CN107558438A - A kind of flood fighting barricade and its construction method - Google Patents

A kind of flood fighting barricade and its construction method Download PDF

Info

Publication number
CN107558438A
CN107558438A CN201710705032.5A CN201710705032A CN107558438A CN 107558438 A CN107558438 A CN 107558438A CN 201710705032 A CN201710705032 A CN 201710705032A CN 107558438 A CN107558438 A CN 107558438A
Authority
CN
China
Prior art keywords
staving
cloth
barricade
vertical bar
flood fighting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710705032.5A
Other languages
Chinese (zh)
Inventor
石少卿
王平
魏军
罗伟铭
李季
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Time Royal Building Technology Co Ltd
Logistical Engineering University of PLA
Original Assignee
Chongqing Time Royal Building Technology Co Ltd
Logistical Engineering University of PLA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Time Royal Building Technology Co Ltd, Logistical Engineering University of PLA filed Critical Chongqing Time Royal Building Technology Co Ltd
Priority to CN201710705032.5A priority Critical patent/CN107558438A/en
Publication of CN107558438A publication Critical patent/CN107558438A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of flood fighting barricade and its construction method, flood fighting barricade includes staving, cladding cloth and filler, the cladding cloth cuff is on the cylinder of staving, the vertical bar overlap edge reserved on cloth is coated to be connected with each other with adjacent cladding cloth vertical bar overlap edge, network structure is formed, filler is packed into staving and coats the slot space surrounded between cloth.Construction method includes:1st, ground grading, staving is placed;2nd, sandstone are packed into staving;3rd, the vertical bar overlap edge coated on cloth is connected with each other, forms network structure;4th, sandstone are filled in the slot space that cladding cloth is surrounded.It is an advantage of the invention that:Sound construction, do not produce breach;And can shorten and construct the time, it is adapted to promptly build;Wall height can increase with flood position.

Description

A kind of flood fighting barricade and its construction method
Technical field
The invention belongs to flood-proof technology field, and in particular to a kind of barricade and its construction method for flood fighting.
Background technology
Flood serious threat people life property safety in natural calamity, while destroy communal facility.In terms of flood control, mesh Before, accumulated mostly using artificial filled sandbags, but this method working strength is big, and efficiency is low, and the sealing effectiveness of dash gear mudstone is not It is good.On the one hand, sandbag flood bank is not firm enough, under the huge impact force action of flood, easily washes away to form breach, danger occurs Feelings;On the other hand, it is low to construct the efficiency of sandbag flood bank, it is longer to construct the time, because flood harm is big, area is wide, resists Flood is pressed for time, and traditional sandbag flood bank is not suitable with flood fighting requirement.The height of other sandbag flood bank is also restrained.
The content of the invention
The problem of existing for existing sandbag flood bank, the technical problems to be solved by the invention are just to provide a kind of flood fighting Barricade, its sound construction, breach is not produced, and can shorten and construct the time, be adapted to promptly build, wall height can be with flood level Put increase.The present invention also provides the construction method of the flood fighting barricade.
A kind of flood fighting barricade provided by the invention, including staving, cladding cloth and filler, the cladding cloth cuff is in staving Cylinder on, coat the vertical bar overlap edge reserved on cloth and be connected with each other with adjacent cladding cloth vertical bar overlap edge, form netted knot Structure, filler are packed into staving and coat the slot space surrounded between cloth;The filler is sandstone, soil or coagulation Soil.
The present invention also provides the construction method of above-mentioned flood fighting barricade, comprises the following steps:
Step 1, ground grading, place by the staving of cladding cloth cuff;
Step 2, sandstone, soil or Concrete Filled are entered in staving;
Step 3, the vertical bar overlap edge for coating the vertical bar overlap edge and adjacent cladding cloth reserved on cloth is connected with each other, formed Network structure;
Step 4, sandstone, soil or concrete are filled in the slot space that cladding cloth is surrounded.
The solution have the advantages that:
1st, by the use of the staving of filler is filled up as flood fighting barricade, completely cutting off in bucket with flood, filler by erodsion of stream or does not wash away, Staving is connected into network structure, will not leave behind breach, and can increase and decrease staving according to the flood flow of water by its sound construction, cladding cloth The number of permutations, it is ensured that resistance flood impact ability.
2nd, staving is connected with each other by coating cloth, is formed Combined type wall block, is easy to quickly assemble, shortens and construct the time; And all material(Including sandstone, soil)Can effectively it utilize, caused by material skewness caused by avoiding sandbag accumulation Waste.
3rd, in young flood, water level is relatively low, to adapt to promptly construct flood fighting barricade, is filled in staving and cladding cloth slot is empty Between material it is less, the wall height constructed is relatively low;As water level rises, constantly can increase to staving and cladding cloth slot space Filler is mended, flood fighting barricade also increases, is advantageous to win the flood fighting time therewith.
Brief description of the drawings
The brief description of the drawings of the present invention is as follows:
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the constitutional diagram of cladding cloth and staving;
Fig. 3 is the bucket body structure schematic diagram of the present invention;
Fig. 4 is the constitutional diagram of anchor pole and annulus;
Fig. 5 is Fig. 4 plan;
Fig. 6 is the outline drawing of disk support.
In figure, 1, staving;2nd, cloth is coated;21st, vertical bar overlap edge;3rd, filler;11st, anchor pole;12nd, annulus;13rd, iron sheet; 14th, roundel;15th, connecting elements;16th, disk support.
Embodiment
The invention will be further described with reference to the accompanying drawings and examples:
As depicted in figs. 1 and 2, flood fighting barricade of the invention, including staving 1, cladding cloth 2 and filler 3, the cladding cloth 2 are bound round It is enclosed on the cylinder of staving 1, coats the vertical bar overlap edge 21 reserved on cloth 2 and interconnected with the adjacent phase of cladding cloth vertical bar overlap edge 21 Connect, form network structure, filler 3 is packed into staving 1 and coats the slot space surrounded between cloth 2;The filler 3 is Sandstone, soil or concrete.
The staving 1 can be metal drum or Plastic Drum, and its shape can be circular, square or more prismatics; The cladding cloth 2 is colour camoufague cloth, canvas or Compound Fabric;Cover cloth vertical bar overlap edge 21 can with slide fastener, belt lock catch or With the overlap edge of rope tying.
Prefabricated profiled staving space-consuming is big, is not easy to carry and transports, for the ease of by the structure material of flood fighting barricade Material is transported to construction ground rapidly, therefore, the staving of the present invention uses following combining structure:
As shown in Fig. 3, Fig. 4 and Fig. 5, staving 1 includes anchor pole 11, annulus 12 and iron sheet 13, and roundlet is arranged at intervals with anchor pole 11 Disk 14, at least three anchor poles surround circle, and annulus 12 is enclosed on the outer ring of anchor pole 11, spacing on roundel 14, with tied silk by annulus 12 tie up on the anchor rods 11, and iron sheet 13 is curled into cylindrical shape, are placed in the inner ring that anchor pole surrounds, the prefabricated company in the outer surface of iron sheet 13 Connection member 15 is fixed on annulus 12.Connecting elements 15 is prefabricated by way of welding to be in the outer surface of iron sheet 13, component form Hooked and can detaining securely is leaned against on annulus 12.
Leaked to prevent from filling sandstone soil, while prevent river from immersing inside above-mentioned staving 1, in staving 1 Bottom is fitted with disk support 16, as shown in fig. 6, disk support is the disk made of metal or plastics.
The construction method of above-mentioned flood fighting barricade, comprises the following steps:
Step 1, ground grading, place by the staving 1 of the cuff of cladding cloth 2;
Step 2, sandstone, soil or Concrete Filled are entered in staving 1;
Step 3, the vertical bar overlap edge 21 for coating the vertical bar overlap edge 21 and adjacent cladding cloth reserved on cloth 2 is connected with each other, Form network structure;
Step 4, sandstone, soil or concrete are filled in the slot space that cladding cloth 2 is surrounded.
It is of course also possible to first carry out step 1, then step 3 is performed, step 2 is finally merged into execution with step 4.

Claims (5)

1. a kind of flood fighting barricade, it is characterized in that:Including staving(1), cladding cloth(2)And filler(3), the cladding cloth(2)Hoop It is enclosed on staving(1)Cylinder on, coat cloth(2)Upper reserved vertical bar overlap edge(21)With adjacent cladding cloth vertical bar overlap edge (21)It is connected with each other, forms network structure, filler(3)It is packed into staving(1)With cladding cloth(2)Between the slot that is surrounded it is empty Between;The filler(3)For sandstone, soil or concrete.
2. flood fighting barricade according to claim 1, it is characterized in that:Described staving(1)Including anchor pole(11), annulus(12) And iron sheet(13), roundel is arranged at intervals with anchor pole 11(14), at least three anchor poles surround circle, annulus(12)It is enclosed on anchor pole (11)It is outer ring, spacing in roundel(14)On, with tied silk by annulus(12)It is banded in anchor pole(11)On, iron sheet(13)It is curled into circle Tubular, it is placed in the inner ring that anchor pole surrounds, iron sheet(13)The prefabricated connecting elements in outer surface(15)It is fixed on annulus(12)On.
3. flood fighting barricade according to claim 2, it is characterized in that:In staving(1)Bottom is fitted with disk support(16).
4. flood fighting barricade construction method described in a kind of claim 1, it is characterized in that, comprise the following steps:
Step 1, ground grading, place by the staving of cladding cloth cuff;
Step 2, sandstone, soil or Concrete Filled are entered in staving;
Step 3, the vertical bar overlap edge for coating the vertical bar overlap edge and adjacent cladding cloth reserved on cloth is connected with each other, formed Network structure;
Step 4, sandstone, soil or concrete are filled in the slot space that cladding cloth is surrounded.
5. flood fighting barricade construction method according to claim 4, it is characterized in that:First carry out step 1, perform step 3 again, most Step 2 is merged into execution with step 4 afterwards.
CN201710705032.5A 2017-08-17 2017-08-17 A kind of flood fighting barricade and its construction method Pending CN107558438A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710705032.5A CN107558438A (en) 2017-08-17 2017-08-17 A kind of flood fighting barricade and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710705032.5A CN107558438A (en) 2017-08-17 2017-08-17 A kind of flood fighting barricade and its construction method

Publications (1)

Publication Number Publication Date
CN107558438A true CN107558438A (en) 2018-01-09

Family

ID=60975628

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710705032.5A Pending CN107558438A (en) 2017-08-17 2017-08-17 A kind of flood fighting barricade and its construction method

Country Status (1)

Country Link
CN (1) CN107558438A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111648825A (en) * 2020-06-16 2020-09-11 中铁十四局集团隧道工程有限公司 Tunnel collapsed cavity rapid retaining wall and emergency treatment construction process

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0620326A1 (en) * 1989-04-07 1994-10-19 Hesco Bastion Limited Improvements relating to a method of making building and shoring structural blocks
CN201485819U (en) * 2009-08-07 2010-05-26 山东济宁鲁水防汛抗旱设备制造有限公司 Telescopic lead wire cage device
US20150299977A1 (en) * 2008-04-18 2015-10-22 Hesco Bastion Limited Gabion system
CN105556036A (en) * 2013-08-29 2016-05-04 海斯科堡垒有限公司 Flood defence barrier
CN106087870A (en) * 2016-08-16 2016-11-09 重庆市晟庄建材有限责任公司 A kind of flood-fighting special reinforcing steel cage
CN207193885U (en) * 2017-08-17 2018-04-06 中国人民解放军后勤工程学院 A kind of flood fighting barricade

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0620326A1 (en) * 1989-04-07 1994-10-19 Hesco Bastion Limited Improvements relating to a method of making building and shoring structural blocks
US20150299977A1 (en) * 2008-04-18 2015-10-22 Hesco Bastion Limited Gabion system
CN201485819U (en) * 2009-08-07 2010-05-26 山东济宁鲁水防汛抗旱设备制造有限公司 Telescopic lead wire cage device
CN105556036A (en) * 2013-08-29 2016-05-04 海斯科堡垒有限公司 Flood defence barrier
CN106087870A (en) * 2016-08-16 2016-11-09 重庆市晟庄建材有限责任公司 A kind of flood-fighting special reinforcing steel cage
CN207193885U (en) * 2017-08-17 2018-04-06 中国人民解放军后勤工程学院 A kind of flood fighting barricade

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111648825A (en) * 2020-06-16 2020-09-11 中铁十四局集团隧道工程有限公司 Tunnel collapsed cavity rapid retaining wall and emergency treatment construction process

Similar Documents

Publication Publication Date Title
CN106400740A (en) Novel plugging method and device used after dike breaking
JP6925684B1 (en) Standing structure of columns
CN213086712U (en) Slope dike protection body of gabion mesh box structure
CN107142898B (en) A kind of dyke crevasse fast plugging device
CN207959233U (en) Ecological grid structures
JP5650063B2 (en) Embankment structure and construction method of embankment structure
CN207193885U (en) A kind of flood fighting barricade
CN201778303U (en) Flood-control intercepting steel mesh
CN109881634B (en) Rapid emergency rescue method for dike breach in flood season by utilizing geosynthetic material for closure
CN107558438A (en) A kind of flood fighting barricade and its construction method
CN205530139U (en) Dykes and dams cut flow net
EP3555373B1 (en) Sack for civil engineering works, method for its manufacture, and realisation of such works
CN104164854A (en) Method for ecologically re-greening hardened slope
CN209227558U (en) A kind of lattice guest's supporting construction suitable for high precipitous rock slope ecological recovery
JP5281974B2 (en) Drain structure
CN110409373A (en) A kind of flood-fighting net device and its application and application method
CN105256763A (en) Diking method based on bamboo raft frame structure
CN107542059B (en) A method of it repairing base soil flow and loses buttress
CN207608880U (en) Box ecoscape barricade
JP6668051B2 (en) Bamboo earth retaining structure
CN1242123C (en) Dam protection and breach closing method using multilayer floating bag, sinking net and cloth in flood fighting
CN212477800U (en) Anchoring gabion retaining wall
CN111321700B (en) Overflowing energy dissipation type ecological bank protection method for anti-scouring and anti-landslide barrier plugs
CN203583437U (en) Pile-net dinas dam mudflat enclosure hydraulic structure
CN203475388U (en) High-strength non-woven geofabriform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 401331 No. 20 Army Service College, North Road, University Town, Shapingba District, Chongqing

Applicant after: SERVICES COLLEGE OF CPLA GROUND FORCE

Applicant after: CHONGQING SHIZHIYU BUILDING TECHNOLOGY Co.,Ltd.

Address before: 401311 School of logistics engineering, University City, Shapingba District, Chongqing

Applicant before: LOGISTICAL ENGINEERING UNIVERSITY OF PLA

Applicant before: CHONGQING SHIZHIYU BUILDING TECHNOLOGY Co.,Ltd.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20180109

RJ01 Rejection of invention patent application after publication