CN107476618A - Stop well construction between a kind of underground deep space of big data intelligence management and control construction - Google Patents

Stop well construction between a kind of underground deep space of big data intelligence management and control construction Download PDF

Info

Publication number
CN107476618A
CN107476618A CN201710814780.7A CN201710814780A CN107476618A CN 107476618 A CN107476618 A CN 107476618A CN 201710814780 A CN201710814780 A CN 201710814780A CN 107476618 A CN107476618 A CN 107476618A
Authority
CN
China
Prior art keywords
well
construction
soil
pile
parking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710814780.7A
Other languages
Chinese (zh)
Inventor
杨小方
金胜华
张�杰
沈亦豪
周林光
严敬忠
江海波
许明星
陈希
金仲远
林彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou City Resources Development Engineering Co Ltd
Original Assignee
Wenzhou City Resources Development Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou City Resources Development Engineering Co Ltd filed Critical Wenzhou City Resources Development Engineering Co Ltd
Priority to CN201710814780.7A priority Critical patent/CN107476618A/en
Publication of CN107476618A publication Critical patent/CN107476618A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H6/00Buildings for parking cars, rolling-stock, aircraft, vessels or like vehicles, e.g. garages

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Soil Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Analytical Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Stop well construction between a kind of underground deep space of big data intelligence management and control construction, it is characterized in that, 5 10m set the infrared automatic warning device of surface subsidence at 34 mouthfuls of underground water intelligence control monitoring wells and 46 on the outside of parking well, on the outside of parking well, by cement mixing pile curtain is enclosed as sealing, by cast-in-situ bored pile or interlocking cast in situ pile as parking well exterior wall, it is segmented the armored concrete interior wall of formwork cast, shaft bottom is reinforced concrete floor and plain concrete back cover layer, well plane is square or rectangle, underliing in back cover layer has soil cement waterstop, the stressometer of soil lateral pressure is welded in the reinforcing bar cage bar of exterior wall, bury to gush on the soil body in bottom hole soil cement waterstop and gush prior-warning device on stress sensing piece or the shaft bottom soil body.Compared with prior art, all constructed with construction overall process according to soil pressure, the change of the shaft bottom waterstop soil body outside every underground water of each intelligent management and control instrument collection, well come management and control, construction equipment is simple, and speed of application is fast, low engineering cost, parking well it is water-tight the advantages that.

Description

Stop well construction between a kind of underground deep space of big data intelligence management and control construction
Technical field
The present invention relates to the well knot that stopped between building field, more particularly to a kind of underground deep space of big data intelligence management and control construction Structure.
Background technology
It is well known that city parking difficulty is a bottleneck of current city development, and an important project supported by commen people, especially Its parking difficulty in Deposits in Eastern Coastal China soft soil foundation city is even more serious, and its reason is that the cell that reform and opening-up is built in one's early years is more Long parking at a specified future date is not planned, is not provided with basement or only one layer of basement.Even if present roadside is all fully parked with private car, still can not Meet growing city parking requirement.
The content of the invention
Stop well construction between a kind of underground deep space of big data intelligence management and control construction of present invention offer, can be soft in China coast The city business district construction of soil base and use, can be deep by the various data that gather in real time, intelligent management and control underground in the construction time Space is stopped the construction of well, reaches that construction site is small, and sensing data is reliable, not only can constantly monitor shaft bottom soil layer not on gush, Well side wall soil body thrust size is constructed to instruct to control, and also simple with construction equipment, speed of application is fast, and engineering cost is low, no Leak, construct the advantages that safer.
Stop well construction between a kind of underground deep space of big data intelligence management and control construction of the present invention, it is characterised in that stops 5-10m distances set 3-4 mouths directly through 10cm, underground water intelligence control monitoring well of the depth more than well depth 10-20m, in parking well on the outside of well Outside 3-5m, if the infrared automatic warning device of surface subsidence at 4-6, on the outside of parking well, by stake footpath 0.5-1.2m, stake is long to be exceeded Parking well depth 1-10m single shaft or multiaxis cement mixing pile encloses curtain as sealing, and by stake footpath 0.7-1.2m, stake is long to exceed parking Well depth 8-30m cast-in-situ bored pile or interlocking cast in situ pile is segmented formwork and pours into a mould thick 0.6- from bottom to top as parking well exterior wall 1m armored concrete interior wall, shaft bottom are reinforced concrete floor and plain concrete back cover layer, and parking well plane is square or square Shape, underlie the soil cement waterstop that is made up of 5-10m solid cements mixing pile or high-pressure rotary jet grouting pile in back cover layer, filled in outer wall drill hole The stressometer of 5-30 monitoring soil lateral pressure is welded with the reinforcing bar cage bar of note stake or interlocking cast in situ pile, and is wired to Ground receiver, bury to gush on the 3-8 soil body in bottom hole soil cement waterstop and gush early warning on stress sensing piece or the shaft bottom soil body Device.
The construction procedure of parking well construction is as follows between a kind of underground deep space of big data intelligence management and control construction:
1. at the construction field (site), construct 2-4 mouth diameter 10cm, depth ratio parking well depth 10-20m groundwater monitoring well (6), A wherein hole is groundwater level monitoring well, and remaining its is underground bearing water monitoring well, and water level monitoring automatic forecasting device is set in well;
2. construction diameter 0.7-1.2m cast-in-situ bored pile or interlocking cast in situ pile, 5-30 are set on the main reinforcement of pile body longitudinal direction Monitor the stressometer of soil lateral pressure;
3. stop in the thick soil cement of the following soil layer cement mixing pile machine of wellhole back cover absolute altitude or churning ram machine construction 5-10m Water band, bury to gush on the 3-8 soil body in the soil cement of waterstop and gush prior-warning device on stress sensing piece or the shaft bottom soil body;
4. on the outside of cast-in-situ bored pile or interlocking cast in situ pile, with mixing pile machine construction 1.2m solid cement soil water-stop curtains;
5. the infrared automatic warning device of surface subsidence at 3-5m peripheral hardwares 4-6 outside parking well;
6. water filling digs a well, the interior soil body is to shaft bottom absolute altitude, then tremie concrete back cover layer.
7. after concrete sealing bottom layer intensity reaches, drawn water in pit shaft, armored concrete bottom is made by existing construction technology Plate.
5. being segmented formwork from bottom to top by current art pours 0.6-1m thickness armored concrete Inner walls, that is, complete a kind of big number According to the construction for the well construction that stopped between the underground deep space of intelligent management and control construction.
The present invention compared with prior art, can use in the city business district of China coast soft soil foundation, have construction complete Soil pressure outside every underground water that process is all collected according to each intelligent management and control instrument, well, the change of the shaft bottom waterstop soil body come Management and control construct, accomplish shaft bottom soil layer not on gush, required construction site is small, and construction equipment is simple, and speed of application is fast, construction costs It is low, parking well it is water-tight the advantages that.
Brief description of the drawings
Fig. 1 is diagrammatic cross-section of the embodiment of the present invention.
Drawing explanation:1 miscellaneous fill, 2 soil cement water-stop curtains, the borehole wall in 3,4 pit shafts, the outer borehole wall of 5 cast-in-situ bored piles, 6 ground Lower water inspection well, the infrared automatic warning device of 7 surface subsidence, 8 muds, 9 argillic horizons, 10 gravel layers, 11 soil cement sealings Band, 12 concrete sealing bottom layers, 13 reinforced concrete floors.
Embodiment
According to Fig. 1, a kind of embodiment construction procedure for the well construction that stopped between underground deep space of big data intelligence management and control construction It is as follows:
1. at the construction field (site), construct 4 mouthfuls of diameter 10cm, depth ratio parking well depth 15m groundwater monitoring well (6), wherein One hole is groundwater level monitoring well, and remaining its is underground bearing water monitoring well, and water level monitoring automatic forecasting device is set in well;
2. construction diameter 1m cast-in-situ bored pile (5), 20 lateral soil pressures of monitoring are set on the main reinforcement of pile body longitudinal direction Stressometer;
3. in the wellhole back cover absolute altitude following soil layer soil cement waterstop (11) of cement churning ram machine construction 8m thickness, stop Buried in the soil cement of water band (11) on 4 soil bodys and gush prior-warning device;
4. on the outside of cast-in-situ bored pile (5), with mixing pile machine construction 1.2m solid cement soil water-stop curtains (2);
5. set the infrared automatic warning device of surface subsidence at 4 (7) at 5m outside parking well;
6. water filling digs a well, the interior soil body is to shaft bottom absolute altitude, then tremie concrete back cover layer (12).
4. after concrete sealing bottom layer (12) intensity reaches, the water in pit shaft (4) is taken out, reinforcing bar is made by existing construction technology Concrete floor (13).
5. being segmented formwork from bottom to top by current art pours 0.6m thickness armored concrete Inner walls (3) to ground, that is, complete The construction of parking well construction between a kind of underground deep space of big data intelligence management and control construction.

Claims (1)

1. stop well construction between a kind of underground deep space of big data intelligence management and control construction, it is characterised in that the 5- on the outside of parking well 10m distances set 3-4 mouths and directly exceed well depth 10-20m underground water intelligence control monitoring well through 10cm, depth, the 3-5m on the outside of parking well, If the infrared automatic warning device of surface subsidence at 4-6, on the outside of parking well, by stake footpath 0.5-1.2m, stake is long to exceed parking well depth The single shaft or multiaxis cement mixing pile for spending 1-10m enclose curtain as sealing, and by stake footpath 0.7-1.2m, stake is long to exceed parking well depth 8- 30m cast-in-situ bored pile or interlocking cast in situ pile is segmented the reinforcing bar that formwork pours into a mould thick 0.6-1m from bottom to top as parking well exterior wall Concrete inner wall, shaft bottom are reinforced concrete floor and plain concrete back cover layer, and parking well plane is square or rectangle, in back cover Layer underlies the soil cement waterstop being made up of 5-10m solid cements mixing pile or high-pressure rotary jet grouting pile, in outer wall drill hole pouring pile or stings The stressometer that 5-30 monitoring soil lateral pressure is welded with the reinforcing bar cage bar of bored concrete pile is closed, and is wired to ground receiver Machine, bury to gush on the 3-8 soil body in bottom hole soil cement waterstop and gush prior-warning device on stress sensing piece or the shaft bottom soil body.
CN201710814780.7A 2017-08-29 2017-08-29 Stop well construction between a kind of underground deep space of big data intelligence management and control construction Withdrawn CN107476618A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710814780.7A CN107476618A (en) 2017-08-29 2017-08-29 Stop well construction between a kind of underground deep space of big data intelligence management and control construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710814780.7A CN107476618A (en) 2017-08-29 2017-08-29 Stop well construction between a kind of underground deep space of big data intelligence management and control construction

Publications (1)

Publication Number Publication Date
CN107476618A true CN107476618A (en) 2017-12-15

Family

ID=60585096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710814780.7A Withdrawn CN107476618A (en) 2017-08-29 2017-08-29 Stop well construction between a kind of underground deep space of big data intelligence management and control construction

Country Status (1)

Country Link
CN (1) CN107476618A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109191792A (en) * 2018-08-15 2019-01-11 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of long-range wired control construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109191792A (en) * 2018-08-15 2019-01-11 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of long-range wired control construction

Similar Documents

Publication Publication Date Title
CN102454167B (en) The construction method of especially big & deep open caisson
CN104612143B (en) Composite pile constructed in drilled hole structure under a kind of solution cavity/soil cave geological conditions
CN105239563A (en) Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method
CN104099943B (en) Diaphram wall and discarded underground civil defense engineering intersection processing method
CN103741714A (en) Construction method for full cover-excavation reverse method of underground engineering
CN105464134B (en) Multi-layer underground space is along inverse combining construction method and supporting construction under existing facility
CN102162253B (en) Precipitation construction method employing pipe embedded in deep foundation pits
CN106049196B (en) Flexible pile combines ballastless track roadbed construction method with stake raft with section
CN105714769A (en) Construction method for anti-sliding cast-in-place pile
CN202194149U (en) Water-proof curtain
CN101196004A (en) Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
CN107829441A (en) It is a kind of do not influence surrounding enviroment draw hole caisson structure and its construction method
CN107190769A (en) Stop well construction between a kind of underground deep space of soft soil foundation
CN110453699B (en) Drainage slide-resistant pile structure of 'rice' -shaped pile core and construction method thereof
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
CN104074197B (en) The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN207659986U (en) A kind of building or structures foundation stabilization underpin pier
CN204356780U (en) A kind of prefabricated abnormity stake on an empty stomach for deep foundation pit supporting structure
CN104264684B (en) A kind of prefabricated abnormity stake and construction method thereof on an empty stomach for deep foundation pit supporting structure
CN219773012U (en) Underground water control structure of foundation pit close to subway group
CN107476618A (en) Stop well construction between a kind of underground deep space of big data intelligence management and control construction
CN205116159U (en) Supporting rig dry process pore -forming bored concrete pile that digs soon of back slip casting
CN101603311B (en) Jet grouting pile construction method adopting heavy hammer-tamping compaction soil preformed hole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Yang Xiaofang

Inventor after: Xu Mingxing

Inventor after: Chen Xi

Inventor after: Jin Zhongyuan

Inventor after: Lin Bin

Inventor after: Xu Menghe

Inventor after: Huang Jiapo

Inventor after: Jin Shenghua

Inventor after: Zhang Jie

Inventor after: Shen Yihao

Inventor after: Zhou Linguang

Inventor after: Yan Jingzhong

Inventor after: Jiang Haibo

Inventor before: Yang Xiaofang

Inventor before: Jin Zhongyuan

Inventor before: Lin Bin

Inventor before: Jin Shenghua

Inventor before: Zhang Jie

Inventor before: Shen Yihao

Inventor before: Zhou Linguang

Inventor before: Yan Jingzhong

Inventor before: Jiang Haibo

Inventor before: Xu Mingxing

Inventor before: Chen Xi

WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20171215