CN107640282A - A kind of multi-purpose vessel axle, rudder system mounting process - Google Patents

A kind of multi-purpose vessel axle, rudder system mounting process Download PDF

Info

Publication number
CN107640282A
CN107640282A CN201710863751.XA CN201710863751A CN107640282A CN 107640282 A CN107640282 A CN 107640282A CN 201710863751 A CN201710863751 A CN 201710863751A CN 107640282 A CN107640282 A CN 107640282A
Authority
CN
China
Prior art keywords
rudder
ship
installation
center line
stock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710863751.XA
Other languages
Chinese (zh)
Inventor
许国华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Hong Kong Marine Mating Machinery Co Ltd
Original Assignee
Nantong Hong Kong Marine Mating Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Hong Kong Marine Mating Machinery Co Ltd filed Critical Nantong Hong Kong Marine Mating Machinery Co Ltd
Priority to CN201710863751.XA priority Critical patent/CN107640282A/en
Publication of CN107640282A publication Critical patent/CN107640282A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of multi-purpose vessel axle, rudder system mounting process, it comprises the following steps:A. before ship launching center line of shafting and rudder system center line determination, the positioning of b. stern pipes and epoxy casting, ship launching after anti-water seal board installation, c. carries out the installation of stern tube shaft, propeller, rudder stock and rudder blade again.Ten-thousand-ton grade special multipurpose vessel axle of the present invention, rudder system mounting process are adopted in such a way, the inconvenience that installation is brought must be carried out on the complete building berth before ship launching by overcoming the marine rear shaft of prior art, propeller, rudder stock, rudder blade equipment, simultaneously inspection declaration axis and rudder line relief ship launching is first determined on building berth, save and prepare marine rear shaft, propeller, rudder stock, the time of rudder blade equipment, shorten the construction period of ship, the utilization rate that shipbuilding unit builds longitudinal building berth of ship is improved, reduces manufacturing cost.

Description

A kind of multi-purpose vessel axle, rudder system mounting process
Technical field
The present invention relates to ship, more particularly to ten-thousand-ton grade special multipurpose vessel axle, rudder system mounting process.
Background technology
Ton Special multi-purpose ship be gross deadweight more than 10000 tons to Bulk Transport cereal, coal, ore in sand form, salt, water The multiduty ships such as large dry bulk cargo thing such as mud, the ship are designed as unit, single shafting, single rudder arrangement form, axis and baseline It is parallel, and in captain's central fore-and-aft vertical plane, rudder stock center line and axis perpendicular.Generally, the shafting of ship and rudder system are both needed to Installed before ship launching, and to shipowner and ship inspection apply for checking and examination it is qualified after could descend water.That is the shafting of ship and rudder system be Carried out on building berth or in dock.Traditional mounting means requires ship, and all axles, rudder system parts must be complete before lower water, It just can ensure that the installation before lower water.And all complete extensions for not only causing ship building period of axle, rudder system parts, Er Qiezao Into the reduction of the utilization rate for the longitudinal building berth for building ship, it will the production to shipbuilding unit causes greatly to adversely affect.
The content of the invention
The technical problems to be solved by the invention are:A kind of shortening ship building period is provided, shipbuilding unit is improved and builds Ten-thousand-ton grade special multipurpose vessel axle, the rudder system mounting process of the utilization rate of longitudinal building berth of ship.
Solve the technical problem, the technical scheme is that:A kind of multi-purpose vessel axle, rudder system mounting process, its Comprise the following steps:
A, before ship launching center line of shafting and rudder system center line determination,
B, the positioning of stern pipe and epoxy casting, ship launching after anti-water seal board installation,
C, the installation of stern tube shaft, propeller, rudder stock and rudder blade is carried out again.
The determination of center line of shafting and rudder system center line mainly includes the following steps that before ship launching in described step a:
1) stern pipe and rudder sleeve arrangement are prepared;
2) pre- bracing wire:The construction that is segmented in watercraft engine room and afterbody and pre- bracing wire is used when closing up, during closing up not Measured caused by welding and deformed on the basis of axis disconnectedly, and corrected in time, so as to it will weld as much as possible caused by Deformation control in minimum, it is ensured that the correct position of axle rudder line;
3) formal shafting and the bracing wire of rudder system:Full ship insertion is completed in hull, and all main welding jobs of afterbody are complete After the completion of portion, the formal bracing wire positioning of shafting and rudder system is proceeded by;
4) inspection of center line of shafting and rudder system center line and apply for checking and examination.
Install stern tube shaft, propeller, rudder stock and rudder blade in described step c and mainly comprise the following steps:
1) preparation of installation is carried out;
2) floading condition requirement during the underwater installation axle rudder system of ship is determined, ballast is carried out to ship;And check this ballast trim Under Hull Strength whether meet to require;
3) operating platform and safety net installed under water are built;
4) installation lifting and transhipment eye plate, hang up properly the lifting appliances such as cucurbit;
5) safe transit of stern tube shaft and lifting;
6) propeller and tail sealing, anti-fishnet appliance arrangement are installed;
7) rudder stock is transported to the bottom of ship, lifts up into steering gear flat and fixes from the bottom up;
8) safe transit of rudder blade in place, rudder stock is packed into from waterborne.
9) rudder stock is put down, carry out rudder stock and rudder blade waterborne are installed without key connection.
10) whole rudder stock and rudder blade are lifted to the height of drawing requirement;Zero-bit is adjusted, is applied for checking and examination appropriate, and it is fixed;
11) steering wheel is installed, only jumps block.
Described rudder stock carries out applying butter protection before lifting.
A kind of multi-purpose vessel axle of the present invention, rudder system mounting process adopt the ship in such a way, overcoming prior art Oceangoing ship tailing axle, propeller, rudder stock, rudder blade equipment must carry out the inconvenience that installation is brought on the complete building berth before ship launching, Simultaneously inspection declaration axis and rudder line relief ship launching is first determined on building berth, saves and prepares marine rear shaft, propeller, rudder stock, rudder blade The time of equipment, the construction period of ship is shortened, improve the utilization rate that shipbuilding unit builds longitudinal building berth of ship, reduce Manufacturing cost.
Embodiment
A kind of multi-purpose vessel axle, rudder system mounting process are by " double fixed middle receipts " Launching processing and " underwater installation axle rudder system " work Skill forms,
1st, the main contents of " double fixed middle receipts " Launching processing:
1) technical preparing and equipment prepare, it is ensured that tail pipe and rudder sleeve arrive factory on schedule.
2) pre- bracing wire:The construction that is segmented in watercraft engine room and afterbody and pre- bracing wire is used when closing up, during closing up not Measured caused by welding and deformed on the basis of axis disconnectedly, and corrected in time, so as to it will weld as much as possible caused by Deformation control in minimum, it is ensured that the correct position of axle rudder line.
3) formal shafting and the bracing wire of rudder system:Full ship insertion is completed in hull, and all main welding jobs of afterbody are complete After the completion of portion, the formal bracing wire positioning of shafting and rudder system is proceeded by.
4) inspection of center line of shafting and rudder system center line and apply for checking and examination.
5) positioning of stern pipe and epoxy casting.
6) anti-water seal board is installed.
7) ship launching.
2nd, the main contents of " underwater installation axle rudder system " technique:
1) according to the actual conditions of shipyard, the preparation of installation is carried out;
2) floading condition requirement during the underwater installation axle rudder system of ship is determined, ballast is carried out to ship;And check this ballast trim Under Hull Strength whether meet to require.
3) operating platform installed under water and safety net etc. are built.
4) installation lifting and transhipment eye plate, hang up properly the lifting appliances such as cucurbit.
5) safe transit of stern tube shaft and lifting.
6) equipment such as propeller and tail sealing, anti-fishnet device is installed.
7) rudder stock is transported to the bottom of ship, lifts up into steering gear flat and fixes from the bottom up;Rudder stock because of this ship is being hung Part is immersed in river during dress, therefore, needs to carry out rudder stock to apply butter protection before lifting.
8) safe transit of rudder blade in place, rudder stock is packed into from waterborne.
9) rudder stock is put down, carry out rudder stock and rudder blade waterborne are installed without key connection.
10) whole rudder stock and rudder blade are lifted to the height of drawing requirement;Zero-bit is adjusted, is applied for checking and examination appropriate, and it is fixed;
11) steering wheel installed according to the requirement of steering wheel factory, only jump block etc..
It is double to center " Launching processing and its meaning
In summary, ship " double to center " Launching processing is the inevitable choice for adapting to Modern Shipbuilding market.It is so-called double fixed Center, i.e. ship must fix two center lines of ship before lower water, and one is center line of shafting, one be rudder system center Line.Also only on the premise of the two center lines are secured, shipowner and ship examine the lower water that can just agree to ship.
The center line of shafting of ship wants to fix, and the tail pipe epoxy casting of ship must just work and complete.The rudder of ship It is that center line wants to fix, the rudder sleeve of ship must should be installed.Therefore, the premise of water is lower water under " double to center " Preceding tail pipe and rudder sleeve arrive factory on schedule and installation is applied for checking and examination.
The implementation of " double to center " Launching processing, not only overcomes the equipment such as marine rear shaft, propeller, rudder stock, rudder blade not The difficulty that can be delivered goods on schedule, solves equipment this " bottleneck " problem.
2nd, " underwater installation axle rudder system " technique and its meaning
Solve water under " double to center ", be not fully solved problem, because the equipment such as the tailing axle of ship, propeller exists To after factory, ship carries out the work such as mechanical and electric equipment installation just on the harbour of shipyard, if now by ship within 2 months or so after lower water Towage carries out shafting and the installation of rudder system to dock, and factory is gone back in towage again afterwards, on the one hand by the towage expense of both expensive and the expense that lies up With on the other hand also being had adverse effect on to ship building period.Also, due to the overheat of market of ship, it is suitable to find Dock be also one be difficult thing.
The realization of " underwater installation axle rudder system " technique, substantial amounts of cost of manufacture is on the one hand reduced, is on the other hand also shortened The construction period of ship, improve the utilization rate of longitudinal building berth of ship.

Claims (4)

1. a kind of multi-purpose vessel axle, rudder system mounting process, it is characterised in that:It comprises the following steps:
A, before ship launching center line of shafting and rudder system center line determination,
B, the positioning of stern pipe and epoxy casting, ship launching after anti-water seal board installation,
C, the installation of stern tube shaft, propeller, rudder stock and rudder blade is carried out again.
2. a kind of multi-purpose vessel axle according to claim 1, rudder system mounting process, it is characterised in that:Described step a The determination of center line of shafting and rudder system center line mainly includes the following steps that before middle ship launching:
1) stern pipe and rudder sleeve arrangement are prepared;
2) pre- bracing wire:The construction that is segmented in watercraft engine room and afterbody and pre- bracing wire is used when closing up, during closing up constantly Measured on the basis of axis and deformed caused by welding, and corrected in time, so as to which as much as possible caused change will be welded Shape is controlled in minimum, it is ensured that the correct position of axle rudder line;
3) formal shafting and the bracing wire of rudder system:Full ship insertion is completed in hull, and all main welding jobs of afterbody are all complete Cheng Hou, proceed by the formal bracing wire positioning of shafting and rudder system;
4) inspection of center line of shafting and rudder system center line and apply for checking and examination.
3. a kind of multi-purpose vessel axle according to claim 1, rudder system mounting process, it is characterised in that:Described step c The installation of middle stern tube shaft, propeller, rudder stock and rudder blade mainly comprises the following steps:
1) preparation of installation is carried out;
2) floading condition requirement during the underwater installation axle rudder system of ship is determined, ballast is carried out to ship;And check under this ballast trim Whether Hull Strength, which meets, requires;
3) operating platform and safety net installed under water are built;
4) installation lifting and transhipment eye plate, hang up properly the lifting appliances such as cucurbit;
5) safe transit of stern tube shaft and lifting;
6) propeller and tail sealing, anti-fishnet appliance arrangement are installed;
7) rudder stock is transported to the bottom of ship, lifts up into steering gear flat and fixes from the bottom up;
8) safe transit of rudder blade in place, rudder stock is packed into from waterborne.
9) rudder stock is put down, carry out rudder stock and rudder blade waterborne are installed without key connection.
10) whole rudder stock and rudder blade are lifted to the height of drawing requirement;Zero-bit is adjusted, is applied for checking and examination appropriate, and it is fixed;
11) steering wheel is installed, only jumps block.
4. a kind of multi-purpose vessel axle according to claim 3, rudder system mounting process, it is characterised in that:Described rudder stock Carry out applying butter protection before lifting.
CN201710863751.XA 2017-09-22 2017-09-22 A kind of multi-purpose vessel axle, rudder system mounting process Withdrawn CN107640282A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710863751.XA CN107640282A (en) 2017-09-22 2017-09-22 A kind of multi-purpose vessel axle, rudder system mounting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710863751.XA CN107640282A (en) 2017-09-22 2017-09-22 A kind of multi-purpose vessel axle, rudder system mounting process

Publications (1)

Publication Number Publication Date
CN107640282A true CN107640282A (en) 2018-01-30

Family

ID=61111919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710863751.XA Withdrawn CN107640282A (en) 2017-09-22 2017-09-22 A kind of multi-purpose vessel axle, rudder system mounting process

Country Status (1)

Country Link
CN (1) CN107640282A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108860450A (en) * 2018-03-28 2018-11-23 广船国际有限公司 A kind of propeller for vessels blade assemble method
CN109795617A (en) * 2019-03-11 2019-05-24 江南造船(集团)有限责任公司 The installation and debugging method of limiting device, steering mechanism and steering mechanism
CN109808831A (en) * 2019-03-18 2019-05-28 重庆交通大学 A kind of method that shipping rudder system is installed under water
CN110606163A (en) * 2018-06-15 2019-12-24 浙江国际海运职业技术学院 Rudder system mounting process
CN110877698A (en) * 2019-11-15 2020-03-13 沪东中华造船(集团)有限公司 3000-ton fishery investigation ship rudder system subsection precision control method
CN113148058A (en) * 2021-04-29 2021-07-23 江苏扬子三井造船有限公司 Process for installing and positioning double-rudder sleeve and tail casting in segmented construction stage
CN113911283A (en) * 2021-11-19 2022-01-11 中船桂江造船有限公司 Method for shortening ship construction period based on ship shafting construction process

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101367426A (en) * 2008-06-24 2009-02-18 中国长江航运集团江东船厂 Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN101481000B (en) * 2008-11-28 2013-03-13 威海中复西港船艇有限公司 Fiberglass boat neck bearing and shafting mounting technique
CN102627139B (en) * 2012-05-08 2014-10-01 上海江南长兴造船有限责任公司 Final assembly method of ship shafting and rudder system
CN104290865A (en) * 2014-08-06 2015-01-21 中国长江航运集团青山船厂 Ship rudder, propeller and shaft installation all-in-one machine

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101367426A (en) * 2008-06-24 2009-02-18 中国长江航运集团江东船厂 Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN101481000B (en) * 2008-11-28 2013-03-13 威海中复西港船艇有限公司 Fiberglass boat neck bearing and shafting mounting technique
CN102627139B (en) * 2012-05-08 2014-10-01 上海江南长兴造船有限责任公司 Final assembly method of ship shafting and rudder system
CN104290865A (en) * 2014-08-06 2015-01-21 中国长江航运集团青山船厂 Ship rudder, propeller and shaft installation all-in-one machine

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108860450A (en) * 2018-03-28 2018-11-23 广船国际有限公司 A kind of propeller for vessels blade assemble method
CN108860450B (en) * 2018-03-28 2019-12-20 广船国际有限公司 Ship propeller blade assembling method
CN110606163A (en) * 2018-06-15 2019-12-24 浙江国际海运职业技术学院 Rudder system mounting process
CN110606163B (en) * 2018-06-15 2021-03-23 浙江国际海运职业技术学院 Rudder system mounting process
CN109795617A (en) * 2019-03-11 2019-05-24 江南造船(集团)有限责任公司 The installation and debugging method of limiting device, steering mechanism and steering mechanism
CN109808831A (en) * 2019-03-18 2019-05-28 重庆交通大学 A kind of method that shipping rudder system is installed under water
CN110877698A (en) * 2019-11-15 2020-03-13 沪东中华造船(集团)有限公司 3000-ton fishery investigation ship rudder system subsection precision control method
CN110877698B (en) * 2019-11-15 2021-06-01 沪东中华造船(集团)有限公司 3000-ton fishery investigation ship rudder system subsection precision control method
CN113148058A (en) * 2021-04-29 2021-07-23 江苏扬子三井造船有限公司 Process for installing and positioning double-rudder sleeve and tail casting in segmented construction stage
CN113148058B (en) * 2021-04-29 2023-08-15 江苏扬子三井造船有限公司 Process for installing and positioning double rudder sleeve and tail casting in stage of sectional construction
CN113911283A (en) * 2021-11-19 2022-01-11 中船桂江造船有限公司 Method for shortening ship construction period based on ship shafting construction process

Similar Documents

Publication Publication Date Title
CN107640282A (en) A kind of multi-purpose vessel axle, rudder system mounting process
CN101367426A (en) Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN104229092B (en) Ship rolling balance automatic control system and method
CN109319045B (en) Construction method of duplex stainless steel chemical tanker bulkhead intermediate product
CN103395477B (en) Combined semi-submerged ship and compound type semi-submerged ship
CN203268291U (en) Novel ship liquid tank swashing device
CN105658513A (en) Method for enlarging a ship and enlarged ship
CN106043610B (en) A kind of method using semi-submerged ship ships that transport
CN100478248C (en) Technology of half ship building berth construction launch and dock floating assembling
US9926041B2 (en) Bulbous bow, a sea-going vessel with such bow, and methods of its manufacture
US3841254A (en) Vessel with removable sections
CN201575245U (en) Flange for liquid cargo system of chemical tanker
KR100914350B1 (en) Tank hydro test method a period of dock stage using buoyancy of half diving state
CN110371270B (en) Method for safely floating and refuting product ship in water
US11286020B2 (en) Ballast water-free vessel using difference in depth of bottom shell plate between bow/stern and midship section and construction method thereof
CN204916099U (en) Semi -submerged barge tilting dive stern deadwood
KR101115168B1 (en) Method for managing floating cranes
KR100785479B1 (en) Installation method and structure with modulation for submerged turret loading into vessel
CN104554649A (en) Ocean-crossing transportation method for binding overall structure broken-up modules of ultra-large type oceanographic engineering
CN111791983A (en) Hull broadside structure of semi-submersible multifunctional transport assembly and disassembly ship
CN109080792A (en) The stowage method of half ship not floating in a kind of dock
CN213008650U (en) Floating bag tool for improving submergence stability of semi-submerged transport ship
CN107585257A (en) A kind of kiloton bulk freighter ship type
CN206171712U (en) Binary freighter lamellar body connection structure
CN205769991U (en) A kind of broken line type bulkhead being applicable to floating production storage unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180130