CN107605490A - Single hole large cross-section tunnel double side wall construction conversion process - Google Patents
Single hole large cross-section tunnel double side wall construction conversion process Download PDFInfo
- Publication number
- CN107605490A CN107605490A CN201710748122.2A CN201710748122A CN107605490A CN 107605490 A CN107605490 A CN 107605490A CN 201710748122 A CN201710748122 A CN 201710748122A CN 107605490 A CN107605490 A CN 107605490A
- Authority
- CN
- China
- Prior art keywords
- side wall
- double side
- tunnel
- predicament
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
Description
Claims (6)
- The conversion process 1. single hole large cross-section tunnel double side wall is constructed, it is characterised in that comprise the following steps:The first step:Mid-board is moved to the left on the left of large cross-section tunnel double side wall overlaps with CRD mid-boards, and double side wall up/down steps face When inverted arch move down to be moved to the interim inverted arch of CRD up/down steps and overlap;Second step:Base tunnel top bar, excavation supporting of getting out of a predicament or an embarrassing situation on the right side of double side wall, double side wall left side base tunnel top bar, get out of a predicament or an embarrassing situation out Supporting is dug, double side wall middle part top bar excavation supporting, reserves Core Soil of being got out of a predicament or an embarrassing situation in the middle part of double side wall;3rd step:Light section benching tunnelling method top bar, excavation supporting of getting out of a predicament or an embarrassing situation;4th step:Top bar, excavation supporting of getting out of a predicament or an embarrassing situation on the left of middle section CRD, CRD right sides top bar excavation supporting;5th step:Get out of a predicament or an embarrassing situation in the middle part of double side wall Core Soil excavation supporting, excavation supporting of being got out of a predicament or an embarrassing situation on the right side of CRD.
- 2. single hole large cross-section tunnel double side wall construction conversion process according to claim 1, it is characterised in that:In the first step A segment distance starts to construct in face of double side wall tunnel excavation to tunnel conversion, while During Initial Stage Construction supporting and temporary supporting system peace Dress.
- 3. single hole large cross-section tunnel double side wall construction conversion process according to claim 2, it is characterised in that:The initial stage Supporting includes the gibs such as main body preliminary bracing, mid-board supporting and interim inverted arch supporting, described after each pilot drive Preliminary bracing needs to close.
- 4. single hole large cross-section tunnel double side wall construction conversion process according to claim 2, it is characterised in that:The bilateral The temporary supporting system construction of wall tunnel stops when being moved to CRD tunnel partition walls and the coincidence of interim inverted arch.
- 5. single hole large cross-section tunnel double side wall construction conversion process according to claim 1, it is characterised in that:In the first step Fine-tuning benching tunnelling method tunnel shoulder height, makes double side wall up/down steps inverted arch be completely superposed with benching tunnelling method step.
- 6. single hole large cross-section tunnel double side wall construction conversion process according to claim 1, it is characterised in that:5th step In, large cross-section tunnel gib and interim inverted arch are removed after construction, carries out two lining constructions.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710748122.2A CN107605490B (en) | 2017-08-28 | 2017-08-28 | Single hole large cross-section tunnel double side wall construction conversion process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710748122.2A CN107605490B (en) | 2017-08-28 | 2017-08-28 | Single hole large cross-section tunnel double side wall construction conversion process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107605490A true CN107605490A (en) | 2018-01-19 |
CN107605490B CN107605490B (en) | 2018-11-09 |
Family
ID=61056174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710748122.2A Active CN107605490B (en) | 2017-08-28 | 2017-08-28 | Single hole large cross-section tunnel double side wall construction conversion process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107605490B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109611101A (en) * | 2018-12-04 | 2019-04-12 | 中铁二十四局集团有限公司 | A kind of section in Tunneling by mining method converts construction technology |
CN109630140A (en) * | 2018-12-14 | 2019-04-16 | 广西大学 | The dynamic partition pilot tunnel method on big cross section gradual change Soft Rock Tunnel stratum |
CN109989757A (en) * | 2019-04-03 | 2019-07-09 | 长安大学 | Super-span tunnel is in V grade of engineering method conversion construction method to IV grade of country rock section |
CN110331980A (en) * | 2019-06-17 | 2019-10-15 | 中国铁建大桥工程局集团有限公司 | A kind of shallow embedding fine sand layer tunnel Varied section transition and conversion construction method |
CN110821502A (en) * | 2019-11-29 | 2020-02-21 | 中铁隧道局集团有限公司 | Novel construction method for entrance section of weak surrounding rock large-span mountain tunnel |
CN112523760A (en) * | 2020-12-18 | 2021-03-19 | 山东高速科技发展集团有限公司科技研发中心 | Construction method for converting double-side-wall pilot tunnel into CD method in large-section tunnel |
CN113389566A (en) * | 2021-07-30 | 2021-09-14 | 中铁十二局集团有限公司 | Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method |
CN113417645A (en) * | 2021-06-01 | 2021-09-21 | 上海宝冶集团有限公司 | Large-section tunnel excavation method based on double-side-wall pit guiding method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000282800A (en) * | 1999-03-30 | 2000-10-10 | Kajima Corp | Method and facilities for stocking, carrying and sending out shield segments in pit |
CN102226398A (en) * | 2011-06-02 | 2011-10-26 | 中铁二院工程集团有限责任公司 | Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method |
CN103628887A (en) * | 2013-11-28 | 2014-03-12 | 中铁十三局集团有限公司 | Large-section water-rich saturated fine sand railway tunnel excavation method |
CN103939106A (en) * | 2014-04-03 | 2014-07-23 | 北京交科公路勘察设计研究院有限公司 | Construction method for converting two side-wall pilot tunnel method to CRD method |
CN104879131A (en) * | 2015-05-06 | 2015-09-02 | 中国电建集团华东勘测设计研究院有限公司 | Large-span tunnel excavation method for upper soft and lower hard compound strata |
CN205936644U (en) * | 2016-08-12 | 2017-02-08 | 中铁二十局集团第四工程有限公司 | Tunnel lining construction structure based on two side wall drift methods |
CN107060772A (en) * | 2017-03-23 | 2017-08-18 | 中铁五局集团成都工程有限责任公司 | Large section construction method is mutated for Line for Passenger Transportation standard section |
-
2017
- 2017-08-28 CN CN201710748122.2A patent/CN107605490B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000282800A (en) * | 1999-03-30 | 2000-10-10 | Kajima Corp | Method and facilities for stocking, carrying and sending out shield segments in pit |
CN102226398A (en) * | 2011-06-02 | 2011-10-26 | 中铁二院工程集团有限责任公司 | Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method |
CN103628887A (en) * | 2013-11-28 | 2014-03-12 | 中铁十三局集团有限公司 | Large-section water-rich saturated fine sand railway tunnel excavation method |
CN103939106A (en) * | 2014-04-03 | 2014-07-23 | 北京交科公路勘察设计研究院有限公司 | Construction method for converting two side-wall pilot tunnel method to CRD method |
CN103939106B (en) * | 2014-04-03 | 2016-05-18 | 北京交科公路勘察设计研究院有限公司 | A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion |
CN104879131A (en) * | 2015-05-06 | 2015-09-02 | 中国电建集团华东勘测设计研究院有限公司 | Large-span tunnel excavation method for upper soft and lower hard compound strata |
CN205936644U (en) * | 2016-08-12 | 2017-02-08 | 中铁二十局集团第四工程有限公司 | Tunnel lining construction structure based on two side wall drift methods |
CN107060772A (en) * | 2017-03-23 | 2017-08-18 | 中铁五局集团成都工程有限责任公司 | Large section construction method is mutated for Line for Passenger Transportation standard section |
Non-Patent Citations (2)
Title |
---|
乔东: "大断面黄土隧道中CRD法向双侧壁导坑法的转换", 《山西建筑》 * |
赵爱军: "双侧壁向CRD转换施工工艺浅析", 《山西建筑》 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109611101A (en) * | 2018-12-04 | 2019-04-12 | 中铁二十四局集团有限公司 | A kind of section in Tunneling by mining method converts construction technology |
CN109630140A (en) * | 2018-12-14 | 2019-04-16 | 广西大学 | The dynamic partition pilot tunnel method on big cross section gradual change Soft Rock Tunnel stratum |
CN109989757A (en) * | 2019-04-03 | 2019-07-09 | 长安大学 | Super-span tunnel is in V grade of engineering method conversion construction method to IV grade of country rock section |
CN110331980A (en) * | 2019-06-17 | 2019-10-15 | 中国铁建大桥工程局集团有限公司 | A kind of shallow embedding fine sand layer tunnel Varied section transition and conversion construction method |
CN110821502A (en) * | 2019-11-29 | 2020-02-21 | 中铁隧道局集团有限公司 | Novel construction method for entrance section of weak surrounding rock large-span mountain tunnel |
CN112523760A (en) * | 2020-12-18 | 2021-03-19 | 山东高速科技发展集团有限公司科技研发中心 | Construction method for converting double-side-wall pilot tunnel into CD method in large-section tunnel |
CN112523760B (en) * | 2020-12-18 | 2022-05-13 | 山东高速工程咨询集团有限公司科技研发中心 | Construction method for converting double-side-wall pilot tunnel into CD method in large-section tunnel |
CN113417645A (en) * | 2021-06-01 | 2021-09-21 | 上海宝冶集团有限公司 | Large-section tunnel excavation method based on double-side-wall pit guiding method |
CN113389566A (en) * | 2021-07-30 | 2021-09-14 | 中铁十二局集团有限公司 | Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method |
CN113389566B (en) * | 2021-07-30 | 2022-04-08 | 中铁十二局集团有限公司 | Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method |
Also Published As
Publication number | Publication date |
---|---|
CN107605490B (en) | 2018-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107605490B (en) | Single hole large cross-section tunnel double side wall construction conversion process | |
CN104047623B (en) | A kind of big across cavern excavation construction method | |
CN104653187B (en) | Water-rich sand layer geology large cross-section tunnel excavation method | |
CN105041349A (en) | Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel | |
CN108442943A (en) | A kind of branch-cut bridge section tunnel and Double side heading method construction method | |
CN102121385B (en) | Tunnel excavation method for extending existing single-hole tunnel into double-arch tunnel | |
CN101566064B (en) | Large-section tunnel construction method | |
CN101086209A (en) | Shield tunneling and shallow tunneling combined construction method for building underground station | |
CN205936644U (en) | Tunnel lining construction structure based on two side wall drift methods | |
CN204457792U (en) | A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building | |
CN110924952B (en) | Construction method for three-step seven-step normal medium rock pillar method conversion of super-large section tunnel | |
CN110735656A (en) | Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method | |
CN104632227A (en) | Subway station excavation technology of single-layer beam arch structure | |
CN106837357A (en) | A kind of no-dig technique pipe-roof method of use curve pipe canopy | |
CN104632245A (en) | Method using multi-pilot-tunnel expanding excavation large-diameter shield tunnel for building subway station | |
CN110905524A (en) | Method for excavating and supporting subway station tunnel by adopting underground excavation construction channel | |
CN106246190B (en) | A kind of nine base tunnel construction methods of tunnel and Double side wall | |
CN101539021A (en) | Road tunnel excavation method | |
CN110486021B (en) | Construction method for converting large-section tunnel into two small-section tunnels | |
CN113107500B (en) | Variable cross-section tunnel construction method | |
CN113027495B (en) | Underground excavation large-span station construction method implemented by interval tunnel organization | |
CN205036380U (en) | Block of four encircles PBA and secretly digs subway station major structure | |
CN204457789U (en) | A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build | |
CN107120119B (en) | The construction method of Underground Subway Station | |
CN108222945A (en) | Utilize the construction method of main and auxiliary layering sap excavating extra-large cross-section Underground Subway Station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Yi Inventor after: Zhang Zhiqiang Inventor after: Zhao Cai Inventor after: Guo Zhen Inventor after: Xu Shaohong Inventor after: Shi Fulong Inventor after: Feng Deding Inventor after: Shi Lei Inventor after: Dong Hanjun Inventor after: Zhang Yong Inventor after: Kang Xiaoping Inventor after: Peng Zhen Inventor after: Xiao Fei Inventor after: He Zuhao Inventor after: Li Xiangyang Inventor before: Dong Hanjun Inventor before: Zhang Zhiqiang Inventor before: Zhao Cai Inventor before: Guo Zhen Inventor before: Xu Shaohong Inventor before: Shi Fulong Inventor before: Feng Deding Inventor before: Shi Lei Inventor before: Liu Yi Inventor before: Zhang Yong Inventor before: Kang Xiaoping Inventor before: Peng Zhen Inventor before: Xiao Fei Inventor before: He Zuhao Inventor before: Li Xiangyang |
|
GR01 | Patent grant | ||
GR01 | Patent grant |