CN107435425A - A kind of toilet resin glue wet combining construction method - Google Patents

A kind of toilet resin glue wet combining construction method Download PDF

Info

Publication number
CN107435425A
CN107435425A CN201710639561.XA CN201710639561A CN107435425A CN 107435425 A CN107435425 A CN 107435425A CN 201710639561 A CN201710639561 A CN 201710639561A CN 107435425 A CN107435425 A CN 107435425A
Authority
CN
China
Prior art keywords
stone material
brick
somebody
resin glue
glue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710639561.XA
Other languages
Chinese (zh)
Inventor
曹颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710639561.XA priority Critical patent/CN107435425A/en
Publication of CN107435425A publication Critical patent/CN107435425A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/0215Flooring or floor layers composed of a number of similar elements specially adapted for being adhesively fixed to an underlayer; Fastening means therefor; Fixing by means of plastics materials hardening after application
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/08Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • E04F15/182Underlayers coated with adhesive or mortar to receive the flooring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • E04F15/186Underlayers covered with a mesh or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of toilet resin glue wet combining construction method, this method concretely comprises the following steps:(1)Engineering technology, which tells somebody what one's real intentions are, deepens unwrapping wire tells somebody what one's real intentions are;(2)Base layer construction is told somebody what one's real intentions are;(3)Material is processed;(4)The configuration of in-site installation materials and apparatus;(5)Wet combining is constructed.The advantage of the invention is that:(1)Time and labour saving;(2)Mortar is reduced, is stacked simple;(3)Anti-pollution, acid and alkali-resistance, corrosion-resistant, not accumulation of salt in the surface soil discoloration, bonding strength are high;(4)The load of floor is reduced, increases the solidification intensity on ground;(5)Sealing closing is closely knit;(6)Service life is grown.

Description

A kind of toilet resin glue wet combining construction method
Technical field
The present invention relates to the realm of building construction, more particularly to a kind of construction method of toilet resin glue wet combining.
Background technology
Toilet elder generation Pipe installing at present, empty closure is hung, it is levelling to do waterproof, water test, protective layer is done, then backfill lightweight and mix Solidifying soil, waterproof, dry rear water test are done, mortar cover is done, finally pastes stone material filleting;Sewage easily slowly oozes from the sealing of stone material Penetrate into, fill concrete is done well by sewage pollution, bottom waterproof, and sewage is not arranged, and is taken care of the pence, and the time is grown, and is caused The more aobvious sternness of environmental problem.
Present stone material dry suspending chip is connected with stone material, due to each decoration corporation confide a technological secret not in time, it is lack of standardization, without one Individual unified national regulation, construction reference, workmen does not have lifelong system, and technical problem be present;Metope base layer construction is put down Whole degree does not reach requirement, and rectification not in time, causes the difficulty of construction in later period to increase;Stone material connects the chip of accessory, different in size, A small number of chip lengths do not reach requirement, also need welding to lengthen at the scene;Cloud stone glue, AB glue and the chip of back face of stone connect, Neither one unified construction technical standard, the connection solidification construction of back face of stone, height is low, of all kinds, makes a lot of variety 's;There is a small amount of construction, accessory chip is arranged on the following of angle bar, force transfer, and chip will bear how many times of endurance i.e. Pulling force downward vertically;What is more important, and a small number of chips are long because connecting, and are fixed with angle bar, screw cannot be used, directly On angle bar chip is fixed with glue;Also many work order location specifications replace dried hanging hang structure glue with cloud stone glue, slacked off in ignoring Material reducing, cost is reduced, seeks quick construction conveniently, stone material dry suspending glue is often substituted with cloud stone glue, causes great potential safety hazard, These irrational constructions, many time bombs are suspended on just as on our peripheries, head, very big potential safety hazard be present.
For above the defects of and the problem of of presence, my invention's resin glue paste ground stone, brick, from surface layer control, Waterproof is controlled layer by layer, and successfully solving the defects of toilet constructs weak point.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of construction method of toilet resin glue stone material wet combining, Neng Goujin Row commercialization is constructed, and shortens the duration, reduces workmen, increases stone material bonding strength, avoids polluting caused by blowdown careless omission.
In order to solve the above technical problems, the technical scheme is that:A kind of construction method of toilet resin glue wet combining, Its innovative point is:Carry out engineering technology to tell somebody what one's real intentions are, deepen unwrapping wire and tell somebody what one's real intentions are, base layer construction is told somebody what one's real intentions are, and strict unified stone material and brick add Work requirement, associated materials prepare, and live wet combining is carried out using resin glue.
Further, the wet combining technique concretely comprises the following steps:
a)Engineering technology, which tells somebody what one's real intentions are, deepens unwrapping wire tells somebody what one's real intentions are:
1st, engineering early stage, the kind of stone material, brick is determined according to Design Requirement Drawing;
2nd, horizontal line, the axial line that engineering unwrapping wire must be handed over according to drawing requirement, proprietor, teams and groups of organizing construction of project management department, depth Change personnel live unwrapping wire together, determines the completion upper thread of stone material, brick, upper thread is completed by stone material, according to the thickness of drawing requirement stone material Degree, the completion upper thread of mortar cover after the basic unit's backfill lightweight concrete and closed-water test of stone material and brick is calculated downwards, it is necessary to By drawing slope requirement or code requirement 0.5%, it is important to consider bottom row's stone material, the size of brick;
3rd, deepen typesetting designer, complete upper thread according to drawing and live stone material, the decoration of brick and carry out typesetting, while to consider Threshold stone positions, and zero brick width of corner can not be less than the 1/3 of specification brick width, and consider decorative effect, divide on typesetting figure Required block number and size are not marked, necessary forces location when particularly flowing specific size and the in-depth of glass degree of position, are paid attention to Stone material periphery finished surface size adds several mm to prevent to stitch towards day;
4th, in-depth typesetting figure drawing to transfer to project administration technical staff audit, the figure be stone material and brick processing, process tell somebody what one's real intentions are, Construction, check and accept and terminate the foundation checked and accepted;
b)Base layer construction is told somebody what one's real intentions are:One of waterproof before fill concrete can be subtracted, other base layer constructions are constant, fill concrete solidification Afterwards, it is necessary to do one of waterproof, after acceptance(check), do mortar cover by slope requirement, surface layer troweling terminates, humidity after 24 hours Maintenance;
c)Stone material, brick processing:
1st, the stone material cutting, brick, according to in-depth typesetting figure, try to arrange in place, see effect, it is underproof to be handled or directly Change, back side waterproof, which can be done, to be done;
2nd, all stone material and brick surfaces must be unified size to bottom thickness, and thickness can not have an error, uniform sizes standard, Brick is processed well than stone material;
3rd, packaging must concentrate bag by the bid section of in-depth typesetting figure, an aspect, a room, a plane, a moulding Fill, document is posted in packaging, the in-depth plan of the block number of stone material and brick processing, size and diminution is enclosed, so as to from the packaging It is known that the position of installation;
4th, scene is transported to, arranges to be transported to close to the position of installation as far as possible, in order to avoid repeatedly carry, collision fracture;
5th, stone material transports to scene, needs the time of several days, stone material substantially dry, stone material to be directly put into installation according to stone material numbering Position;
d)The configuration of in-site installation materials and apparatus:Stone material or brick, rubber hammer, brush, one-shot injector, sanitary cup, ring Oxygen resin glue, curing agent, accelerator, glass fiber reticular cloth, roller, brush, putty knife, blade of carving knife, scraper plate, Plastic Drum, plastics Water bottle, Bai Wan, iron oxide red, iron oxide yellow, iron oxide black, chrome green, titanium ultramarine, titanium dioxide, kind oxidation color, mill base, color essence, All pigment and color, it is necessary to be dissolved in resin glue;
e)Stone material wet combining work progress
1st, etc. after ground solidification is completely dried, floor-dust is first cleaned out, particularly convex pimple, it is necessary to even out or grind It is flat;
2nd, the control line and separator bar of stone material or brick are put on ground according to typesetting figure;
3rd, resin glue is allocated;
4th, the resin glue configured is directly poured on ground, or scraped in the uniform can in ground, glue can also be scraped in stone material or The back side of brick;
5th, and then stone material or brick by number, put up, gently knocked on stone material with hammer, the glue of sealing is emerged, stone Material or brick are paved, if stone material or brickwork joint mouth resin glue less than, it is necessary to timely processing glue, by that analogy, spread therefore, wrapping Including the end processing of stone material or brick will settle at one go;
6th, during resin solidification, beginning intensity is not high, is easy to clear up unnecessary resin material with blade;
7th, etc. clean mirror is made in polishing after solidification in 1-2 days is dried;Vitrified tile is not required to be surface-treated because surface is smooth:Minute surface is done in polishing, During paving construction, every sealing glassine paper auxiliary construction, sealing is struck off, unnecessary resin separates, and is cleared up in time after solidification.
Further, during the step e allotments resin glue, layer of glass fiber fabric or two can be added before ground stone paving Layer glass-fiber-fabric, increase the waterproof effect on ground.
Further, during the step e allotments resin glue, according to temperature plus 1% -4% curing agent, 1%-4% promotes Agent, the color of glue used can be prepared first, but curing agent, accelerator can not match somebody with somebody, and take 100g resin glues to be put into once in proportion Property cup in, inhale 3g curing agent with one-shot injector and put into and stirred in cup, then inhale 3g accelerator with one-shot injector and put into Stir and terminate in cup, it is now with the current when with glue, control and solidified at 15 minutes or so as far as possible.
The advantage of the invention is that:
1st, settle at one go, need not fetch water maintenance after terminating, reduce scene it is artificial, the time is saved, beneficial to the duration in advance;
2nd, the mortar material at scene is reduced, transport and scene are stacked up and down;
3rd, performance:Anti-pollution, acid and alkali-resistance, corrosion-resistant, not accumulation of salt in the surface soil discoloration, bonding strength are high;
4th, the load of floor is reduced, increases the solidification intensity on ground;
5th, the stone material of this technique patch, the closing of periphery sealing are closely knit, and toilet blowdown will not penetrate into ground, free from extraneous odour;
6th, the stone material and brick of this technique patch, sealing closing in periphery is closely knit, increases the protective layer of stone material and brick, controls stone material and brick Water suction, surface layer is not pulverized easily, ftractureed, dilatancy, is not easy to be influenceed by surface humidity, good decorating effect, safe operating life It is long.
Embodiment
The following examples can make professional and technical personnel that the present invention be more fully understood, but therefore not send out this It is bright to be limited among described scope of embodiments.
A kind of toilet resin glue stone material wet combining technique in the present invention, specifically includes following step:
The first step, engineering technology, which tells somebody what one's real intentions are, deepens unwrapping wire tells somebody what one's real intentions are:
1st, engineering early stage, the kind of stone material, brick is determined according to Design Requirement Drawing;
2nd, horizontal line, the axial line that engineering unwrapping wire must be handed over according to drawing requirement, proprietor, teams and groups of organizing construction of project management department, depth Change personnel live unwrapping wire together, determines the completion upper thread of stone material, brick, upper thread is completed by stone material, according to the thickness of drawing requirement stone material Degree, the completion upper thread of mortar cover after the basic unit's backfill lightweight concrete and closed-water test of stone material and brick is calculated downwards, it is necessary to By drawing slope requirement or code requirement 0.5%, it is important to consider bottom row's stone material, the size of brick;
3rd, deepen typesetting designer, complete upper thread according to drawing and live stone material, the decoration of brick and carry out typesetting, while to consider Threshold stone positions, and zero brick width of corner can not be less than the 1/3 of specification brick width, and consider decorative effect, divide on typesetting figure Required block number and size are not marked, necessary forces location when particularly flowing specific size and the in-depth of glass degree of position, are paid attention to Stone material periphery finished surface size adds several mm to prevent to stitch towards day;
4th, in-depth typesetting figure drawing to transfer to project administration technical staff audit, the figure be stone material and brick processing, process tell somebody what one's real intentions are, Construction, check and accept and terminate the foundation checked and accepted;
Second step, base layer construction are told somebody what one's real intentions are:One of waterproof before fill concrete can be subtracted, other base layer constructions are constant, backfill coagulation After soil solidification, it is necessary to do one of waterproof, after acceptance(check), do mortar cover by slope requirement, surface layer troweling terminates, 24 hours Humidity is maintained afterwards;
3rd step, stone material, brick processing:
1st, the stone material cutting, brick, according to in-depth typesetting figure, try to arrange in place, see effect, it is underproof to be handled or directly Change, back side waterproof, which can be done, to be done;
2nd, all stone material and brick surfaces must be unified size to bottom thickness, and thickness can not have an error, uniform sizes standard, Brick is processed well than stone material;
3rd, packaging must concentrate bag by the bid section of in-depth typesetting figure, an aspect, a room, a plane, a moulding Fill, document is posted in packaging, the in-depth plan of the block number of stone material and brick processing, size and diminution is enclosed, so as to from the packaging It is known that the position of installation;
4th, scene is transported to, arranges to be transported to close to the position of installation as far as possible, in order to avoid repeatedly carry, collision fracture;
5th, stone material transports to scene, needs the time of several days, stone material substantially dry, stone material to be directly put into installation according to stone material numbering Position;
4th step, the configuration of in-site installation materials and apparatus:Stone material or brick, rubber hammer, brush, one-shot injector, disposable cup Son, epoxide-resin glue, curing agent, accelerator, glass fiber reticular cloth, roller, brush, putty knife, blade of carving knife, scraper plate, Plastic Drum, Plastic water bottle, Bai Wan, iron oxide red, iron oxide yellow, iron oxide black, chrome green, titanium ultramarine, titanium dioxide, kind oxidation color, mill base, Color essence, all pigment and color, it is necessary to be dissolved in resin glue;
5th step, wet combining work progress:
1st, etc. after ground solidification is completely dried, floor-dust is first cleaned out, particularly convex pimple, it is necessary to even out or grind It is flat;
2nd, the control line and separator bar of stone material are put on ground according to typesetting figure;
3rd, before ground stone paving layer of glass fiber fabric or two layers of glass-fiber-fabric, the waterproof effect for increasing ground can be added to be added according to temperature 1% -4% curing agent, 1%-4% accelerator, the color of glue glue used can be prepared first, but curing agent, accelerator can not match somebody with somebody; Take 100g resin glues to be put into disposable cup in proportion, put into cup and stirred with one-shot injector suction 3g curing agent, then Inhaled 3g accelerator with one-shot injector and put into stir in cup and terminated, it is now with the current when with glue, control as far as possible at 15 minutes Left and right solidifies;
4th, the resin glue configured is directly poured on ground, or scraped in the uniform can in ground, glue can also be scraped in stone material or The back side of brick;
5th, and then stone material or brick by number, put up, gently knocked on stone material with hammer, the glue of sealing is emerged, stone Material or brick are paved, if stone material or brickwork joint mouth resin glue less than, it is necessary to timely processing glue, by that analogy, spread therefore, wrapping Including the end processing of stone material or brick will settle at one go;
6th, during resin solidification, beginning intensity is not high, is easy to clear up unnecessary resin material with blade;
7th, etc. clean mirror is made in polishing after solidification in 1-2 days is dried;Vitrified tile is not required to be surface-treated because surface is smooth:Minute surface is done in polishing, During paving construction, every sealing glassine paper auxiliary construction, sealing is struck off, unnecessary resin separates, and is cleared up in time after solidification.
Construction method in above-described embodiment, every square metre of paving of stone material is 1.5-2.5Kg with resin glue amount, and material is accurate After getting ready, worker's paving 30-60 blocks per hour;
Every square metre of paving of brick, resin glue dosage are 1.5-3Kg, after material preparation, worker's paving 40-60 blocks per hour.
It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, in above-described embodiment and specification Description merely illustrates the principles of the invention, and without departing from the spirit and scope of the present invention, the present invention also has various Changes and improvements, these changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by institute Attached claims and its equivalent circle.

Claims (3)

1. a kind of toilet resin glue wet combining construction method, this method is used for the construction of toilet stone material, brick, vitrified tile, and it is special Sign is:Carry out engineering technology to tell somebody what one's real intentions are, deepen unwrapping wire and tell somebody what one's real intentions are, base layer construction is told somebody what one's real intentions are, and strictly unified processing request, prepares related material Material carries out the wet combining of live stone material, brick, vitrified tile using resin glue, concretely comprises the following steps:
a)Engineering technology, which tells somebody what one's real intentions are, deepens unwrapping wire tells somebody what one's real intentions are:
1st, engineering early stage, the kind of stone material, brick is determined according to Design Requirement Drawing;
2nd, horizontal line, the axial line that engineering unwrapping wire must be handed over according to drawing requirement, proprietor, teams and groups of organizing construction of project management department, depth Change personnel live unwrapping wire together, determines the completion upper thread of stone material, brick, upper thread is completed by stone material, according to the thickness of drawing requirement stone material Degree, the completion upper thread of mortar cover after the basic unit's backfill lightweight concrete and closed-water test of stone material and brick is calculated downwards, it is necessary to By drawing slope requirement or code requirement 0.5%, it is important to consider bottom row's stone material, the size of brick;
3rd, deepen typesetting designer, complete upper thread according to drawing and live stone material, the decoration of brick and carry out typesetting, while to consider Threshold stone positions, and zero brick width of corner can not be less than the 1/3 of specification brick width, and consider decorative effect, divide on typesetting figure Required block number and size are not marked, necessary forces location when particularly flowing specific size and the in-depth of glass degree of position, are paid attention to Stone material periphery finished surface size adds several mm to prevent to stitch towards day;
4th, in-depth typesetting figure drawing to transfer to project administration technical staff audit, the figure be stone material and brick processing, process tell somebody what one's real intentions are, Construction, check and accept and terminate the foundation checked and accepted;
b)Base layer construction is told somebody what one's real intentions are:One of waterproof before fill concrete can be subtracted, other base layer constructions are constant, fill concrete solidification Afterwards, it is necessary to do one of waterproof, after acceptance(check), do mortar cover by slope requirement, surface layer troweling terminates, humidity after 24 hours Maintenance;
c)Stone material, brick processing:
1st, the stone material cutting, brick, according to in-depth typesetting figure, try to arrange in place, see effect, it is underproof to be handled or directly Change, back side waterproof, which can be done, to be done;
2nd, all stone material and brick surfaces must be unified size to bottom thickness, and thickness can not have an error, uniform sizes standard, Brick is processed well than stone material;
3rd, packaging must concentrate bag by the bid section of in-depth typesetting figure, an aspect, a room, a plane, a moulding Fill, document is posted in packaging, the in-depth plan of the block number of stone material and brick processing, size and diminution is enclosed, so as to from the packaging It is known that the position of installation;
4th, scene is transported to, arranges to be transported to close to the position of installation as far as possible, in order to avoid repeatedly carry, collision fracture;
5th, stone material transports to scene, needs the time of several days, stone material substantially dry, stone material to be directly put into installation according to stone material numbering Position;
d)The configuration of in-site installation materials and apparatus:Stone material or brick, rubber hammer, brush, one-shot injector, sanitary cup, ring Oxygen resin glue, curing agent, accelerator, glass fiber reticular cloth, roller, brush, putty knife, blade of carving knife, scraper plate, Plastic Drum, plastics Water bottle, Bai Wan, iron oxide red, iron oxide yellow, iron oxide black, chrome green, titanium ultramarine, titanium dioxide, kind oxidation color, mill base, color essence, All pigment and color, it is necessary to be dissolved in resin glue;
e)Stone material wet combining work progress
1st, etc. after ground solidification is completely dried, floor-dust is first cleaned out, particularly convex pimple, it is necessary to even out or grind It is flat;
2nd, the control line and separator bar of stone material or brick are put on ground according to typesetting figure;
3rd, resin glue is allocated;
4th, the resin glue configured is directly poured on ground, or scraped in the uniform can in ground, glue can also be scraped in stone material or The back side of brick;
5th, and then stone material or brick by number, put up, gently knocked on stone material with hammer, the glue of sealing is emerged, stone Material or brick are paved, if stone material or brickwork joint mouth resin glue less than, it is necessary to timely processing glue, by that analogy, spread therefore, wrapping Including the end processing of stone material or brick will settle at one go;
6th, during resin solidification, beginning intensity is not high, is easy to clear up unnecessary resin material with blade;
7th, etc. clean mirror is made in polishing after solidification in 1-2 days is dried;Vitrified tile is not required to be surface-treated because surface is smooth:Minute surface is done in polishing, During paving construction, every sealing glassine paper auxiliary construction, sealing is struck off, unnecessary resin separates, and is cleared up in time after solidification.
2. toilet according to claim 1 uses resin glue wet combining construction method, it is characterised in that:The step e is adjusted During resin glue, layer of glass fiber fabric or two layers of glass-fiber-fabric can be added before ground stone paving, increase the waterproof effect on ground.
3. toilet according to claim 1 uses resin glue wet combining construction method, it is characterised in that:The step e is adjusted During resin glue, according to temperature plus 1% -4% curing agent, 1%-4% accelerator, the color of glue used can be prepared first, but It is that curing agent, accelerator can not match somebody with somebody;Take 100g resin glues to be put into disposable cup in proportion, inhale 3g curing agent with one-shot injector Put into cup and stir, then inhaled 3g accelerator with one-shot injector and put into stir in cup and terminated, when with glue, now matched somebody with somebody It is current, control and solidified at 15 minutes or so as far as possible.
CN201710639561.XA 2017-07-31 2017-07-31 A kind of toilet resin glue wet combining construction method Pending CN107435425A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710639561.XA CN107435425A (en) 2017-07-31 2017-07-31 A kind of toilet resin glue wet combining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710639561.XA CN107435425A (en) 2017-07-31 2017-07-31 A kind of toilet resin glue wet combining construction method

Publications (1)

Publication Number Publication Date
CN107435425A true CN107435425A (en) 2017-12-05

Family

ID=60461382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710639561.XA Pending CN107435425A (en) 2017-07-31 2017-07-31 A kind of toilet resin glue wet combining construction method

Country Status (1)

Country Link
CN (1) CN107435425A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575550A (en) * 2022-03-23 2022-06-03 安徽三建工程有限公司 Wet pasting process for floor tiles in kitchens and bathrooms

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008057119A (en) * 2006-08-29 2008-03-13 Jdc Corp Waterproof construction method for concrete floor slab for road bridge
JP2011106176A (en) * 2009-11-18 2011-06-02 Kawasaki Heavy Ind Ltd Method for waterproofing and waterproof structure of upper surface of concrete floor slab, and fiber plate
CN102505831A (en) * 2011-12-22 2012-06-20 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN105569238A (en) * 2015-12-24 2016-05-11 曹颖 Construction method for infusion of AB glue and resin glue for curtain wall stone dry-hanging process
CN105666704A (en) * 2016-01-17 2016-06-15 曹颖 Construction method for rapidly connecting stones through epoxy resin adhesive

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008057119A (en) * 2006-08-29 2008-03-13 Jdc Corp Waterproof construction method for concrete floor slab for road bridge
JP2011106176A (en) * 2009-11-18 2011-06-02 Kawasaki Heavy Ind Ltd Method for waterproofing and waterproof structure of upper surface of concrete floor slab, and fiber plate
CN102505831A (en) * 2011-12-22 2012-06-20 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN105569238A (en) * 2015-12-24 2016-05-11 曹颖 Construction method for infusion of AB glue and resin glue for curtain wall stone dry-hanging process
CN105666704A (en) * 2016-01-17 2016-06-15 曹颖 Construction method for rapidly connecting stones through epoxy resin adhesive

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575550A (en) * 2022-03-23 2022-06-03 安徽三建工程有限公司 Wet pasting process for floor tiles in kitchens and bathrooms

Similar Documents

Publication Publication Date Title
CN105672684B (en) A kind of construction method for repairing ground stone hollowing
CN108086113A (en) A kind of road surface precast assembly fast repairing method for being suitable for southern damp-heat area
CN110144790A (en) A kind of construction method of water permeable concrete
CN101457581A (en) Construction method for auto-flowing floor
CN104120855A (en) Construction method for paving ground tile floor
CN108947433B (en) Preparation method of gypsum-based self-leveling floor material
CN108412093A (en) A kind of Modern Landscape decoration loam wall and its construction method
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN103953181B (en) Cement flooring breakage method for repairing and constructing
CN109826456A (en) Mortar curing process
CN110219443A (en) Machinery whitewashing plastering construction method
CN107435425A (en) A kind of toilet resin glue wet combining construction method
CN207420088U (en) A kind of detachable combination cornice for facade rebuilding construction
CN105569238A (en) Construction method for infusion of AB glue and resin glue for curtain wall stone dry-hanging process
CN102888959B (en) A kind of dry powder and mortar External Wall carries out the method for constructing
CN204282784U (en) A kind of face brick filleting compression tool
CN205012344U (en) High steep overflow surface slipform
CN106278065A (en) Imitative stone decoration element and production method thereof
CN107574936A (en) A kind of heat preserving exterior wall construction technology
CN205000655U (en) But cyclic utilization's multi -functional split heads
CN215368500U (en) Flame-retardant anti-cracking extruded polystyrene foam heat-insulation terrace
CN205840190U (en) A kind of pin key connects the mounting structure of prefabricated bench
CN203856170U (en) Non-deforming quartz stone manufactured on site
CN107938907A (en) A kind of inclined roof exempts from formwork construction method
CN104295102B (en) The construction method of steel form fire wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination