CN107386632B - A kind of aluminum alloy mould plate pedestal - Google Patents
A kind of aluminum alloy mould plate pedestal Download PDFInfo
- Publication number
- CN107386632B CN107386632B CN201710571152.0A CN201710571152A CN107386632B CN 107386632 B CN107386632 B CN 107386632B CN 201710571152 A CN201710571152 A CN 201710571152A CN 107386632 B CN107386632 B CN 107386632B
- Authority
- CN
- China
- Prior art keywords
- aluminum alloy
- mould plate
- alloy mould
- positioning screw
- fixed strip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/04—Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
Abstract
The invention discloses a kind of aluminum alloy mould plate pedestals, including the fixed strip (3) for being connect with the top of next layer of wall or the aluminum alloy mould plate (1) on column two sides, and the side of fixed strip (3) can be connect by bolt with the slab form (2) for pouring build floor, positioning screw (4) are connected at the top of fixed strip (3), control strip (5) are connected at the top of positioning screw (4), bridging there are connecting rod (6) between the control strip (5) being located above two sides aluminum alloy mould plate (1).The aluminum alloy mould plate of this layer is connect by the present invention with this layer of slab form and next layer of aluminum alloy mould plate, and the reliability of connection greatly improved.Meanwhile the present invention uses the composite structure of positioning screw and control strip, the installation site of aluminum alloy mould plate can be accurately positioned, improves integrally-built reliability, it is effectively guaranteed that the pouring quality of concrete.
Description
Technical field
The present invention relates to a kind of aluminum alloy mould plate pedestals, belong to building template technical field.
Background technique
With the development of construction industry, requirement of the construction unit to construction quality is higher and higher.Currently, aluminum alloy mould plate due to
It is higher to recycle utilization rate, is widely used in construction.But in the actual construction process, using aluminium in the prior art
When alloy templates pour building wall or column, it is difficult that the aluminum alloy mould plate of this floor wall or column will be poured and pours next layer of wall or column
Aluminum alloy mould plate contraposition arrangement, and the existing aluminum alloy mould plate for pouring walling or column there is also the reliability of connection structure compared with
The problem of difference, directly affects the pouring quality of concrete.
Summary of the invention
The aluminum alloy mould plate for pouring upper one layer of wall or column and next layer of wall can will be poured the object of the present invention is to provide a kind of
Or the aluminum alloy mould plate alignment and the reliable aluminum alloy mould plate pedestal of connection of column, with overcome the deficiencies in the prior art.
The present invention is implemented as follows:
A kind of aluminum alloy mould plate pedestal of the invention is, the aluminum alloy mould plate pedestal include for next layer of wall or column two
The fixed strip of the top connection of the aluminum alloy mould plate in face, and the side of fixed strip can be with the floor that pours build floor by bolt
Template connection, positioning screw is connected at the top of fixed strip, control strip is connected at the top of positioning screw, is being located at two sides
Bridging has connecting rod between control strip above aluminum alloy mould plate.
Above-mentioned connecting rod is continuously arranged in zigzag.
Bolt of the above-mentioned positioning screw by support sleeve and with nut forms, and support sleeve can cover on bolt.
By adopting the above-described technical solution, compared with prior art, the present invention passes through fixed strip and control strip for this layer
Aluminum alloy mould plate for being poured wall or column is connect with the aluminum alloy mould plate for pouring next layer of wall or column, not only ensure that two floors
The aluminum alloy mould plate for pouring walling or column pour plane in the same plane, but also aluminum alloy mould plate company greatly improved
The reliability connect.Meanwhile the present invention uses the composite structure of positioning screw and control strip, and the peace of aluminum alloy mould plate can be accurately positioned
Holding position improves integrally-built reliability, it is effectively guaranteed that the pouring quality of concrete.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the overlooking structure diagram of Fig. 1;
Fig. 3 is the structural schematic diagram of positioning screw of the invention.
The label of attached drawing are as follows: the two sides 1- aluminum alloy mould plate, this layer of slab form of 2-, 3- fixed strip, 4- positioning screw, 5- control
Item processed, 6- connecting rod, 7- bolt or pin.
Specific embodiment
The embodiment of the present invention: the present invention is according to a kind of following positioning sides for pouring upper walls or column aluminum alloy mould plate
Method is constructed and for this method, this method be include the wall or column that multi-storey building is poured using existing aluminum alloy mould plate,
When it is implemented, as shown in Figure 1, existing in advance in the wall or column for the next level for pouring multi-storey building using aluminum alloy mould plate
The top for pouring the aluminum alloy mould plate 1 on the wall of lower first floor or the two sides of column is separately connected a fixed strip 3, and will be used to pour
The slab form 2 of floor is connect with the fixed strip 3, then installs positioning screw 4 at the top of each fixed strip 3,
The top of positioning screw 4 connects upper control strip 5, and make control strip 5 pour plane and aluminum alloy mould plate 1 pour plane setting
In the same plane, it can thus be positioned by aluminum alloy mould plate of the control strip 5 to the wall or column that pour next level,
I.e. on the wall or column for pouring next level, fixation is bolted in the aluminum alloy mould plate of the wall or column that pour next level
On control strip 5, and make its cast plane and control strip 5 pour plane it is concordant after, i.e., the certifiable next level poured out
Wall or column plane and lower first floor wall or column plane in the same plane.
A kind of structural schematic diagram of aluminum alloy mould plate pedestal for the above method of the invention is as shown in FIG. 1 to 3, should
Aluminum alloy mould plate pedestal includes the fixed strip 3 for connecting with the top of next layer of wall or the aluminum alloy mould plate 1 on column two sides, and
The side of fixed strip 3 can be connect by bolt with the slab form 2 for pouring build floor, and positioning spiral shell is connected at the top of fixed strip 3
Bar 4 is connected with control strip 5 at the top of positioning screw 4, in the span for the control strip 5 being located above two sides aluminum alloy mould plate 1
It is connected to connecting rod 6;The fixed strip 3, control strip 5 can be using conventional channel steels or aluminium profile;Its positioning screw 4 by
Support sleeve 4.1 and bolt 4.2 with nut form, and when production should enable support sleeve 4.1 actively cover on bolt 4.2 (such as
Shown in Fig. 3);Conventional bolt or pin 7 can be used to be attached when implementation, between all parts of the present invention.
When construction, before this layer of floor concrete casting, aluminum alloy mould plate pedestal of the invention is loaded onto advance, can be made in this way
This layer of aluminum alloy mould plate can be stably installed on control strip 5.
In order to further increase connective stability of the invention, as shown in Fig. 2, the connecting rod 6 can be connected in zigzag
Continuous arrangement has been thusly-formed the rock-steady structure of multiple triangle connections.
Embodiments of the present invention are not limited to the above embodiments, the various changes made under the premise of not departing from invention objective
Change the protection scope for belonging to invention.
Claims (1)
1. a kind of aluminum alloy mould plate pedestal, it is characterised in that: including for the aluminum alloy mould plate (1) with next layer of wall or column two sides
Top connection fixed strip (3), and the side of fixed strip (3) can be with the slab form (2) that pours build floor by bolt
Connection is connected with positioning screw (4) at the top of fixed strip (3), is connected with control strip (5) at the top of positioning screw (4), respectively
Bridging has connecting rod (6) between control strip (5) above two sides aluminum alloy mould plate (1);The connecting rod (6) is in Z-shaped
Shape is continuously arranged;Bolt (4.2) of the positioning screw (4) by support sleeve (4.1) and with nut forms, and support sleeve (4.1) can cover
On bolt (4.2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710571152.0A CN107386632B (en) | 2013-12-21 | 2013-12-21 | A kind of aluminum alloy mould plate pedestal |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310709281.3A CN104727547B (en) | 2013-12-21 | 2013-12-21 | Pour the localization method of upper walls or post aluminum alloy mould plate |
CN201710571152.0A CN107386632B (en) | 2013-12-21 | 2013-12-21 | A kind of aluminum alloy mould plate pedestal |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310709281.3A Division CN104727547B (en) | 2013-12-21 | 2013-12-21 | Pour the localization method of upper walls or post aluminum alloy mould plate |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107386632A CN107386632A (en) | 2017-11-24 |
CN107386632B true CN107386632B (en) | 2019-10-25 |
Family
ID=53451900
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310709281.3A Active CN104727547B (en) | 2013-12-21 | 2013-12-21 | Pour the localization method of upper walls or post aluminum alloy mould plate |
CN201710571152.0A Active CN107386632B (en) | 2013-12-21 | 2013-12-21 | A kind of aluminum alloy mould plate pedestal |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310709281.3A Active CN104727547B (en) | 2013-12-21 | 2013-12-21 | Pour the localization method of upper walls or post aluminum alloy mould plate |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN104727547B (en) |
Family Cites Families (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1122685A (en) * | 1966-04-29 | 1968-08-07 | Rapid Metal Developments Ltd | Joints between formwork panels |
JP2923238B2 (en) * | 1996-02-16 | 1999-07-26 | 株式会社サンレール | Veranda and its construction method |
US6044614A (en) * | 1996-05-08 | 2000-04-04 | Newtec Concrete Construction Pty Limited | Sequential formwork system for concrete buildings |
CN2672205Y (en) * | 2003-11-04 | 2005-01-19 | 陈赖美铃 | Adjustable building formwork base structure |
KR100917833B1 (en) * | 2009-02-24 | 2009-09-18 | (주)금산씨앤아이 | Form fixing structure for constructing pillar |
CN102425310B (en) * | 2011-12-15 | 2014-02-19 | 中国二十二冶集团有限公司 | Assembly-type residential shear wall structural wall body vertical connection construction method |
CN102561695A (en) * | 2012-01-04 | 2012-07-11 | 广东建星建筑工程有限公司 | Construction method for building buildings by aluminum templates |
CN102808509B (en) * | 2012-08-22 | 2014-09-24 | 中国建筑股份有限公司 | Assembled concrete prefabricated outer hanging wall plate anchoring component and pouring construction method thereof |
CN102926530B (en) * | 2012-11-15 | 2015-05-20 | 福建安厦新型建筑模板制造有限公司 | Steel frame formwork assembly |
CN203097292U (en) * | 2013-02-28 | 2013-07-31 | 歌山建设集团有限公司 | Plugging device of formwork screw rod hole |
CN103206089A (en) * | 2013-04-18 | 2013-07-17 | 成军 | Fabricated aluminum alloy formwork system construction method |
CN203626247U (en) * | 2013-12-21 | 2014-06-04 | 中建四局第三建筑工程有限公司 | Aluminum alloy formwork base for pouring upper-storey wall/column |
-
2013
- 2013-12-21 CN CN201310709281.3A patent/CN104727547B/en active Active
- 2013-12-21 CN CN201710571152.0A patent/CN107386632B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104727547B (en) | 2017-11-03 |
CN107386632A (en) | 2017-11-24 |
CN104727547A (en) | 2015-06-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020118563A1 (en) | Design and rapid construction methods for flush assembly of prefabricated steel beams and floor | |
CN204298825U (en) | Foundation ditch builds elephant trunk supporting and regulating device | |
CN103104090B (en) | Silo concrete whole slip template | |
CN203905233U (en) | Open type dry hanging clay plate curtain wall installation construction structure | |
CN101701494B (en) | Detachable convenient support device of steel structure building template and use method thereof | |
CN103362069A (en) | Steel and concrete combined box girder concrete wing plate formwork and construction method | |
CN208343121U (en) | Prefabricated assembled steel structure concrete wallboard mould | |
CN107386632B (en) | A kind of aluminum alloy mould plate pedestal | |
CN105256923B (en) | Light steel keel partition ground joist fixedly connected part | |
CN201539098U (en) | Detachable convenient support device of steel structure building template | |
CN206267520U (en) | A kind of self-supporting post-cast strip is poured with hanging mould | |
CN105839914A (en) | Adjustable steel beam supporting device and adjustable steel beam supporting system | |
CN203626247U (en) | Aluminum alloy formwork base for pouring upper-storey wall/column | |
CN207244961U (en) | A kind of Prefabricated stacking floor with side flanging for being used to drop plate region | |
CN202831621U (en) | Integrated slipform for silo concrete | |
CN205976472U (en) | Pour mould of building post -cast strip | |
CN203531380U (en) | Size-adjustable formwork system with local supports arranged bellow beam and no support arranged below plate | |
CN202031328U (en) | Fixing device of outer formwork for casting outer concrete wall on floor slab of building | |
CN207244957U (en) | A kind of modularization Prefabricated stacking floor for being used to drop plate region | |
CN103410312A (en) | Template system beam partially supported, plate free of supporting and size adjustable | |
CN105350719A (en) | Large span post-pouring belt early-dismantled mould additionally installed temporary constructional column construction method | |
CN205822778U (en) | A kind of huge post of stiffness is without screw aluminum alloy formwork system | |
CN204040449U (en) | A kind of built-in fitting of Cantilever Beams scaffold | |
CN202969924U (en) | Stair step formwork frame | |
CN212294363U (en) | Integral template for T-beam pouring |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: Beijing road 563000 in Guizhou province Zunyi city Honghuagang District No. 57 Patentee after: The Third Construction Co., Ltd. of China Construction Fourth Engineering Bureau Address before: Beijing road 563003 in Guizhou province Zunyi city Honghuagang District No. 57 Patentee before: THE THIRD CONSTRUCTION & ENGINEERING CO. OF CCFED |
|
CP03 | Change of name, title or address |