CN204753813U - Steel construction conversion truss - Google Patents
Steel construction conversion truss Download PDFInfo
- Publication number
- CN204753813U CN204753813U CN201520457957.9U CN201520457957U CN204753813U CN 204753813 U CN204753813 U CN 204753813U CN 201520457957 U CN201520457957 U CN 201520457957U CN 204753813 U CN204753813 U CN 204753813U
- Authority
- CN
- China
- Prior art keywords
- chord
- upper chord
- column
- lower chord
- truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
本实用新型公开了一种钢结构转换桁架,在两立柱之间水平设有将两立柱连接的上弦杆和下弦杆,上弦杆两端与两立柱顶部连接;在上弦杆和下弦杆之间设有支撑用斜腹杆,斜腹杆以倾斜方式将上弦杆、下弦杆连接;所述立柱为焊接H型钢,外表面布设有栓钉,在立柱和栓钉形成的钢骨外包裹有混凝土以形成钢筋混凝土柱;所述上弦杆和下弦杆为焊接H型钢,外表面均布设有栓钉,上弦杆和栓钉形成的钢骨以及下弦杆和栓钉形成的钢骨外均包裹混凝土,以形成钢筋混凝土梁。本桁架为平面桁架,隐藏于建筑墙体中,既美观又经济而且施工方便。本桁架在平面内有较大刚度,平面外上、下弦杆处均有楼板相连,可确保转换桁架整体受力稳定。
The utility model discloses a steel structure conversion truss. An upper chord and a lower chord connecting the two columns are arranged horizontally between two upright columns, and the two ends of the upper chord are connected with the tops of the two upright columns; There are diagonal rods for support, and the diagonal rods connect the upper chord and the lower chord in an inclined manner; the column is welded H-shaped steel, and the outer surface is equipped with studs, and the steel frame formed by the column and the studs is wrapped with concrete to Reinforced concrete columns are formed; the upper chord and the lower chord are welded H-shaped steel, and studs are evenly distributed on the outer surface, and the steel skeleton formed by the upper chord and the studs and the steel skeleton formed by the lower chord and the studs are all wrapped with concrete, so that form reinforced concrete beams. The truss is a plane truss, hidden in the building wall, which is beautiful, economical and convenient for construction. The truss has a relatively large rigidity in the plane, and the upper and lower chords outside the plane are connected by floors, which can ensure the overall stress stability of the conversion truss.
Description
技术领域 technical field
本实用新型涉及一种钢结构桁架,具体涉及一种钢结构转换桁架,属于建筑技术领域。 The utility model relates to a steel structure truss, in particular to a steel structure transfer truss, which belongs to the technical field of construction.
背景技术 Background technique
目前,工程设计中,经常会遇到建筑底层抽柱形成大跨度空间的建筑功能要求。传统方法是将该位置及以上各层框架柱均取消,采用正交或斜交井字梁楼盖,但这种结构布置方式,会造成整体结构在局部出现单跨框架,对结构整体抗震不利。正交或斜交井字梁楼盖梁高和梁板自重均较大,房间建筑净高减小且经济性差。 At present, in engineering design, it is often encountered that the architectural function requirements of drawing columns at the bottom of the building to form a large-span space. The traditional method is to cancel the frame columns at this location and above each floor, and adopt orthogonal or oblique well-shaped beam floors, but this structural arrangement will cause single-span frames to appear locally in the overall structure, which is not conducive to the overall seismic resistance of the structure. . Orthogonal or oblique well-shaped beam floor girder height and beam slab self-weight are large, the net building height of the room is reduced and the economy is poor.
发明内容 Contents of the invention
针对现有技术存在的上述不足,本实用新型的目的是提供一种钢结构转换桁架,本转换桁架既能取消该位置一层框架柱,又能承托两层以上各层该位置的框架柱。 In view of the above-mentioned deficiencies in the prior art, the purpose of this utility model is to provide a steel structure conversion truss, which can not only cancel the frame column of the first floor at this position, but also support the frame columns at this position of two or more floors .
为实现上述目的,本实用新型的技术方案是这样来实现的: In order to achieve the above object, the technical solution of the utility model is achieved in this way:
一种钢结构转换桁架,包括两立柱,在两立柱之间水平设有将两立柱连接的上弦杆和下弦杆,上弦杆两端与两立柱顶部连接,上弦杆和下弦杆之间的垂直距离为所在楼层层高;在上弦杆和下弦杆之间设有支撑用斜腹杆,斜腹杆以倾斜方式将上弦杆、下弦杆连接;所述立柱为焊接H型钢,外表面布设有栓钉,在立柱和栓钉形成的钢骨外包裹有混凝土以形成钢筋混凝土柱;所述上弦杆和下弦杆为焊接H型钢,外表面均布设有栓钉,上弦杆和栓钉形成的钢骨以及下弦杆和栓钉形成的钢骨外均包裹混凝土,以形成钢筋混凝土梁。 A steel structure conversion truss, including two uprights, between the two uprights there is an upper chord and a lower chord connecting the two uprights horizontally, the two ends of the upper chord are connected with the tops of the two uprights, the vertical distance between the upper chord and the lower chord is the height of the floor where it is located; between the upper chord and the lower chord, there is a diagonal rod for support, and the diagonal rod connects the upper chord and the lower chord in an inclined manner; the column is welded H-shaped steel, and the outer surface is equipped with studs , the steel frame formed by the column and the studs is wrapped with concrete to form a reinforced concrete column; the upper chord and the lower chord are welded H-shaped steel, and the outer surface is evenly provided with studs, the steel frame formed by the upper chord and the studs and The steel frame formed by the bottom chords and studs is covered with concrete to form reinforced concrete beams.
所述立柱与上弦杆和下弦杆连接处设有立柱牛腿,上弦杆和下弦杆两端分别通过螺栓与立柱牛腿连接,以实现与立柱的连接。 A column corbel is provided at the connection between the column and the upper chord and the lower chord, and the two ends of the upper chord and the lower chord are respectively connected to the column corbel by bolts to realize the connection with the column.
所述斜腹杆为焊接H型钢,且所有斜腹杆以“W”方式依次首尾相接;在上弦杆和下弦杆与斜腹杆连接处设有弦杆牛腿,所有斜腹杆通过螺栓与弦杆牛腿连接。 The diagonal rods are welded H-shaped steel, and all the diagonal rods are connected end-to-end in a "W" manner; chord corbels are arranged at the connection between the upper chord and the lower chord and the diagonal rods, and all the diagonal rods are connected by bolts Connect with chord corbels.
相比现有技术,本实用新型具有如下有益效果: Compared with the prior art, the utility model has the following beneficial effects:
1、本桁架为平面桁架,隐藏于建筑墙体中,既美观又经济而且施工方便。 1. The truss is a plane truss, hidden in the building wall, which is beautiful, economical and convenient for construction.
2、本桁架在平面内有较大刚度,平面外上、下弦杆处均有楼板相连,可确保转换桁架整体受力稳定。 2. The truss has a relatively large rigidity in the plane, and the upper and lower chords outside the plane are connected by floors, which can ensure the overall stress stability of the conversion truss.
附图说明 Description of drawings
图1-本实用新型结构示意图。 Fig. 1 - structural representation of the utility model.
具体实施方式 Detailed ways
下面结合附图对本实用新型作进一步说明。 Below in conjunction with accompanying drawing, the utility model is further described.
参见图1,从图上可以看出,本实用新型钢结构转换桁架,包括两立柱1,在两立柱1之间水平设有将两立柱连接的上弦杆2和下弦杆3,上弦杆2两端与两立柱1顶部连接,上弦杆2和下弦杆3之间的垂直距离为所在楼层层高。在上弦杆2和下弦杆3之间设有支撑用斜腹杆4,斜腹杆4以倾斜方式将上弦杆2、下弦杆3连接。所述立柱1为焊接H型钢,外表面按技术要求满布栓钉5,目的是抵抗剪力、提高钢骨与混凝土的握裹力,在立柱和栓钉形成的钢骨外包裹混凝土,形成钢筋混凝土柱。所述上弦杆2和下弦杆3为焊接H型钢,外表面按技术要求满布栓钉5,上弦杆和栓钉形成的钢骨以及下弦杆和栓钉形成的钢骨外均包裹混凝土,以形成钢筋混凝土梁。 Referring to Fig. 1, it can be seen from the figure that the steel structure conversion truss of the present invention includes two uprights 1, and an upper chord 2 and a lower chord 3 connecting the two uprights 1 are arranged horizontally between the two uprights 1, and the upper chord 2 is two The end is connected with the top of two columns 1, and the vertical distance between the upper chord 2 and the lower chord 3 is the height of the floor. Between the upper chord 2 and the lower chord 3, there is a supporting diagonal rod 4, and the diagonal rod 4 connects the upper chord 2 and the lower chord 3 in an oblique manner. The column 1 is welded H-shaped steel, and the outer surface is covered with studs 5 according to the technical requirements. Reinforced concrete columns. The upper chord 2 and the lower chord 3 are welded H-shaped steel, and the outer surface is covered with studs 5 according to the technical requirements. form reinforced concrete beams.
所述立柱1与上弦杆和下弦杆连接处设有立柱牛腿6,上弦杆2和下弦杆3两端分别通过螺栓与立柱牛腿6连接,以实现与立柱的连接。 A column corbel 6 is provided at the connection between the column 1 and the upper chord and the lower chord, and the two ends of the upper chord 2 and the lower chord 3 are respectively connected to the column corbel 6 by bolts to realize the connection with the column.
在上弦杆2和下弦杆3与斜腹杆连接处设有弦杆牛腿7,所有斜腹杆4通过螺栓与弦杆牛腿7连接。斜腹杆4为外露型钢,上、下砌砖墙,砌筑时房间内露出,房间外不露出。实际设计时,所述斜腹杆4为焊接H型钢,且所有斜腹杆4以“W”方式依次首尾相接,这样更能够确保桁架片的整体强度。 A chord corbel 7 is arranged at the connection between the upper chord 2 and the lower chord 3 and the diagonal rod, and all the diagonal rods 4 are connected with the chord corbel 7 by bolts. The oblique web bar 4 is an exposed section steel, and the upper and lower brick walls are exposed in the room when building by laying bricks or stones, but not exposed outside the room. In actual design, the diagonal webs 4 are welded H-shaped steels, and all the diagonal webs 4 are sequentially connected end to end in a "W" manner, which can better ensure the overall strength of the truss pieces.
采用这种结构布置方式,除转换层(转换桁架)外,其他层均为普通柱网梁柱布置,既不影响建筑功能,又可取得较好经济性。 With this structural layout, except for the transfer floor (transfer truss), the other floors are arranged with ordinary column net beams and columns, which does not affect the building function and can achieve better economy.
以上实施例仅说明本实用新型的技术方案而非限制,尽管参照较佳实施例对实用新型方案进行了详细说明,本领域的普通技术人员应当理解,可以对本实用新型的技术方案进行修改或者等同替换,而不脱离本实用新型技术方案的宗旨和范围,其均应涵盖在本实用新型的权利要求范围内。 The above embodiments only illustrate the technical solution of the utility model without limitation, although the utility model solution has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solution of the utility model can be modified or equivalent Replacement, without departing from the purpose and scope of the technical solution of the utility model, all of them should be covered by the scope of the claims of the utility model.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520457957.9U CN204753813U (en) | 2015-06-30 | 2015-06-30 | Steel construction conversion truss |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520457957.9U CN204753813U (en) | 2015-06-30 | 2015-06-30 | Steel construction conversion truss |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204753813U true CN204753813U (en) | 2015-11-11 |
Family
ID=54468536
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520457957.9U Expired - Lifetime CN204753813U (en) | 2015-06-30 | 2015-06-30 | Steel construction conversion truss |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204753813U (en) |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105780922A (en) * | 2016-03-24 | 2016-07-20 | 杭州江润科技有限公司 | Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss |
| CN106049670A (en) * | 2016-06-03 | 2016-10-26 | 河海大学 | Embedded type steel truss system |
| CN107386444A (en) * | 2017-08-31 | 2017-11-24 | 福建工程学院 | More Pin space trusses transformational structures |
| CN107460974A (en) * | 2017-07-28 | 2017-12-12 | 河北三山建材科技有限公司 | The insulation attachment structure of wallboard and post beam |
| CN107460948A (en) * | 2017-08-16 | 2017-12-12 | 长安大学 | The double-deck RC plate-type transfer floors and construction method of superstructure are poured after a kind of |
| CN108049690A (en) * | 2018-02-02 | 2018-05-18 | 中国地震局工程力学研究所 | A kind of new shearing steel truss coupling beam for assembling replacement |
| CN109779117A (en) * | 2019-02-22 | 2019-05-21 | 中冶南方都市环保工程技术股份有限公司 | A kind of shuttle shape list slope roof truss |
| CN111648600A (en) * | 2020-06-29 | 2020-09-11 | 广东保辉建筑工程有限公司 | Construction process of built-in type steel structure system of high-rise building structure conversion layer |
| CN112227715A (en) * | 2020-10-21 | 2021-01-15 | 贵州建工集团第一建筑工程有限责任公司 | Construction method of section steel concrete conversion truss shear wall |
| CN112359708A (en) * | 2020-10-30 | 2021-02-12 | 广东三浦车库股份有限公司 | Extra-heavy steel structure instability system |
| CN113958004A (en) * | 2021-09-07 | 2022-01-21 | 江苏省建筑工程集团有限公司 | Large-span cantilever truss structure and construction method thereof |
| CN116220201A (en) * | 2023-02-16 | 2023-06-06 | 中建五局第三建设有限公司 | conversion truss |
| CN118911411A (en) * | 2024-10-11 | 2024-11-08 | 上海建工四建集团有限公司 | Large-span steel structure conversion truss system and unloading method thereof |
-
2015
- 2015-06-30 CN CN201520457957.9U patent/CN204753813U/en not_active Expired - Lifetime
Cited By (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105780922B (en) * | 2016-03-24 | 2017-10-31 | 杭州江润科技有限公司 | Large span steel reinforced concrete transfer truss segmental hoisting formwork system construction method |
| CN105780922A (en) * | 2016-03-24 | 2016-07-20 | 杭州江润科技有限公司 | Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss |
| CN106049670B (en) * | 2016-06-03 | 2018-07-24 | 河海大学 | Flush type steel girder system |
| CN106049670A (en) * | 2016-06-03 | 2016-10-26 | 河海大学 | Embedded type steel truss system |
| CN107460974B (en) * | 2017-07-28 | 2018-11-09 | 河北三山建材科技有限公司 | The heat preservation connection structure of wallboard and column beam |
| CN107460974A (en) * | 2017-07-28 | 2017-12-12 | 河北三山建材科技有限公司 | The insulation attachment structure of wallboard and post beam |
| CN107460948A (en) * | 2017-08-16 | 2017-12-12 | 长安大学 | The double-deck RC plate-type transfer floors and construction method of superstructure are poured after a kind of |
| CN107460948B (en) * | 2017-08-16 | 2019-09-13 | 长安大学 | A double-layer RC slab transfer layer and its construction method for post-cast superstructure |
| CN107386444A (en) * | 2017-08-31 | 2017-11-24 | 福建工程学院 | More Pin space trusses transformational structures |
| CN108049690A (en) * | 2018-02-02 | 2018-05-18 | 中国地震局工程力学研究所 | A kind of new shearing steel truss coupling beam for assembling replacement |
| CN109779117A (en) * | 2019-02-22 | 2019-05-21 | 中冶南方都市环保工程技术股份有限公司 | A kind of shuttle shape list slope roof truss |
| CN111648600A (en) * | 2020-06-29 | 2020-09-11 | 广东保辉建筑工程有限公司 | Construction process of built-in type steel structure system of high-rise building structure conversion layer |
| CN112227715A (en) * | 2020-10-21 | 2021-01-15 | 贵州建工集团第一建筑工程有限责任公司 | Construction method of section steel concrete conversion truss shear wall |
| CN112359708A (en) * | 2020-10-30 | 2021-02-12 | 广东三浦车库股份有限公司 | Extra-heavy steel structure instability system |
| CN113958004A (en) * | 2021-09-07 | 2022-01-21 | 江苏省建筑工程集团有限公司 | Large-span cantilever truss structure and construction method thereof |
| CN116220201A (en) * | 2023-02-16 | 2023-06-06 | 中建五局第三建设有限公司 | conversion truss |
| CN118911411A (en) * | 2024-10-11 | 2024-11-08 | 上海建工四建集团有限公司 | Large-span steel structure conversion truss system and unloading method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204753813U (en) | Steel construction conversion truss | |
| CN104453197B (en) | High Large Cantilever concrete structural steel shape supports platform | |
| CN103352563B (en) | The board-like bar frame gang form of self-supporting and construction method thereof | |
| CN102535672B (en) | Novel hybrid huge anti-seismic structure and construction method thereof | |
| CN102392536B (en) | Construction method for long-span hanging vestibule type template support system | |
| WO2013166658A1 (en) | Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork | |
| CN102127930A (en) | Net die member for steel-concrete building and method for constructing enclosure by combining net die members and filling into a frame shear wall | |
| CN102454217A (en) | Bunchy tube structure for concrete core tubes and integrally-assembled space steel grids | |
| CN105625566B (en) | Assembly concrete orthogonal-diagonal lattice space lattice box structure tube-in-tube structure | |
| CN101029502A (en) | Built-in steel-case or H-shaped concrete assembled beam frame of angle steel concrete pile | |
| CN102704569A (en) | Multilayer large-span assembling integral type space steel grid building structure and manufacturing method | |
| CN102444270B (en) | Sleeve joint oblique key type support bracket | |
| CN102140850B (en) | Frame with floors of composite grid structure and construction method thereof | |
| CN107237398A (en) | A kind of new multi and tall steel building assembled combined structure system | |
| CN206615674U (en) | A kind of single belt vestibule of Square Steel Tubes Truss structure | |
| CN102767282B (en) | Prefabricated high formwork construction method for cantilever beam of oversized special-shaped conversion layer | |
| CN208668732U (en) | A kind of large-span concrete prismatic surface arch grid shell roof structure | |
| CN116290367A (en) | A separate beam-column joint and its system of a prefabricated steel structure | |
| CN102454292A (en) | Supporting steel frame of high altitude large-span cantilever structure mold frame | |
| CN201991226U (en) | Flange template support structure | |
| CN111877559B (en) | Steel-wood mixed crossed chord-opening arch shell structure | |
| CN206070560U (en) | Steel beam foundation of construction elevator | |
| CN213204468U (en) | A close post truss system of encorbelmenting of wearing layer for high-order conversion of large-span big encorbelment | |
| CN205713090U (en) | The template of a kind of V-type concrete column sets up structure | |
| CN204728549U (en) | A kind of lightweight composite floor |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20151111 |