Info

Publication number
CN107401285A
CN107401285A CN201710888462.5A CN201710888462A CN107401285A CN 107401285 A CN107401285 A CN 107401285A CN 201710888462 A CN201710888462 A CN 201710888462A CN 107401285 A CN107401285 A CN 107401285A
Authority
CN
China
Prior art keywords
wall
brick
stand
stones
laying bricks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710888462.5A
Other languages
Chinese (zh)
Inventor
徐敏
庞建勇
严旺
何壮志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui University of Science and Technology
Original Assignee
Anhui University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui University of Science and Technology filed Critical Anhui University of Science and Technology
Priority to CN201710888462.5A priority Critical patent/CN107401285A/en
Publication of CN107401285A publication Critical patent/CN107401285A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/22Tools or apparatus for setting building elements with mortar, e.g. bricklaying machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention discloses a kind of building construction technology field machinery, relates in particular to a kind of new stand and grouts wall telephone and construction method, this kind of wall-building machine, be made up of three parts, respectively spreads out sizing device, mobile device, lowering or hoisting gear;The adjustable height of lowering or hoisting gear is set according to the mode of wanted masonry panel and wall brick specification, building wall position is determined by artificial unwrapping wire, it is artificial to build the lowering or hoisting gear that stand sizing device is connected to after one layer and is provided with PLC by laying bricks or stones, it is placed in one end of one layer of brick wall, the adjuster in movable support is adjusted according to wanted masonry panel thickness in the other end and fixes movable support on brick wall, steel strand wires one end is connected on draw ring, the other end passes through movable support, the installation of whole device is completed in steel strand wires fixator access power shaft box, two layers of brick wall are proceeded by build by laying bricks or stones.The structure is both simple in construction, easy to use, and building wall is carried out by the way of man-computer cooperation, not only improves operating efficiency, reduces artificial use, and ensures construction quality.

Description

Semi-automatic stand paddle wall-building machine and construction method
Technical field
The invention belongs to building construction technology field, relates in particular to a kind of new stand and grouts wall telephone and construction method.
Background technology
With the continuous development of society, Urbanization Construction paces are accelerated, and people are growing to the demand in house.Built in room During, the wall in house is mostly formed using common brick or cement brick by that must put in order to pile up, conventional masonry way There are full broken joint, full header method, fourth along folder block, one along fourth etc., and piling up for house wall is mostly manually built by multiple workers Build;For normal, a consummate tiler needs that the brick wall of a building new house, most bricklaying could be built 4 to 6 weeks Environment is poor, and worker is mostly the elderly, and muscle power is very limited, and not only labor intensity is big by pure manual work, efficiency is low, Er Qierong Easily because longevity of service, produce fatigue and cause miswork.In architectural environment, worker's personal safety hidden danger also be present.Pin To this situation existing a variety of machineries of building a wall, but existing automatic wall building machine function is limited to now, it is impossible to a variety of masonry way are catered to, Complicated to cause operation to have certain inconvenience, maintenance cost costliness and inconvenient maintenance when breaking down, result in can not be big Operating efficiency is improved in degree, conscientiously useful help is not provided to worker.
The content of the invention
In view of the shortcomings of the prior art, the present invention provides a kind of new stand and grouts wall telephone and construction method, this kind of machinery, both It is simple in construction, easy to use, building wall is carried out by the way of man-computer cooperation, not only improves operating efficiency, reduction manually makes With, and ensure construction quality.
To realize object above, the present invention is achieved by the following technical programs:
Semi-automatic stand paddle wall-building machine, it is made up of three parts, respectively spreads out sizing device, mobile device, lowering or hoisting gear.
Wherein described stand sizing device includes mortar funnel, stand slurry roller bearing, fixed glides, mortar control panel, draw ring.Mortar leaks Struggle against for holding mortar of laying bricks, the stand slurry amount of mortar is controlled by the openings of sizes of mortar control panel, stand slurry roller bearing is used when stand is starched In compacting mortar and control stand slurry thickness, on the one hand fixed glides can provide the sliding rail of the device, on the other hand limit Stand slurry position, reduces the work of vertical marked rod when building a wall.
Further, the mobile device, it is connected to by a steel strand wires one end on the draw ring of stand sizing device, the other end leads to Cross movable support and be involved in power shaft and pull the process of stand sizing device to carry out stand slurry, the rotation speed of power shaft so as to reach Degree can be adjusted according to Practical Project situation.
Further, the lowering or hoisting gear is the lifting of control stand sizing device, and stand sizing device is connected on lowering or hoisting gear, Lowering or hoisting gear controls the lifting of stand sizing device by PLC, and adjustable height is the thickness of one block of common brick or cement brick Degree, the specification of general cement brick is 190mm × 190mm × 390mm, and common brick regular size is 240mm × 115mm × 53mm, is risen Falling unit sets multiple adjustable heights, respectively 53mm, 115mm, 90mm, 190mm etc..
Semi-automatic stand paddle wall-building machine, including following construction procedure:
A the adjustable height of lowering or hoisting gear) is set according to the mode of wanted masonry panel and wall brick specification, by artificial Unwrapping wire determines building wall position, proceeds by one layer of brick wall and builds by laying bricks or stones.Building by laying bricks or stones for one layer of brick wall is true by the way of manually building by laying bricks or stones Surely build line by laying bricks or stones, build the lowering or hoisting gear that stand sizing device is connected to after one layer and is provided with PLC by laying bricks or stones;
B the stand sizing device and lowering or hoisting gear that connect) are placed in brick wall one end;
C the distance of two fixed glides, as brick wall thickness) are adjusted by bolt thereon, is fixed on one layer of brick wall, Movable support is fixed on the brick wall other end, power shaft is nearby installed on ground, the power shaft is made with low-power motor For power, it is transferred to steel strand wires and can be manually pulled out;
D) after said apparatus installation, steel strand wires one end is connected on the draw ring of stand sizing device, the other end is by can Mobile support saddle is connected in power shaft box, and starting motor can be involved in steel strand wires in it;
E) after device installation, the mortar (cement that will mix:Lime:Yellow sand=1:1:6) mortar funnel is poured into It is interior, start power shaft and proceed by stand slurry, brick is manually started during being starched at stand, use is scraped at vertical abutment joint between brick and brick Device is starched by the vertically artificial starching of upper pulpboard, can be discovered in time in engineering process by the way of artificial mechanism is used cooperatively Deviation is corrected in time;
F) when the sensing chip in the fixed glides for spreading out sizing device touches the induction installation of movable support, lowering or hoisting gear Lifting is carried out according to original setting adjustable height, proceeds by three layers of brick starching;
G) promote lowering or hoisting gear to put brick wall and start three layers of brick masonry of starching side progress, carry out the block of brick wall by that analogy Build.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is the semi-automatic stand paddle wall-building machine structural representation of the present invention;
Fig. 2 is present invention stand sizing device structural representation;
Fig. 3 is present invention stand sizing device front view;
Fig. 4 is present invention stand sizing device fixed glides schematic diagram;
Fig. 5 is movable support structural representation of the present invention;
Fig. 6 is power shaft structural representation of the present invention;
The vertical starching plate structure schematic diagram of Fig. 7 present invention;
Fig. 8 is lowering or hoisting gear schematic diagram of the present invention:
In figure:1. sizing device is spread out, 11. mortar funnels, 12. stand slurry roller bearings, 13. fixed glides, 15. regulating bolts, 16. sand Slurry control panel, 17. draw rings, 2. steel strand wires, 3. movable supports, 31. axle wheels, 32. support frames, 33. fixed plates, 34. adjusters, 4. power shaft, 41. steel strand wires fixators, 42. axle wheels, 43. support frames, 44. power shaft boxes, 5. walls, 6. vertical starchings Plate, 7. lowering or hoisting gears, 71. cranes, 72. links, 73. movable pulleys
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, clear, complete description is carried out to the technical scheme in invention, it is clear that described embodiment is of the invention Part of the embodiment, rather than whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not having The other embodiments obtained under the premise of creative work are made, belong to protection scope of the present invention.
With reference to accompanying drawing 1 to Fig. 8, the invention will be further described:
Semi-automatic stand paddle wall-building machine of the present invention, as illustrated, including stand sizing device 1, steel strand wires 2, removable branch Seat 3, vertically power shaft 4, upper pulpboard 6, lowering or hoisting gear 7, set according to the mode of wanted masonry panel and wall brick specification The adjustable height of lowering or hoisting gear, building wall position is determined by artificial unwrapping wire, proceed by one layer of brick wall and build by laying bricks or stones.One layer of brick wall Build by laying bricks or stones and determine to build line by laying bricks or stones by the way of manually building by laying bricks or stones, stand sizing device is connected to after building one layer by laying bricks or stones PLC programming controls is installed The lowering or hoisting gear 7 of device processed, one end of one layer of brick wall is placed in, movable support is adjusted according to wanted masonry panel thickness in the other end Adjuster 34 on 3 fixes movable support 3 on brick wall, and the one end of steel strand wires 2 is connected on draw ring 17, and the other end is by can Mobile support saddle 3, steel strand wires fixator 41 access in power shaft box 44 installation for completing whole device, proceed by two layers of brick wall Build by laying bricks or stones.
With reference to Fig. 2 and Fig. 3, the stand sizing device includes mortar funnel 11, stand slurry roller bearing 12, fixed glides 13, regulation Bolt 15, mortar control panel 16, draw ring 17, wherein the mortar funnel is made of stainless steel, and funnel wall thickness 10mm -20mm, chi (a length and width wherein direction size is consistent with wall thickness, typically by very little 100mm × 180mm × 500mm -200mm × 400mm × 700mm Brick wall thickness is 240mm, and load-bearing wall thickness is up to 380mm), the stand slurry roller bearing material is the material poor with cement mortar phasic property Matter (such as stainless steel), a diameter of 100mm -150mm, length are brick wall thickness, and regulating bolt is used to spread out sizing device and brick wall Connection.More preferable to play fixed glides effect, the mortar control panel controls slurry amount under the mortar funnel unit interval by push-and-pull.
With reference to Fig. 4, the fixed glides use starches roller bearing identical material with stand, and size is not limited, its inner side by Guide rail, stand sizing device movement is limited and to mortar position limitation.
With reference to Fig. 5, the movable support axle wheel is by 31, and support frame 32, fixed plate 33, adjuster 34 forms, wherein adjusting Section device is fixed on brick wall by twisting bolt come the width of adjustment fixing plate, and fixed plate width is slightly larger than brick wall thickness, support frame On the one hand whole support body is can support, another aspect support frame can be rotated, and change the position of bearing axle wheel.
With reference to Fig. 6, the power shaft is by steel strand wires fixator 41, axle wheel 42, support frame 43,44 groups of power shaft box Into steel strand wires one end is tied up on the sizing device of stand, and the other end is tied up in power shaft by movable support through steel strand wires fixator In box, steel strand wires can be involved in power shaft box by starting motor, and support frame here is identical with movable support.
With reference to Fig. 7, the vertical starching sheet material matter is steel, and size is brick wall thickness × mono- brick height, and lower end has one to lack Mouthful, the breach is that cement mortar is spread out at slurry.
With reference to Fig. 8, the lowering or hoisting gear includes crane 71, and link 72, movable pulley 73, crane is by PLC programming controls Device control processed, link connection crane and stand sizing device, movable pulley are used to move whole device.
Reference picture 1~8, its construction procedure, method and relevant parameter are as follows:
A the proportioning of binding material) is carried out before masonry panel, the main component of conventional binding material is cement, yellow sand And lime paste.Different material fits and material grading (i.e. weight ratio) can be selected as required.Here using mixing Illustrated exemplified by mortar, it is cement that optional stage, which is matched somebody with somebody,:Lime:Yellow sand=1:1:6.
B) lay bricks before wall, first base surface or or flooring on make each layer absolute altitude on schedule by standard water, and use cement mortar Or C10 pea gravel concretens are levelling.Architecture bottom layer wall body can be defined by axis location nail on sight rail and draw linen thread, along linen thread linen thread Lower plumb bob is hung, wall body center line axis is put on base surface, and wall body central axis is defined ejection longitudinal cross wall line at one's side accordingly, and Make door-window opening position.To ensure the coincidence of each floor layer wall body axis, and it is consistent with foundation location axis, using advance Wall body central axis of the pilot measurement on wall face, so as to upward pilot measurement.The pilot measurement of axis is the key of unwrapping wire, it is necessary to will by drawing Size is asked to be checked with metallic tape.Then, by floor wall body center line, each wall sideline is ejected, marks door-window opening position.
C) further, by selected masoning method, pendulum brick sample is tried in wall base top surface unwrapping wire position, and (raw pendulum, i.e., do not spread Ash), door and window pile is met the modulus of brick as far as possible, deviation hour can be adjusted by perps, with reduce cut brick quantity, and ensure brick and Brickwork joint marshalling, uniformly, is laid bricks efficiency with improving.It is particularly important in dry wall is built by laying bricks or stones to put brick sample.
D) further, vertical marked rod can not had to again using semi-automatic stand paddle wall-building machine at this, manually building one by laying bricks or stones Building by laying bricks or stones for two layers of wall brick is proceeded by after layer brick, sizing device 1 will be spread out is connected to the lowering or hoisting gear 7 of PLC is installed And it is placed on brick wall one end.
E) further, fixed glides 13 are stuck on one layer of brick, regulation regulating bolt makes it firmly be stuck on brick wall.
F) further, steel strand wires one end is connected on the draw ring of stand sizing device using steel strand wires 2, steel strand wires 2 pass through Movable support 3, it is another to be fixed on brick wall by twisting bolt come the width of adjustment fixing plate 33 for adjuster 34 in movable support On end, fixed plate width is slightly larger than brick wall thickness, on the one hand support frame 32 can support whole support body, and another aspect support frame can be with Rotated, change the position of bearing axle wheel, reach the space-saving function of actual conditions.
G) further, nearby on ground install power shaft 4, the power shaft using low-power motor as power, Steel strand wires 2 are accessed in power shaft box 44 through steel strand wires fixator 41.
H after) installing apparatus above, two layers of brick wall are proceeded by and are built by laying bricks or stones, started motor and start stand slurry, at the same it is artificial on Brick, carry out vertical mortar joint using vertical upper pulpboard 6 and smear slurry.
I) when the sensing chip in the fixed glides for spreading out sizing device touches the induction installation of movable support 3, lifting dress Put 7 and carry out lifting according to original setting adjustable height, manual mobile lifting device 7 is put wall end initiating terminal and proceeded by three layers of brick Slurry, next built by laying bricks or stones as two layers of brick wall building method carry out three layers of brick wall.
It should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations, although ginseng The present invention is described in detail according to previous embodiment, those of ordinary skill in the art should be understood:It still can be right Technical scheme described in foregoing embodiments is modified, or carries out equivalent substitution to some technical characteristics therein, and These modifications are replaced, and the essence of appropriate technical solution is departed from the spirit and model of various embodiments of the present invention technical scheme Enclose.

Claims (6)

1. a kind of new stand of the present invention grouts wall telephone and construction method, including stand sizing device 1, steel strand wires 2, movable support 3rd, power shaft 4, vertically upper pulpboard 6, lowering or hoisting gear 7, liter is set according to the mode of wanted masonry panel and wall brick specification The adjustable height of falling unit, building wall position is determined by artificial unwrapping wire, proceed by one layer of brick wall and build by laying bricks or stones.One layer of brick wall Build by laying bricks or stones and determine to build line by laying bricks or stones by the way of manually building by laying bricks or stones, stand sizing device is connected to after building one layer by laying bricks or stones PLC programming Controls are installed The lowering or hoisting gear 7 of device, one end of one layer of brick wall is placed in, movable support 3 is adjusted according to wanted masonry panel thickness in the other end On adjuster 34 fix movable support 3 on brick wall, the one end of steel strand wires 2 is connected on draw ring 17, the other end is by can Mobile support saddle 3, steel strand wires fixator 41 access in power shaft box 44 installation for completing whole device, proceed by two layers of brick wall Build by laying bricks or stones.
2. a kind of new stand according to claim 1 grouts wall telephone and construction method, it is characterised in that the stand sizing device Including mortar funnel (11), stand slurry roller bearing (12), fixed glides (13), mortar control panel (16), draw ring (17).Mortar funnel (11) it is used to hold mortar of laying bricks, exposing mortar funnel (11) bottom opening size by mortar control panel (16) push-and-pull controls sand The stand slurry amount of slurry, stand slurry roller bearing (12) is used to be compacted mortar and controls stand slurry thickness, fixed glides (13) one side energy when stand is starched The sliding rail of the device is enough provided, on the other hand limitation stand slurry position, reduce the work of vertical marked rod when building a wall.
3. a kind of new stand according to claim 1 grouts wall telephone and construction method, it is characterised in that the steel strand wires (2) one end is connected on the draw ring (17) of stand sizing device (1), and the other end is involved in power shaft box by movable support (3) (44) process of stand sizing device is pulled to carry out stand slurry so as to reach in, the velocity of rotation of the power shaft (4) can be according to reality Border project situation is adjusted.
4. a kind of new stand according to claim 1 grouts wall telephone and construction method, it is characterised in that the lowering or hoisting gear (7) it is to control the lifting for spreading out sizing device (1), the stand sizing device (1) is connected on the lowering or hoisting gear (7), the lifting Device (7) controls the lifting of stand sizing device (1) by PLC, and adjustable height is one block of common brick or cement brick Thickness, the specification of general cement brick is 190mm × 190mm × 390mm, and common brick regular size is 240mm × 115mm × 53mm, Lowering or hoisting gear sets multiple adjustable heights, respectively 53mm, 115mm, 90mm, 190mm etc..
5. a kind of new stand according to claim 1 grouts wall telephone and construction method, it is characterised in that the vertical starching Plate (6) is the easy plane that slurry is smeared for carrying out vertical mortar joint, and the vertically upper pulpboard (6) is stood on into brick side, existed using scraper Cement mortar is spread thereon, has both been ensured to smear slurry speed or has been ensured the starching uniformity.
6. a kind of new stand according to claim 1 grouts wall telephone and construction method, it is characterised in that including following construction Step:
A) carry out the proportioning of binding material before masonry panel, the main component of conventional binding material be cement, yellow sand and Lime paste.Different material fits and material grading (i.e. weight ratio) can be selected as required.Here mixed mortar is used Exemplified by illustrate, optional stage is with being cement:Lime:Yellow sand=1:1:6.
B) lay bricks before wall, first base surface or or flooring on make each layer absolute altitude on schedule by standard water, and with cement mortar or C10 Pea gravel concreten is levelling.Architecture bottom layer wall body can be defined by axis location nail on sight rail and draw linen thread, under being hung along linen thread linen thread Plumb bob, wall body center line axis is put on base surface, and accordingly wall body central axis be defined ejection longitudinal cross wall line, and making at one's side Door-window opening position.To ensure the coincidence of each floor layer wall body axis, and it is consistent with foundation location axis, using advance pilot measurement Wall body central axis on wall face, so as to upward pilot measurement.The pilot measurement of axis is the key of unwrapping wire, it is necessary to chi by drawing It is very little to be checked with metallic tape.Then, by floor wall body center line, each wall sideline is ejected, marks door-window opening position.
C) further, by selected masoning method, pendulum brick sample (raw pendulum, i.e., do not spread ash) is tried in wall base top surface unwrapping wire position, to the greatest extent The modulus for making door and window pile meet brick is measured, deviation hour can be adjusted by perps, and brick quantity is cut to reduce, and ensure brick and brickwork joint row Row are neat, uniform, to improve efficiency of laying bricks.It is particularly important in dry wall is built by laying bricks or stones to put brick sample.
D) further, vertical marked rod can not had to again using semi-automatic stand paddle wall-building machine at this, manually building one layer of brick by laying bricks or stones Building by laying bricks or stones for two layers of wall brick is proceeded by afterwards, will be spread out sizing device (1) and is connected to the lowering or hoisting gear (7) of PLC is installed And it is placed on brick wall one end.
E) further, fixed glides (13) are stuck on one layer of brick, regulation regulating bolt makes it firmly be stuck on brick wall.
F) further, steel strand wires one end is connected on the draw ring of stand sizing device using steel strand wires (2), steel strand wires (2) pass through Movable support (3), adjuster (34) is fixed on brick by twisting bolt come the width of adjustment fixing plate (33) in movable support On the wall other end, fixed plate width is slightly larger than brick wall thickness, and support frame (32) on the one hand can support whole support body, on the other hand prop up Support can be rotated, and changed the position of bearing axle wheel, reached the space-saving function of actual conditions.
G) further, power shaft (4) is nearby installed, the power shaft is using low-power motor as power, steel on ground Twisted wire (2) is interior through steel strand wires fixator (41) access power shaft box (44).
H after) installing apparatus above, two layers of brick wall is proceeded by and are built by laying bricks or stones, started motor and start stand slurry, while manually upper brick, make Vertical mortar joint, which is carried out, with vertical upper pulpboard (6) smears slurry.
I) when the sensing chip in the fixed glides for spreading out sizing device touches the induction installation of movable support (3), lowering or hoisting gear (7) lifting is carried out according to original setting adjustable height, manual mobile lifting device (7) puts wall end initiating terminal and proceeds by three layers of brick Starching, next built by laying bricks or stones as two layers of brick wall building method carry out three layers of brick wall.
CN201710888462.5A 2017-09-27 2017-09-27 Semi-automatic stand paddle wall-building machine and construction method Pending CN107401285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710888462.5A CN107401285A (en) 2017-09-27 2017-09-27 Semi-automatic stand paddle wall-building machine and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710888462.5A CN107401285A (en) 2017-09-27 2017-09-27 Semi-automatic stand paddle wall-building machine and construction method

Publications (1)

Publication Number Publication Date
CN107401285A true CN107401285A (en) 2017-11-28

Family

ID=60388521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710888462.5A Pending CN107401285A (en) 2017-09-27 2017-09-27 Semi-automatic stand paddle wall-building machine and construction method

Country Status (1)

Country Link
CN (1) CN107401285A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107654078A (en) * 2017-11-29 2018-02-02 贵州兴贵恒远新型建材有限公司 A kind of mobile wall building equipment of building block assembled wall
CN110792275A (en) * 2019-11-29 2020-02-14 重庆科技学院 Movable wall building device
CN112854690A (en) * 2021-02-26 2021-05-28 中国十七冶集团有限公司 Masonry mortar joint standardized construction device and use method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB191125049A (en) * 1910-11-14 1911-12-21 Uberto Cagnassi Improvements in Machines for use in Building Walls and the like.
EP1221516A2 (en) * 2000-11-06 2002-07-10 Tubag Trass-, Zement- und Steinwerke Gmbh Method and device for application of a thin mortar bed
CN103953132A (en) * 2014-05-06 2014-07-30 株洲博尔曼科技发展有限公司 Novel construction method for concrete block masonry wall
CN105863229A (en) * 2016-04-19 2016-08-17 长江师范学院 Building external wall surface brick paving machine
CN206053379U (en) * 2016-08-31 2017-03-29 山西四建集团有限公司 A kind of particular manufacturing craft for improving masonry mortar joint construction quality
CN206205466U (en) * 2016-09-29 2017-05-31 中冶天工集团天津有限公司 A kind of masonry mortar lying device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB191125049A (en) * 1910-11-14 1911-12-21 Uberto Cagnassi Improvements in Machines for use in Building Walls and the like.
EP1221516A2 (en) * 2000-11-06 2002-07-10 Tubag Trass-, Zement- und Steinwerke Gmbh Method and device for application of a thin mortar bed
CN103953132A (en) * 2014-05-06 2014-07-30 株洲博尔曼科技发展有限公司 Novel construction method for concrete block masonry wall
CN105863229A (en) * 2016-04-19 2016-08-17 长江师范学院 Building external wall surface brick paving machine
CN206053379U (en) * 2016-08-31 2017-03-29 山西四建集团有限公司 A kind of particular manufacturing craft for improving masonry mortar joint construction quality
CN206205466U (en) * 2016-09-29 2017-05-31 中冶天工集团天津有限公司 A kind of masonry mortar lying device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107654078A (en) * 2017-11-29 2018-02-02 贵州兴贵恒远新型建材有限公司 A kind of mobile wall building equipment of building block assembled wall
CN107654078B (en) * 2017-11-29 2024-04-19 盛德力建筑工程(广东)有限公司 Movable wall building equipment for building block assembly type wall body
CN110792275A (en) * 2019-11-29 2020-02-14 重庆科技学院 Movable wall building device
CN110792275B (en) * 2019-11-29 2023-08-11 重庆科技学院 Movable wall building device
CN112854690A (en) * 2021-02-26 2021-05-28 中国十七冶集团有限公司 Masonry mortar joint standardized construction device and use method

Similar Documents

Publication Publication Date Title
CN107401285A (en) Semi-automatic stand paddle wall-building machine and construction method
CN104278841B (en) The method of casting concrete in steel pipe column
CN107327128A (en) One kind white washed wall device
CN107859232A (en) A kind of sand aerated concrete sheet material of built-in line box line pipe and preparation method thereof
CN106638940A (en) Fabricated high-rise residence precast concrete component construction method
CN111075165A (en) Wall cement patching machine
CN110924692A (en) Masonry pipeline direct-buried construction method
US20200248427A1 (en) Composite slotting equipment combined static pressure and vibration of polymer anti-seepage wall and using method thereof
CN107605177A (en) The construction method of efficient precast floor slab and its independent support frame
CN201202281Y (en) Vibrating formwork walling machine
CN106083150A (en) Self-heat conserving autoclaved lightweight sand aerated concrete block and wall construction technique thereof
CN104343239A (en) Electric threading pipe dark laying construction technology for aerated concrete filler wall punching
CN107806114A (en) Basement roof closes late poured band structure and construction method in advance
CN108951840A (en) Based on setting bracket single side formwork basement arc external wall construction method
CN201187143Y (en) Multifunctional grouting apparatus
CN104846745B (en) Urban high-pier support-free formwork turnover construction method
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN217484327U (en) Quick testing arrangement of concrete slump
CN113668820B (en) Composite inorganic building thermal insulation mortar construction system and construction method thereof
CN109057343A (en) A kind of building concrete pouring procedure
CN201649569U (en) Automatic wall plasterer
CN109183821A (en) A kind of quick detachable predetermined level precipitation well construction and construction method
CN113914530B (en) Inclined roof fish scale type concrete structure and construction method
CN216340729U (en) Ceramic tile laying mechanism
CN206158117U (en) Wall ground floating screed instrument of making level

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171128

WD01 Invention patent application deemed withdrawn after publication