CN107574749A - A kind of karst depression people broker's storehouse road structure and preparation method - Google Patents

A kind of karst depression people broker's storehouse road structure and preparation method Download PDF

Info

Publication number
CN107574749A
CN107574749A CN201710787589.8A CN201710787589A CN107574749A CN 107574749 A CN107574749 A CN 107574749A CN 201710787589 A CN201710787589 A CN 201710787589A CN 107574749 A CN107574749 A CN 107574749A
Authority
CN
China
Prior art keywords
steel plate
horizontal support
reinforcing bar
section
support section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710787589.8A
Other languages
Chinese (zh)
Inventor
沈志平
陈德茂
袁江文
张建磊
孙洪
朱军
吴斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Zhengye Engineering & Investment Inc Ltd
Original Assignee
Guizhou Zhengye Engineering & Investment Inc Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Zhengye Engineering & Investment Inc Ltd filed Critical Guizhou Zhengye Engineering & Investment Inc Ltd
Priority to CN201710787589.8A priority Critical patent/CN107574749A/en
Publication of CN107574749A publication Critical patent/CN107574749A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)
  • Road Signs Or Road Markings (AREA)

Abstract

The invention discloses a kind of karst depression people broker's storehouse road structure and preparation method, and it includes horizontal support section and people broker's storehouse road, and people broker's storehouse road is fixed on the upper surface of horizontal support section;One end of horizontal support section and diagonal brace section is separately fixed at karst cliff(5)It is interior;Horizontal support section is fixedly connected with the other end of diagonal brace section;The side of horizontal support section is fixed with guard rail(4);When solving prior art and building view people broker's storehouse road in the complicated place of the topography and geomorphologies such as karst scenic spot, the mode of generally use hand excavation and explosion is carried out, mode heavy damage auto-ignition environment is built using such, serious, and technical problems such as construction cost is high are destroyed to scenic spot.

Description

A kind of karst depression people broker's storehouse road structure and preparation method
Technical field
The invention belongs to plank road technology, more particularly to a kind of karst depression people broker's storehouse road structure and preparation method.
Background technology
Karst be earth's surface and underground water solublerock is carried out one kind based on chemolysis, supplemented by mechanical denuding The unusual landscape of geologic process and its a variety of earth's surfaces for being formed, underground and phenomenon general name.The distribution of China karst area is wide, Karst landscape is various, and metamorphosis is changeable, creates the munificent Karst Tourism Resources in China;As karst area basis is set The development of construction and tourist industry is applied, travelling products is innovated, supporting corresponding tourism service facilities, will be karst area tourist industry The direction developed.However, due to karst area especially southwest, traffic is relatively inaccessible, supporting tourism service facilities Relative deficiency.Especially at karst scenic spot, view people broker's storehouse road is even more one and required supplementation with and supporting tourist facilities.
Because the general topography and geomorphology in karst scenic spot is complicated, especially even more so in the steep region of some landform, existing skill When building these local view people broker's storehouse roads, the mode of generally use hand excavation and explosion is carried out art, using so Build mode heavy damage auto-ignition environment, scenic spot is destroyed serious, and construction cost is high.
The content of the invention
The technical problem to be solved in the present invention:A kind of karst depression people broker's storehouse road structure and preparation method are provided, to solve When prior art builds view people broker's storehouse road in the complicated place of the topography and geomorphologies such as karst scenic spot, generally use hand excavation and quick-fried Broken mode is carried out, and mode heavy damage auto-ignition environment is built using such, and scenic spot is destroyed seriously, and is constructed into Originally the technical problem such as high.
Technical solution of the present invention:
A kind of karst depression people broker's storehouse road structure, it includes horizontal support section and people broker's storehouse road, and people broker's storehouse road is fixed on horizontal branch Support the upper surface of section;One end of horizontal support section and diagonal brace section is separately fixed in karst cliff;Horizontal support section and diagonal brace section The other end be fixedly connected;The side of horizontal support section is fixed with guard rail.
People broker's storehouse road includes reinforcing bar, and reinforcing bar center bottom is welded with band steel, and reinforcing bar both ends bottom is welded with first etc. Corner angle and the second equal leg angle.
The anchor head end of horizontal support section bends downwards and is anchored in basement rock palisades, and downward bending angle is 10-15 degree.
The angle of diagonal brace section and horizontal direction is 45-70 degree;Diagonal brace section includes the second reinforcing bar and third corner angle, and second Reinforcing bar and third corner angle are welded to connect.
The connection end of horizontal support section and diagonal brace section is welded to connect by steel plate.
The length of reinforcing bar is 0.8 meter -1.2 meters, and the arrangement spacing of across pitch is 3-6 centimetres.
A kind of preparation method of karst depression people broker's storehouse road structure, it includes:
Step 1, makes diagonal brace section, and diagonal brace section includes the second reinforcing bar and third corner angle, the second reinforcing bar and third corner angle It is welded to connect;For second Bar Anchorage of diagonal brace section in basement rock palisades, the angle with horizontal direction is 45-70 degree;
Step 2, production technique supporting section, the anchor head end of horizontal support section bend downwards and are anchored in basement rock palisades, be turned under Knuckle degree is 10-15 degree;
Step 3, horizontal support section and diagonal brace section are welded to connect with steel plate, the thickness of steel plate is 8 millimeters;
Step 4, the second steel plate and the 3rd steel plate are welded to connect with horizontal support section, the second steel plate after welding, In the same plane, top edge is in same level for three steel plates and steel plate;Second steel plate, the thickness of the 3rd steel plate are 8 millimeters;
Step 5, the second equal leg angle of connection and the first equal leg angle is respectively welded in steel plate and the second steel plate top edge;
Step 6, band steel is welded to connect in the 3rd steel plate top edge;
Step 7, reinforcing bar, reinforcing bar and the first grade corner are laid above band steel between the second equal leg angle and the first equal leg angle It is welded to connect between steel and the second equal leg angle, between reinforcing bar and band steel;
Step 8, move towards to set guard rail along plank road, guard rail is highly 1.1 meters, and the handrail 16 for forming guard rail is 60 × 40 × 1.8 millimeters of square steel, component 15 are 40 × 40 × 1.8 millimeters of square steel, and it is equilateral that the column of guard rail is welded on second On angle steel.
Beneficial effects of the present invention:
The present invention on the cliff of karst area by setting horizontal support section and diagonal brace section, and by horizontal support section and diagonal brace section Top is welded and fixed, and forms a firm supporting construction;People broker's storehouse road is laid in horizontal support section, realizing people can be The purpose walked safely on karst cliff;And work progress does not need explosion and opens big digging greatly;Avoid because of constructing road and Caused by open greatly it is big dig and the significantly destruction to ecological environment, have make the best use of the situation, beneficial to environmental protection the advantages of;The present invention is also With the characteristics of simple in construction, cost is low, easy to operate;Prior art is solved on the complicated ground of the topography and geomorphologies such as karst scenic spot During Fang Xiujian view people broker's storehouse roads, the mode of generally use hand excavation and explosion is carried out, and to build mode tight using such Auto-ignition environment is destroyed again, and serious, and technical problems such as construction cost is high are destroyed to scenic spot.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2 is diagonal brace segment structure schematic diagram of the present invention;
Fig. 3 is the present inventor broker's storehouse road structural representation;
Fig. 4 is guard rail structural representation of the present invention.
Embodiment
A kind of karst depression people broker's storehouse road structure, it includes horizontal support section and people broker's storehouse road, and people broker's storehouse road is fixed on water The upper surface of flat supporting section;One end of horizontal support section and diagonal brace section is separately fixed in karst cliff 5;Horizontal support section and tiltedly The other end of support section 2 is fixedly connected;The side of horizontal support section is fixed with guard rail 4.
People broker's storehouse road includes reinforcing bar 13, and the center bottom of reinforcing bar 13 is welded with band steel 14, the welding of the both ends bottom of reinforcing bar 13 There are the first equal leg angle 11 and the second equal leg angle 12.People broker's storehouse road broadband is typically at 900 millimeters;450 millis in people broker's storehouse road Meter Chu bottoms Welding flat steel 14.
The anchor head end of horizontal support section bends downwards and is anchored in basement rock palisades, and downward bending angle is 10-15 degree.
The angle of diagonal brace section and horizontal direction is 45-70 degree;Diagonal brace section includes the second reinforcing bar 10 and third corner angle 9, Second reinforcing bar 10 and third corner angle 9 are welded to connect.
The connection end of horizontal support section and diagonal brace section is welded to connect by steel plate 8;A fixed planar delta is formed, it is right People broker's storehouse road is supported and fixed.
The length of reinforcing bar 13 is 0.8 meter -1.2 meters, and the arrangement spacing of across pitch is 3-6 centimetres.
A kind of preparation method of karst depression people broker's storehouse road structure, it includes:
Step 1, makes diagonal brace section, and diagonal brace section includes the second reinforcing bar and third corner angle, the second reinforcing bar and third corner angle It is welded to connect;For second Bar Anchorage of diagonal brace section in basement rock palisades, the angle with horizontal direction is 45-70 degree;
Step 2, production technique supporting section, the anchor head end of horizontal support section bend downwards and are anchored in basement rock palisades, be turned under Knuckle degree is 10-15 degree;
Step 3, horizontal support section and diagonal brace section are welded to connect with steel plate, the thickness of steel plate is 8 millimeters;
Step 4, the second steel plate 6 and the 3rd steel plate 7 are welded to connect with horizontal support section, the second steel plate after welding 6th, in the same plane, top edge is in same level for the 3rd steel plate 7 and steel plate 8;Second steel plate 6, the 3rd steel plate 7 Thickness be 8 millimeters;Second steel plate 6 and the 3rd steel plate 7 play leveling effect;
Step 5, the second equal leg angle 12 of connection and the first equal leg angle is respectively welded in the top edge of 8 and second steel plate of steel plate 6 11;
Step 6, band steel 14 is welded to connect in the top edge of the 3rd steel plate 7;
Step 7, between the second equal leg angle 12 and the first equal leg angle 11 above band steel 14 lay reinforcing bar 13, reinforcing bar 13 with It is welded to connect between first equal leg angle 11 and the second equal leg angle 12, between reinforcing bar 13 and band steel 14;
Step 8, move towards to set guard rail 4 along plank road, the height of guard rail 4 is 1.1 meters, forms the handrail 16 of guard rail 4 For 60 × 40 × 1.8 millimeters of square steel, component 15 is 40 × 40 × 1.8 millimeters of square steel, and the column of guard rail 4 is welded on second etc. On corner angle 12.

Claims (7)

1. a kind of karst depression people broker's storehouse road structure, it includes horizontal support section and people broker's storehouse road, it is characterised in that:People broker's storehouse road It is fixed on the upper surface of horizontal support section;One end of horizontal support section and diagonal brace section is separately fixed at karst cliff(5)It is interior;It is horizontal Supporting section is fixedly connected with the other end of diagonal brace section;The side of horizontal support section is fixed with guard rail(4).
A kind of 2. karst depression people broker's storehouse road structure according to claim 1, it is characterised in that:People broker's storehouse road includes Reinforcing bar(13), reinforcing bar(13)Center bottom is welded with band steel(14), reinforcing bar(13)Both ends bottom is welded with the first equal leg angle (11)With the second equal leg angle(12).
A kind of 3. karst depression people broker's storehouse road structure according to claim 1, it is characterised in that:The anchor head of horizontal support section End bends and is anchored in basement rock palisades downwards, and downward bending angle is 10-15 degree.
A kind of 4. karst depression people broker's storehouse road structure according to claim 1, it is characterised in that:Diagonal brace section and horizontal direction Angle be 45-70 degree;Diagonal brace section includes the second reinforcing bar(10)With third corner angle(9), the second reinforcing bar(10)It is third with Corner angle(9)It is welded to connect.
A kind of 5. karst depression people broker's storehouse road structure according to claim 1, it is characterised in that:Horizontal support section and diagonal brace The connection end of section passes through steel plate(8)It is welded to connect.
A kind of 6. karst depression people broker's storehouse road structure according to claim 2, it is characterised in that:Reinforcing bar(13)Length be 0.8 meter -1.2 meters, the arrangement spacing of across pitch is 3-6 centimetres.
7. a kind of preparation method of karst depression people broker's storehouse road structure, it includes:
Step 1, makes diagonal brace section, and diagonal brace section includes the second reinforcing bar(10)With third corner angle(9), the second reinforcing bar(10)With Third corner angle(9)It is welded to connect;Second reinforcing bar of diagonal brace section(10)It is anchored in basement rock palisades(5)In, with horizontal direction Angle is 45-70 degree;
Step 2, production technique supporting section, the anchor head end of horizontal support section bend downwards and are anchored in basement rock palisades, be turned under Knuckle degree is 10-15 degree;
Step 3, use steel plate(8)It is welded to connect horizontal support section and diagonal brace section, steel plate(8)Thickness be 8 millimeters;
Step 4, by the second steel plate(6)With the 3rd steel plate(7)It is welded to connect with horizontal support section, second after welding is thick Steel plate(6), the 3rd steel plate(7)And steel plate(8)In the same plane, top edge is in same level;Second steel plate (6), the 3rd steel plate(7)Thickness be 8 millimeters;
Step 5, in steel plate(8)With the second steel plate(6)The second equal leg angle of connection is respectively welded in top edge(12)With first etc. Corner angle(11);
Step 6, in the 3rd steel plate(7)Top edge is welded to connect band steel(14);
Step 7, in the second equal leg angle(12)With the first equal leg angle(11)Between band steel(14)Reinforcing bar is laid above(13), Reinforcing bar(13)With the first equal leg angle(11)With the second equal leg angle(12)Between, reinforcing bar(13)With band steel(14)Between weld Connection;
Step 8, move towards to set guard rail along plank road(4), guard rail(4)Highly it is 1.1 meters, forms guard rail(4)'s Handrail 16 is 60 × 40 × 1.8 millimeters of square steel, and component 15 is 40 × 40 × 1.8 millimeters of square steel, guard rail(4)Column welding In the second equal leg angle(12)On.
CN201710787589.8A 2017-09-04 2017-09-04 A kind of karst depression people broker's storehouse road structure and preparation method Pending CN107574749A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710787589.8A CN107574749A (en) 2017-09-04 2017-09-04 A kind of karst depression people broker's storehouse road structure and preparation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710787589.8A CN107574749A (en) 2017-09-04 2017-09-04 A kind of karst depression people broker's storehouse road structure and preparation method

Publications (1)

Publication Number Publication Date
CN107574749A true CN107574749A (en) 2018-01-12

Family

ID=61029945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710787589.8A Pending CN107574749A (en) 2017-09-04 2017-09-04 A kind of karst depression people broker's storehouse road structure and preparation method

Country Status (1)

Country Link
CN (1) CN107574749A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH083922A (en) * 1994-06-21 1996-01-09 Hazama Gumi Ltd Suspension bridge anchor and construction method
CN202298440U (en) * 2011-10-31 2012-07-04 中国水电顾问集团华东勘测设计研究院 Steel trestle structure used on cliff terrains
CN103225257A (en) * 2013-04-09 2013-07-31 中钢集团马鞍山矿山研究院有限公司 Cantilever beam structure of antique plank road along cliff and construction technology thereof
CN205036096U (en) * 2015-08-14 2016-02-17 中国建筑第八工程局有限公司 Be used for accessible device that passes through of three -dimensional support of reinforcing bar
CN205741874U (en) * 2016-06-02 2016-11-30 中国水利水电第五工程局有限公司 A kind of high gradient slope safety alarm level plank road
CN206109965U (en) * 2016-08-30 2017-04-19 西北水利水电工程有限责任公司 Steel plank road in water and electricity building site

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH083922A (en) * 1994-06-21 1996-01-09 Hazama Gumi Ltd Suspension bridge anchor and construction method
CN202298440U (en) * 2011-10-31 2012-07-04 中国水电顾问集团华东勘测设计研究院 Steel trestle structure used on cliff terrains
CN103225257A (en) * 2013-04-09 2013-07-31 中钢集团马鞍山矿山研究院有限公司 Cantilever beam structure of antique plank road along cliff and construction technology thereof
CN205036096U (en) * 2015-08-14 2016-02-17 中国建筑第八工程局有限公司 Be used for accessible device that passes through of three -dimensional support of reinforcing bar
CN205741874U (en) * 2016-06-02 2016-11-30 中国水利水电第五工程局有限公司 A kind of high gradient slope safety alarm level plank road
CN206109965U (en) * 2016-08-30 2017-04-19 西北水利水电工程有限责任公司 Steel plank road in water and electricity building site

Similar Documents

Publication Publication Date Title
US11072898B2 (en) Combined energy dissipation scaffolding structure for preventing falling rock for high and steep slope in seismic region
CN103243652B (en) A kind of large-span non-floor type cast-in-place beam falsework and construction method thereof
CN201053123Y (en) Deep foundation ditch tower crane platform base frame
CN106436592A (en) Bridge widening structure using Z-shaped steel plate connectors and construction method thereof
CN106351343A (en) Basement outer wall waterproof protection structure capable of realizing synchronous crossing construction and construction method thereof
CN107700366A (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN205775786U (en) A kind of novel railway curve Cable-stayed Bridge with Slanted Pylon
CN205662832U (en) Under hold formula beiLei beam steel suspension bridge
CN105887913A (en) Design method for steel structure platform and trestle structure for shallow water area pole and tower foundation construction
CN104929047A (en) V-shaped pier outer support construction method
CN107313628A (en) A kind of basic digging-free assembled tower-type space garage and its construction method
CN207176478U (en) A kind of karst depression people broker's storehouse road structure
CN104612105A (en) Steel concrete structure type flood control wall
CN107574749A (en) A kind of karst depression people broker's storehouse road structure and preparation method
CN216040719U (en) Template support cantilever bearing structure
CN104612032A (en) Large-span inclined arched bridge tower cable-stayed bridge
CN102392417A (en) Dual-cantilever bearing support structure for large steel pipe and installation method
CN204401462U (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water
CN203393594U (en) Pre-stressed concrete variable cross-section box girder bridge with internally-arranged slant legged rigid frame
CN106013752A (en) Construction method for movable observation and construction dual-purpose platform
CN208934293U (en) Vertical shaft stair
CN208563084U (en) A kind of trestle based on arch bridge
CN106087753A (en) A kind of Cast-in-situ Beam beam-type support is without Temporary Piers construction
KR101047943B1 (en) A extension footpath with reinforcement equipment and it's construction method
CN206986735U (en) A kind of movable bridge suspension platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180112

RJ01 Rejection of invention patent application after publication