CN107460948A - The double-deck RC plate-type transfer floors and construction method of superstructure are poured after a kind of - Google Patents

The double-deck RC plate-type transfer floors and construction method of superstructure are poured after a kind of Download PDF

Info

Publication number
CN107460948A
CN107460948A CN201710702881.5A CN201710702881A CN107460948A CN 107460948 A CN107460948 A CN 107460948A CN 201710702881 A CN201710702881 A CN 201710702881A CN 107460948 A CN107460948 A CN 107460948A
Authority
CN
China
Prior art keywords
layer
change
over panels
plate
superstructure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710702881.5A
Other languages
Chinese (zh)
Other versions
CN107460948B (en
Inventor
黄华
田冰
吴涛
刘伯权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201710702881.5A priority Critical patent/CN107460948B/en
Publication of CN107460948A publication Critical patent/CN107460948A/en
Application granted granted Critical
Publication of CN107460948B publication Critical patent/CN107460948B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention provides the double-deck RC plate-type transfer floors and construction method for pouring superstructure after a kind of, including first layer RC change-over panels and second layer RC change-over panels, support to form hollow layer by frame column between first layer RC change-over panels and second layer RC change-over panels;The thickness of described first layer RC change-over panels is less than the thickness of second layer RC change-over panels, and concealed beam is provided with second layer RC change-over panels;Shear wall, energy dissipating shear wall and frictiona damping mechanism are poured after being provided with described hollow layer.Due to being configured with a certain amount of reinforcing bar in the plate above and below conversion layer, interlayer sets energy-dissipating device, both alleviates the quality of conversion laminate, makes it have enough bearing capacities again to meet top after-pouring building structure.The special component arrangement of interlayer, strengthens structural integrity, enhances structural seismic performance so that the neighbouring layer of conversion layer will not turn into antidetonation weak floor.

Description

The double-deck RC plate-type transfer floors and construction method of superstructure are poured after a kind of
Technical field
The invention belongs to building engineering field, the conversion layer structure being related in building structure, and in particular to watered after a kind of The double-deck RC plate-type transfer floors and construction method of portion's structure.
Background technology
It is complicated in build, conversion layer is set in the diversified building of functional requirement, is that structural engineer is upper and lower in order to realize Rotating fields type is changed, the post net of upper and lower layer, axis change or simultaneously transformational structure form and structure axis arrangement and take Effective ways.Since 20th century five, the sixties propose conversion layer structure concept, the analysis means and design of conversion layer structure Technology is more and more diversified, also increasingly tends to be ripe so that conversion layer structure obtained in modern high-rise building it is more next More it is widely applied.Several conversion layer structures commonly used in current engineering include transfer beam, truss conversion, Box-transfer storey, thickness Plate conversion etc..Above conversion layer structure adapts to different buildings and its functional requirement.Currently with the fast development of economic construction, deposit In a class formation putting into effect in advance due to bottom, and superstructure then needs later stage planning construction, therefore conversion layer just needs The complicated building of the superstructure bodily form is adapted to, so as to meet the needs of practical structures.
Slab transformational structure is as shown in figure 1, the structure is the form for being easiest to meet building function requirement in transformational structure. When upper and lower layer post net axis misalignment is more, or top shear wall structure arrangement very irregular and infrastructural requirements arrangement huge pillar Net and when being difficult to support direct with beam, is a kind of preferable structure type using transfer slab.It is using the advantages of transfer slab Upper and lower structures flexible arrangement, it is not necessary to consistency from top to bottom;Shortcoming be from great (up to thousands of tons of), cost is high, construction when formwork, Reinforcing bar colligation is difficult, and is related to the series of problems such as the construction of mass concrete.In design, due to the power transmission road of thick transfer slab Footpath is not apparent, and local stiffness is excessive, and stress is complicated, and the method for simplifying temporarily without maturation can use, so that Structure Calculation is very multiple It is miscellaneous;Due to design shearing resistance and Punching Shear needs, the thickness of change-over panel is very big, this cause change-over panel quality and rigidity mutation, The reaction increase of structure, the neighbouring layer of conversion layer more turn into weak floor during geological process, are unfavorable for structural seismic.The opposing party Face, due to the increase conducted oneself with dignity with geological process, the load of bottom vertical structure substantially increases, and design difficulty is with increase.Research Show, the internal force of thick transfer slab and displacement are extremely uneven, and maximin can differ tens times, and need to pass through improvement can adopt With.
The content of the invention
In view of the deficienciess of the prior art, it is an object of the present invention to the double-deck RC (reinforcing bars of superstructure are poured after a kind of Concrete, abbreviation RC) plate-type transfer floor and construction method, solution overcome existing thick-plate-type transformational structure from it is great, cost is high The shortcomings that, the globality of after-pouring superstructure is enhanced, the flexibility for after-pouring superstructure arrangement provides condition.
In order to solve the above-mentioned technical problem, the present invention, which adopts the following technical scheme that, is achieved:
The double-deck RC plate-type transfer floors of superstructure, including first layer RC change-over panels and second layer RC conversions are poured after a kind of Plate, support to form hollow layer by frame column between first layer RC change-over panels and second layer RC change-over panels;
Described first layer RC change-over panels are located at framework column bottom and are connected with substructure, and second layer RC change-over panels are located at It is connected at the top of frame column and with superstructure;
The thickness of described first layer RC change-over panels is less than the thickness of second layer RC change-over panels, is set in second layer RC change-over panels It is equipped with concealed beam;
After-pouring shear wall, energy dissipating shear wall and frictiona damping mechanism are provided with described hollow layer.
The present invention also has following distinguishing feature:
Described frictiona damping mechanism includes frcition damper, and the corner of frcition damper is connected to the one of support bar End, the other end of support bar are connected with connecting seat respectively, and a pair of connecting seats are arranged on the upper surface of first layer RC change-over panels, another The coupling beam for being used for connecting the after-pouring shear wall in conversion layer is arranged on to connecting seat, coupling beam is located at second layer RC change-over panels Lower surface, four connecting seats are symmetrically laid using frcition damper as symmetrical centre.
The thickness of described first layer RC change-over panels is 300~400mm, and the thickness of described second layer RC change-over panels is 600~800mm.
Described energy dissipating shear wall is laid between the frame column in hollow layer at conversion layer corner, energy dissipating shearing Wall is connected with concealed beam, energy dissipating shear wall L-shaped, hollow or I-shaped laying on each angle of conversion layer.
Described frictiona damping mechanism is laid in hollow layer to be located at behind conversion layer edge and poured between shear wall.
The present invention give it is a kind of after pour superstructure double-deck RC plate-type transfer floors construction method, this method include with Lower step:
Step 1, according to building requirement, carry out overall structure load calculating;
Step 2, conversion layer structure Design of Bearing Capacity:According to overall structure load, substructure is designed, according to The load of superstructure, the first layer RC change-over panels of conversion layer and the thickness and arrangement of reinforcement of second layer RC change-over panels are determined, it is determined that disappearing Can shear wall, the quantity and position of frictiona damping mechanism;
Step 3, the construction of substructure:Conventional construction is carried out to substructure;
Step 4, the construction of first layer RC change-over panels:First layer RC change-over panel scaffold buildings, formwork supporting plate, steel in colligation plate Muscle, then carry out pouring and conserving for concrete;
Step 5, the construction of hollow layer center trestle:The reinforcing bar of colligation frame column, formwork supporting plate, casting concrete simultaneously conserve;
Step 6, the construction of second layer RC change-over panels:Second layer RC change-over panel scaffold buildings, formwork supporting plate, colligation second Reinforcing bar and concealed beam reinforcing bar inside layer RC change-over panels, the pre-embedded steel slab for connecting energy dissipating shear wall is provided with concealed beam, then Carry out pouring and conserving for concrete;
Step 7, after-pouring shear wall is poured in hollow layer, between a pair of after-pouring shear walls at grade Coupling beam is set, then energy dissipating shear wall and frcition damper mechanism are installed;
Step 8, superstructure design:According to using function, superstructure is designed;
Step 9, the construction of superstructure:Conventional construction is carried out to superstructure.
The thickness of pre-embedded steel slab in described concealed beam is 12~25mm, every the pre-buried one piece of pre-buried steel of 200~600mm Plate, junction steel plate is embedded in energy dissipating shear wall by peg at the top of energy dissipating shear wall, the thickness of junction steel plate for 15~ 25mm。
The energy dissipating shear wall and frame column and concealed beam fix be by frictional high-strength bolts, backing plate by junction steel plate with Pre-embedded steel slab connects.
Described connecting seat includes the bottom plate and top plate that weld together, and the thickness of bottom plate is 10~20mm, the thickness of top plate Spend for 8~15mm.
The present invention compared with prior art, has the following technical effect that:
(I) due to being configured with a certain amount of reinforcing bar in the plate above and below conversion layer, interlayer sets energy-dissipating device, both alleviates and turns The quality of laminate is changed, makes it have enough bearing capacities again to meet top after-pouring building structure.
(II) the special component arrangement of interlayer, strengthens structural integrity, enhances structural seismic performance so that conversion layer Neighbouring layer will not turn into antidetonation weak floor.
(III) changing the gross thickness of interlaminar board reduces, and greatly reduces cost, also make it that structure integral rigidity is uniform, has Beneficial to the needs of antidetonation.
(IV) engineering of later stage planning construction is needed to provide a kind of reliable conversion layer structure form for superstructure, so as to Meet the needs of practical structures.
Brief description of the drawings
Fig. 1 is the structural representation of existing thick-plate-type conversion layer.
Fig. 2 is the overall structure diagram of conversion layer.
Fig. 3 is the positive structure diagram of conversion layer.
Fig. 4 is the internal structure schematic diagram of conversion layer.
Fig. 5 is the structural representation of energy dissipating shear wall.
Fig. 6 is the assembly relation schematic diagram between energy dissipating shear wall and concealed beam.
Fig. 7 is the structural representation of frictiona damping mechanism.
Fig. 8 is the horizontal layout schematic diagram of substructure.
Fig. 9 is the interlayer horizontal layout schematic diagram of conversion layer.
Figure 10 is the horizontal layout schematic diagram of superstructure.
Figure 11 is the finite element instance model for emulating example.
Figure 12 is the Stress Map of the first layer RC plates of conversion layer.
Figure 13 is the Stress Map of the second layer RC plates of conversion layer.
Figure 14 is floor maximum displacement under X-direction geological process.
Figure 15 is story drift under X-direction geological process.
Figure 16 is floor maximum displacement under Y-direction geological process.
Figure 17 is story drift under Y-direction geological process.
The implication of each label is in figure:1- first layer RC change-over panels, 2- second layer RC change-over panels, 3- frame columns, in 4- Dead level, 5- substructures, 6- superstructures, 7- conversion layers, 8- concealed beams, 9- energy dissipating shear walls, 10- frictiona damping mechanisms, after 11- Pour shear wall, 12- coupling beams, 13- pre-embedded steel slabs, 14- pegs, 15- junction steel plates, 16- frictional high-strength bolts, 17- backing plates;
(10-1)-frcition damper, (10-2)-support bar, (10-3)-connecting seat, (10-4)-connecting seat;
WithIt is axis, 1., 2., 3., 4., 5. and is 6. also axis.
Explanation is further explained in detail to the particular content of the present invention with reference to embodiments.
Embodiment
Specific embodiment of the invention given below is, it is necessary to which explanation is that the invention is not limited in implement in detail below Example, all equivalents done on the basis of technical scheme each fall within protection scope of the present invention.
Embodiment:
Defer to above-mentioned technical proposal, as shown in Figures 2 to 7, the present embodiment provide it is a kind of after pour the double-deck RC of superstructure Plate-type transfer floor, including first layer RC change-over panels 1 and second layer RC change-over panels 2, first layer RC change-over panels 1 and second layer RC conversions Hollow layer 4 is formed by the support of frame column 3 between plate 2;
Described first layer RC change-over panels 1 are located at the bottom of frame column 3 and are connected with substructure 5, second layer RC change-over panels 2 It is connected positioned at the top of frame column 3 and with superstructure 6;
The thickness of described first layer RC change-over panels 1 is less than the thickness of second layer RC change-over panels 2, second layer RC change-over panels 2 Inside it is provided with concealed beam 8;
After-pouring shear wall 11, energy dissipating shear wall 9 and frictiona damping mechanism 10 are provided with described hollow layer 4.
Frictiona damping mechanism 10 includes frcition damper 10-1, and frcition damper 10-1 corner is connected to support bar 10-2 one end, the support bar 10-2 other end are connected with connecting seat 10-3,10-4 respectively, and a pair of connecting seat 10-3 are arranged on the The upper surface of one layer of RC change-over panel 1, another pair connecting seat 10-4, which is arranged on, to be used to connect the after-pouring shear wall 11 in conversion layer 7 Coupling beam 12 on, coupling beam 12 is located at the lower surface of second layer RC change-over panels 2, and four connecting seats 10-3,10-4 are with frcition damper 10-1 is that symmetrical centre is symmetrically laid.
The thickness of first layer RC change-over panels 1 is 300~400mm, and reinforcement scheme is:The inside reinforcing bar of first layer RC change-over panels 1 Two layers of arrangement, two layers of 250~350mm of vertical interval, cage bar can be arranged diagonally above and below point, also can be parallel to two Hold side arrangement.
The thickness of second layer RC change-over panels 2 is 600~800mm, and the deck-molding of concealed beam 8 is equal to thickness of slab, cast-in-place with plate;Arrangement of reinforcement side Case is:Second layer RC change-over panels 2 inside reinforcing bar point two layers of arrangement up and down, two layers of 550~750mm of vertical interval, cage bar parallel to Two side-struts arrange that concealed beam reinforcing bar divides stirrup and vertical muscle, its stirrup and plate muscle vertical interval 25mm~50mm.
Energy dissipating shear wall 9 is laid between the frame column 3 in hollow layer 4 at 7 four jiaos of conversion layer, energy dissipating shear wall 9 It is connected with concealed beam 8, energy dissipating shear wall 9 L-shaped, hollow or I-shaped laying on each angle of conversion layer 7, makes structure as far as possible Mass centre overlapped with center of rigidity.Conventional energy dissipating shear wall known to the use of energy dissipating shear wall 9.
Frictiona damping mechanism 10 is laid in hollow layer 4 to be located at behind the edge of conversion layer 7 and poured between shear wall 11.Friction Conventional friction damper known to damper 10-1 uses.
The construction method that the double-deck RC plate-type transfer floors of superstructure are poured after the present embodiment comprises the following steps:
Step 1, according to building requirement, carry out overall structure load calculating;
Step 2, conversion layer structure Design of Bearing Capacity:According to overall structure load, substructure 5 is designed, according to The load of superstructure 6, the first layer RC change-over panels 1 of conversion layer 7 and the thickness and arrangement of reinforcement of second layer RC change-over panels 2 are determined, really Determine energy dissipating shear wall 9, the quantity of frictiona damping mechanism 10 and position;
Step 3, the construction of substructure:Conventional construction is carried out to substructure 5;
Step 4, the construction of first layer RC change-over panels:The scaffold building of first layer RC change-over panels 1, formwork supporting plate, steel in colligation plate Muscle, then carry out pouring and conserving for concrete;
Step 5, the construction of hollow layer center trestle:The reinforcing bar of colligation frame column 3, formwork supporting plate, casting concrete simultaneously conserve;
Step 6, the construction of second layer RC change-over panels:The scaffold building of second layer RC change-over panels 2, formwork supporting plate, colligation second The inside reinforcing bar of layer RC change-over panels 2 and concealed beam reinforcing bar, the pre-embedded steel slab 13 for connecting energy dissipating shear wall 9 is provided with concealed beam 8, Then pouring and conserving for concrete is carried out;
Step 7, after-pouring shear wall 11 is poured in hollow layer 4, a pair of after-pouring shear walls 11 at grade Between coupling beam 12 is set, then energy dissipating shear wall 9 and frcition damper mechanism 10 are installed;
Step 8, superstructure design:According to using function, superstructure is designed;
Step 9, the construction of superstructure:Conventional construction is carried out to superstructure 6.
In work progress it should be noted that energy dissipating shear wall 9 and frictiona damping mechanism 10 need in a pre-installation it is supporting Embedment Construction, it is specific as follows:
The thickness of pre-embedded steel slab 13 in concealed beam 8 is 12~25mm, every the pre-buried one piece of pre-embedded steel slab 13 of 200~600mm, Junction steel plate 15 is embedded in energy dissipating shear wall 9 by the top of energy dissipating shear wall 9 by peg 14, and the thickness of junction steel plate 15 is 15 ~25mm.
It is that will be connected steel by frictional high-strength bolts 16, backing plate 17 that energy dissipating shear wall 9 is fixed with frame column 3 and concealed beam 8 Plate 15 connects with pre-embedded steel slab 13.
Connecting seat 10-3 includes the bottom plate and top plate that weld together, and the thickness of bottom plate is 10~20mm, the thickness of top plate For 8~15mm.
Emulation testing example:
The technical scheme of embodiment is deferred to, this emulation example provides a kind of specific application scenarios, and the analysis of this emulation example is real Example is RC high-rise building of 20 layers of the building with double-deck RC change-over panels, and substructure is building for commercial use, and superstructure is Standardized house.The construction bottom uses large bay frame shear wall structure, and conversion layer is arranged on third layer, the 4th layer to 20 Layer is shear wall structure.This engineering design service life is 50 years, and seismic fortification intensity is 8 degree, and basic seismic design accelerates Angle value is 0.2g, and classification of design earthquake is first group, and safe class is two level.Site category is II classes, and Characteristic Site Period is 0.35s, structural plan layout drawing is as shown in Fig. 8 to Figure 10, and dimensional units are mm in figure.
Substructure per 4.2m a height of layer by layer, the floor height of conversion layer be 2.85m, superstructure it is often a height of layer by layer 2.85m.In conversion layer, the thickness of first layer RC change-over panels is 300mm, and the thickness of second layer RC change-over panels is 700mm.
Pre-embedded steel slab thickness in concealed beam is 15mm, is separated by pre-buried one piece of 500mm, and junction steel plate thickness is 15mm.Energy dissipating Shear wall is four, L-shaped, is laid between the frame column at conversion layer corner.Coupling beam anchoring steel plate slab be 10mm, welding steel thickness are 10mm.Frictiona damping mechanism is six, is symmetrically laid in pour behind conversion layer edge and cuts Between power wall.
Finite element modelling is carried out to the emulation example using ANSYS softwares, obtained finite element instance model such as Figure 10 institutes Show.The Stress Map of obtained first layer RC change-over panels is as shown in figure 12, and the Stress Map of second layer RC plates is as shown in figure 13, from It can be seen from the figure that, the maximum stress of first layer RC change-over panels is 6.05MPa, and the maximum stress of second layer RC plates is 3.22MPa, Stress is all far below the cubic compressive strength standard value of C30 concrete.
Senditivity experriments:If the double-deck RC plate-type transfer floors in the emulation example are replaced by Thick Plate Transfer Story, change-over panel Thick 1200mm, acquired results with using double-deck RC plate-type transfer floors acquired results to such as shown in Figure 14 to Figure 17, from figure As can be seen that the X with slab conversion layer structure is compared in the maximum displacement under the X-direction geological process with double-deck RC conversion harden structures Maximum displacement under the geological process of direction reduces 26.6%;Under Y-direction geological process with double-deck RC conversion harden structures most Big displacement reduces 40.6% compared to the maximum displacement under the Y-direction geological process of tape thickness plank frame.Two kinds of band different switchings The maximum story drift of the structure of layer is respectively less than elastic displacement angle between floors limit value 1/1000;X with double-deck RC conversion harden structures Levels maximum displacement angle under the geological process of direction is than compared to upper and lower under the X-direction geological process with slab conversion layer structure Layer maximum displacement angle ratio reduces 10.0%;Levels dominant bit under Y-direction geological process with double-deck RC conversion harden structures Angle is moved than reducing 14.8% compared to the levels maximum displacement angle under the Y-direction geological process with slab conversion layer structure.
X, Y-direction for building two major axes orientations, to model apply horizontal direction earthquake when, just choose this two Individual direction, emulate in figure corresponding to example and marked X, Y-direction.
In summary, quality of the present invention due to both alleviating conversion laminate there is provided double-deck RC plates, makes it have foot again Enough bearing capacities meet top after-pouring building structure;By setting special component, structural seismic performance is strengthened so that turn Antidetonation weak floor will not be turned into by changing the neighbouring layer of layer;Changing the gross thickness of interlaminar board reduces, and greatly reduces cost, also makes It is uniform to obtain structure integral rigidity, is advantageous to the needs of antidetonation.

Claims (9)

1. the double-deck RC plate-type transfer floors of superstructure are poured after a kind of, it is characterised in that including first layer RC change-over panels (1) and Two layers of RC change-over panels (2), supported and formed by frame column (3) between first layer RC change-over panels (1) and second layer RC change-over panels (2) Hollow layer (4);
Described first layer RC change-over panels (1) are located at frame column (3) bottom and are connected with substructure (5), second layer RC conversions Plate (2) is located at the top of frame column (3) and is connected with superstructure (6);
The thickness of described first layer RC change-over panels (1) is less than the thickness of second layer RC change-over panels (2), second layer RC change-over panels (2) concealed beam (8) is provided with;
After-pouring shear wall (11), energy dissipating shear wall (9) and frictiona damping mechanism (10) are provided with described hollow layer (4).
2. the double-deck RC plate-type transfer floors of superstructure are poured after as claimed in claim 1, it is characterised in that described friction resistance Buddhist nun mechanism (10) includes frcition damper (10-1), and the corner of frcition damper (10-1) is connected to support bar (10-2) One end, the other end of support bar (10-2) are connected with connecting seat (10-3,10-4) respectively, and a pair of connecting seats (10-3) are arranged on the The upper surface of one layer of RC change-over panel (1), another pair connecting seat (10-4) are arranged on the after-pouring for being used for connecting in conversion layer (7) and cut In the coupling beam (12) of power wall (11), coupling beam (12) is located at the lower surface of second layer RC change-over panels (2), four connecting seats (10-3, It is 10-4) that symmetrical centre is symmetrically laid with frcition damper (10-1).
3. the double-deck RC plate-type transfer floors of superstructure are poured after as claimed in claim 1, it is characterised in that described first layer The thickness of RC change-over panels (1) is 300~400mm, and the thickness of described second layer RC change-over panels (2) is 600~800mm.
4. the double-deck RC plate-type transfer floors of superstructure are poured after as claimed in claim 1, it is characterised in that described energy dissipating is cut Power wall (9) is laid between the frame column (3) in hollow layer (4) at conversion layer (7) corner, energy dissipating shear wall (9) with it is dark Beam (8) is connected, energy dissipating shear wall (9) L-shaped, hollow or I-shaped laying on each angle of conversion layer (7).
5. the double-deck RC plate-type transfer floors of superstructure are poured after as claimed in claim 2, it is characterised in that described friction resistance Buddhist nun mechanism (10) is laid in hollow layer (4) to be located at behind conversion layer (7) edge and poured between shear wall (11).
6. the construction method of the double-deck RC plate-type transfer floors of superstructure is poured after a kind of, it is characterised in that this method includes following Step:
Step 1, according to building requirement, carry out overall structure load calculating;
Step 2, conversion layer structure Design of Bearing Capacity:According to overall structure load, substructure (5) is designed, according to upper The load of portion's structure (6), determine the first layer RC change-over panels (1) of conversion layer (7) and the thickness of second layer RC change-over panels (2) and match somebody with somebody Muscle, determine energy dissipating shear wall (9), the quantity and position of frictiona damping mechanism (10);
Step 3, the construction of substructure:Conventional construction is carried out to substructure (5);
Step 4, the construction of first layer RC change-over panels:First layer RC change-over panels (1) scaffold building, formwork supporting plate, steel in colligation plate Muscle, then carry out pouring and conserving for concrete;
Step 5, the construction of hollow layer center trestle:The reinforcing bar of colligation frame column (3), formwork supporting plate, casting concrete simultaneously conserve;
Step 6, the construction of second layer RC change-over panels:Second layer RC change-over panels (2) scaffold building, formwork supporting plate, the colligation second layer The internal reinforcing bar of RC change-over panels (2) and concealed beam reinforcing bar, the pre-buried steel for connecting energy dissipating shear wall (9) is provided with concealed beam (8) Plate (13), then carry out pouring and conserving for concrete;
Step 7, after-pouring shear wall (11) is poured in hollow layer (4), a pair of after-pouring shear walls at grade (11) coupling beam (12) is set between, energy dissipating shear wall (9) and frcition damper mechanism (10) are then installed;
Step 8, superstructure design:According to using function, superstructure is designed;
Step 9, the construction of superstructure:Conventional construction is carried out to superstructure (6).
7. construction method as claimed in claim 6, it is characterised in that the thickness of the pre-embedded steel slab (13) in described concealed beam (8) Spend for 12~25mm, pass through peg (14) at the top of the pre-buried one piece of pre-embedded steel slab (13) of 200~600mm, energy dissipating shear wall (9) Junction steel plate (15) is embedded in energy dissipating shear wall (9), the thickness of junction steel plate (15) is 15~25mm.
8. construction method as claimed in claim 7, it is characterised in that the energy dissipating shear wall (9) and frame column (3) and concealed beam (8) fixation is to be connected junction steel plate (15) and pre-embedded steel slab (13) by frictional high-strength bolts (16), backing plate (17).
9. construction method as claimed in claim 8, it is characterised in that described connecting seat (10-3) includes what is welded together Bottom plate and top plate, the thickness of bottom plate is 10~20mm, and the thickness of top plate is 8~15mm.
CN201710702881.5A 2017-08-16 2017-08-16 The double-deck RC plate-type transfer floor and construction method of superstructure are poured after a kind of Expired - Fee Related CN107460948B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710702881.5A CN107460948B (en) 2017-08-16 2017-08-16 The double-deck RC plate-type transfer floor and construction method of superstructure are poured after a kind of

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710702881.5A CN107460948B (en) 2017-08-16 2017-08-16 The double-deck RC plate-type transfer floor and construction method of superstructure are poured after a kind of

Publications (2)

Publication Number Publication Date
CN107460948A true CN107460948A (en) 2017-12-12
CN107460948B CN107460948B (en) 2019-09-13

Family

ID=60549997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710702881.5A Expired - Fee Related CN107460948B (en) 2017-08-16 2017-08-16 The double-deck RC plate-type transfer floor and construction method of superstructure are poured after a kind of

Country Status (1)

Country Link
CN (1) CN107460948B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952223A (en) * 2018-09-21 2018-12-07 郑州成功财经学院 A variety of house type residential housings with thick-plate-type conversion layer
CN112227715A (en) * 2020-10-21 2021-01-15 贵州建工集团第一建筑工程有限责任公司 Construction method of section steel concrete conversion truss shear wall
CN113494148A (en) * 2021-09-08 2021-10-12 中国船舶重工集团国际工程有限公司 Large-span conversion truss-shear wall structure and construction process
CN113502909A (en) * 2021-07-26 2021-10-15 中国建筑第二工程局有限公司 Intelligent building energy-saving house and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201292572Y (en) * 2008-11-19 2009-08-19 江苏省江建集团有限公司 Post-cast strip aerial transfer layer
CN102383503A (en) * 2011-08-26 2012-03-21 中国江西国际经济技术合作公司 Truss imitating type damper structure transfer layer
CN102619331A (en) * 2011-03-08 2012-08-01 青光绪 Once molding construction method of beam-type conversion layer of high-rise building by steel pipe supporting and laminated pouring
CN103132625A (en) * 2011-11-30 2013-06-05 青建集团股份公司 Damping control device based on magnetostrictive friction
US20150047285A1 (en) * 2013-08-15 2015-02-19 Building Materials Investment Corporation Shingle with transition device for impact resistance
CN204753813U (en) * 2015-06-30 2015-11-11 中冶建工集团有限公司 Steel construction conversion truss

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201292572Y (en) * 2008-11-19 2009-08-19 江苏省江建集团有限公司 Post-cast strip aerial transfer layer
CN102619331A (en) * 2011-03-08 2012-08-01 青光绪 Once molding construction method of beam-type conversion layer of high-rise building by steel pipe supporting and laminated pouring
CN102383503A (en) * 2011-08-26 2012-03-21 中国江西国际经济技术合作公司 Truss imitating type damper structure transfer layer
CN103132625A (en) * 2011-11-30 2013-06-05 青建集团股份公司 Damping control device based on magnetostrictive friction
US20150047285A1 (en) * 2013-08-15 2015-02-19 Building Materials Investment Corporation Shingle with transition device for impact resistance
CN204753813U (en) * 2015-06-30 2015-11-11 中冶建工集团有限公司 Steel construction conversion truss

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952223A (en) * 2018-09-21 2018-12-07 郑州成功财经学院 A variety of house type residential housings with thick-plate-type conversion layer
CN108952223B (en) * 2018-09-21 2024-06-07 郑州成功财经学院 Multi-family type residential building with thick plate type conversion layer
CN112227715A (en) * 2020-10-21 2021-01-15 贵州建工集团第一建筑工程有限责任公司 Construction method of section steel concrete conversion truss shear wall
CN113502909A (en) * 2021-07-26 2021-10-15 中国建筑第二工程局有限公司 Intelligent building energy-saving house and construction method
CN113494148A (en) * 2021-09-08 2021-10-12 中国船舶重工集团国际工程有限公司 Large-span conversion truss-shear wall structure and construction process
CN113494148B (en) * 2021-09-08 2021-12-07 中国船舶重工集团国际工程有限公司 Large-span conversion truss-shear wall structure and construction process

Also Published As

Publication number Publication date
CN107460948B (en) 2019-09-13

Similar Documents

Publication Publication Date Title
CN107090925B (en) Reinforced precast reinforced concrete shear wall, structural system and construction method thereof
CN107460948B (en) The double-deck RC plate-type transfer floor and construction method of superstructure are poured after a kind of
CN105863257B (en) Plate-beam separated high formwork connecting support building method for multi-story and high-rise reinforced concrete structure
CN104818772B (en) A kind of large span long cantilever conjoined structure and construction technology
CN110409624B (en) Reverse calculation and construction method for large equipment installation and main body structure
CN212534174U (en) Raft foundation steel bar supporting tool
CN106522419A (en) Column-supported-by-beam transfer beam with steel plate reinforced concrete shear walls arranged in adjacent spans
CN111851825A (en) Fabricated form-removal-free prefabricated steel bar truss floor and construction method thereof
CN110130558A (en) Square formed fences system and construction method made of steel secondary beam and truss arranged crosswise
CN109424072A (en) The connecting node and construction method of spacer bar concrete column on a kind of girder steel
CN212897482U (en) Construction platform for high-rise building overhanging structural layer
CN206233656U (en) Steel frame mill building structure
CN203603073U (en) Reinforced concrete lattice type composite platform beam of elevated station
CN210002942U (en) transformation structure of old building brick column
CN2721748Y (en) Semi-shutup pressing assemlbed floor of steel plate
CN2714671Y (en) Closed pressing steel plate combined floor board
CN201671063U (en) Movable steel base for construction precast beams and standard knot thereof
CN111424948A (en) Construction method and construction platform for cantilever structure layer of high-rise building
JP7370626B2 (en) Side span support structure for a continuous T-girder viaduct spanning the existing railway line
CN102392417A (en) Dual-cantilever bearing support structure for large steel pipe and installation method
KR20200132159A (en) Slim transfer mat structure and construction method with reverse drop panel
CN206428854U (en) It is a kind of adjacent across the beam support conversion beam for setting steel plate concrete shear wall
CN104831928A (en) Construction method for high-altitude large-span concrete connected structure formwork supporting steel platform
CN212802185U (en) Prefabricated steel bar truss floor of assembled form removal-free
CN112609966B (en) Construction method for constructing super-thick concrete top plate by utilizing simple latticed column laminated slab system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190913