be welded by shaped steel, lower to be contacted with rolling bar, and upper support is micro- Regulating mechanism.It is (i.e. signified with the horizontal arrow in Fig. 2 that adjustment casing and micro-adjusting mechanism cooperation can carry out horizontal equipment transverse shifting The vertical direction in direction) fine setting, make the bolt hole of equipment to be installed and the bolt alignment of infrastructure device.Jack is the dynamic of saddle Power source, the installation of equipment vertical drop completion equipment is made by the falling of jack.
Preferably, adjust and layering branch backing plate is provided between casing and saddle, wherein layering branch backing plate is including more The size identical cuboid of individual stacking, each cuboid can make falling distance controlling in a fixed numbers, and this is solid Fixed number value is the thickness of cuboid.
Preferably, adjusting the end set of casing has adjustment hanger.Hanger is adjusted by shackle and steel wire rope to connect Chain block is connect as the power laterally adjusted.Casing is welded by shaped steel or steel plate, can support larger weight while have There is smooth upper and lower surface, be easy to support and adjust.
Preferably, a part for the upper surface of saddle is in cambered surface.Generally circular arc, facilitate place apparatus.
Preferably, the side of saddle is set fluted, and jack is contained in groove.Typically in the both sides of saddle Respectively there is a groove, each groove part accommodates a jack, makes support more steady.
Preferably, the length of saddle is consistent with the length for adjusting casing, the width of the width and adjustment casing of saddle Degree is consistent.
Preferably, rolling bar includes the multiple cylinders be arrangeding in parallel, such as three cylinders.Rolling bar can be steel Pipe or round steel, rolling bar can be solid or hollow.
Preferably, micro-adjusting mechanism includes the multiple cylinders be arrangeding in parallel.Micro-adjusting mechanism can be steel pipe or circle Steel, can be solid or hollow.
According to the another aspect of exemplary embodiment, there is provided a kind of self installation method of horizontal equipment, this method use root According to the self installation mold of exemplary embodiment, wherein horizontal equipment to be installed is mounted to outside basis and inner side in framework On the basis of, the self installation method of horizontal equipment comprises the following steps:
Step 1:Between outer side base plinth and inner side basis, at close outside basis, first set horizontal equipment oneself is set Installation mold, whipline suspension hook is connected to the outer end of horizontal equipment to be installed, will be to be installed by main hoisting crane suspension hook Horizontal equipment is sling and is moved in the framework, until the inner of horizontal equipment to be installed is located at oneself of first set horizontal equipment On the saddle of installation mold;
Step 2:Main hoisting crane suspension hook is removed, horizontal equipment to be installed is sling by whipline suspension hook, passes through first The self installation mold of the rolling bar movement first set horizontal equipment of the self installation mold of horizontal equipment is covered, horizontal is set to be installed It is standby to be moved to lower portion, until the self installation mold of first set horizontal equipment will contact inner side basis;
Step 3:Between outer side base plinth and inner side basis, at the close outside basis, second set of horizontal equipment is installed Self installation mold, and remove the self installation mold of first set horizontal equipment;
Step 4:By the rolling bar of whipline suspension hook and the self installation mold of second set of horizontal equipment to lower portion Mobile horizontal equipment to be installed, until whipline suspension hook is stopped by framework;
Step 5:3rd set of horizontal equipment is installed between the self installation mold of outer side base plinth and second set of horizontal equipment Self installation mold, remove whipline suspension hook;
Step 6:It is horizontal by the self installation mold and the 3rd set of rolling bar second set of horizontal equipment of movement of two complete equipments The installation clamping fixture of equipment, horizontal equipment to be installed is moved to the surface on outside basis and inner side basis;
Step 7:The self installation mold of second set of horizontal equipment of regulation and the installation clamping fixture of the 3rd set of horizontal equipment it is micro- Regulating mechanism, the installation bolt hole of horizontal equipment to be installed is set to be aligned with the installation bolt on outside basis and inner side basis;
Step 8:Pass through the thousand of the self installation mold of second set of horizontal equipment and the installation clamping fixture of the 3rd set of horizontal equipment Jin top lifts the height of horizontal equipment to be installed, then extract out second set of horizontal equipment self installation mold and the 3rd set it is horizontal One cuboid of the layering branch backing plate of the installation clamping fixture of equipment, reduce the height of jack so that horizontal equipment to be installed returns Fall on layering branch backing plate;
Step 9:Repeating said steps 8, until installation bolt fully enters installation bolt hole.
Method disclosed by the invention carries out the horizontal transport and self installation of equipment in framework, installation using self installation with mold Process safety is reliable;Self installation is installed with mold, and suspension centre is not set in framework, not by the shadow of frame structure and intensity Ring;This method is installed, and operation is highly low, can be operated in relatively low framework;Framework is installed almost without influence, had Installation and project overall progress beneficial to whole framework.
Embodiment 1
Fig. 1 shows the schematic diagram of the self installation mold of horizontal equipment according to an embodiment of the invention.Fig. 2 shows The schematic diagram that the self installation of horizontal equipment according to an embodiment of the invention is worked with mold is gone out.
Included according to the self installation of the horizontal equipment of exemplary embodiment with mold:Supporter 2, lower section roll with rolling bar 1 Connection, it is the walking mechanism of self installation mold, rolling bar 1 drives the longitudinal direction of supporter 2 (i.e. in Fig. 2 under the traction of chain block Horizontal arrow direction) it is mobile;Micro-adjusting mechanism 6 is arranged on supporter 2, can lead to the adjusting tank of the top of micro-adjusting mechanism 6 Laterally (i.e. the direction vertical with the horizontal arrow direction in Fig. 2) motion of body 3;Jack 4 is set by the adjustment casing 3 The top of micro-adjusting mechanism 6 is placed in, jack 4 can drive equipment to move up and down;Saddle 5 is supported on the jack 4.
Rolling bar 1 includes the multiple cylinders be arrangeding in parallel, and rolling bar 1 can be with steel pipe or round steel.
Adjustment mechanism 6 includes the multiple cylinders be arrangeding in parallel, and adjustment mechanism 6 can be steel pipe or round steel.
Supporter 2 can be welded by shaped steel.
Adjustment casing 3 both sides are welded with adjustment hanger 31, and adjustment casing 3 can be welded by shaped steel or steel plate.
Layering branch backing plate 7 is provided between adjustment casing 3 and saddle 5, wherein, layering branch backing plate 7 includes multiple stackings Size identical cuboid.
A part for the upper surface of saddle 5 is cambered surface 51, and two sides of saddle are respectively arranged with a groove 52, very heavy Top 4 is contained in groove 52.
Fig. 3 a, Fig. 3 b, Fig. 3 c, Fig. 3 d, Fig. 3 e and Fig. 3 f show horizontal equipment according to an embodiment of the invention Each step of self installation method operation chart.
Step 1:Between outer side base plinth 12-1 and inner side basis 12-2, at close outside basis 12-1, first set is set The self installation of horizontal equipment mold 11, whipline suspension hook 9 is connected to the outer end of horizontal equipment 10 to be installed, hung by master Horizontal equipment 10 to be installed is sling and is moved in the framework 13 by hoist lifting hook 8, until in horizontal equipment 10 to be installed End is located on saddle of the self installation of first set horizontal equipment with mold 11, as shown in Figure 3 a;
Step 2:Main hoisting crane suspension hook is removed, is sling horizontal equipment 10 to be installed by whipline suspension hook 9, mobile the The self installation of set of horizontal type equipment mold 11, by horizontal equipment 10 to be installed to moving inside framework 13, until first set crouches The self installation mold 11 of formula equipment will contact the basic 12-2 in inner side, as shown in Figure 3 b;
Step 3:Between outer side base plinth 12-1 and inner side basis 12-2, at close outside basis 12-1, second set is installed The self installation of horizontal equipment mold 14, and the self installation mold 11 of first set horizontal equipment is removed, as shown in Figure 3 c;
Step 4:By the self installation of whipline suspension hook 9 and second set of horizontal equipment with mold 14 to moving inside framework 13 Horizontal equipment 10 to be installed is moved, until whipline suspension hook 9 is stopped by framework 13, as shown in Fig. 3 c and Fig. 3 d;
Step 5:It is sleeping with installing the 3rd set between mold 14 in the self installation of outer side base plinth 12-1 and second set of horizontal equipment The self installation of formula equipment mold 15, as shown in Figure 3 d, remove whipline suspension hook 9;
Step 6:The self installation mold 14 and the installation clamping fixture 15 of the 3rd set of horizontal equipment of mobile second set of horizontal equipment, Horizontal equipment 10 to be installed is moved to the basic 12-1 and inner side basis 12-2 in outside surface;
Step 7:Adjust the self installation mold 14 and the installation clamping fixture 15 of the 3rd set of horizontal equipment of second set of horizontal equipment Micro-adjusting mechanism, make the installation bolt hole of horizontal equipment 10 to be installed and outside basis 12-1 and inner side basis 12-2 installation Bolt is aligned, as shown in Figure 3 e;
Step 8:Pass through the self installation mold 14 and the installation clamping fixture 15 of the 3rd set of horizontal equipment of second set of horizontal equipment Jack 4 lift the height of horizontal equipment 10 to be installed, then extract the self installation of second set of horizontal equipment out with the He of mold 14 One cuboid of the layering branch backing plate 7 of the installation clamping fixture 15 of the 3rd set of horizontal equipment, reduce the height of jack 4 so that treat Installation horizontal equipment 10 is fallen back on layering branch backing plate 7, as shown in Fig. 2 and Fig. 3 f;
Step 9:Repeating said steps 8, until installation bolt fully enters installation bolt hole.
It will be understood by those skilled in the art that the purpose of the description to embodiments of the invention is only for exemplarily saying above The beneficial effect of bright embodiments of the invention, it is not intended to limit embodiments of the invention to given any example.
It is described above various embodiments of the present invention, described above is exemplary, and non-exclusive, and It is not limited to disclosed each embodiment.In the case of without departing from the scope and spirit of illustrated each embodiment, for this skill Many modifications and changes will be apparent from for the those of ordinary skill in art field.The selection of term used herein, purport The principle of each embodiment, practical application or improvement to the technology in market are best being explained, or is making the art Other those of ordinary skill are understood that each embodiment disclosed herein.

Claims (9)

1. a kind of self installation mold of horizontal equipment, including:
Supporter (2);
Rolling bar (1), rolling are connected to below the supporter (2), and the supporter (2) can be driven to vertically move;
Micro-adjusting mechanism (6), it is arranged on the supporter (2), the adjustment casing above the micro-adjusting mechanism (6) can be driven (3) transverse shifting;
Jack (4), it is arranged at by the adjustment casing (3) above the micro-adjusting mechanism (6);
Saddle (5), it is supported on the jack (4).
2. the self installation mold of horizontal equipment according to claim 1, wherein, the adjustment casing (3) and the saddle Layering branch backing plate (7) is provided between seat (5), the layering branch backing plate (7) includes the size identical cuboid of multiple stackings.
3. the self installation mold of horizontal equipment according to claim 2, wherein, the end of the adjustment casing (3) is set It is equipped with adjustment hanger (31).
4. the self installation mold of horizontal equipment according to claim 2, wherein, the one of the upper surface of the saddle (5) Part is in cambered surface (51).
5. the self installation mold of horizontal equipment according to claim 2, wherein, the side of the saddle (5) is provided with Groove (52), the jack (4) are contained in the groove (52).
6. the self installation mold of horizontal equipment according to claim 2, wherein, the length of the saddle (5) with it is described The length of adjustment casing (3) is consistent, and the width of the saddle (5) is consistent with the width of the adjustment casing (3).
7. the self installation mold of horizontal equipment according to claim 2, wherein, the rolling bar (1) includes be arrangeding in parallel Multiple cylinders.
8. the self installation mold of horizontal equipment according to claim 2, wherein, the micro-adjusting mechanism (6) includes parallel The multiple cylinders set.
9. a kind of self installation method of horizontal equipment, using the horizontal equipment according to any one of claim 2-8 from Installation mold, wherein horizontal equipment to be installed (10) is mounted to outside basic (12-1) and inner side basis in framework (13) On (12-2), the self installation method of the horizontal equipment comprises the following steps:
Step 1:Between outer side base plinth (12-1) and inner side basic (12-2), close to basic (12-1) place in outside, setting first The self installation of horizontal equipment is covered with mold (11), and whipline suspension hook (9) is connected to the outer end of horizontal equipment to be installed (10), Horizontal equipment to be installed (10) is sling and is moved in framework (13) by main hoisting crane suspension hook (8), until to be installed horizontal The inner of equipment (10) is located at the self installation of first set horizontal equipment with the saddle (5) of mold (11);
Step 2:Main hoisting crane suspension hook (8) is removed, is sling horizontal equipment to be installed (10) by whipline suspension hook (9), is moved The self installation of dynamic first set horizontal equipment is with mold (11), by horizontal equipment to be installed (10) to mobile inside framework (13), directly Self installation mold (11) to first set horizontal equipment will contact inner side basis (12-2);
Step 3:Between outer side base plinth (12-1) and inner side basic (12-2), close to basic (12-1) place in outside, installation second The self installation of horizontal equipment is covered with mold (14), and removes the self installation of first set horizontal equipment with mold (11);
Step 4:It is internal to framework (13) with mold (14) by the self installation of whipline suspension hook (9) and second set of horizontal equipment Mobile horizontal equipment (10) to be installed, until whipline suspension hook (9) is stopped by framework (13);
Step 5:It is sleeping with installing the 3rd set between mold (14) in the self installation of outer side base plinth (12-1) and second set of horizontal equipment The self installation of formula equipment mold (15), dismounting whipline suspension hook (9);
Step 6:The self installation mold (14) and the installation clamping fixture (15) of the 3rd set of horizontal equipment of mobile second set of horizontal equipment, Horizontal equipment to be installed (10) is moved to outside basic (12-1) and the surface of inner side basic (12-2);
Step 7:Adjust the self installation mold (14) and the installation clamping fixture (15) of the 3rd set of horizontal equipment of second set of horizontal equipment Micro-adjusting mechanism (6), make the installation bolt hole of horizontal equipment to be installed (10) and outside basic (12-1) and inner side basis (12- 2) installation bolt alignment;
Step 8:Pass through the self installation mold (14) and the installation clamping fixture (15) of the 3rd set of horizontal equipment of second set of horizontal equipment Jack (4) lift the height of horizontal equipment (10) to be installed, then extract the self installation mold of second set of horizontal equipment out (14) and the layering branch backing plate (7) of the installation clamping fixture (15) of the 3rd set of horizontal equipment a cuboid, reduce the jack (4) height so that horizontal equipment (10) to be installed is fallen back on the layering branch backing plate (7);
Step 9:Repeating said steps 8, until the installation bolt fully enters installation bolt hole.
CN201610694659.0A 2016-08-19 2016-08-19 The self installation mold and its installation method of horizontal equipment Pending CN107756014A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610694659.0A CN107756014A (en) 2016-08-19 2016-08-19 The self installation mold and its installation method of horizontal equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610694659.0A CN107756014A (en) 2016-08-19 2016-08-19 The self installation mold and its installation method of horizontal equipment

Publications (1)

Publication Number Publication Date
CN107756014A true CN107756014A (en) 2018-03-06

Family

ID=61262116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610694659.0A Pending CN107756014A (en) 2016-08-19 2016-08-19 The self installation mold and its installation method of horizontal equipment

Country Status (1)

Country Link
CN (1) CN107756014A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201922237U (en) * 2010-11-26 2011-08-10 天津振汉机械装备有限公司 Installing mould for large-diameter flange
CN202114446U (en) * 2011-06-03 2012-01-18 中国石化集团第四建设公司 Tool for mounting and demounting of horizontal equipment in frame
US20120181735A1 (en) * 2009-10-21 2012-07-19 Masahiro Ooe Workpiece elevating support device
CN202963036U (en) * 2012-11-26 2013-06-05 青岛润丰铝箔有限公司 Aluminium foil mill working roll bearing box assembly and disassembly equipment
CN204366386U (en) * 2014-12-11 2015-06-03 中石化石油工程技术服务有限公司 Side door of blowout preventer opening device
CN104895337A (en) * 2015-05-26 2015-09-09 中国化学工程第三建设有限公司 Installation method of large horizontal equipment in concrete framework
CN205314590U (en) * 2016-01-21 2016-06-15 广东茂化建集团有限公司 Special mechanism of main equipment dismouting in factory building and frame
CN205471624U (en) * 2016-03-08 2016-08-17 佳马机械涂覆科技(苏州)有限公司 Window glass handling device
CN205927779U (en) * 2016-08-19 2017-02-08 中石化重型起重运输工程有限责任公司 Certainly, mould for installation of horizontal equipment

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120181735A1 (en) * 2009-10-21 2012-07-19 Masahiro Ooe Workpiece elevating support device
CN201922237U (en) * 2010-11-26 2011-08-10 天津振汉机械装备有限公司 Installing mould for large-diameter flange
CN202114446U (en) * 2011-06-03 2012-01-18 中国石化集团第四建设公司 Tool for mounting and demounting of horizontal equipment in frame
CN202963036U (en) * 2012-11-26 2013-06-05 青岛润丰铝箔有限公司 Aluminium foil mill working roll bearing box assembly and disassembly equipment
CN204366386U (en) * 2014-12-11 2015-06-03 中石化石油工程技术服务有限公司 Side door of blowout preventer opening device
CN104895337A (en) * 2015-05-26 2015-09-09 中国化学工程第三建设有限公司 Installation method of large horizontal equipment in concrete framework
CN205314590U (en) * 2016-01-21 2016-06-15 广东茂化建集团有限公司 Special mechanism of main equipment dismouting in factory building and frame
CN205471624U (en) * 2016-03-08 2016-08-17 佳马机械涂覆科技(苏州)有限公司 Window glass handling device
CN205927779U (en) * 2016-08-19 2017-02-08 中石化重型起重运输工程有限责任公司 Certainly, mould for installation of horizontal equipment

Similar Documents

Publication Publication Date Title
CN103738834B (en) A kind of adjustable 3 hanging methods
CN104453231B (en) Gantry type building construction lifting device as well as manufacturing method and construction method thereof
CN108328509A (en) A kind of building machinery material elevator with safe spacing function
CN105936441A (en) Cloth feeding lifting device for cloth paving machine
CN207347122U (en) A kind of automatic Lift-on/Lift-off System of bridge construction
CN107253673B (en) A kind of Architectural Equipment hanging apparatus
CN106216408A (en) A kind of device for changing wide and heavy plate mill hydraulic AGC cylinder and using method thereof
CN108910761B (en) Clamp moving operation table of feeding and discharging trolley and clamp replacing method
CN104495602B (en) Stretcher jaw equipment hoisting method and device
CN105735629A (en) Lifting device for building-attached lifting scaffold
CN210001467U (en) Hoisting device used in limited space workshop
CN204958222U (en) Mechanical equipment hoists frame
CN104882267B (en) Method for adding angle ring to transformer coil assembly
CN205927779U (en) Certainly, mould for installation of horizontal equipment
CN107756014A (en) The self installation mold and its installation method of horizontal equipment
CN206720609U (en) Flexibility pneumatic lifting transfer machine
CN215755931U (en) Large transformer hoisting equipment in factory building
CN206172887U (en) Novel handling of fluid pressure type tank car device
CN109019359A (en) A kind of small building lifting equipment
CN103101842B (en) Deep well equipment installation and maintenance travelling crane
CN207771621U (en) For the grinding wheel demoulding equipment in grinding wheel pressing process
CN102226959A (en) Transformer lifting method
CN206104558U (en) A device for changing width heavy plate mill hydraulic pressure AGC jar
CN207243262U (en) The hanging apparatus of generating set electricity generator stator
CN205527399U (en) A hoisting accessory for large -scale pressure steel pipe turn -over

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180306

RJ01 Rejection of invention patent application after publication