CN107598562A - A kind of interior climb support and its installation method with fixed cage - Google Patents

A kind of interior climb support and its installation method with fixed cage Download PDF

Info

Publication number
CN107598562A
CN107598562A CN201710651284.4A CN201710651284A CN107598562A CN 107598562 A CN107598562 A CN 107598562A CN 201710651284 A CN201710651284 A CN 201710651284A CN 107598562 A CN107598562 A CN 107598562A
Authority
CN
China
Prior art keywords
fixed cage
tower
tower section
stock
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710651284.4A
Other languages
Chinese (zh)
Other versions
CN107598562B (en
Inventor
班云
姚雁涛
曹培源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Weihai New Heavy Industry Ltd By Share Ltd
Original Assignee
Weihai New Heavy Industry Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Weihai New Heavy Industry Ltd By Share Ltd filed Critical Weihai New Heavy Industry Ltd By Share Ltd
Priority to CN201710651284.4A priority Critical patent/CN107598562B/en
Publication of CN107598562A publication Critical patent/CN107598562A/en
Application granted granted Critical
Publication of CN107598562B publication Critical patent/CN107598562B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to building demolition field,Specifically a kind of interior climb support and its installation method with fixed cage,Including tower seat basis,Multistage thick stick synchronous lifting device,Tower body,Stock,Rotating assembly,Tower top and drawstring,The fixed cage of ring-type is cased with tower section,Fixed cage inner ring is in the square limitting casing being engaged with tower section,The spacing of limitting casing and tower internode is 1cm 3cm,Limitting casing inwall is provided with the limited impression corresponding with tower section outer wall adapter sleeve,Tower section is provided with bolt,Fixed cage is provided with telescopic boom hydraulic jack or cylinder linking arm,Linking arm one end is connected with fixed cage,The other end is provided with the connecting plate being connected with removing building end face,Connecting plate is provided with connecting hole,The expansion bolt that connecting plate is connected with removing building is provided with connecting hole,The effectively firm interior support that climbs of support,Installation is quick,It is simple and convenient.

Description

A kind of interior climb support and its installation method with fixed cage
Technical field
The present invention relates to building demolition field, specifically a kind of interior climb support and its installation side with fixed cage Method.
Background technology
With industrialization development and urban planning demand, many Architectural Equipments are required for removing, when the similar steam power plant of dismounting 200 meters, 300 meters of superelevation, large-scale chimney, it is more convenient using the interior dismounting machinery that climbs, inside climb and remove the height of machinery and be By the cumulative realization of jacking frame, in practical operation, inclination occurs, in stuck phenomenon in the air in jacking frame when cumulative, specially Profit CN 206188316U patent discloses a kind of multistage thick stick synchronization lifting dress for being used for jacking frame in demolishing buildings field To put, the lowering or hoisting gear is made up of base mechanism, hydraulic cylinder link gear, multi-cylinder linkage frame, be hinged fixed seat and balance weight body assembling, Due to being provided with multi-cylinder linkage frame on hydraulic cylinder link gear, while balance weight body is provided with multi-cylinder linkage frame again, made Obtaining lowering or hoisting gear can lean on the deadweight of balance weight body to realize mechanical synchronization in jacking, particularly when falling after rise, and working platform face is not Easily tilting, equipment can smoothly reach working depth place, synchronous smooth stabilization when the patent realizes jacking frame jacking, fallen after rise, Same vertical plane can not be maintained at but if inside climbing and removing mechanical erection, the whole interior dismounting machinery that climbs easily swings or inclined Tiltedly, climb in can not ensureing and remove the safe construction of machinery, internally climb remove mechanically and interior climb remove machinery and cover People and thing under lid scope cause severe safety hazards.
The content of the invention
The purpose of the present invention is exactly to solve above-mentioned the deficiencies in the prior art, there is provided a kind of interior with fixed cage Climb support and its installation method, and the effectively firm interior support that climbs of support, installation is quick, simple and convenient.
The technical solution adopted by the present invention is:
It is a kind of with the support that climbed in fixed cage, including tower seat is basic, multistage thick stick synchronous lifting device, tower body, stock, returns Turn assembly, tower top and drawstring, multistage thick stick synchronous lifting device includes base mechanism, hydraulic cylinder link gear, multi-cylinder linkage frame, bottom Adapter sleeve is provided with the outside of the vertex of seat mechanism upper surface four, multi-cylinder linkage frame is provided with the alignment pin for the positioning of tower section, tower body It is made up of tower section, tower section is quadrangle cube, and the fixed cage of ring-type is cased with tower section, and fixed cage inner ring is in and tower section phase The square limitting casing coordinated, the spacing of limitting casing and tower internode be 1cm-3cm, tower section be provided with removably, be fixed cage The bolt of positioning, compartment of terrain is provided with the linking arm away from inner ring on fixed cage, and linking arm one end is connected with fixed cage Connect, the other end is provided with the connecting plate being connected with removing building end face, and connection plate shape builds connection end with the dismounting being connected Shape at face is corresponding, and connecting plate is provided with connecting hole, and connecting hole is interior swollen provided with connecting plate is connected with dismounting building Swollen bolt.
Further, the support that inside climbs is additionally provided with balance umbrella, and balance umbrella is provided with balance umbrella frame, balance umbrella stand and balance umbrella Top, balance umbrella stand both ends connect rotating assembly and tower top respectively, and balance umbrella top lower end is connected on balance umbrella stand, balanced on umbrella top End is connected with balance umbrella frame one end, and the balance umbrella frame other end is connected with tower top, ensures to climb in whole by balancing umbrella umbrella shaped support The stabilization of ascending branch frame.
Further, tower section outer wall is provided with adapter sleeve, and adapter sleeve is divided into bolt connection set, or bearing pin adapter sleeve, fixed Stock limitting casing inwall is provided with the limited impression corresponding with tower section outer wall adapter sleeve, and limited impression ensures that fixed cage is smooth It is inserted in tower section.
Further, described linking arm is telescopic boom hydraulic jack or cylinder, the cylinder seat of hydraulic jack or cylinder with Fixed cage is connected, and the telescopic arm front end of hydraulic jack or cylinder is provided with connecting plate, and connecting plate is provided with connecting hole, connecting hole It is interior to be provided with the expansion bolt that connecting plate is connected with removing building.
Further, drawstring is carbon fibre composite, has the characteristics of light weight, high intensity, softness.
Further, fixed cage lower surface is provided with the detent being engaged with tower section bolt, ensures Ta Jieding Position bolt is connected with fixed cage lower surface.
Further, the length of bolt is bigger 1cm- than the spacing of Ta Jie and fixed cage limitting casing on tower section outer wall 3cm, ensure tower section bolt and the firm connection of fixed cage.
Present invention also offers a kind of with the support installation method that climbed in fixed cage, comprise the following steps:
Step 1:Climb support in installation
Tower seat basis is made using armored concrete first, multistage thick stick synchronous lifting device is installed on the basis of tower seat, by stock It is placed on multistage thick stick synchronous lifting device upper surface, stock bottom face adapter sleeve and multistage thick stick synchronous lifting device base mechanism Adapter sleeve is bolted on the outside of the vertex of upper surface four, and stock one side is provided with tower section approach aperture, by the first tower Section inserted from stock approach aperture and be placed on multistage thick stick synchronous lifting device multi-cylinder linkage frame upper surface, the first tower section with it is more Cylinder linkage rack upper surface position pin connection, by operating the hydraulic power pack of multistage thick stick synchronous lifting device, with multistage thick stick To an incremental design height, the first tower section bottom is fixed on set by latch for the first tower section jacking of synchronous lifting device connection On frame, the second tower section ... N tower sections are sequentially inserted from stock approach aperture, until the first tower section top lifting height and stock are high Degree is engaged, and highly should ensure that all fixed cages can be fixed on the tower section on stock top beyond the tower section of stock height On;
Corresponding to remove the inner wall size of building from low to high, fixed cage is sequentially penetrated into up to stock top, set from the first tower section Vertically to bolt is spaced apart on frame upper column section peripheric surface, bolt support is connected to fixed cage lower surface;
Rotating assembly, balance umbrella and tower top, tower top connection stay cord one end are sequentially installed on the first tower section.
Step 2: fixed cage is sequentially installed
By operating the hydraulic power pack of multistage thick stick synchronous lifting device, continue to insert jacking tower from stock approach aperture Section, phase is connected respectively until lowermost end fixed cage is jacked to first setting setting height(from bottom), drawstring one end of tower top connection Ensure that fixed cage is steady on corresponding lowermost end installation fixed cage, operating personnel reaches fixed cage along fixed cage and connected Connecting plate on arm builds joint with corresponding remove, and the expansion bolt on connecting plate in connecting hole connects with removing building end face Connect;
As the connecting plate on fixed cage linking arm is in larger distance from building connecting end surface is removed, extend telescoping hydraulic cylinder or gas Cylinder, connecting plate is connected with removing building connecting end surface, pulled down respectively on fixed cage after lowermost end fixed cage installation Drawstring and Ta Jie on corresponding bolt;
Above-mentioned installation steps are repeated, continues the jacking of tower section, insert operation, remaining fixed cage is sequentially jacked respective settings peace Dress height, and complete installation of the remaining fixed cage in respective settings setting height(from bottom).
Beneficial effects of the present invention are:The support that inside climbs includes multistage thick stick synchronous lifting device, is synchronously risen by multistage thick stick Falling unit is stable to tower body tower section to be jacked, building corresponding height operation is removed to superelevation on the support that climbed including cumulative realization, The fixed cage of ring-type is cased with tower section, the support installation method that inside climbs discloses tower section in support installation of climbing inside and driven admittedly Determine stock jacking and reach fixed cage setting height(from bottom), realize that fixed cage is connected with removing the connected contact surface of building, and fixed cover Limited impression that frame inwall is provided with ensures that fixed cage is smoothly inserted in tower section, and fixed cage limitting casing and tower internode are away from for 1cm- 3cm, ensure that tower body tower section is maintained at same vertical plane, the whole interior support that climbs is not in swing or inclination, is climbed in guarantee Personal security in the range of support.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of multistage thick stick synchronous lifting device in Fig. 1;
Fig. 3 is the topology example one of fixed sleeve part in Fig. 1;
Fig. 4 is enlarged drawing I in Fig. 3;
Fig. 5 is the topology example two of fixed sleeve part in Fig. 1;
Fig. 6 is tower section topology example one in Fig. 1;
Fig. 7 is tower section topology example two in Fig. 1;
Fig. 8 is scheme of installation of the present invention;
Fig. 9 is enlarged drawing II in Fig. 8;
Sequence number in figure:1 tower seat basis, 2 multistage thick stick synchronous lifting devices, 2.1 base mechanisms, 2.11 adapter sleeves, 2.2 hydraulic cylinders connection Motivation structure, 2.3 multi-cylinder linkage framves, 2.31 alignment pins, 3 tower bodies, 3.1 tower sections, 3.11 bearing pin adapter sleeves, 3.12 bolts, 3.13 bolt connection sets, 4 stocks, 5 rotating assemblies, 6 tower tops, 7 drawstrings, 8 fixed cages, 8.1 limitting casings, 8.2 limited impressions, 8.3 linking arms, 8.4 connecting plates, 8.5 connecting holes, 8.6 expansion bolts, 8.7 telescopic hydraulic oil cylinders or cylinder, 9 balance umbrellas, 9.1 Balance umbrella stand, 9.2 balance umbrella tops, 9.3 balance umbrella frames.
Embodiment
As shown in accompanying drawing 1- Fig. 2, a kind of interior support that climbs with fixed cage, including tower foundation 1, multistage thick stick are synchronous Lowering or hoisting gear 2, tower body 3, stock 4, rotating assembly 5, tower top 6 and drawstring 7, multistage thick stick synchronous lifting device 2 include base mechanism 2.1st, hydraulic cylinder link gear 2.2, multi-cylinder linkage frame 2.3, the vertex outside of 2.1 upper surface of base mechanism four are provided with adapter sleeve 2.11, multi-cylinder linkage frame 2.3 is provided with alignment pin 2.31, and tower body 3 is connected by multiple tower sections 3.1 by 3.1 4 jiaos of outer walls of tower section The connection composition of set 2.11, tower section 3.1 is quadrangle cube, except no standard section of tower crane is marked time on tower section 3.1, other structures Identical with standard section of tower crane structure, standard section of tower crane is also referred to as jacking frame, and adapter sleeve 2.11 divides for the internal thread of example in accompanying drawing 6 The bearing pin connection adapter sleeve 3.11 of example, multistage thick stick synchronous lifting device 2 are protected in bolt connection adapter sleeve 3.13, or accompanying drawing 7 The jacking to the stabilization of tower section 3.1 is demonstrate,proved, the fixed cage 8 of ring-type is cased with tower section 3.1;
As shown in accompanying drawing 3- accompanying drawings 7, the inner ring of fixed cage 8 is the square limitting casing 8.1 being engaged with tower section 3.1, limitting casing 8.1 Similar to the structure of tower section 3.1, the horizontal cross-section of limitting casing 8.1 is square structure, the inner circumferential chi of each fixed cage limitting casing 8.1 Very little identical and be less than the inner circumferential size of stock 4, the inwall of limitting casing 8.1 is provided with corresponding with the outer wall adapter sleeve 2.11 of tower section 3.1 Limited impression 8.2, such as accompanying drawing 3 and accompanying drawing 5, limited impression 8.2 ensures that fixed cage 8 is smoothly inserted in tower section 3.1, ensures limitting casing 8.1 and the spacing of tower section 3.1 are 1cm-3cm, and adapter sleeve 2.11 limits if being arranged on the situation of the inwall of tower section 3.1, fixed cage 8 The position inwall of frame 8.1 does not have to then set limited impression 8.2, and tower section 3.1 is provided with positioning spiral shell that is detachable, being positioned for fixed cage 8 Bolt 3.12, the length of bolt 3.12 is bigger than the spacing of tower section 3.1 and fixed cage limitting casing 8.1 on the outer wall of tower section 3.1 1cm-3cm, ensure the stable support fixed cage 8 of bolt 3.12, the outer shroud compartment of terrain of fixed cage 8 is provided with the company away from inner ring Arm 8.3 is connect, the one end of linking arm 8.3 is connected with fixed cage 8, and the other end is provided with the connecting plate being connected with removing building end face 8.4, the shape of connecting plate 8.4 is corresponding with the shape at the dismounting building connecting end surface being connected, and such as removes and builds to be large-scale super During chimney stack, the shape of connecting plate 8.4 is set to the arc corresponding with inner wall of stack shape, makes connecting plate 8.4 with removing in building Wall connection more fastens, and connecting plate 8.4 is provided with connecting hole 8.5, is provided with connecting hole 8.5 connecting plate 8.4 building phase with removing Light weight, high intensity, the carbon fibre composite of softness can be used in the expansion bolt 8.6 of connection, drawstring 7, and drawstring 7 can pacify It is connected, can also be connected when needing to use with tower top 6 with tower top 6 in advance during dress;
The linking arm 8.3 being equipped with outside fixed cage 8 is telescopic hydraulic oil cylinder or cylinder 8.7, and linking arm 8.3 is in fixed cage Distributed quantity is no less than two on 8 outer walls, if it is necessary, can be directly in fixed cage 8 according to fixed needs in Super High Outer wall annular distribution welds more link arms 8.3.
The support that inside climbs is additionally provided with balance umbrella 9, and balance umbrella 9 is provided with balance umbrella stand 9.1, balance umbrella top 9.2 and balance umbrella frame 9.3, balance umbrella stand 9.1 both ends are connected with rotating assembly 5 and tower top 6 respectively, and the lower end of balance umbrella top 9.2 is connected to balance umbrella stand On 9.1, the upper end of balance umbrella top 9.2 is connected with balance umbrella frame 9.3 one end, and the balance other end of umbrella frame 9.3 is connected with tower top 6, is passed through The umbrella shaped support of umbrella 9 is balanced to keep the whole interior bracket stable that climbs.
A kind of interior support installation method that climbs with fixed cage, comprises the following steps:
Step 1:Climb support in installation
Tower seat basis 1 is made using armored concrete first, multistage thick stick synchronous lifting device 2 is installed on tower seat basis 1, will be covered Frame 4 is placed on the multistage upper surface of thick stick synchronous lifting device 2, the bottom face adapter sleeve 2.11 of stock 4 and multistage thick stick synchronous lifting device 2 Adapter sleeve 2.11 is bolted on the outside of the vertex of upper surface four of base mechanism 2.1, and the one side of stock 4 is provided with tower section 3.1 approach apertures, the first tower section 3.1 is inserted from the approach aperture of stock 4 and is placed on multistage thick stick synchronous lifting device multi-cylinder The upper surface of linkage rack 2.3, the first tower section is connected with the upper surface alignment pin 2.31 of multi-cylinder linkage frame 2.3, same by operating multistage thick stick The hydraulic power pack 2.3 of lowering or hoisting gear 2 is walked, the first tower section 3.1 being connected with multistage thick stick synchronous lifting device 2 is jacked to one Individual to be incremented by design height, the bottom of the first tower section 3.1 is fixed on stock 4 by latch, sequentially inserted from the approach aperture of stock 4 Second tower section 3.1 ... N towers section 3.1, until the top lifting height of the first tower section 3.1 is engaged with the height of stock 4, and beyond set The height of tower section 3.1 of the height of frame 4 should ensure that all fixed cages 8 can be fixed on the tower section 3.1 on the top of stock 4;
Corresponding to remove the inner wall size of building from low to high, the fixed cage 8 of corresponding size sequentially penetrates from the first tower section 3.1 Stock 4 top is reached, vertically to being spaced apart bolt 3.12, bolt 3.12 on the peripheric surface of 4 upper column section of stock 3.1 Support is connected to the lower surface of fixed cage 4;
Rotating assembly 5, balance umbrella 9 and tower top 6, the one end of 6 connection stay cord of tower top 7, drawstring 7 are sequentially installed on the first tower section 3.1 The other end is first hanging to be placed, and can also be connected again with tower top 6 when needing to use drawstring 7.
Step 2:Fixed cage 8 is sequentially installed
By operating the hydraulic power pack 2.2 of multistage thick stick synchronous lifting device 2, continue to insert from the approach aperture of stock 4, push up Tower section 3.1 is risen, until first setting installation height that lowermost end fixed cage 8 is set from low to high by jacking to dismounting building Degree, one end of drawstring 7 that tower top 6 connects connect the side of lowermost end fixed cage 8 four respectively, or are connected to fixed cage connection On arm 8.3, the balance and stability of fixed cage 8 is kept, operating personnel is reached on fixed cage linking arm 8.3 along fixed cage 8 Connecting plate 8.4 connects end face junction with corresponding dismounting building, the expansion bolt 8.6 on connecting plate 8.4 in connecting hole 8.5 with Remove the connection of building end face;
As the connecting plate 8.4 on fixed cage linking arm 8.3 from remove building connecting end surface it is in larger distance, extend telescopic hydraulic Oil cylinder or cylinder 8.7, the elongation of connecting plate 8.4 is set to connect with removing building connecting end surface, after the installation of lowermost end fixed cage 8 Corresponding bolt 8.6 on the drawstring 7 and Ta Jie 3.1 connected on fixed cage 8 is pulled down respectively;
Above-mentioned installation steps are repeated, continuation tower section is inserted, lifting operation, and remaining fixed cage 8 is sequentially jacked and arrives respective settings Setting height(from bottom), installation of the remaining fixed cage 8 in respective settings setting height(from bottom) is completed, such as accompanying drawing 8- accompanying drawings 9.
Fixed cage 8 ensures that tower body tower section 3.1 is maintained at same vertical plane, it is whole in climb support be not in swing or Tilt, realize and remove building corresponding height operation on the support that climbs inside to superelevation, personnel in the range of the support that climbed in guarantee Safety.
Embodiments of the present invention are not limited to above-described embodiment, and that is made on the premise of present inventive concept is not departed from is various Change is belonged within protection scope of the present invention.

Claims (8)

1. a kind of with the support that climbed in fixed cage, including tower seat is basic, multistage thick stick synchronous lifting device, tower body, stock, Rotating assembly, tower top and drawstring, multistage thick stick synchronous lifting device include base mechanism, hydraulic cylinder link gear, multi-cylinder linkage frame, Adapter sleeve is provided with the outside of the vertex of base mechanism upper surface four, multi-cylinder linkage frame is provided with the alignment pin for the positioning of tower section, tower Body is made up of tower section, and tower section is quadrangle cube, it is characterised in that:The fixed cage of ring-type, fixed cage are cased with tower section Inner ring is in the square limitting casing that is engaged with tower section, and the spacing of limitting casing and tower internode be 1cm-3cm, and tower section is provided with detachably , bolt for fixed cage positioning, compartment of terrain is provided with the linking arm away from inner ring on fixed cage, linking arm one end with Fixed cage is connected, and the other end is provided with the connecting plate being connected with removing building end face, and connection plate shape is torn open with what is be connected Except the shape of building connecting end surface is corresponding, connecting plate is provided with connecting hole, is provided with connecting hole and builds connecting plate with removing The expansion bolt being connected.
A kind of 2. interior support that climbs with fixed cage according to claim 1, it is characterised in that:Provided with balance umbrella, Balance umbrella and be provided with balance umbrella frame, balance umbrella stand and balance umbrella top, balance umbrella stand both ends connect rotating assembly and tower top, balanced respectively Umbrella top lower end is connected on balance umbrella stand, and balance umbrella top upper end is connected with balance umbrella frame one end, balances the umbrella frame other end and tower top Connection, by balancing umbrella umbrella shaped support come the stable whole interior support that climbs.
A kind of 3. interior support that climbs with fixed cage according to claim 1, it is characterised in that:Tower section outer wall is provided with Adapter sleeve, adapter sleeve are divided into bolt connection set, or bearing pin adapter sleeve, and fixed cage limitting casing inwall is provided with and tower section outer wall The corresponding limited impression of adapter sleeve.
A kind of 4. interior support that climbs with fixed cage according to claim 1, it is characterised in that:Described linking arm For telescopic boom hydraulic jack or cylinder, the cylinder seat of hydraulic jack or cylinder is connected with fixed cage, hydraulic jack or cylinder Telescopic arm front end be provided with connecting plate, connecting plate is provided with connecting hole, is provided with connecting hole and connecting plate is connected with removing to build The expansion bolt connect.
A kind of 5. interior support that climbs with fixed cage according to claim 1, it is characterised in that:Drawstring is carbon fiber Composite.
A kind of 6. interior support that climbs with fixed cage according to claim 1, it is characterised in that:Fixed cage lower end Face is provided with the detent being engaged with tower section bolt.
A kind of 7. interior support that climbs with fixed cage according to claim 1, it is characterised in that:It is fixed on tower section outer wall The length of position bolt is bigger 1cm-3cm than the spacing of Ta Jie and fixed cage limitting casing.
A kind of 8. installation method of the interior support that climbs with fixed cage described in claim 1, it is characterised in that:Including with Lower step:
Step 1:Climb support in installation
Tower seat basis is made using armored concrete first, multistage thick stick synchronous lifting device is installed on the basis of tower seat, by stock It is placed on multistage thick stick synchronous lifting device upper surface, stock bottom face adapter sleeve and multistage thick stick synchronous lifting device base mechanism Adapter sleeve is bolted on the outside of the vertex of upper surface four, and stock one side is provided with tower section approach aperture, by the first tower Section inserted from stock approach aperture and be placed on multistage thick stick synchronous lifting device multi-cylinder linkage frame upper surface, the first tower section with it is more Cylinder linkage rack upper surface position pin connection, by operating the hydraulic power pack of multistage thick stick synchronous lifting device, with multistage thick stick To an incremental design height, the first tower section bottom is fixed on set by latch for the first tower section jacking of synchronous lifting device connection On frame, the second tower section ... N tower sections are sequentially inserted from stock approach aperture, until the first tower section top lifting height and stock are high Degree is engaged, and highly should ensure that all fixed cages can be fixed on the tower section on stock top beyond the tower section of stock height On;
Corresponding to remove the inner wall size of building from low to high, corresponding fixed cage is sequentially penetrated into up on stock from the first tower section Portion, vertically to bolt is spaced apart on stock upper column section peripheric surface, bolt support is connected to fixed cage lower end Face;
Rotating assembly, balance umbrella and tower top, tower top connection stay cord one end are sequentially installed on the first tower section.
Step 2: fixed cage is sequentially installed
By operating the hydraulic power pack of multistage thick stick synchronous lifting device, continue to insert from stock approach aperture, jack tower Section, it is connected to until lowermost end fixed cage is jacked to first setting setting height(from bottom), drawstring one end of tower top connection Ensure that fixed cage is steady on lowermost end fixed cage, operating personnel reaches the connection on fixed cage linking arm along fixed cage Plate is removed at building connecting end surface with corresponding, and the expansion bolt on connecting plate in connecting hole is connected with removing building end face;
As the connecting plate on fixed cage linking arm from remove building connecting end surface it is in larger distance, extend telescopic hydraulic oil cylinder or Cylinder, connecting plate is connected with removing building connecting end surface, fixed cage is pulled down respectively after lowermost end fixed cage installation On drawstring and Ta Jie on corresponding bolt;
Above-mentioned installation steps are repeated, continuation tower section is inserted, lifting operation, and remaining fixed cage is sequentially jacked respective settings peace Dress height, and complete installation of the remaining fixed cage in respective settings setting height(from bottom).
CN201710651284.4A 2017-08-02 2017-08-02 It is a kind of with bracket and its installation method of climbing in fixed cage Active CN107598562B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710651284.4A CN107598562B (en) 2017-08-02 2017-08-02 It is a kind of with bracket and its installation method of climbing in fixed cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710651284.4A CN107598562B (en) 2017-08-02 2017-08-02 It is a kind of with bracket and its installation method of climbing in fixed cage

Publications (2)

Publication Number Publication Date
CN107598562A true CN107598562A (en) 2018-01-19
CN107598562B CN107598562B (en) 2019-12-03

Family

ID=61064421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710651284.4A Active CN107598562B (en) 2017-08-02 2017-08-02 It is a kind of with bracket and its installation method of climbing in fixed cage

Country Status (1)

Country Link
CN (1) CN107598562B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868194A (en) * 2018-07-30 2018-11-23 威海新特重工股份有限公司 A kind of chimney demolition device and chimney demolition method
CN109057396A (en) * 2018-07-30 2018-12-21 威海新特重工股份有限公司 A kind of building method of chimney demolition scaffold
CN109879179A (en) * 2019-01-25 2019-06-14 中亿丰建设集团股份有限公司 A kind of assembling type steel structure tower crane platform

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2466125Y (en) * 2001-02-28 2001-12-19 长沙中联重工科技发展股份有限公司 Self-lifting internal creeping lifting-up system
CN2679123Y (en) * 2002-12-19 2005-02-16 胡建锋 Internally creeping tower crane
CN201665485U (en) * 2009-12-29 2010-12-08 长沙中联重工科技发展股份有限公司 Internal-climbing device of tower crane and internal-climbing component of tower crane
CN203394032U (en) * 2013-07-29 2014-01-15 中天建设集团有限公司天津分公司 Inside-cylinder climb-type operation frame
CN106219419A (en) * 2016-09-19 2016-12-14 中国建筑第八工程局有限公司 High-rise building large-scale swing arm tower crane is converted to plug-in construction method by interior climbing in situ
CN206188316U (en) * 2016-11-24 2017-05-24 威海新特重工有限公司 Multistage thick stick synchronous lifting gear

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2466125Y (en) * 2001-02-28 2001-12-19 长沙中联重工科技发展股份有限公司 Self-lifting internal creeping lifting-up system
CN2679123Y (en) * 2002-12-19 2005-02-16 胡建锋 Internally creeping tower crane
CN201665485U (en) * 2009-12-29 2010-12-08 长沙中联重工科技发展股份有限公司 Internal-climbing device of tower crane and internal-climbing component of tower crane
CN203394032U (en) * 2013-07-29 2014-01-15 中天建设集团有限公司天津分公司 Inside-cylinder climb-type operation frame
CN106219419A (en) * 2016-09-19 2016-12-14 中国建筑第八工程局有限公司 High-rise building large-scale swing arm tower crane is converted to plug-in construction method by interior climbing in situ
CN206188316U (en) * 2016-11-24 2017-05-24 威海新特重工有限公司 Multistage thick stick synchronous lifting gear

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868194A (en) * 2018-07-30 2018-11-23 威海新特重工股份有限公司 A kind of chimney demolition device and chimney demolition method
CN109057396A (en) * 2018-07-30 2018-12-21 威海新特重工股份有限公司 A kind of building method of chimney demolition scaffold
CN108868194B (en) * 2018-07-30 2023-12-22 威海新特重工股份有限公司 Chimney dismantling device and chimney dismantling method
CN109879179A (en) * 2019-01-25 2019-06-14 中亿丰建设集团股份有限公司 A kind of assembling type steel structure tower crane platform
CN109879179B (en) * 2019-01-25 2024-03-26 中亿丰建设集团股份有限公司 Assembled steel construction tower crane platform

Also Published As

Publication number Publication date
CN107598562B (en) 2019-12-03

Similar Documents

Publication Publication Date Title
CN102839812B (en) Intelligent construction platform for construction of super high-rise building
CN107598562A (en) A kind of interior climb support and its installation method with fixed cage
CN100480481C (en) Quadrangular pyramid sphere net case falsework-free constructing and mounting method and hoisting machine tool
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN107386244B (en) Truss-like hydraulic bolt lifting device
CN207048345U (en) Construction discharge platform device
CN207647152U (en) Tower lifts constructing device certainly
CN105060198A (en) Automatic lifting tower for forest fireproof observation
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN211666622U (en) Test device capable of climbing up and down and turning plate to stand in counter-force well
CN205329648U (en) Open and inspect among large -scale pumped storage unit and repair with dismantling structure
CN210917388U (en) Easy dismouting formula underground structure
CN110410277B (en) Wind driven generator tower and installation method thereof
CN210439678U (en) Large-scale concrete tank dome can climb high formwork support system
CN113336108A (en) Movable mast tool for dismantling high-altitude tower crane in cooling tower
CN111392609A (en) Side-hanging type novel support frame, novel full-automatic climbing system and climbing method thereof
CN206053355U (en) A kind of tower concrete spreader
CN110014521A (en) Bar planting assistor and its construction method at the top of secondary structure constructional column
CN212404874U (en) Integrated hoisting platform for construction of cable tower decoration component
CN211572829U (en) Novel cable bridge crossing rod
CN209778232U (en) Self-elevating gantry lifter
CN212388957U (en) Movable platform special for detecting and maintaining sealing wall of heat accumulation chamber on side coke side of top-mounted coke oven machine
CN214990104U (en) A quick hoisting device for road bridge tunnel construction
CN217126856U (en) Assembly type arched steel structure assembling equipment
CN219622208U (en) Bearing frame for building construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant