CN107642065B - 一种疏浚吹填充砂袋施工工艺 - Google Patents

一种疏浚吹填充砂袋施工工艺 Download PDF

Info

Publication number
CN107642065B
CN107642065B CN201710938012.2A CN201710938012A CN107642065B CN 107642065 B CN107642065 B CN 107642065B CN 201710938012 A CN201710938012 A CN 201710938012A CN 107642065 B CN107642065 B CN 107642065B
Authority
CN
China
Prior art keywords
sand
filling
blowing
warehouse
dredging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710938012.2A
Other languages
English (en)
Other versions
CN107642065A (zh
Inventor
刘恩伟
冯国林
周志强
文栋
杨兵
郑旺
陆书勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Tianjin Dredging Co Ltd
CCCC National Engineering Research Center of Dredging Technology and Equipment Co Ltd
CCCC Tianjin Dredging Engineering Co Ltd
Original Assignee
CCCC Tianjin Dredging Co Ltd
CCCC TDC Binhai Environmental Channel Dredging Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Tianjin Dredging Co Ltd, CCCC TDC Binhai Environmental Channel Dredging Co Ltd filed Critical CCCC Tianjin Dredging Co Ltd
Priority to CN201710938012.2A priority Critical patent/CN107642065B/zh
Publication of CN107642065A publication Critical patent/CN107642065A/zh
Application granted granted Critical
Publication of CN107642065B publication Critical patent/CN107642065B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Barrages (AREA)
  • Revetment (AREA)

Abstract

本发明涉及一种疏浚吹填充砂袋施工工艺。包括以下步骤,(1)优化砂库方案,根据砂库地形和贝壳含量分布,分析设立的砂库区域的砂源质量,选取贝壳含量低于20%的外缘区域进行挖泥作业;(2)在砂库的外缘修建临时充砂袋挡埝,阻挡潮水以增加有效取砂时间;(3)在砂库四周区域根据地形划分设立2‑4个小砂库;(4)在挖泥作业的绞吸挖泥船的主管路上加装三通分流器,主管路排出大体积贝壳及粘土球,支管作为吹砂管将筛分得到的合格砂源向砂库内进行吹砂;(5)在主砂库与各小砂库之间轮流取砂对充砂袋进行吹填,安排挖泥作业的绞吸挖泥船向取砂完成的砂库内再次吹砂;(6)重复步骤(5)。

Description

一种疏浚吹填充砂袋施工工艺
技术领域
本发明属于疏浚施工技术领域,尤其涉及一种疏浚吹填充砂袋施工工艺。
背景技术
在疏浚现场施工中,通常涉及到充砂袋施工工艺,即引堤采用两侧充砂袋围堰,之后进行内部回填,形成引堤本体。项目施工中,充砂袋前期采用水下取砂工艺,但因土质原因通常不能成功实施,因此通常采用绞吸船进场备砂,之后采取干地取砂充填砂袋,然而此种方式下,施工成本会显著提升,而且对施工的工期产生明显影响。改进充砂袋施工工艺的关键点和难点是砂源的获取。
现场施工条件下,砂源获取上通常受限于以下因素:(1)现场砂源贝壳含量高,施工中堵管严重。绞吸吹填砂源中贝壳含量较高,现场取样分析,砂源中贝壳含量体积占比高。因贝壳类流动性较差,不易输送,充砂施工中泥浆泵软管和吹砂管线频繁堵管。(2)现场资源匮乏,船机设备有限。项目所在地资源匮乏,无充砂袋施工所需的铺排船、运砂船和吹沙船,现场施工所需的接力泵站、发电机平台、对拉平台均利用现场物资焊接改造而成。(3)设计临时围堰位置水深较深、风浪大、潮流急且涨落潮流速较大,局部区域达到4节,充砂袋围堰定位施工难度大。(4)充砂袋设计区域水下地形复杂,起伏变化较大。项目施工区域水下地形复杂,暗礁和深槽密布,地形起伏变化较大;且砂库两侧均为深槽,充砂施工管线无法避免。(5)临时围堰深水区充砂袋分层填筑施工,难度较大。根据临时围堰设计图纸,深水区需要分层施工,完成第一层充砂袋后,绞吸船内侧反压吹填,再进行第二层施工,难度较大。(6)现场困难预估不足。项目水工由协作单位负责施工,前期考察期间对该项目难度预估不足,进场吹砂管线均为旧管,质量较差,施工期间爆裂较多,严重影响施工。
因此根据项目施工需要开发一种吹填充砂袋施工工艺显得尤为必要。
发明内容
本发明为解决公知技术中存在的技术问题而提供一种疏浚吹填充砂袋施工工艺,解决背景技术中指出的诸多问题。
本发明为解决公知技术中存在的技术问题所采取的技术方案是:一种疏浚吹填充砂袋施工工艺包括以下步骤,(1)优化砂库方案,根据砂库地形和贝壳含量分布,分析设立的砂库区域的砂源质量,选取贝壳含量低于20%的外缘区域进行挖泥作业;(2)在砂库的外缘修建临时充砂袋挡埝,阻挡潮水以增加有效取砂时间;(3)在砂库四周区域根据地形划分设立2-4个小砂库;(4)在挖泥作业的绞吸挖泥船的主管路上加装三通分流器,主管路排出大体积贝壳及粘土球,支管作为吹砂管将筛分得到的合格砂源向砂库内进行吹砂;(5)在主砂库与各小砂库之间轮流取砂对充砂袋进行吹填,安排挖泥作业的绞吸挖泥船向取砂完成的砂库内再次吹砂;(6)重复步骤(5)。
本发明的优点和积极效果是:本发明提供了一种疏浚吹填充砂袋施工工艺,与现有的施工工艺相比,本技术方案中通过优化砂库的位置以及数量配置、修建临时潮水挡埝,为吹砂取砂提供了合适的现场施工条件。通过在绞吸挖泥船的主管路上设置三通分流器对主管路内的泥水混合物进行筛分,实现了合格砂源的持续获取,解决了背景技术中砂源获取难度大、贝壳等杂志含量高带来的堵管问题。由于优化了砂源的质量,故对现场的船机设备和接力泵站等的要求明显降低。通过在主砂库与多个小砂库之间轮流取砂和吹砂,实现了不间断作业的效果,提升了项目施工的速度,加快了工期。
优选地:还包括直接吹填充砂袋的步骤,在挖泥作业的绞吸挖泥船主管路上的三通分流器的支管端部加装闸阀以及连接管路,连接管路直接与充砂袋的进砂口对接连接。
具体实施方式
为能进一步了解本发明的发明内容、特点及功效,兹举以下实施例详细说明如下:
本发明的疏浚吹填充砂袋施工工艺包括以下步骤,(1)优化砂库方案,根据砂库地形和贝壳含量分布,分析设立的砂库区域的砂源质量,选取贝壳含量低于20%的外缘区域进行挖泥作业;(2)在砂库的外缘修建临时充砂袋挡埝,阻挡潮水以增加有效取砂时间;(3)在砂库四周区域根据地形划分设立2-4个小砂库;(4)在挖泥作业的绞吸挖泥船的主管路上加装三通分流器,主管路排出大体积贝壳及粘土球,支管作为吹砂管将筛分得到的合格砂源向砂库内进行吹砂;(5)在主砂库与各小砂库之间轮流取砂对充砂袋进行吹填,安排挖泥作业的绞吸挖泥船向取砂完成的砂库内再次吹砂;(6)重复步骤(5)。
本实施例中,还包括直接吹填充砂袋的步骤,在挖泥作业的绞吸挖泥船主管路上的三通分流器的支管端部加装闸阀以及连接管路,连接管路直接与充砂袋的进砂口对接连接。此步骤下,充砂袋的吹填效率为40m3/h,仍有提升空间,作为一种辅助工艺进行。
1、排除充砂袋的吹砂管线故障:
(1)全面排查吹砂管线,将质量较差的吹砂管全部更换;
(2)为防止吹砂过程中管线频繁起浮弯折,在接力泵船出口管线处改造焊接排气阀,及时排出施工过程中吹砂管线中的空气,避免管线起浮;
(3)吹砂管线沉放时考虑潮流影响,低平潮沉放,并在管线易出现弯折区域改造加装橡胶胶管。
2、降低吹砂管堵管风险
(1)适当降低泥浆泵浓度,降低堵塞风险。增加吸砂泥浆泵补水高压水枪,适当降低泥浆泵吸砂浓度;其次在泥浆泵出口处焊接补水支管,增大泥浆泵水带流速,降低水带堵塞风险;第三将补水泥浆泵补水口调整至合流器,降低吹砂管线堵塞风险;
(2)调整水带和吹砂管布设,保持管线施工期间平顺,避免弯折出现;
(3)因泥浆泵水带易出现弯折堵塞,因此延长吹砂管线长度,缩短泥浆泵水带长度,降低水带堵塞风险。
3、形成备砂砂库
(1)优化砂库方案。根据砂库地形和贝壳含量分布,分析砂库区域砂源质量,选取贝壳含量稍低的外缘区域施工;
(2)为减少砂库外缘施工受潮水的影响,现场在砂库外缘修建临时充砂袋挡埝,阻挡潮水,增加有效取砂时间;
(3)将砂库四周区域根据地形划分为2-4个小砂库,取砂作业时轮流取砂,安排绞吸挖泥船在取砂完成的小砂库内再次吹砂,并适当提高砂层厚度,满足取砂要求;
4、主管路的改进
(1)在主管路上安装三通分流器提高备砂质量
为储备优质砂源,利用三通改造分流器,主管路排出大体积贝壳及粘土球等,支管实现对砂的过滤。同时,绞吸挖泥船开挖上层砂切泥厚度可适当加深,备砂同时保证疏浚效率;
三通分流器的结构:在支管的内端焊接固定滤网,滤网可以采用如钢板切割、钢筋焊接制成等方式,格栅间隙均为设定为10mm-20mm;
经过12小时的备砂试验,砂库的沙坑标高上升约1m,其余地区暂无明显变化,坡比平缓,吹填砂质量良好。
(2)绞吸挖泥船直接吹填充砂袋
为提高充砂产量,避免泥浆泵接力取砂造成的堵管爆管,在支管管口焊接法兰、增加闸阀,直接连接充砂袋的进砂口进行吹填。

Claims (2)

1.一种疏浚吹填充砂袋施工工艺,其特征是:包括以下步骤,
(1)优化砂库方案,根据砂库地形和贝壳含量分布,分析设立的砂库区域的砂源质量,选取贝壳含量低于20%的外缘区域进行挖泥作业;
(2)在砂库的外缘修建临时充砂袋挡埝,阻挡潮水以增加有效取砂时间;
(3)在砂库四周区域根据地形划分设立2-4个小砂库;
(4)在挖泥作业的绞吸挖泥船的主管路上加装三通分流器,主管路排出大体积贝壳及粘土球,支管作为吹砂管将筛分得到的合格砂源向砂库内进行吹砂;三通分流器通过在三通管的支管内端焊接固定滤网得到,滤网为格栅结构且格栅间隙为10mm-20mm;在接力泵船出口管线处安装排气阀,及时排出施工过程中吹砂管线中的空气;在吸砂泥浆泵处加设补水高压水枪,降低泥浆泵的吸砂浓度;在泥浆泵出口处焊接补水支管,增大泥浆泵水带流速,降低水带堵塞风险;将补水泥浆泵补水口调整至合流器,降低吹砂管线堵塞风险;
(5)在主砂库与各小砂库之间轮流取砂对充砂袋进行吹填,安排挖泥作业的绞吸挖泥船向取砂完成的砂库内再次吹砂;
(6)重复步骤(5)。
2.如权利要求1所述的疏浚吹填充砂袋施工工艺,其特征是:还包括直接吹填充砂袋的步骤,在挖泥作业的绞吸挖泥船主管路上的三通分流器的支管端部加装闸阀以及连接管路,连接管路直接与充砂袋的进砂口对接连接。
CN201710938012.2A 2017-10-11 2017-10-11 一种疏浚吹填充砂袋施工工艺 Active CN107642065B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710938012.2A CN107642065B (zh) 2017-10-11 2017-10-11 一种疏浚吹填充砂袋施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710938012.2A CN107642065B (zh) 2017-10-11 2017-10-11 一种疏浚吹填充砂袋施工工艺

Publications (2)

Publication Number Publication Date
CN107642065A CN107642065A (zh) 2018-01-30
CN107642065B true CN107642065B (zh) 2019-12-17

Family

ID=61122923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710938012.2A Active CN107642065B (zh) 2017-10-11 2017-10-11 一种疏浚吹填充砂袋施工工艺

Country Status (1)

Country Link
CN (1) CN107642065B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162248B (zh) * 2018-09-25 2023-12-19 中交(天津)疏浚工程有限公司 一种远距离输送砂浆充填砂袋施工系统
CN109778784B (zh) * 2019-02-28 2020-09-15 重庆大学 一种远海钙质砂吹填微生物弱胶结装置及其施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102628273A (zh) * 2012-03-20 2012-08-08 水利部交通运输部国家能源局南京水利科学研究院 利用疏浚土充灌筑堤的大型充灌袋筑堤方法及其设备
CN205421371U (zh) * 2015-11-30 2016-08-03 中国港湾工程有限责任公司 码头地区珊瑚礁回填造地用填充装置
CN106869149A (zh) * 2017-01-12 2017-06-20 中交天航南方交通建设有限公司 一种用于土工管袋的拦砂坝蓄水充填施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102628273A (zh) * 2012-03-20 2012-08-08 水利部交通运输部国家能源局南京水利科学研究院 利用疏浚土充灌筑堤的大型充灌袋筑堤方法及其设备
CN205421371U (zh) * 2015-11-30 2016-08-03 中国港湾工程有限责任公司 码头地区珊瑚礁回填造地用填充装置
CN106869149A (zh) * 2017-01-12 2017-06-20 中交天航南方交通建设有限公司 一种用于土工管袋的拦砂坝蓄水充填施工方法

Also Published As

Publication number Publication date
CN107642065A (zh) 2018-01-30

Similar Documents

Publication Publication Date Title
CN110924961B (zh) 一种盾构机下穿既有车站始发的施工方法
CN106015737A (zh) 跨河沉管整体安装的施工方法
CN107642065B (zh) 一种疏浚吹填充砂袋施工工艺
CN109137943B (zh) 一种围填海的土方填筑施工工艺
CN103883797A (zh) 一种钢丝网骨架塑料复合管的施工方法
CN105544575A (zh) 一种采用钢桁架加筋的水下封底混凝土施工方法
CN110284547A (zh) 取水管的施工方法
CN107035918A (zh) 一种给水管件工程施工方法
CN110656621A (zh) 一种河道截流体系构造及施工方法
CN112901207A (zh) 运营隧道硫酸盐腐蚀段二衬换拱时洞内塌方的处治方法
CN111119277B (zh) 江河中取水管道穿越围堰连接的方法
CN111305355A (zh) 超大口径混凝土雨水管道接口防渗工艺
CN113832979A (zh) 一种基坑水冲法土方开挖施工方法
CN110565686A (zh) 管廊下穿河道的施工方法
CN106869149B (zh) 一种用于土工管袋的拦砂坝蓄水充填施工方法
CN104612128B (zh) 适用于水下淤泥环境的真空预压加固施工方法
CN110939150A (zh) 一种应对承压水突涌事故状态下的大水力坡降比薄壁结构快速构建的抢险方法
CN215169989U (zh) 冻结法加固60米级超长距离联络通道的冻结体系
CN109680699B (zh) 一种闭式海水源热泵系统干地施工方法
CN112921998A (zh) 一种适用于深厚淤泥覆盖层的围堰围护放坡基坑开挖方法
CN113152489B (zh) 一种诱导堆积体滑坡的结构及其施工方法
CN115506316B (zh) 高外水压力下密闭空间渗漏竖井混凝土回填方法
CN110985017A (zh) 膨胀土地层盾构下穿雨水箱涵的施工方法
CN112594444B (zh) 一种水厂至高山的供水主管道施工方法
CN117090207B (zh) 一种沉管隧道基础灌砂处理装置及施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: Room 346, Chentang technology incubator, 17 Yujiang Road, Hexi District, Tianjin, 300221

Patentee after: CCCC (Tianjin) Dredging Engineering Co.,Ltd.

Patentee after: CCCC TIANJIN DREDGING Co.,Ltd.

Address before: Tianhang building, No.1, Zhongxin Road, Tanggu District, Binhai New Area, Tianjin 300450

Patentee before: CCCC-TDC BINHAI ENVIRONMENTAL CHANNEL DREDGING Co.,Ltd.

Patentee before: CCCC TIANJIN DREDGING Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211018

Address after: Room 346, Chentang technology incubator, 17 Yujiang Road, Hexi District, Tianjin, 300221

Patentee after: CCCC (Tianjin) Dredging Engineering Co.,Ltd.

Patentee after: CCCC TIANJIN DREDGING Co.,Ltd.

Patentee after: NATIONAL ENGINEERING RESEARCH CENTER OF DREDGING TECHNOLOGY AND EQUIPMENT

Address before: Room 346, Chentang technology incubator, 17 Yujiang Road, Hexi District, Tianjin, 300221

Patentee before: CCCC (Tianjin) Dredging Engineering Co.,Ltd.

Patentee before: CCCC TIANJIN DREDGING Co.,Ltd.