CN107471406A - Wallboard preparation method with distribution box - Google Patents
Wallboard preparation method with distribution box Download PDFInfo
- Publication number
- CN107471406A CN107471406A CN201710808526.6A CN201710808526A CN107471406A CN 107471406 A CN107471406 A CN 107471406A CN 201710808526 A CN201710808526 A CN 201710808526A CN 107471406 A CN107471406 A CN 107471406A
- Authority
- CN
- China
- Prior art keywords
- distribution box
- spool
- wallboard
- panel
- mould
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/14—Producing shaped prefabricated articles from the material by simple casting, the material being neither forcibly fed nor positively compacted
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to a kind of wallboard preparation method with distribution box, by per side, increase 100mm determines the width of prefabricated panel on distribution box width dimensions;Prefabricated panel height is determined according to story height and slab thickness;Wallboard thickness is with both sides masonry panel with thick;According to the Joining Technology of spool, spool attended operation space is reserved among panel tops and bottom, both ends reserve supporting leg and are easily installed;The outside size of wallboard is made with punching block, the circular hole of reinforcing bar and spool is drilled out on mould;Distribution box is placed in mould, spool, two layers of bar-mat reinforcement of inside/outside bed are installed;Pour lightweight concrete material.Concrete strength removes mould after meeting requirement, and site operation can be transported after reaching installation strength.The present invention have distribution box wallboard preparation method, avoid it is secondary shave chisel, closure, improve structure safety, reduction labor strength, save the engineering time, reduce construction cost, improve efficiency of construction, improve construction quality.
Description
Technical field
The present invention relates to a kind of construction techniques, is to be related to a kind of wallboard making side with distribution box specifically
Method.
Background technology
In building engineering construction, civil buildings are all every there is provided every layer in substantial amounts of distribution box, particularly Housing Project
There is distribution box at family, indoor each socket, illumination or broadband networks, wired because distribution box is the total control switch of power supply
The pipelines such as TV are all drawn from heavy current box or weak current box, cause distribution box position pipeline to concentrate, or even heavy current box and light current
Case is arranged on the upper-lower position of same position wall.
In general construction method is:The hole of electronic box is reserved during building wall, after having built by laying bricks or stones, with professional grooving tool
Shave the position for digging out spool.Professional spool is blocked after installing with cement mortar or concrete.It is reserved because spool is intensive
Electronic box dimension of opening is all bigger, the easily quality problems such as cracking, hollowing, and being reduced because spool shaves chisel during closure
Thickness of wall body, Secondary Disturbance is carried out to wall, has weakened wall resistance to overturning, have impact on structure safety.This construction party
Method complex procedures, the cycle is long, and the work post constructed is more, shaves that the building waste dug out is more, and construction cost is big.
The content of the invention
For above-mentioned deficiency of the prior art, the present invention provides a kind of easy construction, improves construction quality, reduces construction
The wallboard preparation method with distribution box of cost.
The technical solution used in the present invention is:
A kind of wallboard preparation method with distribution box, comprises the following steps:
By per side, increase 100mm determines the width of prefabricated panel on distribution box width dimensions;Distribution box is close to wall edge side
100 millimeters of increase.
Prefabricated panel height is determined according to story height and slab thickness;
Wallboard thickness is with both sides masonry panel with thick;
According to the Joining Technology of spool, spool attended operation space is reserved among panel tops and bottom, both ends reserve supporting leg just
In installation;
The outside size of wallboard is made with punching block, the circular hole of reinforcing bar and spool is drilled out on mould;
Distribution box is placed in mould, spool, two layers of bar-mat reinforcement of inside/outside bed are installed;
Pour lightweight concrete material.Concrete strength meets to remove mould after requiring, can transported after reaching installation strength
Site operation.
Spool stretches out wall plate member 20mm, is easy to joint to connect.
In order to ensure that prefabricated panel is reliably connected with surrounding wall, set in wallboard side and stretch out connection reinforcing bar.
The beneficial effect of the present invention compared with the prior art:
The present invention have distribution box wallboard preparation method, avoid it is secondary shave chisel, closure, improve structure safety, reduction work
People's labor intensity, saves the engineering time, reduces construction cost, improves efficiency of construction, improves construction quality.
Brief description of the drawings
Fig. 1 is the main structure diagram of the prefabricated panel for the wallboard preparation method that the present invention has distribution box;
Fig. 2 is Fig. 1 1-1 cross section structure diagrams.
Critical piece symbol description in accompanying drawing:
In figure:
1st, lightweight concrete 2, distribution box
3rd, spool 4, supporting leg
5th, reinforcing bar.
Embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Accompanying drawing 1-2 is understood, a kind of wallboard preparation method with distribution box, is comprised the following steps:
By per side, increase 100mm determines the width of prefabricated panel on the width dimensions of distribution box 2;When there is multiple distribution boxs 2 in wallboard
When, increase 100mm as panel width apart from every side using two distribution boxs 2 of outermost.
Prefabricated panel height is determined according to story height and slab thickness;
Wallboard thickness is with both sides masonry panel with thick;
According to the Joining Technology of spool 3, spool attended operation space is reserved among panel tops and bottom, both ends reserve supporting leg 4
It is easily installed;
The outside size of wallboard is made with punching block, the circular hole of reinforcing bar 5 and spool 3 is drilled out on mould;
Distribution box 2 is placed in mould, spool 3, two layers of bar-mat reinforcement of inside/outside bed are installed;
Pour lightweight concrete material 1.Concrete strength meets to remove mould after requiring, can transported after reaching installation strength
Site operation.
Spool 3 stretches out wall plate member 20mm, is easy to joint to connect.
In order to ensure that prefabricated panel is reliably connected with surrounding wall, set in wallboard side and stretch out connection reinforcing bar 5.
The present invention have distribution box wallboard preparation method, avoid it is secondary shave chisel, closure, improve structure safety, drop
Low labor strength, saves the engineering time, reduces construction cost, improves efficiency of construction, improves construction quality.
The above described is only a preferred embodiment of the present invention, not the structure of the present invention is made any formal
Limitation.Any simple modification, equivalent change and modification that every technical spirit according to the present invention is made to above example,
Belong in the range of technical scheme.
Claims (3)
1. a kind of wallboard preparation method with distribution box, it is characterised in that comprise the following steps:
By per side, increase 100mm determines the width of prefabricated panel on distribution box width dimensions;
Prefabricated panel height is determined according to story height and slab thickness;
Wallboard thickness is with both sides masonry panel with thick;
According to the Joining Technology of spool, spool attended operation space is reserved among panel tops and bottom, both ends reserve supporting leg just
In installation;
The outside size of wallboard is made with punching block, the circular hole of reinforcing bar and spool is drilled out on mould;
Distribution box is placed in mould, spool, two layers of bar-mat reinforcement of inside/outside bed are installed;
Pour lightweight concrete material.
2. there is the wallboard preparation method of distribution box according to claim 1, it is characterised in that:Spool stretches out wall plate member
20mm, it is easy to joint to connect.
3. there is the wallboard preparation method of distribution box according to claim 1, it is characterised in that:In order to ensure prefabricated panel with
Surrounding wall is reliably connected, and is set in wallboard side and is stretched out connection reinforcing bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710808526.6A CN107471406A (en) | 2017-09-09 | 2017-09-09 | Wallboard preparation method with distribution box |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710808526.6A CN107471406A (en) | 2017-09-09 | 2017-09-09 | Wallboard preparation method with distribution box |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107471406A true CN107471406A (en) | 2017-12-15 |
Family
ID=60584780
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710808526.6A Pending CN107471406A (en) | 2017-09-09 | 2017-09-09 | Wallboard preparation method with distribution box |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107471406A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114658142A (en) * | 2022-03-03 | 2022-06-24 | 中建一局集团建设发展有限公司 | Ceramsite concrete wallboard mounting structure and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10131283A (en) * | 1996-11-01 | 1998-05-19 | Sekisui Chem Co Ltd | Main entrance porch with storage box for delivered article and building |
CN203049909U (en) * | 2012-08-03 | 2013-07-10 | 北京奇迪惠民科技投资有限公司 | Modularized building wallboard for realizing pre-embedding of hydropower pipelines |
CN205944955U (en) * | 2016-08-17 | 2017-02-08 | 中天建设集团有限公司天津分公司 | Whole prefabricated component of line box |
CN106499046A (en) * | 2016-11-17 | 2017-03-15 | 西咸新区矩阵实业有限公司 | Architectural Equipment pipeline integral structure and design and construction process based on inverted ladder type slot type combined wall board |
-
2017
- 2017-09-09 CN CN201710808526.6A patent/CN107471406A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10131283A (en) * | 1996-11-01 | 1998-05-19 | Sekisui Chem Co Ltd | Main entrance porch with storage box for delivered article and building |
CN203049909U (en) * | 2012-08-03 | 2013-07-10 | 北京奇迪惠民科技投资有限公司 | Modularized building wallboard for realizing pre-embedding of hydropower pipelines |
CN205944955U (en) * | 2016-08-17 | 2017-02-08 | 中天建设集团有限公司天津分公司 | Whole prefabricated component of line box |
CN106499046A (en) * | 2016-11-17 | 2017-03-15 | 西咸新区矩阵实业有限公司 | Architectural Equipment pipeline integral structure and design and construction process based on inverted ladder type slot type combined wall board |
Non-Patent Citations (1)
Title |
---|
张波等: "《装配式混凝土结构工程》", 30 September 2016 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114658142A (en) * | 2022-03-03 | 2022-06-24 | 中建一局集团建设发展有限公司 | Ceramsite concrete wallboard mounting structure and construction method thereof |
CN114658142B (en) * | 2022-03-03 | 2024-01-30 | 中建一局集团建设发展有限公司 | Ceramsite concrete wallboard mounting structure and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101265724B (en) | Run-through steel plate type square steel tube concrete column and axle i-beam node | |
CN108589986B (en) | Assembled composite wall structure based on bolt connection and construction method thereof | |
CN104895049A (en) | Prefabrication-cast-in-situ mixed underground continuous wall and construction method thereof | |
CN103924710B (en) | Low layer assembled combined wall house Plate Welding node structure | |
CN104805912A (en) | Connecting node of prefabricated air conditioner panel and prefabricated shear wall | |
CN106836469B (en) | Assembly type building | |
CN107558633A (en) | It is provided with the installation method of the prefabricated panel with distribution box | |
CN103938785A (en) | Precast concrete member | |
CN108286341B (en) | Anti-cracking steel mesh template structure at joint of different substrate materials and construction method using same | |
CN105089177B (en) | Prefabrication type steel truss concrete shear wall and manufacture method | |
CN102787690A (en) | Partition board with light fillers or empty holes in internal part and method | |
CN109667376B (en) | Novel superposed floor system suitable for H-shaped steel beam of steel structure and construction method thereof | |
CN105275145B (en) | A kind of assembled multifunction composite wall panel | |
CN107471406A (en) | Wallboard preparation method with distribution box | |
CN107546635A (en) | The construction method of pre-buried electrical power wiring box on a kind of shear wall | |
WO2008149165A2 (en) | Prefabricated concrete buildings | |
CN205224391U (en) | Multi -functional composite wall panel of assembled | |
CN210482733U (en) | Prefabricated wallboard with embedded sleeve | |
CN204940527U (en) | With the precast member for reinforcing bar concrete that indeterminate node connects | |
CN104878863B (en) | Construction method of light composite floor | |
CN206220351U (en) | A kind of assembled grid wallboard | |
CN206090623U (en) | Prefabricated inspection shaft of construction efficient | |
CN204780859U (en) | Prefabrication - cast -in -place mixed underground continuous wall | |
CN212078228U (en) | Prefabricated wallboard structure of grooving is exempted from to on-spot pipeline | |
CN106703015A (en) | Steel plate concrete prefabricated part, permanent-temporary combined underground enclosure system and construction methods |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171215 |
|
RJ01 | Rejection of invention patent application after publication |