CN107687155A - A kind of storehouse basin antiseepage is anti-to lift structure and method for arranging - Google Patents
A kind of storehouse basin antiseepage is anti-to lift structure and method for arranging Download PDFInfo
- Publication number
- CN107687155A CN107687155A CN201710891569.5A CN201710891569A CN107687155A CN 107687155 A CN107687155 A CN 107687155A CN 201710891569 A CN201710891569 A CN 201710891569A CN 107687155 A CN107687155 A CN 107687155A
- Authority
- CN
- China
- Prior art keywords
- geomembrane
- coarse sand
- cobble
- storehouse
- boulder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/16—Sealings or joints
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Revetment (AREA)
Abstract
本发明公布了一种库盆防渗抗抬动结构及布置方法,预先清理调节库(1)的库堤(1.3)的下表面直至设计的清基线(2),在所述的清基线(2)的上方铺设有下层土工膜(3),在所述的下层土工膜(3)的上方向上回填有卵砾石开挖料(5),在所述的卵砾石开挖料(5)的上方铺设有上层土工膜(4),在所述的上层土工膜(4)上安装有若干逆止阀(6);所述的下层土工膜(3)的两端向上顺延至库堤(1.3)顶部形成延伸部(3.3),所述的延伸部(3.3)与所述的上层土工膜(4)连成一个封闭的整体;它克服了现有技术中采用单一的排水措施难以解决库盆抗浮稳定的缺点,具有减小对逆止阀排水效果的依赖性,保证调节库安全有效运行的优点。
The invention discloses an anti-seepage and anti-lifting structure and arranging method of a reservoir basin, which pre-cleanes and adjusts the lower surface of the bank (1.3) of the reservoir (1) until the designed clearing baseline (2), in which the clearing baseline ( 2) is laid with a lower layer of geomembrane (3), above the upper direction of the lower layer of geomembrane (3) backfilled with pebble gravel excavation material (5), in the described pebble gravel excavation material (5) The upper layer geomembrane (4) is laid on the top, and some check valves (6) are installed on the upper layer geomembrane (4); the two ends of the lower layer geomembrane (3) are extended upwards to the embankment ( 1.3) The top forms an extension (3.3), and the extension (3.3) is connected with the upper geomembrane (4) to form a closed whole; The disadvantage of the anti-floating stability of the basin has the advantages of reducing the dependence on the drainage effect of the check valve and ensuring the safe and effective operation of the regulating reservoir.
Description
技术领域technical field
本发明涉及到土木工程中的水利水电工程技术领域,更加具体地说是一种库盆防渗抗抬动结构及布置方法。The invention relates to the technical field of water conservancy and hydropower engineering in civil engineering, and more specifically relates to an anti-seepage and anti-lifting structure and an arrangement method for a reservoir basin.
背景技术Background technique
甘肃夹山子水库铺设土工膜防渗,防渗面积57.93万m2,土工膜最大承压水深30m,防渗效果良好,是国内水库建设中首次采用大面积、高水头作用下的塑膜防渗新技术、新工艺。The Jiashanzi Reservoir in Gansu Province is paved with geomembrane for anti-seepage, with an anti-seepage area of 579,300 m 2 and a maximum water depth of 30m under pressure. New technology, new process.
泰安抽水蓄能电站上水库库底采用HDPE土工膜水平防渗,具有适应库底大范围填渣区变形能力强、防渗效果好的特点。土工膜防渗面积16万m2,膜上最大工作水头约37m,日最大工作水头变幅24m,是我国大型水电工程首次采用土工膜作为永久工程防渗方案。The bottom of the upper reservoir of Tai'an Pumped Storage Power Station adopts HDPE geomembrane for horizontal anti-seepage, which has the characteristics of strong deformation ability to adapt to the large-scale slag filling area at the bottom of the reservoir and good anti-seepage effect. The anti-seepage area of the geomembrane is 160,000 m 2 , the maximum working water head on the membrane is about 37m, and the maximum daily working head variation is 24m. It is the first time that a large-scale hydropower project in China uses geomembrane as a permanent anti-seepage solution.
南水北调中线总干渠渠道采用复合土工膜防渗,高地下水位渠段采用逆止阀自流内排、水泵抽排或换填结合排水法来降低地下水位。其中总干渠黄河北一菱河北段的部分渠段中渠基分布有大量卵石,透水性较强,采用单一的排水措施难以达到效果。设计采用换填法与排水法相结合的措施解决这一问题。通过在渠基设置粘性土换填层,改变渠基渗流特性,降低衬砌板下扬压力,确保衬砌板抗浮稳定,同时在换填层下设置集水暗管排水管网,将外水排入渠道内,以降低换填层下渗流压力,解决换填层抗浮稳定问题。但此渗控方案在缺乏粘性土的地区难以实施。Composite geomembrane anti-seepage is adopted for the main channel of the middle line of the South-to-North Water Diversion Project, and the high groundwater level channel section adopts self-flow internal drainage with check valve, water pump drainage or replacement and filling combined drainage method to reduce the groundwater level. Among them, there are a large number of pebbles distributed in part of the canal section of the Yellow River Hebei-Linghe Hebei section of the main canal, which has strong water permeability, and it is difficult to achieve the effect with a single drainage measure. The design adopts a combination of filling method and drainage method to solve this problem. By setting a cohesive soil replacement layer on the canal foundation, the seepage characteristics of the canal foundation can be changed, the downlift pressure of the lining slab can be reduced, and the anti-floating stability of the lining slab can be ensured. In order to reduce the seepage pressure under the replacement layer and solve the problem of anti-floating stability of the replacement layer. However, this seepage control scheme is difficult to implement in areas lacking cohesive soil.
发明内容Contents of the invention
本发明的第一目的在于克服上述背景技术的不足之处而提出一种库盆防渗抗抬动结构。The first purpose of the present invention is to overcome the shortcomings of the above-mentioned background technology and propose an anti-seepage and anti-lifting structure for the storage basin.
本发明的技术方案是通过如下措施来实施的:一种库盆防渗抗抬动结构,预先清理调节库的库堤的下表面直至设计的清基线,在所述的清基线的上方铺设有下层土工膜,The technical solution of the present invention is implemented through the following measures: a storage basin anti-seepage and anti-lifting structure, which pre-cleanes the lower surface of the storage embankment of the adjustment storage until the designed clearing baseline, and lays above the clearing baseline Underlying geomembrane,
在所述的下层土工膜的上方向上回填有卵砾石开挖料,在所述的卵砾石开挖料的上方铺设有上层土工膜,在所述的上层土工膜上安装有若干逆止阀;Backfill pebble excavation materials above the lower layer geomembrane, lay an upper layer geomembrane above the pebble gravel excavation material, and several check valves are installed on the upper layer geomembrane ;
所述的下层土工膜的两端向上顺延至库堤顶部形成延伸部,所述的延伸部与所述的上层土工膜连成一个封闭的整体。The two ends of the lower geomembrane extend upwards to the top of the dike to form an extension, and the extension is connected with the upper geomembrane to form a closed whole.
在上述技术方案中:在所述的上层土工膜下表面与所述的卵砾石开挖料之间粗砂下垫层,在所述的上层土工膜上表面依次铺设有粗砂上垫层和干砌石。In the above technical scheme: between the lower surface of the upper geomembrane and the pebble gravel excavation material, the coarse sand underlayment is successively laid on the upper surface of the upper geomembrane with a coarse sand underlayment and dry Masonry.
在上述技术方案中:在所述的下层土工膜的延伸部外侧设置有卵砾石开挖料填筑区,在所述的卵砾石开挖料填筑区的外坡顺坡设置有铅丝石笼。In the above technical scheme: a pebble excavation material filling area is provided outside the extension of the lower geomembrane, and lead wire gabions are arranged on the outer slope of the pebble gravel excavation material filling area along the slope .
在上述技术方案中:在所述的下层土工膜的延伸部内侧与所述的卵砾石开挖料之间,以及所述的延伸部外侧与卵砾石开挖料填筑区之间均沿纵向设置有粗砂保护层,所述的粗砂保护层与所述的卵砾石开挖料和卵砾石开挖料填筑区齐平铺设。In the above technical solution: between the inner side of the extension of the lower geomembrane and the pebble excavation material, and between the outer side of the extension and the pebble excavation material filling area are all along the longitudinal direction A coarse sand protection layer is provided, and the coarse sand protection layer is laid flush with the pebble gravel excavation material and the pebble gravel excavation material filling area.
在上述技术方案中:所述的下层土工膜距离干砌石的上表面深度为2-4米。In the above technical solution: the depth of the lower geomembrane from the upper surface of the dry stone is 2-4 meters.
在上述技术方案中:在所述的下层土工膜下方与所述的清基线之间铺设有第一粗砂垫层,在所述的下层土工膜上方与所述的卵砾石开挖料之间铺设有第二粗砂垫层。In the above technical solution: a first coarse sand cushion is laid between the bottom of the lower geomembrane and the base clearing line, and between the above the lower geomembrane and the pebble excavation material A second coarse sand bedding is laid.
本发明的第二目的在于提出一种布置方法:一种库盆防渗抗抬动结构的布置方法,它包括如下步骤;The second object of the present invention is to propose an arrangement method: an arrangement method for an anti-seepage and anti-lift structure of a storage basin, which includes the following steps;
①、首先对调节库沿河布置的库堤进行清基和开挖直至设计的清基线高程位置;①. Firstly, carry out foundation clearing and excavation for the embankment arranged along the river of the regulating reservoir until the designed elevation position of the clearing baseline;
②、在所述的库堤下部依次水平铺设15厘米厚第一粗砂垫层、下层土工膜、15厘米厚第二粗砂垫层;2. Laying a 15-centimeter-thick first coarse sand cushion, a lower geomembrane, and a 15-centimeter-thick second coarse-sand cushion horizontally successively at the bottom of the embankment;
③、采用所述的卵砾石开挖料填筑所述的库堤,同时将所述的下层土工膜向上延伸并形成延伸部,在所述的延伸部两侧铺设0.5米厚的粗砂保护层,且所述的粗砂保护层与所述的卵砾石开挖料填筑同步进行;③. Use the pebble gravel excavation material to fill the embankment, extend the lower geomembrane upwards to form an extension, and lay 0.5 meters thick coarse sand on both sides of the extension for protection. layer, and the coarse sand protection layer is carried out synchronously with the filling of the pebble and gravel excavation material;
④、在施工所述的库堤的同时,开挖所述的调节库中部的库盆至库底开挖线高程位置;④. While constructing the embankment described above, excavate the reservoir basin in the middle of the regulating reservoir to the elevation position of the excavation line at the bottom of the reservoir;
⑤、沿步骤④中的库底开挖线上铺设15厘米厚第一粗砂垫层,再在所述的第一粗砂垫层上依次铺设下层土工膜和15厘米厚的所述的第二粗砂垫层;5. Lay the first coarse sand cushion with a thickness of 15 centimeters along the excavation line at the bottom of the reservoir in step 4, and then lay the lower geomembrane and the first coarse sand cushion with a thickness of 15 centimeters successively on the first coarse sand cushion. Two coarse sand cushions;
⑥、在步骤⑤中的第二粗砂垫层上部所述的卵砾石开挖料直至上层土工膜的粗砂下垫层的底面高程;6. The gravel excavation material described in the second coarse sand cushion top in step 5. is until the bottom surface elevation of the coarse sand lower cushion of the upper layer of geomembrane;
⑦、在步骤⑥中所述的卵砾石开挖料上部铺设15厘米厚的所述的粗砂下垫层,再在所述的粗砂下垫层往上铺设上层土工膜,然后在所述的上层土工膜浇筑有若干混凝土基座,将所述的上层土工膜伸入到混凝土基座中,且在所述的混凝土基座中预埋PVC排水管;7. Lay the 15 cm thick described coarse sand underlayment on the pebble gravel excavation material top described in step 6., then lay the upper layer of geomembrane on the coarse sand underlayment, and then lay The upper layer geomembrane is poured with several concrete bases, the upper layer geomembrane is extended into the concrete base, and PVC drainage pipes are pre-embedded in the concrete base;
⑧、在所述的上层土工膜上部依次往上铺设15厘米厚的粗砂上垫层和30厘米厚的干砌石,最后在步骤⑦的PVC排水管中安装有逆止阀;8. Lay 15 centimeters of thick coarse sand upper cushion and 30 centimeters of dry masonry successively on the top of the upper geomembrane, and finally a check valve is installed in the PVC drainage pipe of step 7.
⑨、将所述的上层土工膜和下层土工膜两侧连为一体并浇入库堤顶部的混凝土结构内形成封闭结构。9. Connect the two sides of the upper geomembrane and the lower geomembrane into one body and pour them into the concrete structure on the top of the embankment to form a closed structure.
在上述技术方案中:在所述的下层土工膜的外侧设置有所述的卵砾石开挖料填筑区,在所述的卵砾石开挖料填筑区的外坡顺坡设置有铅丝石笼。In the above technical scheme: the pebble excavation material filling area is arranged on the outer side of the lower geomembrane, and lead wire stone is arranged on the outer slope of the pebble gravel excavation material filling area along the slope cage.
在上述技术方案中:所述的下层土工膜距离干砌石上表面的深度为2-4米。In the above technical solution: the depth of the lower geomembrane from the upper surface of the dry masonry is 2-4 meters.
本发明具有如下优点:1、大大减少防渗墙工程量,节省投资约 3700万人民币(具体详见具体实施中表1)。2、取消管网排水系统,运行管理便利。3、减小对逆止阀排水效果的依赖性,保证调节库安全有效运行。The present invention has following advantages: 1, greatly reduce cut-off wall engineering quantity, save investment about 37 million RMB (see Table 1 in concrete implementation for details). 2. The pipe network drainage system is canceled, and the operation and management are convenient. 3. Reduce the dependence on the drainage effect of the check valve to ensure the safe and effective operation of the regulating reservoir.
附图说明Description of drawings
图1为本发明的结构布置示意图。Fig. 1 is a schematic diagram of the structural arrangement of the present invention.
图2为上层土工膜与逆止阀的结构布置示意图。Figure 2 is a schematic diagram of the structural arrangement of the upper geomembrane and the check valve.
图中:调节库1、库底开挖线1.1、库盆1.2、库堤1.3、清基线2、下层土工膜3、卵砾石开挖料填筑区3.1、铅丝石笼3.2、延伸部3.3、上层土工膜4、卵砾石开挖料5、粗砂保护层5.1、第一粗砂垫层5.2、第二粗砂垫层5.3、逆止阀6、混凝土基座7、PVC排水管 7.1、粗砂下垫层8、粗砂上垫层9、干砌石10。In the figure: regulating reservoir 1, reservoir bottom excavation line 1.1, reservoir basin 1.2, reservoir embankment 1.3, clearing base line 2, lower geomembrane 3, gravel excavation material filling area 3.1, lead wire gabion 3.2, extension part 3.3, Upper geomembrane 4, gravel excavation material 5, coarse sand protective layer 5.1, first coarse sand cushion 5.2, second coarse sand cushion 5.3, check valve 6, concrete base 7, PVC drainage pipe 7.1, coarse Cushion under sand 8, cushion on coarse sand 9, dry stone 10.
具体实施方式detailed description
下面结合附图详细说明本发明的实施情况,但它们并不构成对本发明的限定,仅作举例而已;同时通过说明对本发明的优点将变得更加清楚和容易理解。The implementation of the present invention will be described in detail below in conjunction with the accompanying drawings, but they do not constitute a limitation to the present invention, but are only examples; at the same time, the advantages of the present invention will become clearer and easier to understand through description.
参照图1-2所示:一种库盆防渗抗抬动结构,预先清理调节库1 的库堤1.3的下表面直至设计的清基线2,在所述的清基线2的上方铺设有下层土工膜3,Referring to Fig. 1-2, it is an anti-seepage and anti-lifting structure for the storage basin. The lower surface of the embankment 1.3 of the adjustment storage 1 is pre-cleaned until the designed clearing base line 2, and a lower layer is laid above the clearing base line 2. Geomembrane 3,
在所述的下层土工膜3的上方向上回填有卵砾石开挖料5,在所述的卵砾石开挖料5的上方铺设有上层土工膜4,在所述的上层土工膜4上安装有若干逆止阀6;Above described lower layer geomembrane 3, be backfilled with pebble gravel excavation material 5 upwards, above described pebble gravel excavation material 5, lay with upper strata geomembrane 4, install on described upper strata geomembrane 4 There are several check valves 6;
所述的下层土工膜3的两端向上顺延至库堤1.3顶部并形成延伸部3.3,所述的延伸部3.3与所述的上层土工膜4连成一个封闭的整体。Both ends of the lower geomembrane 3 extend upwards to the top of the dike 1.3 to form an extension 3.3, and the extension 3.3 is connected with the upper geomembrane 4 to form a closed whole.
在所述的上层土工膜4下表面与所述的卵砾石开挖料5之间粗砂下垫层8,在所述的上层土工膜4上表面依次铺设有粗砂上垫层9和干砌石10。Between the lower surface of the upper geomembrane 4 and the gravel excavation material 5, the coarse sand underlayment 8 is successively laid on the upper surface of the upper geomembrane 4 with a coarse sand upper cushion 9 and dry laying. Stone 10.
在所述的下层土工膜3的延伸部3.3内侧与所述的卵砾石开挖料5之间,以及外侧与卵砾石开挖料填筑区3.1之间均沿纵向设置有粗砂保护层5.1,所述的粗砂保护层5.1与所述的卵砾石开挖料5和卵砾石开挖料填筑区3.1齐平铺设。Between the inner side of the extension part 3.3 of the lower geomembrane 3 and the pebble excavation material 5, and between the outer side and the pebble gravel excavation material filling area 3.1, a coarse sand protective layer 5.1 is arranged longitudinally , the coarse sand protective layer 5.1 is laid flush with the pebble and gravel excavation material 5 and the pebble and gravel excavation material filling area 3.1.
在所述的下层土工膜3的延伸部3.3的外侧设置有卵砾石开挖料填筑区3.1,在所述的卵砾石开挖料填筑区3.1的外坡顺坡设置有铅丝石笼3.2。On the outer side of the extension part 3.3 of the lower geomembrane 3, a pebble excavation material filling area 3.1 is arranged, and a lead wire gabion 3.2 is arranged on the outer slope of the pebble gravel excavation material filling area 3.1 along the slope .
所述的下层土工膜3距离干砌石10上表面的深度为2-4米。The depth of the lower geomembrane 3 from the upper surface of the dry stone 10 is 2-4 meters.
在所述的下层土工膜3下方与所述的库底开挖线1.1之间铺设有第一粗砂垫层5.2。A first coarse sand cushion layer 5.2 is laid between the lower geomembrane 3 and the reservoir bottom excavation line 1.1.
本发明还包括一种布置方法:一种库盆防渗抗抬动结构的布置方法,它包括如下步骤;The present invention also includes an arrangement method: an arrangement method for an anti-seepage and anti-lifting structure of a storage basin, which includes the following steps;
①、首先对调节库1的库堤1.3进行清基和开挖直至设计的清基线2高程位置;①. Firstly, carry out foundation clearing and excavation to the embankment 1.3 of the regulating reservoir 1 until the designed elevation position of the clearing baseline 2;
②、在所述的库堤1.3下部依次水平铺设15厘米厚的第一粗砂垫层5.2、下层土工膜3、15厘米厚的所述的第二粗砂垫层5.3;2. Lay the first coarse sand cushion 5.2, the lower layer geomembrane 3, and the second coarse sand cushion 5.3 with a thickness of 15 centimeters horizontally successively at the bottom of the embankment 1.3;
③、采用卵砾石开挖料5填筑所述的库堤1.3,同时将所述的下层土工膜3两侧向上延伸并形成延伸部3.3,在所述的延伸部3.3两侧铺设0.5米厚的粗砂保护层5.1,且所述的粗砂保护层5.1与所述的卵砾石开挖料5的填筑同步进行;③. Use pebble gravel excavation material 5 to fill the embankment 1.3, and simultaneously extend the two sides of the lower geomembrane 3 upwards to form an extension 3.3, and lay 0.5 meters thick on both sides of the extension 3.3 The coarse sand protection layer 5.1, and the filling of the coarse sand protection layer 5.1 and the pebble excavation material 5 is carried out synchronously;
④、在施工所述的库堤1.3的同时,开挖所述的调节库1中部的库盆1.2至库底开挖线1.1高程位置;④. While constructing the embankment 1.3 described above, excavate the reservoir basin 1.2 in the middle of the regulating reservoir 1 to the elevation position of the excavation line 1.1 at the bottom of the reservoir;
⑤、沿步骤④中的库底开挖线1.1上铺设15厘米厚第一粗砂垫层5.2,再在所述的第一粗砂垫层5.2上依次铺设下层土工膜3和15 厘米厚的所述的第二粗砂垫层5.3;5. Lay the first coarse sand cushion 5.2 with a thickness of 15 centimeters on the excavation line 1.1 at the bottom of the reservoir in step 4., then lay the lower floor geomembrane 3 and 15 centimeters thick on the first coarse sand cushion 5.2 successively. The second coarse sand cushion layer 5.3;
⑥、在步骤⑤中的第二粗砂垫层5.3上部的卵砾石开挖料5直至上层土工膜4的粗砂下垫层8的底面高程;6. The second coarse sand cushion layer 5.3 top in step 5. The gravel excavation material 5 until the bottom surface elevation of the coarse sand lower cushion layer 8 of the upper geomembrane 4;
⑦、在步骤⑥中所述的卵砾石开挖料5上部铺设15cm厚的所述的粗砂下垫层8,再在所述的粗砂下垫层8往上铺设上层土工膜4,然后在所述的上层土工膜4浇筑有若干混凝土基座7,将所述的上层土工膜4伸入到混凝土基座7中,且在所述的混凝土基座7中预埋PVC排水管7.1;7. Lay the 15cm thick described coarse sand underlayment 8 on the pebble excavation material 5 tops described in step 6., then lay the upper floor geomembrane 4 on the coarse sand underlayment 8, and then A number of concrete bases 7 are poured on the upper geomembrane 4, and the upper geomembrane 4 is inserted into the concrete base 7, and PVC drainage pipes 7.1 are pre-embedded in the concrete base 7;
⑧、在所述的上层土工膜4上部依次往上铺设15厘米厚的粗砂上垫层9和30厘米厚的干砌石10,最后在步骤⑦的PVC排水管7.1 中安装逆止阀6;8. Lay 15 centimeters thick coarse sand upper cushion 9 and 30 centimeters thick dry masonry stone 10 upwards successively on the upper strata geomembrane 4 tops, finally install check valve 6 in the PVC drainage pipe 7.1 of step 7;
⑨、将所述的上层土工膜4和下层土工膜5两侧连为一体并浇入库堤1.3顶部的混凝土结构内形成封闭结构。9. Connect the two sides of the upper layer geomembrane 4 and the lower layer geomembrane 5 into one body and pour them into the concrete structure at the top of the embankment 1.3 to form a closed structure.
表1Table 1
上述未详细说明的部分均为现有技术。The parts not described in detail above are all prior art.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710891569.5A CN107687155B (en) | 2017-09-27 | 2017-09-27 | An anti-seepage and anti-lifting structure and layout method of storage basin |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710891569.5A CN107687155B (en) | 2017-09-27 | 2017-09-27 | An anti-seepage and anti-lifting structure and layout method of storage basin |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107687155A true CN107687155A (en) | 2018-02-13 |
CN107687155B CN107687155B (en) | 2023-04-25 |
Family
ID=61156695
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710891569.5A Active CN107687155B (en) | 2017-09-27 | 2017-09-27 | An anti-seepage and anti-lifting structure and layout method of storage basin |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107687155B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108547260A (en) * | 2018-06-05 | 2018-09-18 | 中国电建集团贵阳勘测设计研究院有限公司 | Seepage-proofing treatment structure for reservoir full-reservoir basin in karst region and construction method |
CN109555084A (en) * | 2019-01-17 | 2019-04-02 | 中国电建集团华东勘测设计研究院有限公司 | Bottom storehouse geomembrane anti-seepage bedding gas collection exhaust structure and its construction method |
CN112796281A (en) * | 2021-01-28 | 2021-05-14 | 中国电建集团北京勘测设计研究院有限公司 | A joint structure of asphalt concrete panel and surrounding rigid concrete |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101429757A (en) * | 2008-12-10 | 2009-05-13 | 河南国网宝泉抽水蓄能有限公司 | Construction method for asphalt concrete and clay soil anti-seepage connector and full anti-seepage dam basin |
CN102839629A (en) * | 2012-08-17 | 2012-12-26 | 北京科技大学 | Method and structure for disturbed riverbed seepage-proof governing |
CN202767031U (en) * | 2012-03-16 | 2013-03-06 | 中国水电顾问集团华东勘测设计研究院 | Reservoir basin clay paving and seepage preventing structure |
CN102995599A (en) * | 2012-11-15 | 2013-03-27 | 西安理工大学 | Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal |
CN207727514U (en) * | 2017-09-27 | 2018-08-14 | 长江勘测规划设计研究有限责任公司 | A kind of library basin antiseepage is anti-to lift structure |
-
2017
- 2017-09-27 CN CN201710891569.5A patent/CN107687155B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101429757A (en) * | 2008-12-10 | 2009-05-13 | 河南国网宝泉抽水蓄能有限公司 | Construction method for asphalt concrete and clay soil anti-seepage connector and full anti-seepage dam basin |
CN202767031U (en) * | 2012-03-16 | 2013-03-06 | 中国水电顾问集团华东勘测设计研究院 | Reservoir basin clay paving and seepage preventing structure |
CN102839629A (en) * | 2012-08-17 | 2012-12-26 | 北京科技大学 | Method and structure for disturbed riverbed seepage-proof governing |
CN102995599A (en) * | 2012-11-15 | 2013-03-27 | 西安理工大学 | Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal |
CN207727514U (en) * | 2017-09-27 | 2018-08-14 | 长江勘测规划设计研究有限责任公司 | A kind of library basin antiseepage is anti-to lift structure |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108547260A (en) * | 2018-06-05 | 2018-09-18 | 中国电建集团贵阳勘测设计研究院有限公司 | Seepage-proofing treatment structure for reservoir full-reservoir basin in karst region and construction method |
CN109555084A (en) * | 2019-01-17 | 2019-04-02 | 中国电建集团华东勘测设计研究院有限公司 | Bottom storehouse geomembrane anti-seepage bedding gas collection exhaust structure and its construction method |
CN109555084B (en) * | 2019-01-17 | 2023-09-12 | 中国电建集团华东勘测设计研究院有限公司 | Reservoir bottom geomembrane impermeable-laid gas collection and exhaust structure and construction method thereof |
CN112796281A (en) * | 2021-01-28 | 2021-05-14 | 中国电建集团北京勘测设计研究院有限公司 | A joint structure of asphalt concrete panel and surrounding rigid concrete |
Also Published As
Publication number | Publication date |
---|---|
CN107687155B (en) | 2023-04-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205874850U (en) | Railway soft soil foundation light soil roadbed structure | |
CN103046565B (en) | Draining method for ultra-deep batholith deep foundation pit | |
CN103741714A (en) | Full-cover excavation top-down construction method for underground engineering | |
CN104131575A (en) | Plugging and drainage method for dam foundation on karst highly developed stratum | |
CN109208545B (en) | Construction method of artificial landscape overflow dam with energy dissipation effect | |
CN110004991B (en) | Underground structure anti-floating system based on convex wing foot plate and construction method | |
CN207760804U (en) | A kind of Multi-functional economy dike structure | |
CN106759133A (en) | The mixing structure of dam type and construction method of a kind of homogeneous earth and rockfill dam and rock | |
CN102995599A (en) | Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal | |
CN104790410B (en) | A kind of Support of Foundation Pit Excavation method that is applicable to shallow water mud river course | |
CN106049379B (en) | Temporary power generation method during construction lag of downstream of spillway and rockfill self-breaking dam | |
CN111519580A (en) | A kind of embankment anti-seepage structure and construction method | |
CN107687155B (en) | An anti-seepage and anti-lifting structure and layout method of storage basin | |
CN107152012A (en) | Sluice construction technique | |
CN203939036U (en) | A kind of steel sheet pile cofferdam structure that is applicable to river course | |
CN207727514U (en) | A kind of library basin antiseepage is anti-to lift structure | |
CN202865796U (en) | Bank protection structure with reinforced concrete prefabricated slab piles | |
CN104372765A (en) | Frame column type frame bank protection structure for city watercourse and construction method of bank protection structure | |
CN102535289A (en) | Variable cross-section structure of roadbed deep infiltration trench and construction method thereof | |
CN111441372A (en) | Landslide foundation treatment embankment structure and construction method | |
CN113216124B (en) | An anti-seepage cofferdam system for ship lock reconstruction and expansion project | |
CN101413269A (en) | Vacuum curtain water stop and atmospheric pressure support deep pit digging construction method | |
CN114439027A (en) | Construction method of concrete building foundation on deep and strong permeable foundation of hydropower project | |
CN106761914B (en) | A kind of routed water water damage prevention and controls of shallow buried coal seam mine raceway groove flood | |
CN102704437A (en) | Coal mining subsidence area cultivation water source reconstruction method suitable for complex mountain area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |