CN107527546A - Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation - Google Patents

Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation Download PDF

Info

Publication number
CN107527546A
CN107527546A CN201710643416.9A CN201710643416A CN107527546A CN 107527546 A CN107527546 A CN 107527546A CN 201710643416 A CN201710643416 A CN 201710643416A CN 107527546 A CN107527546 A CN 107527546A
Authority
CN
China
Prior art keywords
wooden stick
stick unit
earth
unit
simulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710643416.9A
Other languages
Chinese (zh)
Inventor
闻礼双
厉新华
李晓悦
杨毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Underground Space Construction And Development Center
Original Assignee
Hangzhou Underground Space Construction And Development Center
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Underground Space Construction And Development Center filed Critical Hangzhou Underground Space Construction And Development Center
Priority to CN201710643416.9A priority Critical patent/CN107527546A/en
Publication of CN107527546A publication Critical patent/CN107527546A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B25/00Models for purposes not provided for in G09B23/00, e.g. full-sized devices for demonstration purposes

Abstract

The invention discloses the experimental provision that a kind of simulation CRD method constructing tunnels cause earth's surface deformation, including model casing, the soil body of the filling provided with compacting in model casing, tunnel hole is provided with the soil body, tunnel hole interpolation is equiped with wooden stick, wooden stick is provided with a longitudinally split face and at least one horizontal partition face along its axial direction, wooden stick is divided into left side wooden stick in longitudinally split face and left side wooden stick and right side wooden stick are divided at least two layers of wooden stick unit of setting stacked on top of one another by right side wooden stick two parts, at least one horizontal partition face respectively;Also include corresponding with wooden stick unit set and for wooden stick unit inserted from tunnel hole in extraction in tunnel hole as tunnel hole inwall lining cutting interior wall pieces, all interior wall pieces collectively form the shape and structure identical tubular structure with tunnel hole;Earth's surface deformation measuring system is additionally provided with above model casing.The invention also discloses the experimental method that a kind of simulation CRD method constructing tunnels cause earth's surface deformation.

Description

Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation
Technical field
It is specific to cause earth's surface for a kind of simulation CRD method constructing tunnels the invention belongs to underground engineering experimental technique field The experimental provision and experimental method of deformation, the process that CRD method constructing tunnels cause earth's surface to deform can be simulated, is design and construction The optimization of scheme provides foundation, and effective prediction work is played to the potential safety hazard of existed building around job site and structures With.
Background technology
CRD construction full name intersect middle-wall method, are a kind of method for tunnel construction suitable for soft stratum, especially for Control subsidence has good effect, is typically mainly used in the construction of urban subway.Because its cost is high, therefore on the mountain ridge Less use in tunnel, but under special circumstances, it can also use, such as swelled ground stratum.In existing CRD methods constructing tunnel In technology, focus mostly on the different CRD methods construction under specific engineering geological condition, without corresponding analogue means, therefore Laboratory can not be simulated by CRD method constructing tunnel processes again.
The content of the invention
In view of this, it is an object of the invention to provide the experiment that a kind of simulation CRD method constructing tunnels cause earth's surface deformation Device and experimental method, CRD method constructing tunnel processes can be accurately simulated, so as to be exploration and solution CRD method constructing tunnels Data foundation is provided to earth's surface and the influence problem of building.
To reach above-mentioned purpose, the present invention provides following technical scheme:
Present invention firstly provides the experimental provision that a kind of simulation CRD method constructing tunnels cause earth's surface deformation, including model casing, institute The soil body of the filling provided with compacting in model casing is stated, is provided with tunnel hole in the soil body, the tunnel hole interpolation is equiped with use In the wooden stick for supporting the tunnel hole, the wooden stick is provided with a longitudinally split face and at least one transverse direction along its axial direction The wooden stick is divided into left side wooden stick and right side wooden stick two parts, at least one horizontal stroke by divisional plane, the longitudinally split face The left side wooden stick and right side wooden stick are divided at least two layers of wooden stick unit of setting stacked on top of one another respectively to divisional plane;Also wrap Include to correspond with the wooden stick unit and set and for being inserted in the wooden stick unit from the tunnel hole in extraction Enter in the tunnel hole as the tunnel hole inwall lining cutting interior wall pieces, all interior wall pieces collectively form and The shape and structure identical tubular structure of the tunnel hole;Earth's surface deformation measuring system is additionally provided with above the model casing.
Further, the horizontal partition face is arranged to two, the left side wooden stick by the horizontal partition face be divided into from Upper left wooden stick unit, left wooden stick unit and the lower-left wooden stick unit being up to cascading down;The right side wooden stick is by institute State horizontal partition face and be divided into wooden stick unit and bottom right wooden stick list in the upper right wooden stick unit being cascading from top to bottom, the right side Member;Or
The horizontal partition face is arranged to one, and the left side wooden stick is divided into above first by the horizontal partition face Wooden stick unit and underlying second wooden stick unit, the right side wooden stick are divided into above by the horizontal partition face 3rd wooden stick unit and underlying 4th wooden stick unit.
Further, the horizontal partition face is arranged to two;The upper left wooden stick unit, left wooden stick unit, lower-left wood The maximum gauge of wooden stick unit and bottom right wooden stick unit in the vertical direction is equal in rod unit, upper right wooden stick unit, the right side.
Further, wood in the upper left wooden stick unit, left wooden stick unit, lower-left wooden stick unit, upper right wooden stick unit, the right side Handle I is respectively equipped with same one end end face of rod unit and bottom right wooden stick unit;And the upper left wooden stick unit, left wooden stick list In member, lower-left wooden stick unit, upper right wooden stick unit, the right side graduated scale I is equipped with wooden stick unit and bottom right wooden stick unit.
Further, the horizontal partition face is arranged to one, the first wooden stick unit, the second wooden stick unit, the 3rd wood The maximum gauge of rod unit and the 4th wooden stick unit on data direction is equal.
Further, the first wooden stick unit, the second wooden stick unit, the 3rd wooden stick unit and the 4th wooden stick unit is same End end face is provided with handle II, and the first wooden stick unit, the second wooden stick unit, the 3rd wooden stick unit and the 4th wooden stick unit Same one end end face be provided with graduated scale II.
Further, the interior wall pieces are used and are cut into the tunnel hole shape and structure identical PE pipes;The mould Molding box is made of safety glass block.
Further, the earth's surface deformation measuring system includes being disposed on the installation crossbeam above the model casing, institute State interval installation on installation crossbeam and be provided with amesdial, corresponding inserting with the amesdial in the soil body is provided with and described thousand The measuring basis seat for dividing the measurement head of table to coordinate.
Further, the measuring basis seat is the hexagonal double-ended bolt being inserted into the soil body.
The invention also provides a kind of experiment dress for causing earth's surface to deform using simulation CRD method constructing tunnels as described above Put to simulate the experimental method that CRD method constructing tunnels cause earth's surface to deform, comprise the following steps:
1)The soil body is successively inserted in the model casing and is tamped, and works as the soil body and inserts the downside that height reaches the tunnel hole During edge, the wooden stick is placed on to the setting position of the model casing, and continues to insert the soil body, until the soil body all loads Complete;
2)The earth's surface deformation measuring system is installed above the model casing;
3)After soil stabilization, tunnel excavation process simulation is carried out, tunnel excavation analogy method is:According to CRD method constructing tunnels Process, the speed being calculated according to practice of construction process and the likelihood ratio, distance and time of stopping over extract the wood successively Rod unit, and the interior wall pieces being correspondingly arranged with each wooden stick unit are inserted into the tunnel hole as lining cutting simultaneously;Directly It is completely drawn out to all wooden stick units, all interior wall pieces are inserted into the tunnel hole;It is and real-time in the process Record earth's surface deformation data;
4)Repeat step 1)To step 3), at different rates, distance and the time simulation CRD method constructing tunnel mistakes that stop over Journey, obtain different earth's surface deformation datas;
5)Following two relation curves are drawn according to obtained earth's surface deformation data:M- earth's surface deflection curve when a.;B. it is each The final deformation curve of cross section earth's surface;Rule Summary, effective reference data is provided for final CRD method constructing tunnels.
The beneficial effects of the present invention are:
The simulation CRD method constructing tunnels of the present invention cause the experimental provision and experimental method of earth's surface deformation, can simulate CRD method tunnels Influence of the road construction to earth's surface deformation, obtains the definite relation between different construction parameters and earth's surface deformation, is design and construction The optimization of scheme provides foundation, and effective prediction work is played to the potential safety hazard of existed building around job site and structures With.
Brief description of the drawings
In order that the purpose of the present invention, technical scheme and beneficial effect are clearer, the present invention provides drawings described below and carried out Explanation:
Fig. 1 is the structural representation for the experimental provision embodiment 1 that present invention simulation CRD method constructing tunnels cause earth's surface deformation;
Fig. 2 is Fig. 1 top view;
Fig. 3 is the experimental provision simulation tunnel digging process for causing earth's surface deformation using the present embodiment simulation CRD method constructing tunnels Use state figure;
Fig. 4 is Fig. 3 rearview;
Fig. 5 is the structural representation for the experimental provision embodiment 2 that present invention simulation CRD method constructing tunnels cause earth's surface deformation;
Fig. 6 is the experimental provision simulation tunnel digging process for causing earth's surface deformation using the present embodiment simulation CRD method constructing tunnels Use state figure;
Fig. 7 is Fig. 6 rearview.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings, so that those skilled in the art can be with It is better understood from the present invention and can be practiced, but illustrated embodiment is not as a limitation of the invention.
Embodiment 1
As shown in figure 1, the structure of the experimental provision embodiment 1 of earth's surface deformation is caused to be shown for present invention simulation CRD method constructing tunnels It is intended to.The simulation CRD method constructing tunnels of the present embodiment cause the experimental provision that earth's surface deforms, including model casing 1, in model casing 1 The soil body 2 of the filling provided with compacting, the soil body 2 is interior to be provided with tunnel hole, and tunnel hole interpolation is equiped with for supporting tunnel hole Wooden stick, wooden stick are provided with a longitudinally split face and at least one horizontal partition face along its axial direction, and longitudinally split face is by wooden stick It is divided into left side wooden stick and right side wooden stick two parts, at least one horizontal partition face splits left side wooden stick and right side wooden stick respectively For at least two layers of wooden stick unit of setting stacked on top of one another.Specifically, the horizontal partition face of the present embodiment is arranged to two, left side wood Rod is divided into the upper left wooden stick unit 3 being cascading from top to bottom, left wooden stick unit 4 and lower-left wood by horizontal partition face Rod unit 5;Right side wooden stick is divided into wood in the upper right wooden stick unit 6 being cascading from top to bottom, the right side by horizontal partition face Rod unit 7 and bottom right wooden stick unit 8, two horizontal partition faces are parallel to each other, and horizontal partition face is vertical with longitudinally split face, indulge It is located to divisional plane on vertical direction.
The experimental provision that the simulation CRD method constructing tunnels of the present embodiment cause earth's surface to deform also is included with wooden stick unit one by one It is correspondingly arranged and is used to insert in tunnel hole as in tunnel hole in extraction from tunnel hole in wooden stick unit The interior wall pieces that wall liner is built, it is respectively interior wall pieces 3a, interior wall pieces 4a, interior wall pieces 5a, interior wall pieces 6a, interior wall pieces 7a and interior wall pieces 8a, All interior wall pieces collectively form the shape and structure identical tubular structure with tunnel hole;The top of model casing 1 is additionally provided with ground Table deformation measuring system.
The earth's surface deformation measuring system of the present embodiment includes the installation crossbeam 9 for being disposed on the top of model casing 1, and installation is horizontal Interval installation is provided with amesdial 10 on beam 9, is provided with the measurement head with amesdial 10 in the soil body 2 with the one-to-one corresponding inserting of amesdial 10 The measuring basis seat 11 of cooperation.The measuring basis seat 11 of the present embodiment is the hexagonal double-ended bolt being inserted into the soil body 2.
Specifically, the upper left wooden stick unit 3 of the present embodiment, left wooden stick unit 4, lower-left wooden stick unit 5, upper right wooden stick list The maximum gauge of wooden stick unit 7 and the in the vertical direction of bottom right wooden stick unit 8 is equal in member 6, the right side.Upper left wooden stick unit 3, a left side Same one end of wooden stick unit 7 and bottom right wooden stick unit 8 in middle wooden stick unit 4, lower-left wooden stick unit 5, upper right wooden stick unit 6, the right side Handle I 12 is respectively equipped with end face;And upper left wooden stick unit 3, left wooden stick unit 4, lower-left wooden stick unit 5, upper right wooden stick list In member 6, the right side graduated scale I is equipped with wooden stick unit 7 and bottom right wooden stick unit 8.
The interior wall pieces of the present embodiment are used and are cut into tunnel hole shape and structure identical PE pipes;Model casing 1 uses Safety glass block is made.Specifically, the radial section of the tunnel hole of the present embodiment is circle, on the front-rear side walls of model casing with Tunnel hole is correspondingly provided with through hole.
The experimental provision that earth's surface deforms is caused using the simulation CRD method constructing tunnels of the present embodiment to simulate CRD methods tunnel Construction causes the experimental method that earth's surface deforms, and comprises the following steps:
1)The soil body 2 is successively inserted in model casing 1 and is tamped, and works as the soil body 2 and inserts the lower edge that height reaches tunnel hole When, wooden stick is placed on to the setting position of model casing, and continue to insert the soil body 2, until the soil body all complete by filling;
2)Earth's surface deformation measuring system is installed above model casing 1;
3)After the soil body 2 is stable, tunnel excavation process simulation is carried out, tunnel excavation analogy method is:According to CRD method constructing tunnels Process, the speed being calculated according to practice of construction process and the likelihood ratio, distance and time of stopping over extract wooden stick list successively Member, i.e., according to setting parameter by upper left wooden stick unit 3, left wooden stick unit 4, lower-left wooden stick unit 5, upper right wooden stick unit 6, Wooden stick unit 7 and bottom right wooden stick unit 8 are extracted successively in the right side, and simultaneously insert the interior wall pieces being correspondingly arranged with each wooden stick unit Enter into tunnel hole and be used as lining cutting;Until all wooden stick units are completely drawn out, all interior wall pieces are inserted into Tunnel-hole In hole;And record earth's surface deformation data in real time in the process;
4)Repeat step 1)To step 3), at different rates, distance and the time simulation CRD method constructing tunnel mistakes that stop over Journey, obtain different earth's surface deformation datas;
5)Following two relation curves are drawn according to obtained earth's surface deformation data:M- earth's surface deflection curve when a.;B. it is each The final deformation curve of cross section earth's surface;Rule Summary, effective reference data is provided for final CRD method constructing tunnels.
The simulation CRD method constructing tunnels of the present embodiment cause the experimental provision and experimental method of earth's surface deformation, can simulate The influence that CRD methods constructing tunnel deforms to earth's surface, the definite relation between different construction parameters and earth's surface deformation is obtained, for design Optimization with arrangement and method for construction provides foundation, and the potential safety hazard of existed building around job site and structures is played effectively in advance Survey acts on.
Embodiment 2
As shown in figure 4, the structure of the experimental provision embodiment 2 of earth's surface deformation is caused to be shown for present invention simulation CRD method constructing tunnels It is intended to.The simulation CRD method constructing tunnels of the present embodiment cause the experimental provision that earth's surface deforms, including model casing 1, in model casing 1 The soil body 2 of the filling provided with compacting, the soil body 2 is interior to be provided with tunnel hole, and tunnel hole interpolation is equiped with for supporting tunnel hole Wooden stick, wooden stick are provided with a longitudinally split face and at least one horizontal partition face along its axial direction, and longitudinally split face is by wooden stick It is divided into left side wooden stick and right side wooden stick two parts, at least one horizontal partition face splits left side wooden stick and right side wooden stick respectively For at least two layers of wooden stick unit of setting stacked on top of one another.Specifically, the horizontal partition face of the present embodiment is arranged to one, left side wood Rod is divided into the first wooden stick unit 13 above and underlying second wooden stick unit 14, right side wood by horizontal partition face Rod is divided into the 3rd wooden stick unit 15 above and underlying 4th wooden stick unit 16 by horizontal partition face.This implementation The horizontal partition face of example is vertical with longitudinally split face, and longitudinally split face is located on vertical direction.
Specifically, the first wooden stick unit 13, the second wooden stick unit 14, the 3rd wooden stick unit 15 and the 4th wooden stick unit 16 exist Maximum gauge on data direction is equal.First wooden stick unit 13, the second wooden stick unit 14, the 3rd wooden stick unit 15 and the 4th wood Same one end end face of rod unit 16 is provided with handle II 17, and the first wooden stick unit 13, the second wooden stick unit 14, the 3rd wooden stick list Same one end end face of the wooden stick unit 16 of member 15 and the 4th is provided with graduated scale II.
The experimental provision that the simulation CRD method constructing tunnels of the present embodiment cause earth's surface to deform also is included with wooden stick unit one by one It is correspondingly arranged and is used to insert in tunnel hole as in tunnel hole in extraction from tunnel hole in wooden stick unit The interior wall pieces that wall liner is built, it is respectively that interior wall pieces 13a, interior wall pieces 14a, interior wall pieces 15a and interior wall pieces 16a, all interior wall pieces are total to With the shape and structure identical tubular structure formed with tunnel hole;The top of model casing 1 is additionally provided with earth's surface deformation measuring system.
The other structures of the present embodiment are same as Example 1, no longer tire out one by one and state.
The interior wall pieces of the present embodiment are used and are cut into tunnel hole shape and structure identical PE pipes;Model casing 1 uses Safety glass block is made.Specifically, the radial section of the tunnel hole of the present embodiment is circle.
The experimental provision that earth's surface deforms is caused using the simulation CRD method constructing tunnels of the present embodiment to simulate CRD methods tunnel Construction causes the experimental method that earth's surface deforms, and comprises the following steps:
1)The soil body 2 is successively inserted in model casing 1 and is tamped, and works as the soil body 2 and inserts the lower edge that height reaches tunnel hole When, wooden stick is placed on to the setting position of model casing, and continue to insert the soil body 2, until the soil body all complete by filling;
2)Earth's surface deformation measuring system is installed above model casing 1;
3)After the soil body 2 is stable, tunnel excavation process simulation is carried out, tunnel excavation analogy method is:According to CRD method constructing tunnels Process, the speed being calculated according to practice of construction process and the likelihood ratio, distance and time of stopping over extract wooden stick list successively Member, i.e., according to the parameter of setting by the first wooden stick unit 13, the second wooden stick unit 14, the 3rd wooden stick unit 15 and the 4th wooden stick list Member 16 is extracted successively;And the interior wall pieces being correspondingly arranged with each wooden stick unit are inserted into tunnel hole as lining cutting simultaneously; Until all wooden stick units are completely drawn out, all interior wall pieces are inserted into tunnel hole;And remember in real time in the process Record earth's surface deformation data;
4)Repeat step 1)To step 3), at different rates, distance and the time simulation CRD method constructing tunnel mistakes that stop over Journey, obtain different earth's surface deformation datas;
5)Following two relation curves are drawn according to obtained earth's surface deformation data:M- earth's surface deflection curve when a.;B. it is each The final deformation curve of cross section earth's surface;Rule Summary, effective reference data is provided for final CRD method constructing tunnels.
The simulation CRD method constructing tunnels of the present embodiment cause the experimental provision and experimental method of earth's surface deformation, can simulate The influence that CRD methods constructing tunnel deforms to earth's surface, the definite relation between different construction parameters and earth's surface deformation is obtained, for design Optimization with arrangement and method for construction provides foundation, and the potential safety hazard of existed building around job site and structures is played effectively in advance Survey acts on.
Embodiment described above is only to absolutely prove preferred embodiment that is of the invention and being lifted, protection model of the invention Enclose not limited to this.The equivalent substitute or conversion that those skilled in the art are made on the basis of the present invention, in the present invention Protection domain within.Protection scope of the present invention is defined by claims.

Claims (10)

1. a kind of simulation CRD method constructing tunnels cause the experimental provision that earth's surface deforms, it is characterised in that:It is described including model casing The soil body of the filling provided with compacting in model casing, the soil body is interior to be provided with tunnel hole, and the tunnel hole interpolation, which is equiped with, to be used for The wooden stick of the tunnel hole is supported, the wooden stick is provided with a longitudinally split face and at least one transverse direction point along its axial direction The wooden stick is divided into left side wooden stick and right side wooden stick two parts, at least one transverse direction by face, the longitudinally split face The left side wooden stick and right side wooden stick are divided at least two layers of wooden stick unit of setting stacked on top of one another by divisional plane respectively;Also include Correspond and set and for being inserted in the wooden stick unit from the tunnel hole in extraction with the wooden stick unit The interior wall pieces of the interior inwall lining cutting as the tunnel hole of the tunnel hole, all interior wall pieces collectively form and institute State the shape and structure identical tubular structure of tunnel hole;Earth's surface deformation measuring system is additionally provided with above the model casing.
2. simulation CRD method constructing tunnels according to claim 1 cause the experimental provision that earth's surface deforms, it is characterised in that: The horizontal partition face is arranged to two, and the left side wooden stick is divided into stack gradually from top to bottom and set by the horizontal partition face Upper left wooden stick unit, left wooden stick unit and the lower-left wooden stick unit put;The right side wooden stick is split by the horizontal partition face For be once stacked from top to bottom upper right wooden stick unit, it is right in wooden stick unit and bottom right wooden stick unit;Or
The horizontal partition face is arranged to one, and the left side wooden stick is divided into above first by the horizontal partition face Wooden stick unit and underlying second wooden stick unit, the right side wooden stick are divided into above by the horizontal partition face 3rd wooden stick unit and underlying 4th wooden stick unit.
3. simulation CRD method constructing tunnels according to claim 2 cause the experimental provision that earth's surface deforms, it is characterised in that: The horizontal partition face is arranged to two;The upper left wooden stick unit, left wooden stick unit, lower-left wooden stick unit, upper right wooden stick The maximum gauge of wooden stick unit and bottom right wooden stick unit in the vertical direction is equal in unit, the right side.
4. simulation CRD method constructing tunnels according to claim 3 cause the experimental provision that earth's surface deforms, it is characterised in that: Wooden stick unit and bottom right wood in the upper left wooden stick unit, left wooden stick unit, lower-left wooden stick unit, upper right wooden stick unit, the right side Handle I is respectively equipped with same one end end face of rod unit;And the upper left wooden stick unit, left wooden stick unit, lower-left wooden stick list In member, upper right wooden stick unit, the right side graduated scale I is equipped with wooden stick unit and bottom right wooden stick unit.
5. simulation CRD method constructing tunnels according to claim 2 cause the experimental provision that earth's surface deforms, it is characterised in that: The horizontal partition face is arranged to one, the first wooden stick unit, the second wooden stick unit, the 3rd wooden stick unit and the 4th wooden stick Maximum gauge of the unit on data direction is equal.
6. simulation CRD method constructing tunnels according to claim 5 cause the experimental provision that earth's surface deforms, it is characterised in that: The first wooden stick unit, the second wooden stick unit, same one end end face of the 3rd wooden stick unit and the 4th wooden stick unit are provided with hand Handle II, and the first wooden stick unit, the second wooden stick unit, the 3rd wooden stick unit and the 4th wooden stick unit same one end end face on Provided with graduated scale II.
7. simulation CRD method constructing tunnels according to claim 1 cause the experimental provision that earth's surface deforms, it is characterised in that: The interior wall pieces are used and are cut into the tunnel hole shape and structure identical PE pipes;The model casing uses safety glass Block is made.
8. the simulation CRD method constructing tunnels according to claim any one of 1-7 cause the experimental provision that earth's surface deforms, it is special Sign is:The earth's surface deformation measuring system includes being disposed on the installation crossbeam above the model casing, and the installation is horizontal Interval installation is provided with amesdial on beam, is provided with the survey with the amesdial in the soil body with amesdial one-to-one corresponding inserting Measure the measuring basis seat that head coordinates.
9. simulation CRD method constructing tunnels according to claim 8 cause the experimental provision that earth's surface deforms, it is characterised in that: The measuring basis seat is the hexagonal double-ended bolt being inserted into the soil body.
10. a kind of simulation CRD method constructing tunnels using as described in claim any one of 1-9 cause the experiment dress that earth's surface deforms Put to simulate the experimental method that CRD method constructing tunnels cause earth's surface to deform, it is characterised in that:Comprise the following steps:
1)The soil body is successively inserted in the model casing and is tamped, and works as the soil body and inserts the downside that height reaches the tunnel hole During edge, the wooden stick is placed on to the setting position of the model casing, and continues to insert the soil body, until the soil body all loads Complete;
2)The earth's surface deformation measuring system is installed above the model casing;
3)After soil stabilization, tunnel excavation process simulation is carried out, tunnel excavation analogy method is:According to CRD method constructing tunnels Process, the speed being calculated according to practice of construction process and the likelihood ratio, distance and time of stopping over extract the wood successively Rod unit, and the interior wall pieces being correspondingly arranged with each wooden stick unit are inserted into the tunnel hole as lining cutting simultaneously;Directly It is completely drawn out to all wooden stick units, all interior wall pieces are inserted into the tunnel hole;It is and real-time in the process Record earth's surface deformation data;
4)Repeat step 1)To step 3), at different rates, distance and the time simulation CRD method constructing tunnel mistakes that stop over Journey, obtain different earth's surface deformation datas;
5)Following two relation curves are drawn according to obtained earth's surface deformation data:M- earth's surface deflection curve when a.;B. it is each The final deformation curve of cross section earth's surface;Rule Summary, effective reference data is provided for final CRD method constructing tunnels.
CN201710643416.9A 2017-07-31 2017-07-31 Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation Pending CN107527546A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710643416.9A CN107527546A (en) 2017-07-31 2017-07-31 Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710643416.9A CN107527546A (en) 2017-07-31 2017-07-31 Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation

Publications (1)

Publication Number Publication Date
CN107527546A true CN107527546A (en) 2017-12-29

Family

ID=60680443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710643416.9A Pending CN107527546A (en) 2017-07-31 2017-07-31 Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation

Country Status (1)

Country Link
CN (1) CN107527546A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643925A (en) * 2018-05-17 2018-10-12 中铁十二局集团有限公司 Intersect the cycle construction method of the tunneling section under mid-board engineering method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003314188A (en) * 2002-04-23 2003-11-06 Ohbayashi Corp Method for predicting settlement in excavation of tunnel
CN101144384A (en) * 2007-11-01 2008-03-19 中铁二局股份有限公司 Tunnel engineering non-blasting weak disturbance excavating method
CN101900642A (en) * 2010-04-27 2010-12-01 西安理工大学 Physical model test device and method for ground fissure earth tunnel
CN102226399A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel three-bench cable-bracing excavation construction method
CN103000068A (en) * 2012-08-28 2013-03-27 浙江工业大学 Tunnel construction process simulating test method
CN103105310A (en) * 2013-01-22 2013-05-15 北京工业大学 Testing device and method of ground deformation caused by simulating metro shield tunnel construction
CN104713987A (en) * 2015-01-25 2015-06-17 北京工业大学 Model test apparatus for stimulating tunnel excavation process
CN207397573U (en) * 2017-07-31 2018-05-22 杭州市地下空间建设发展中心 Simulation CRD method constructing tunnels cause the experimental provision that earth's surface deforms

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003314188A (en) * 2002-04-23 2003-11-06 Ohbayashi Corp Method for predicting settlement in excavation of tunnel
CN101144384A (en) * 2007-11-01 2008-03-19 中铁二局股份有限公司 Tunnel engineering non-blasting weak disturbance excavating method
CN101900642A (en) * 2010-04-27 2010-12-01 西安理工大学 Physical model test device and method for ground fissure earth tunnel
CN102226399A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel three-bench cable-bracing excavation construction method
CN103000068A (en) * 2012-08-28 2013-03-27 浙江工业大学 Tunnel construction process simulating test method
CN103105310A (en) * 2013-01-22 2013-05-15 北京工业大学 Testing device and method of ground deformation caused by simulating metro shield tunnel construction
CN104713987A (en) * 2015-01-25 2015-06-17 北京工业大学 Model test apparatus for stimulating tunnel excavation process
CN207397573U (en) * 2017-07-31 2018-05-22 杭州市地下空间建设发展中心 Simulation CRD method constructing tunnels cause the experimental provision that earth's surface deforms

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643925A (en) * 2018-05-17 2018-10-12 中铁十二局集团有限公司 Intersect the cycle construction method of the tunneling section under mid-board engineering method

Similar Documents

Publication Publication Date Title
Liu et al. Analysis of ground movement due to metro station driven with enlarging shield tunnels under building and its parameter sensitivity analysis
CN104568706A (en) Fluid-solid coupled similar simulation experimental platform
CN103837360B (en) A kind of tunneltron canopy construction method excavation simulation device and implementation thereof
CN103940394B (en) The monitoring system and method for tunneltron canopy construction method excavation simulation device
CN203745218U (en) Simulation excavation apparatus of tunnel pipe roof construction method
CN106066920A (en) The overlapping tunnel shield-tunneling construction numerical analysis method to underpining Influence of Pile Foundation up and down
CN103866736B (en) The shake of a kind of ore deposit is on the physical simulation experiment system and method for coal mine underground reservoir impact
CN204359659U (en) A kind of fluid structurecoupling similarity simulation experiment platform
CN103061774A (en) Shield tunnel construction environment simulation unit
CN110967252A (en) Device for simulating influence of shield tunnel construction on existing tunnel and using method thereof
CN104196012A (en) Karst cave processing method based on BIM
CN108362856B (en) Model experiment device for simulating long-term ground settlement of urban high-density area
CN110362932B (en) Shallow subsurface tunnel pipe curtain structure calculation model that buries under complicated environmental condition
CN207397573U (en) Simulation CRD method constructing tunnels cause the experimental provision that earth's surface deforms
CN109826633A (en) Existing shield tunnel simulator and analogy method are worn under a kind of shield machine
CN107527546A (en) Simulation CRD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation
CN109087028A (en) Karst strata metro construction shield machine section risk evaluating method and system
CN207063983U (en) A kind of simulation CD method constructing tunnels cause the experimental provision that earth's surface deforms
CN108205055B (en) Shallow undercut tunnel stratum deformation test system that buries under operation highway
Katebi et al. The influence of surface buildings and ground stratification on lining loads applying the finite element method
CN107524446A (en) Simulation CD method constructing tunnels cause the experimental provision and experimental method of earth's surface deformation
CN112257154B (en) Transparent construction monitoring method and system for urban tunnel
Zhang et al. Numerical simulation on the stability of surrounding rock of horizontal rock strata in the tunnel
CN107024575A (en) Simulate experimental rig and test method that tunneling boring constructing tunnel triggers earth's surface deformation
Wei et al. Numerical simulation of effect of foundation pit excavation on underlain shield tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171229