CN107738978A - A kind of removable tower crane Integral transporting hanging beam and its operation principle - Google Patents

A kind of removable tower crane Integral transporting hanging beam and its operation principle Download PDF

Info

Publication number
CN107738978A
CN107738978A CN201711033177.1A CN201711033177A CN107738978A CN 107738978 A CN107738978 A CN 107738978A CN 201711033177 A CN201711033177 A CN 201711033177A CN 107738978 A CN107738978 A CN 107738978A
Authority
CN
China
Prior art keywords
strutbeam
tower crane
hanging beam
flange
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711033177.1A
Other languages
Chinese (zh)
Inventor
田云
陶思宇
马鸿
罗靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ZHENHUA HEAVY INDUSTRY QIDONG MARINE ENGINEERING Co Ltd
Original Assignee
SHANGHAI ZHENHUA HEAVY INDUSTRY QIDONG MARINE ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI ZHENHUA HEAVY INDUSTRY QIDONG MARINE ENGINEERING Co Ltd filed Critical SHANGHAI ZHENHUA HEAVY INDUSTRY QIDONG MARINE ENGINEERING Co Ltd
Priority to CN201711033177.1A priority Critical patent/CN107738978A/en
Publication of CN107738978A publication Critical patent/CN107738978A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The invention discloses a kind of removable tower crane Integral transporting hanging beam, including girder, strutbeam A, strutbeam B, flange and eye plate, the left and right ends of the girder are welded and fixed the eye plate up and down, the inner side of the left and right ends of the girder is welded and fixed one end of the strutbeam B, the other end of the strutbeam B, which is fixed, welds the flange, the both ends of the strutbeam A are equally fixed to weld the flange, it is fixedly connected between the strutbeam A and strutbeam B by flange and connecting bolt, rectangular configuration is connected into by flange between the girder, strutbeam A, strutbeam B.Of the invention novel in design, safe and reliable, the present invention can be combined and split by flange and connecting bolt, easy to operate, improve operating efficiency;The present invention can realize tower crane Integral transporting, avoid dismounting when tower crane shifts every time, avoid application risk, improve tower crane utilization rate, reduce use cost.

Description

A kind of removable tower crane Integral transporting hanging beam and its operation principle
Technical field
The present invention relates to ocean engineering structure to build frock technical field, particularly a kind of removable tower crane Integral transporting With hanging beam and its operation principle.
Background technology
Tower crane builds a kind of conventional crane gear of unit as ship and ocean engineering structure, in segmentation advance fitting-out rank Section, block assembly and big close up the stage and suffer from being widely applied.Tower crane has that use cost is low, covering radius is big, convenient fast The features such as prompt.
But tower crane self structure weight is very big, complicated, installation and removal be required for taking a long time with it is huge Cost.
Existing tower crane movement method is from tower crane bottom Piecemeal erection and dismounting, there is that this risk is big, cost is high, the cycle The characteristics of long.During tower crane movement, higher cost of wheeling is also taken.
The content of the invention
The purpose of the present invention is overcome the deficiencies in the prior art, there is provided a kind of removable tower crane Integral transporting hanging beam and its Operation principle.
The technical solution adopted by the present invention is:
A kind of removable tower crane Integral transporting hanging beam, its innovative point are:Including girder, strutbeam A, strutbeam B, flange and eye Plate, the left and right ends of the girder are welded and fixed the eye plate up and down, and the inner side of the left and right ends of the girder is welded admittedly Fixed strutbeam B one end, the other end of the strutbeam B, which is fixed, welds the flange, the equally fixed weldering in both ends of the strutbeam A The flange is connect, is fixedly connected between the strutbeam A and strutbeam B by flange and connecting bolt, the girder, strutbeam A, strutbeam Rectangular configuration is connected into by flange between B.
Further, the left and right sides fixed setting reinforcing plate of the eye plate.
A kind of operation principle of removable tower crane Integral transporting hanging beam is also provided, its innovative point is that specific steps are such as Under:
The first step:The girder and strutbeam B and strutbeam A completed with welding are transported to tower crane movement place, and root from storage space The girder of hanging beam, strutbeam A and strutbeam B are placed in tower crane tower body surrounding according to on-site actual situations;
Second step:The strutbeam A of hanging beam and strutbeam B are rigidly fixed using bolt and flange, are connected rectangular structure;
3rd step:According to tower crane hoisting point position and the suspension centre pattern reasonable disposition handling lockset of crane;
4th step:Crane integrally slings tower crane by hanging beam, needs to meet lifting safety code requirement during movement;
5th step:By tower crane movement to new placement place, carry out the fixation work of tower crane column foot, during this period, crane and Hanging beam need to keep stress;
6th step:After crane pine hook, the connecting bolt of lockset and hanging beam is dismantled, hanging beam is transported to storage space
Beneficial effects of the present invention are as follows:
Of the invention novel in design, safe and reliable, the present invention can be issued to tower crane in the construction existing hanging device of unit and integrally move The purpose of fortune, use cost are relatively low;The present invention can be combined and split by flange and connecting bolt, easy to operate, improve work Make efficiency;The present invention can realize tower crane Integral transporting, avoid dismounting when tower crane shifts every time, avoid application risk, Improve tower crane utilization rate, reduce use cost;The present invention can be split as two single hanging beams based on girder, meet to build If unit others lifting demand, it is possible to achieve one hang it is multi-purpose.
Brief description of the drawings
The present invention is described in further details with reference to the accompanying drawings and detailed description.
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the top view of the present invention;
Fig. 3 is the side view of the present invention.
In figure:1 girder, 2 strutbeam A, 3 strutbeam B, 4 flanges, 5 eye plates, 6 reinforcing plates.
Embodiment
A kind of removable tower crane Integral transporting hanging beam as Figure 1-3, including girder 1, strutbeam A 2, strutbeam B 3, Flange 4 and eye plate 5, the left and right ends of girder 1 are welded and fixed the eye plate 5 up and down, and the inner side of the left and right ends of girder 1 is welded Fixed strutbeam B 3 one end is connect, strutbeam B 3 other end fixes welded flange 4, the strutbeam A 2 equally fixed welding in both ends Orchid 4, is fixedly connected between strutbeam A 2 and strutbeam B 3 by flange 4 and connecting bolt, between girder 1, strutbeam A 2, strutbeam B 3 Rectangular configuration is connected into by flange 4.The left and right sides fixed setting reinforcing plate 6 of eye plate 5.
A kind of operation principle of removable tower crane Integral transporting hanging beam described in usage right requirement 1, it is characterised in that Comprise the following steps that:
The first step:The girder 1 and strutbeam B 3 and strutbeam A 2 completed with welding are transported to tower crane movement place from storage space, And the girder 1, strutbeam A 2 and strutbeam B 3 of hanging beam are placed in tower crane tower body surrounding according to on-site actual situations;
Second step:The strutbeam A 2 of hanging beam and strutbeam B 3 are rigidly fixed using bolt and flange 4, are connected rectangular knot Structure;
3rd step:According to tower crane hoisting point position and the suspension centre pattern reasonable disposition handling lockset of crane, and pass through eye plate 5 and tower Suspension centre is fixedly connected;
4th step:Crane integrally slings tower crane by hanging beam, needs to meet lifting safety code requirement during movement;
5th step:By tower crane movement to new placement place, carry out the fixation work of tower crane column foot, during this period, crane and Hanging beam need to keep stress;
6th step:After crane pine hook, the connecting bolt of lockset and hanging beam is dismantled, hanging beam is transported to storage space.
Described above is the preferred embodiment of the present invention, it is impossible to the interest field of the present invention is limited with this.It should refer to Go out, for those skilled in the art, technical scheme is modified or equivalent substitution, all Protection scope of the present invention is not departed from.

Claims (3)

  1. A kind of 1. removable tower crane Integral transporting hanging beam, it is characterised in that:Including girder, strutbeam A, strutbeam B, flange and eye Plate, the left and right ends of the girder are welded and fixed the eye plate up and down, and the inner side of the left and right ends of the girder is welded admittedly Fixed strutbeam B one end, the other end of the strutbeam B, which is fixed, welds the flange, the equally fixed weldering in both ends of the strutbeam A The flange is connect, is fixedly connected between the strutbeam A and strutbeam B by flange and connecting bolt, the girder, strutbeam A, strutbeam Rectangular configuration is connected into by flange between B.
  2. A kind of 2. removable tower crane Integral transporting hanging beam according to claim 1, it is characterised in that:A left side for the eye plate Reinforcing plate is fixedly installed in right both sides.
  3. A kind of 3. operation principle of the removable tower crane Integral transporting hanging beam described in usage right requirement 1, it is characterised in that tool Body step is as follows:
    The first step:The girder and strutbeam B and strutbeam A completed with welding are transported to tower crane movement place, and root from storage space The girder of hanging beam, strutbeam A and strutbeam B are placed in tower crane tower body surrounding according to on-site actual situations;
    Second step:The strutbeam A of hanging beam and strutbeam B are rigidly fixed using bolt and flange, are connected rectangular structure;
    3rd step:According to tower crane hoisting point position and the suspension centre pattern reasonable disposition handling lockset of crane;
    4th step:Crane integrally slings tower crane by hanging beam, needs to meet lifting safety code requirement during movement;
    5th step:By tower crane movement to new placement place, carry out the fixation work of tower crane column foot, during this period, crane and Hanging beam need to keep stress;
    6th step:After crane pine hook, the connecting bolt of lockset and hanging beam is dismantled, hanging beam is transported to storage space.
CN201711033177.1A 2017-10-30 2017-10-30 A kind of removable tower crane Integral transporting hanging beam and its operation principle Pending CN107738978A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711033177.1A CN107738978A (en) 2017-10-30 2017-10-30 A kind of removable tower crane Integral transporting hanging beam and its operation principle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711033177.1A CN107738978A (en) 2017-10-30 2017-10-30 A kind of removable tower crane Integral transporting hanging beam and its operation principle

Publications (1)

Publication Number Publication Date
CN107738978A true CN107738978A (en) 2018-02-27

Family

ID=61233068

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711033177.1A Pending CN107738978A (en) 2017-10-30 2017-10-30 A kind of removable tower crane Integral transporting hanging beam and its operation principle

Country Status (1)

Country Link
CN (1) CN107738978A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021111122A1 (en) * 2019-12-03 2021-06-10 Subsea 7 Limited Spreader structures for lifting loads
CN113830656A (en) * 2021-10-12 2021-12-24 中船黄埔文冲船舶有限公司 Fixed frock of removal tympany group

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2404147A1 (en) * 1974-01-29 1975-07-31 Credelca Ag Lifting tackle with counterbalancing system - has hydraulic cylinders pivoting at auxiliary frame beam centres and on lifting hook
CN2765891Y (en) * 2004-12-24 2006-03-22 宗胜琪 Distance change type rectangular hanger
CN204057655U (en) * 2014-08-18 2014-12-31 中国航天空气动力技术研究院 A kind of composite aircraft suspension bracket
CN204847752U (en) * 2015-06-30 2015-12-09 沪东中华造船(集团)有限公司 Be used for hanging small -size sectionalised gallows of hook type crane handling
CN106044537A (en) * 2016-07-18 2016-10-26 中国建筑第五工程局有限公司深圳分公司 Truss for movably lifting horizontal platy objects

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2404147A1 (en) * 1974-01-29 1975-07-31 Credelca Ag Lifting tackle with counterbalancing system - has hydraulic cylinders pivoting at auxiliary frame beam centres and on lifting hook
CN2765891Y (en) * 2004-12-24 2006-03-22 宗胜琪 Distance change type rectangular hanger
CN204057655U (en) * 2014-08-18 2014-12-31 中国航天空气动力技术研究院 A kind of composite aircraft suspension bracket
CN204847752U (en) * 2015-06-30 2015-12-09 沪东中华造船(集团)有限公司 Be used for hanging small -size sectionalised gallows of hook type crane handling
CN106044537A (en) * 2016-07-18 2016-10-26 中国建筑第五工程局有限公司深圳分公司 Truss for movably lifting horizontal platy objects

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021111122A1 (en) * 2019-12-03 2021-06-10 Subsea 7 Limited Spreader structures for lifting loads
CN113830656A (en) * 2021-10-12 2021-12-24 中船黄埔文冲船舶有限公司 Fixed frock of removal tympany group

Similar Documents

Publication Publication Date Title
CN107738978A (en) A kind of removable tower crane Integral transporting hanging beam and its operation principle
CN203947421U (en) Compound beam cable stayed bridge direction across bridge prestress application device
CN205500610U (en) Handling system of low latitude group
CN205527291U (en) A frame type frame for hoisting two superimposed sheets
CN206051351U (en) Hang a kind of purlin for assembling and disassembling construction for bridge-collision-avoidance wall form
CN104018680A (en) Lifting method of large-span solid-web type arc beam
CN204850048U (en) Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel
CN203486787U (en) Integral lifting device for cabinet top of Wiggins coal gas cabinet
CN103835294A (en) Concrete casting frame for construction of cast-in-place pile and using method
CN105883605A (en) Web reinforcing device for crane
CN202380754U (en) Floor-type steel transfer trolley
CN201903043U (en) Plate girder laminated beam
CN204185146U (en) Construction of Steel Structure overhang crane between skyscraper two tall buildings
CN204873489U (en) Large -scale bridge crane girder inner structure
CN107055367A (en) The central jack-up system of internally climbing tower crane
CN211646007U (en) Bridge pier hanging surrounding basket construction platform
CN203497919U (en) Integral lifting device of helicopter platform
CN208869171U (en) One kind lifting reusable porous grade for steelwork tower truss and hangs lid
CN208856786U (en) Hoisting tooling suitable for Turbo-charged Marine Boiler
CN106185597A (en) A kind of large-scale Analytic Tower merogenesis special hanger for hoisting and hanging method
CN110921484B (en) Hoisting device and hoisting method for wet-process sulfuric acid production equipment
CN201980841U (en) Lifting lug for lifting helicopter platform and torch tower
CN205204600U (en) Mainboard fortune group
CN203681685U (en) Special chassis for full-hydraulic pipelayer
CN203112397U (en) Simple olecranon hoisting equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180227