CN103939106B - A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion - Google Patents

A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion Download PDF

Info

Publication number
CN103939106B
CN103939106B CN201410132331.0A CN201410132331A CN103939106B CN 103939106 B CN103939106 B CN 103939106B CN 201410132331 A CN201410132331 A CN 201410132331A CN 103939106 B CN103939106 B CN 103939106B
Authority
CN
China
Prior art keywords
interim
wall
tunnel
conversion
progressively
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410132331.0A
Other languages
Chinese (zh)
Other versions
CN103939106A (en
Inventor
许崇帮
王华牢
赵旭
朱连臣
刘涛
汪成兵
周宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO CONSTRUCTION ENGINEERING GROUP Co Ltd
BEIJING JIAOKE HIGHWAY SURVEYING DESIGN AND RESEARCH INSTITUTE
Beijing University of Technology
Original Assignee
QINGDAO CONSTRUCTION ENGINEERING GROUP Co Ltd
BEIJING JIAOKE HIGHWAY SURVEYING DESIGN AND RESEARCH INSTITUTE
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO CONSTRUCTION ENGINEERING GROUP Co Ltd, BEIJING JIAOKE HIGHWAY SURVEYING DESIGN AND RESEARCH INSTITUTE, Beijing University of Technology filed Critical QINGDAO CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201410132331.0A priority Critical patent/CN103939106B/en
Publication of CN103939106A publication Critical patent/CN103939106A/en
Application granted granted Critical
Publication of CN103939106B publication Critical patent/CN103939106B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

Double side wall pilot tunnel method, to a construction method for CRD method conversion, comprises that step is as follows: when tunnel tunnel face front quality of surrounding rock overall distribution is even, the temporarily middle wall in the employing left and right sides moves realization conversion simultaneously in the middle of tunnel; When tunnel supremo's face quality of surrounding rock skewness, wherein a side quality is better, and opposite side country rock is when more broken, adopt one-sided interim in wall sidesway realize conversion. The present invention can select reasonably construction transduction pathway according to geological conditions in constructing tunnel process and orographic condition, and the object of conversion and control is clear and definite, can ensure safety for tunnel engineering, improves efficiency of construction.

Description

A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion
Technical field
The present invention relates to vcehicular tunnel, city underground engineering technical field, especially relate to a kind of double side wall and leadThe construction method of hole normal direction CRD method conversion.
Background technology
In the design and construction such as vcehicular tunnel, city underground engineering, need be according to tunnel structure span and constructionThe wall rock condition disclosing is selected different construction methods, and conversion method between different construction method is neglected alwaysDepending on, make in practice of construction engineering method conversion unorderedly follow, without Zhang Keyi, often make engineering method conversion and control tooConservative, or engineering method transfer process construction risk is excessive, causes national wealth waste or property loss, peopleMember's injures and deaths.
Summary of the invention
The object of the invention is to design the construction method of a kind of novel double side wall pilot tunnel method to the conversion of CRD method,Address the above problem.
To achieve these goals, the technical solution used in the present invention is as follows:
Double side wall pilot tunnel method, to a construction method for CRD method conversion, comprises that step is as follows:
When tunnel tunnel face front quality of surrounding rock overall distribution is even, adopt the left and right sides interim in wall simultaneously toIn the middle of tunnel, mobile realization changed;
When tunnel supremo's face quality of surrounding rock skewness, wherein a side quality is better, and opposite side country rock is forWhen broken, adopt one-sided interim middle wall sidesway to realize conversion.
When tunnel tunnel face front quality of surrounding rock overall distribution is even, self nothing on cross section is aobviousWork difference, when surrounding rock stability is easier to control, its step is as follows:
The first step, during left side is interim, the interim middle wall in wall and right side all progressively moves to center, tunnel, left sideThe interim inverted arch of base tunnel and the interim inverted arch of right side base tunnel along with the left and right sides interim in the progressively broadening of movement of wall, inBetween the constriction progressively of interim inverted arch of base tunnel;
Second step, when in described left side is interim, the interim middle wall in wall and described right side contacts, stops mobile;
The 3rd step, cancel the described right side of rear construction interim in wall, retain described left side interim in wall, willDuring described left side is interim, wall is converted to the interim middle wall in centre in CRD method, completes engineering method conversion;
When tunnel supremo's face quality of surrounding rock skewness, wherein a side quality is better, and opposite side country rock is forWhen broken, its step is as follows:
When tunnel tunnel face right front country rock is during than left front variance:
The first step, during right side is interim, wall remains unchanged, and during left side is interim, wall progressively moves to centre position, tunnel,The interim inverted arch progressively broadening thereupon of left side base tunnel, constriction progressively of the interim inverted arch of middle base tunnel;
Second step, when in described left side is interim, wall moves to centre position, stops moving, and described left side is facedTime in wall be converted to centre in CRD method interim in wall;
The 3rd step, removes the interim middle wall in described right side, completes engineering method conversion;
When tunnel tunnel face left front country rock is during than right front variance:
The first step, during left side is interim, wall remains unchanged, and during right side is interim, wall progressively moves to centre position, the right sideThe progressively broadening thereupon of the interim inverted arch of side base tunnel, constriction progressively of the interim inverted arch of middle base tunnel;
Second step, when in described right side is interim, wall moves to centre position, stops moving, and described right side is facedTime in wall be converted to centre in CRD method interim in wall;
The 3rd step, removes the interim middle wall in described left side, completes engineering method conversion;
When conversion, transformation segment length is controlled at 30-35m.
In constructing tunnel of the present invention, double side wall pilot tunnel method, to the construction method of CRD method conversion, can be slapped according to tunnelSon in face of square Change in surrounding rocks situation select corresponding translative mode, when tunnel tunnel face front Change in surrounding rocks evenAdopt the interim middle wall in the left and right sides in the middle of tunnel, to move conversion simultaneously. , when tunnel tunnel face front country rockThe left and right side difference in change opposite sex is large, adopts one-sided interim middle wall sidesway conversion, and faces by progressive adjustmentsTime in the method for wall, make to excavate base tunnel and reach predetermined size, realize the progressively conversion of engineering method. This constructionMethod is simple, can rationally utilize tunnel surrounding self bearing capacity simultaneously, effectively improves constructing tunnel effectRate and safety.
In the present invention, be to change progressive adjustments temporary support structures position according to wall rock condition, progressively change and leadThe mode of hole span, realizes double side wall pilot tunnel method and is converted to CRD method. The tunnel tunnel face when construction of double side wall base tunnelIf front Change in surrounding rocks evenly adopts the left and right sides, interim middle wall moves conversion simultaneously in the middle of tunnel. If encloseThe rock left and right side difference in change opposite sex is large, adopts one-sided interim middle wall sidesway conversion. In double side wall pilot tunnel method oneWhen wall reaches precalculated position in locating temporarily, remove the interim middle wall formation CRD method in another place.
The present invention relates to vcehicular tunnel, city underground engineering, be particularly useful for that engineering structure span is large, constructionThe underground engineering that requirement of settlement control is high. For the conventional double side wall pilot tunnel method of vcehicular tunnel and CRD method, proposeThe construction method of double side wall pilot tunnel method to CRD method conversion, for the safety conversion of two kinds of construction methods provides guarantorBarrier. The technical solution adopted for the present invention to solve the technical problems is: 1) determine two according to Change in surrounding rocks conditionThe pattern of side wall drift normal direction CRD method conversion; 2) providing double side wall pilot tunnel method according to translative mode turns to CRD methodThe path of changing.
Beneficial effect of the present invention can be summarized as follows:
1, the present invention can select reasonably to execute according to geological conditions in constructing tunnel process and orographic conditionWork transduction pathway, the object of conversion and control is clear and definite, can ensure safety for tunnel engineering, and raising is executedWork efficiency rate.
2, construction technology of the present invention is simple, and implementation cost is cheap.
Brief description of the drawings
Fig. 1 is double side wall pilot tunnel method structure chart
Fig. 2 is CRD method structure chart
Fig. 3 is two wall sidesways pattern conversion placed in the middle construction drawing.
Fig. 4 is single wall lateral displacement mode conversion construction drawing.
In Fig. 1,2,1 tunnel just serves as a contrast, 2 left sides interim in wall, 3 right sides interim in wall, 4 left side base tunnelsWall, 8 left sides in interim in the middle of the interim inverted arch of base tunnel, the interim inverted arch of 6 right side base tunnel, 7 in the middle of interim inverted arch, 5Top headings, 13 in the middle of base tunnel under base tunnel, 10 right side top headings, 11 right sides, 12 under side top heading, 9 left sidesMiddle lower base tunnel.
Detailed description of the invention
In order to make technical problem solved by the invention, technical scheme and beneficial effect clearer, withUnder by reference to the accompanying drawings and embodiment, the present invention is further elaborated. Should be appreciated that described hereinSpecific embodiment only in order to explain the present invention, be not intended to limit the present invention.
A kind of double side wall pilot tunnel method as shown in Figures 1 to 4, to the construction method of CRD method conversion, comprises stepRapid as follows:
When tunnel tunnel face front quality of surrounding rock overall distribution is even, adopt the left and right sides interim in wall simultaneously toIn the middle of tunnel, mobile realization changed; When tunnel supremo's face quality of surrounding rock skewness, wherein a side quality is better,And opposite side country rock is when more broken, adopt one-sided interim in wall sidesway realize conversion.
In the embodiment being more preferably:
When tunnel tunnel face front quality of surrounding rock overall distribution is even, self nothing on cross section is aobviousWork difference, when surrounding rock stability is easier to control, its step is as follows: the first step, wall 2 Hes during left side is interimDuring right side is interim, wall 3 all progressively moves to center, tunnel, the interim inverted arch 4 of left side base tunnel and right side base tunnelInterim inverted arch 6 along with the left and right sides interim in the progressively broadening of movement of wall, the interim inverted arch of middle base tunnel byStep constriction; Second step, when in described left side is interim, the interim middle wall 3 in wall 2 and described right side contacts, stopsOnly mobile; The 3rd step, cancel the described right side of rear construction interim in wall 3, retain described left side interim in wall2, interim described left side middle wall 2 is converted to the interim middle wall 7 in centre in CRD method, complete engineering method conversion;
When tunnel supremo's face quality of surrounding rock skewness, wherein a side quality is better, and opposite side country rock is forWhen broken, its step is as follows:
When tunnel tunnel face right front country rock is during than left front variance: the first step, during right side is interim, wall 3 is protectedHold constantly, during left side is interim, wall 2 progressively moves to centre position, tunnel, and the interim inverted arch of left side base tunnel thereuponProgressively broadening, progressively constriction of 5 of interim inverted arch of middle base tunnel; Second step, wall 2 in described left side is interimWhile moving to centre position, stop moving, the centre that interim described left side middle wall 2 is converted in CRD method is facedTime in wall 7; The 3rd step, removes the interim middle wall 3 in described right side, completes engineering method conversion;
When tunnel tunnel face left front country rock is during than right front variance: the first step, during left side is interim, wall 2 is protectedHold constantly, during right side is interim, wall 3 progressively moves to centre position, and the interim inverted arch of right side base tunnel thereupon progressivelyBroadening, progressively constriction of 5 of interim inverted arch of middle base tunnel; Second step, in described right side is interim, wall 3 moves toWhen in the centre position, stop mobile, described right side is interim in wall 3 be converted to centre in CRD method interim inWall 7; The 3rd step, removes the interim middle wall 2 in described left side, completes engineering method conversion;
In the embodiment being more preferably: when conversion, transformation segment length is controlled at 30-35m.
In certain preferred embodiment:
As shown in Figure 3, suppose tunnel tunnel face right front, left front Change in surrounding rocks same difference, left side is facedTime in wall 2, right side interim in wall 3 progressively move (seeing Fig. 3 (2)) to centre position, left side base tunnel is interimInverted arch 4, the interim inverted arch 6 of right side base tunnel along with the left and right sides interim in the movement of wall progressively increase, middle base tunnel5 of interim inverted arch progressively shorten (seeing Fig. 3 (2)). In left side is interim, wall, the interim middle wall in right side joinWhile touching (seeing Fig. 3 (3)), stop mobile; The interim middle wall 3 in right side of canceling rear construction, retains left side and facesTime in wall 2(interim in the middle of being now converted in wall 7), complete engineering method conversion (seeing Fig. 3 (4)). Transformation segmentLength should be controlled at 30-35m.
As shown in Figure 4, suppose that tunnel tunnel face right front country rock is more poor than left front, wall during right side is interim3 remain unchanged, and during left side is interim, wall 2 progressively moves (seeing Fig. 4 (2)), left side base tunnel to centre positionInterim inverted arch 4 progressively increases thereupon, and 5 of the interim inverted arch of middle base tunnel progressively shorten (seeing Fig. 4 (2)). WhenWhen during left side is interim, wall 2 moves to centre position, stop mobile (in the middle of in interim now, wall 2 is converted toWall 7 in interim) (seeing Fig. 4 (3)), remove the interim middle wall in right side, complete engineering method conversion (seeing Fig. 4 (4)).Transformation segment length should be controlled at 30-35m.
More than by the detailed description of concrete and preferred embodiment the present invention, but those skilled in the artShould be understood that the present invention is not limited to the above embodiment, within the spirit and principles in the present invention all,Any amendment of doing, be equal to replacement etc., within protection scope of the present invention all should be included in.

Claims (2)

1. double side wall pilot tunnel method, to a construction method for CRD method conversion, is characterized in that:
When tunnel tunnel face front quality of surrounding rock overall distribution is even, self nothing on cross section is aobviousWork difference, when surrounding rock stability is easier to control, its step is as follows:
The first step, during left side is interim, the interim middle wall in wall and right side all progressively moves to center, tunnel, left sideThe interim inverted arch of base tunnel and the interim inverted arch of right side base tunnel along with the left and right sides interim in the progressively broadening of movement of wall, inBetween the constriction progressively of interim inverted arch of base tunnel;
Second step, when in described left side is interim, the interim middle wall in wall and described right side contacts, stops mobile;
The 3rd step, cancel the described right side of rear construction interim in wall, retain described left side interim in wall, willDuring described left side is interim, wall is converted to the interim middle wall in centre in CRD method, completes engineering method conversion;
When tunnel tunnel face front quality of surrounding rock skewness, wherein a side quality is better, and opposite side country rockWhen more broken, its step is as follows:
When tunnel tunnel face right front country rock is during than left front variance:
The first step, during right side is interim, wall remains unchanged, and during left side is interim, wall progressively moves to centre position, tunnel,The interim inverted arch progressively broadening thereupon of left side base tunnel, constriction progressively of the interim inverted arch of middle base tunnel;
Second step, when in described left side is interim, wall moves to centre position, stops moving, and described left side is facedTime in wall be converted to centre in CRD method interim in wall;
The 3rd step, removes the interim middle wall in described right side, completes engineering method conversion;
When tunnel tunnel face left front country rock is during than right front variance:
The first step, during left side is interim, wall remains unchanged, and during right side is interim, wall progressively moves to centre position, the right sideThe progressively broadening thereupon of the interim inverted arch of side base tunnel, constriction progressively of the interim inverted arch of middle base tunnel;
Second step, when in described right side is interim, wall moves to centre position, stops moving, and described right side is facedTime in wall be converted to centre in CRD method interim in wall;
The 3rd step, removes the interim middle wall in described left side, completes engineering method conversion.
2. double side wall pilot tunnel method according to claim 1 is to the construction method of CRD method conversion, and its feature existsIn: when conversion, transformation segment length is controlled at 30-35m.
CN201410132331.0A 2014-04-03 2014-04-03 A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion Active CN103939106B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410132331.0A CN103939106B (en) 2014-04-03 2014-04-03 A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410132331.0A CN103939106B (en) 2014-04-03 2014-04-03 A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion

Publications (2)

Publication Number Publication Date
CN103939106A CN103939106A (en) 2014-07-23
CN103939106B true CN103939106B (en) 2016-05-18

Family

ID=51186952

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410132331.0A Active CN103939106B (en) 2014-04-03 2014-04-03 A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion

Country Status (1)

Country Link
CN (1) CN103939106B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605490A (en) * 2017-08-28 2018-01-19 中交第二航务工程局有限公司 Single hole large cross-section tunnel double side wall construction conversion process

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631475A (en) * 2015-01-20 2015-05-20 中铁隧道集团有限公司杭州公司 Safe and fast construction method of down-traversing river shallow depth bored tunnel
CN106246192A (en) * 2016-08-22 2016-12-21 北京市政路桥股份有限公司 Large-scale karst cave treatment under a kind of tunnel basis and base plate and tunnel excavation method
CN106246191B (en) * 2016-08-22 2018-10-30 北京市市政工程研究院 A kind of hole body is dredged, fills plentiful large-scale karst cave treatment and tunnel excavation method deeply
CN106640093A (en) * 2017-01-11 2017-05-10 中铁四局集团第工程有限公司 Tunnel excavating face blasting construction method
CN106761779B (en) * 2017-01-24 2019-02-15 中铁二十局集团第六工程有限公司 A kind of shallow-depth-excavation tunnel passes through the construction method of box culvert
CN107490336B (en) * 2017-08-22 2019-04-09 浙江工业大学 A kind of experimental provision and test method for simulating CRD method constructing tunnel
CN109611101A (en) * 2018-12-04 2019-04-12 中铁二十四局集团有限公司 A kind of section in Tunneling by mining method converts construction technology
CN109989757B (en) * 2019-04-03 2021-07-23 长安大学 Construction method conversion construction method of ultra-large span tunnel from V-level to IV-level surrounding rock section
CN110454171B (en) * 2019-08-21 2021-03-12 中铁隧道局集团有限公司 Method for converting construction from step method to double-side-wall pit guiding method in tunnel
CN111119909A (en) * 2020-02-21 2020-05-08 中国铁建重工集团股份有限公司 Tunnel excavation method
CN112523760B (en) * 2020-12-18 2022-05-13 山东高速工程咨询集团有限公司科技研发中心 Construction method for converting double-side-wall pilot tunnel into CD method in large-section tunnel
CN113389566B (en) * 2021-07-30 2022-04-08 中铁十二局集团有限公司 Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720504A (en) * 2012-06-13 2012-10-10 北京市公路桥梁建设集团有限公司 Double-side-wall-pilot-hole subsection bench cut method construction method
CN102852525B (en) * 2012-09-29 2015-01-28 中铁二局股份有限公司 Underground tunnel enlarging and excavating method from small section of single-line tunnel to large section of double-line tunnel
CN103334761B (en) * 2013-06-28 2015-06-24 中国一冶集团有限公司 Method of constructing shallow tunnel underground passage variable-cross section cross mid-partition wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605490A (en) * 2017-08-28 2018-01-19 中交第二航务工程局有限公司 Single hole large cross-section tunnel double side wall construction conversion process
CN107605490B (en) * 2017-08-28 2018-11-09 中交第二航务工程局有限公司 Single hole large cross-section tunnel double side wall construction conversion process

Also Published As

Publication number Publication date
CN103939106A (en) 2014-07-23

Similar Documents

Publication Publication Date Title
CN103939106B (en) A kind of double side wall pilot tunnel method is to the construction method of CRD method conversion
CN104837142A (en) Calibration method of positioning reference point in wireless positioning system, and wireless positioning system
CN103510520A (en) Sectionalized construction method of deep and large foundation pit
CN105204247A (en) Liquid crystal pixel unit, and pixel unit dark fringe control method
CN103793136A (en) Method for operating mobile terminal and mobile terminal
CN208153024U (en) It is a kind of with prevent tunnel perimeter convergence and vault sinking support protection mechanism
CN105243208A (en) Spherical crown-shaped rock-soil excavation section information expressing method
CN102748033B (en) Overlength pipe jacking anti-drag slurry point storehouse filling mechanism
CN103741696A (en) Vertical enclosing purlin added inner support system
CN204098517U (en) An anti-crush is connected under ditch
CN103046555A (en) Bidirectional adjustable integration cruciform-joint joints for steel pipe bracing
CN204570718U (en) A kind of raft foundation with fluid pipeline path
CN103279219A (en) Method and system for moving cursor of touch screen device
CN104120888B (en) A kind of civil engineering bar reinforcement positioning device
CN207177876U (en) Shale gas well pattern structure
CN103775098A (en) Method and device for detecting flyover crossing tunnel construction based on train vibration in partition mode
Mustafin et al. Improving geodetic support in construction taking into account zones of tectonic disturbances and application of topocentric coordinates< TITLE lang=""> CoвepшeнcTвoвaнie geoдeзiчeckogo oбecпeчeнiya в cTpoiTeльcTвe c yчёTon зoн TekToнiчeckix нapyшeнiй i пpineнeнiya ToпoцeнTpiчeckix koopдiнaT
CN105003283B (en) A kind of top-bottom cross tunnel shock-absorbing structure and its construction method
CN203977442U (en) A kind of carrier structure of controlling underground structure sedimentation
CN205259461U (en) Novel cement saddle bar
CN203498867U (en) Enlarged-base multi-tower building construction structure
CN204781407U (en) Antidetonation steel member
CN205000712U (en) Single loop cut -offs into steel pipe shaft tower that different phase sequences were arranged
CN104700592A (en) Swinger control system
CN204059989U (en) A kind of civil engineering bar reinforcement positioning device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant