CN109191792A - Stop well construction between a kind of underground deep space of long-range wired control construction - Google Patents

Stop well construction between a kind of underground deep space of long-range wired control construction Download PDF

Info

Publication number
CN109191792A
CN109191792A CN201810965135.XA CN201810965135A CN109191792A CN 109191792 A CN109191792 A CN 109191792A CN 201810965135 A CN201810965135 A CN 201810965135A CN 109191792 A CN109191792 A CN 109191792A
Authority
CN
China
Prior art keywords
construction
pile
long
wired
support pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810965135.XA
Other languages
Chinese (zh)
Inventor
杨小方
徐孟鹤
黄加坡
张�杰
沈亦豪
周林光
严敬忠
江海波
许明星
陈希
金仲远
王斌
林彬
叶瑶瑶
谷舒
金苗苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou City Resources Development Engineering Co Ltd
Original Assignee
Wenzhou City Resources Development Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou City Resources Development Engineering Co Ltd filed Critical Wenzhou City Resources Development Engineering Co Ltd
Priority to CN201810965135.XA priority Critical patent/CN109191792A/en
Publication of CN109191792A publication Critical patent/CN109191792A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/02Alarms for ensuring the safety of persons
    • G08B21/10Alarms for ensuring the safety of persons responsive to calamitous events, e.g. tornados or earthquakes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/18Status alarms
    • G08B21/182Level alarms, e.g. alarms responsive to variables exceeding a threshold
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C19/00Electric signal transmission systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

It is more than that the cement mixing pile of cutting depth 5-10m does sealing and encloses curtain that parking well construction all has as existing Soft Deep Foundation Pit technology between a kind of underground deep space of long-range wired control construction, the cast-in-situ bored pile of cutting depth 8-30m is had more than as support pile, there is armored concrete interior wall on the inside of support pile, it is characterized in that, the silicon fiml strain gauge transducer that outer soil body lateral stress is cheated in test is welded on the outside of the support pile on reinforcing bar, and it is wired to the outer data collection processor of well, then the computer terminal of distant place is connected to by conducting wire.Compared with prior art, have can resistance to shear of soil variation on the outside of wired monitoring civil engineering structure at a distance in real time avoid parking well construction from the major accidents such as collapsing once stress is more than warning data early warning immediately.

Description

Stop well construction between a kind of underground deep space of long-range wired control construction
Technical field
The present invention relates to the well knots that stops between building field more particularly to a kind of underground deep space of long-range wired control construction Structure.
Background technique
It is well known that city parking difficulty is the bottleneck of current city development, especially in Deposits in Eastern Coastal China soft soil foundation city The parking difficulty in city is even more serious, in addition, many accidents occurred in various regions architecture Foundation Pit Engineering since reform and opening-up, has studied carefully its original Because being to cheat outer soil pressure variation because of non-real-time dynamic monitoring.One field boundary heavy rain, level of ground water rise, and cheat the mechanical property hair of the outer soil body It is raw to change, it finds and takes measures not in time, directly contribute the generation of foundation pit collapse accident.
Summary of the invention
The present invention provides the well construction that stops between the underground deep space of long-range wired control construction a kind of, can be in China coast weak soil The municipal construction of ground and use, can be by acquiring the lateral stress data of the soil body on the outside of hole in the construction time in real time, and passes through number Telecommunication point is converted into according to processor, and wired to be sent to terminal computer, monitoring personnel downloads the monitoring software on computer at a distance, just Hole outside soil stress change curve can be observed in real time, and guiding construction guarantees sidewall safety.
Parking well construction and existing Soft Deep Foundation Pit skill between a kind of underground deep space of long-range wired control construction of the present invention It is more than that the cement mixing pile of cutting depth 5-10m does sealing and encloses curtain that art is the same, which all to be had, has more than the brill of cutting depth 8-30m Hole pouring pile has armored concrete interior wall as support pile on the inside of support pile, which is characterized in that on the outside of the support pile on reinforcing bar It is welded with test and cheats the silicon fiml strain gauge transducer of outer soil body lateral stress, and be wired to the outer data collection processor of well, The computer terminal of distant place is connected to by conducting wire again.Computer downloads the detection system software, just will appear hole on computer screen Outer resistance to shear of soil change curve, peak value exceed setting target, that is, early warning.
It can resistance to shear of soil becomes on the outside of wired monitoring civil engineering structure at a distance in real time compared with prior art, the present invention having Change, once stress is more than warning data early warning immediately, avoids the major accidents such as parking well construction collapsing.
Detailed description of the invention
Fig. 1 is parking well construction diagrammatic cross-section of the embodiment of the present invention.
Fig. 2 is silicon fiml strain gauge transducer structural schematic diagram of the embodiment of the present invention, a top view, b sectional view.
Drawing explanation: 1 ground concrete layer, 2 soil cement water-stop curtains, 3 capping beams, 4 support piles, 5 mine pits, 6 reinforcing bars are mixed Solidifying soil interior wall, 7 data collection processors, 8 muds, 9 argillic horizons, 10 gravel layers, 11 soil cements reinforce waterstop, and 12 elements are mixed Solidifying grave bottom, 13 reinforced concrete floors, 14 fixed metal weld tabs, 15 inductive reactances, 16 diaphragm sides, 17 varistors, 18 Thin silicon diaphragm, 19 titanium dioxide silicon wafers, 20 vacuum chambers, 21 borosilicic acid slides.
Specific embodiment
According to Fig. 1, parking well construction embodiment construction procedure is as follows between a kind of underground deep space of long-range wired control construction:
1. showing field boundary in underground parking well construction, support pile (4) of the first construction drill bored concrete pile as parking well construction is being cheated At longitudinal main reinforcement lower end of well (5) surrounding pile body, middle part and the upward 3-6m in lower end, equipped with the 30-50 being distributed at a certain distance The silicon fiml strain gauge transducer of a induction soil body lateral pressure, and sensor conductor is involved from the top of support pile (4) and is connected to data Acquisition Processor (7), then data collection processor (7) is accessed into distant place computer terminal with conducting wire;
2. in mine pit (5) back cover absolute altitude following soil layer cement mixing pile machine or the cement of whirl spraying ram machine construction 5-10m thickness Soil reinforces waterstop (11);
3. constructing 1.2m solid cement soil water-stop curtain (2) with mixing pile machine on the outside of support pile (4);
4. in support pile (4) top pouring armored concrete capping beam (3);
5. grabbing the soil body that cone is dug in capping beam (3) to water filling in mine pit (5), and with punching, data collection processor (7) is connect Upper power supply, monitoring system start monitoring and cheat outer resistance to shear of soil variation, and the elastic sensing element of silicon fiml sheet type sensor is solid for periphery The thin silicon diaphragm (18) of deposit category weld tabs (14).It radial strain and is tangentially answered when thin silicon diaphragm (18) stress deformation, at center Change reaches positive maximum value, and edge radial strain reaches negative maximum value, tangential strain zero.Separately strained with two Titanium dioxide silicon wafer (19) is attached to respectively at positive and negative maximum strain, is connected into the half-bridge circuit of adjacent bridge arm to obtain larger sensitivity, It is sealed in vacuum chamber (20) outer cover borosilicic acid slide (21).Strain data is processed into electric signal by data collection processor (7), Terminal computer server is sent to by conducting wire, as long as monitoring personnel downloads the monitoring system software on host computer, is just reached Resistance to shear of soil change curve avoids cheating once the super early warning line of curve, takes immediate steps on the outside of distant place wired monitoring mine pit (5) Wall cave-in accident.Soil is taken to get shaft bottom absolute altitude, then underwater pouring plain concrete back cover layer (12).
6. drawing water in mine pit (5), after concrete sealing bottom layer (12) intensity reaches by current art construction reinforced bar concrete Bottom plate (13);
7. being segmented the armored concrete interior wall (6) that formwork pours 0.8-1m thickness from bottom to top by current art, that is, complete this The construction of invention.

Claims (1)

1. stop well construction between a kind of underground deep space of long-range wired control construction, which is characterized in that the reinforcing bar on the outside of support pile On be welded with test and cheat the silicon fiml strain gauge transducer of outer soil body lateral stress, and be wired to well data acquisition process outside Device, then it is connected to by conducting wire the computer terminal of distant place.
CN201810965135.XA 2018-08-15 2018-08-15 Stop well construction between a kind of underground deep space of long-range wired control construction Pending CN109191792A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810965135.XA CN109191792A (en) 2018-08-15 2018-08-15 Stop well construction between a kind of underground deep space of long-range wired control construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810965135.XA CN109191792A (en) 2018-08-15 2018-08-15 Stop well construction between a kind of underground deep space of long-range wired control construction

Publications (1)

Publication Number Publication Date
CN109191792A true CN109191792A (en) 2019-01-11

Family

ID=64919646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810965135.XA Pending CN109191792A (en) 2018-08-15 2018-08-15 Stop well construction between a kind of underground deep space of long-range wired control construction

Country Status (1)

Country Link
CN (1) CN109191792A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593624A (en) * 2019-09-27 2019-12-20 张率 Radiation type vertical shaft underground parking lot and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457533A (en) * 2007-12-13 2009-06-17 上海隧道工程股份有限公司 Foundation ditch digging real-time detection method
CN204728302U (en) * 2015-07-07 2015-10-28 山西省交通科学研究院 A kind of base pit stability prior-warning device
CN107190769A (en) * 2016-12-08 2017-09-22 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of soft soil foundation
CN107476618A (en) * 2017-08-29 2017-12-15 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of big data intelligence management and control construction
CN208766812U (en) * 2018-08-15 2019-04-19 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of long-range wired control construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457533A (en) * 2007-12-13 2009-06-17 上海隧道工程股份有限公司 Foundation ditch digging real-time detection method
CN204728302U (en) * 2015-07-07 2015-10-28 山西省交通科学研究院 A kind of base pit stability prior-warning device
CN107190769A (en) * 2016-12-08 2017-09-22 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of soft soil foundation
CN107476618A (en) * 2017-08-29 2017-12-15 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of big data intelligence management and control construction
CN208766812U (en) * 2018-08-15 2019-04-19 温州市城市资源开发工程有限公司 Stop well construction between a kind of underground deep space of long-range wired control construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593624A (en) * 2019-09-27 2019-12-20 张率 Radiation type vertical shaft underground parking lot and construction method thereof

Similar Documents

Publication Publication Date Title
CN105239563A (en) Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN107524138A (en) A kind of ultra-deep foundation pit construction method of underground continuous wall
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN208766812U (en) Stop well construction between a kind of underground deep space of long-range wired control construction
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN103266600A (en) Occlusion pile of full reinforcement pile and construction method thereof
CN110258658A (en) The leakage anticipation of diaphram wall and the construction method of processing
CN208721064U (en) Real-time monitoring system across existing subway tunnel on a kind of city tunnel
CN108442370A (en) The broken pile connector processing method of prestressed concrete pipe pile
CN109191792A (en) Stop well construction between a kind of underground deep space of long-range wired control construction
CN105180787A (en) High-pressure grouting lifting deformation monitor and installation method thereof
CN114033388A (en) Vertical shaft construction method for underground tunnel top pipe of water-rich silt layer
CN107190769A (en) Stop well construction between a kind of underground deep space of soft soil foundation
CN108205055A (en) Ground Deformation for Shallow Tunnel pilot system under a kind of operation highway
CN102505685A (en) Tubular pile defect processing method
CN107780407A (en) Secondary precipitation union dynamic consolidation soft base processing method
CN107675700A (en) The construction method of diaphram wall
CN109138006A (en) A kind of underground parking well construction with vibrating string type sensor and unidirectional RF chip
CN209538248U (en) A kind of underground parking well construction with vibrating string type sensor and unidirectional RF chip
CN210658410U (en) Inverted wall hanging surrounding well structure
CN202170513U (en) No undergoing force slab prestressed high strength concrete pipe pile base
CN206974504U (en) Deep footing groove enclosing structure real time on-line monitoring system
CN206971243U (en) Draw hole caisson structure in a kind of wall for not influenceing surrounding enviroment
CN206607584U (en) A kind of PHC piles

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Chen Xi

Document name: Notice of First Examination Opinion

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: WENZHOU CITY RESOURCES DEVELOPMENT ENGINEERING Co.,Ltd. Person in charge of patents

Document name: Deemed withdrawal notice