CN103362069A - Steel and concrete combined box girder concrete wing plate formwork and construction method - Google Patents
Steel and concrete combined box girder concrete wing plate formwork and construction method Download PDFInfo
- Publication number
- CN103362069A CN103362069A CN2013103285431A CN201310328543A CN103362069A CN 103362069 A CN103362069 A CN 103362069A CN 2013103285431 A CN2013103285431 A CN 2013103285431A CN 201310328543 A CN201310328543 A CN 201310328543A CN 103362069 A CN103362069 A CN 103362069A
- Authority
- CN
- China
- Prior art keywords
- steel
- plate
- concrete
- support
- box girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
一种钢混结合箱梁混凝土翼板模板及施工方法。模板包括多根支撑横梁、多根支撑纵梁、两列支撑立柱、多根拉杆、多个螺母、多片垫片、多条纵楞、多个钢盖板托架和多块钢盖板。本发明的钢混结合箱梁混凝土翼板模板及施工方法是在已架设好的钢箱梁顶板上设置钢盖板,使钢盖板与钢箱梁形成模板体系,不仅能够解决跨路施工无支架施工的问题,而且在具体施工中,无需大型吊装设备配合,仅需人工操作即可完成安装,并且能够非常方便、精确地调节底模标高,所以精度高。另外对于不同尺寸的翼板,只需制作不同规格的模板设备,所用模板设备材料较少,均为常用工程用结构钢,加工难度小,使用简单,有利于现场施工使用,因此能够缩短工期,施工成本低。
A steel-concrete combined box girder concrete wing plate formwork and a construction method thereof. The template includes a plurality of supporting beams, a plurality of supporting longitudinal beams, two columns of supporting columns, a plurality of tie rods, a plurality of nuts, a plurality of gaskets, a plurality of flutes, a plurality of steel cover plate brackets and a plurality of steel cover plates. The steel-concrete combined box girder concrete wing plate formwork and construction method of the present invention is to install a steel cover plate on the top plate of the steel box girder that has been erected, so that the steel cover plate and the steel box girder form a formwork system, which can not only solve the problem of cross-road construction. The problem of bracket construction, and in the specific construction, there is no need for large-scale hoisting equipment to cooperate, and the installation can be completed only by manual operation, and the elevation of the bottom mold can be adjusted very conveniently and accurately, so the precision is high. In addition, for wing plates of different sizes, it is only necessary to make formwork equipment of different specifications. The formwork equipment materials used are less, and they are all commonly used engineering structural steel. The construction cost is low.
Description
技术领域technical field
本发明属于桥梁建设辅助设备技术领域,特别是涉及一种钢混结合箱梁混凝土翼板模板及施工方法。The invention belongs to the technical field of bridge construction auxiliary equipment, in particular to a steel-concrete combined box girder concrete wing plate template and a construction method.
技术背景technical background
随着桥梁建设的飞速发展,钢混结合箱梁屡见不鲜。翼板是钢混结合箱梁的主要组成部分,而翼板模板则成为钢混结合箱梁施工的重要构件。目前常用的翼板施工方法是采用支架法在主路上搭设门洞状翼板模板体系进行施工作业。但这种方法需要吊车的配合,同时要求桥下必须有符合吊装作业的场地,而且吊装作业对道路的交通影响较大,另外占路吊装时对吊车司机的要求也很高,因此,在桥下吊车作业场地选取困难的情况下,翼板模板安装将极为困难。另外,这种施工方法对于车流量较大的主路来说,不仅施工安全难以保证,并且由于支架法施工安装及拆除支架周期较长,从而导致施工成本增加。此外,该方法进行翼板施工时安全风险也较大。With the rapid development of bridge construction, steel-concrete combined box girders are common. The wing plate is the main component of the steel-concrete box girder, and the wing plate formwork becomes an important component in the construction of the steel-concrete box girder. At present, the commonly used wing plate construction method is to use the bracket method to set up a door-shaped wing plate formwork system on the main road for construction work. However, this method requires the cooperation of the crane, and at the same time requires that there must be a site suitable for the hoisting operation under the bridge, and the hoisting operation has a great impact on the road traffic. When it is difficult to select the working site for the crane, the installation of the wing plate formwork will be extremely difficult. In addition, this construction method is not only difficult to guarantee the construction safety for the main road with a large traffic flow, but also increases the construction cost due to the long period of installation and removal of the support in the construction of the support method. In addition, the safety risk is also relatively large when the method is used for wing construction.
发明内容Contents of the invention
为了解决上述问题,本发明的目的在于提供一种制作简易、使用方便,并且精度高、能够缩短工期的钢混结合箱梁混凝土翼板模板及施工方法。In order to solve the above problems, the object of the present invention is to provide a steel-concrete combined box girder concrete wing formwork and a construction method that is easy to manufacture, easy to use, high in precision, and can shorten the construction period.
为了达到上述目的,本发明提供的钢混结合箱梁混凝土翼板模板包括多根支撑横梁、多根支撑纵梁、两列支撑立柱、多根拉杆、多个螺母、多片垫片、多条纵楞、多个钢盖板托架和多块钢盖板;其中两列支撑立柱沿桥的纵向等间距对称安装在两片已架设好的钢箱梁的顶板外侧边缘上,上端顶面上设有钢板,并且钢板上水平安装有一根与支撑立柱排列方向相同的支撑纵梁;多根支撑横梁沿桥的横向等间距水平安装在支撑纵梁的顶部;钢盖板托架为杆状结构,下端形成有一个挂钩,每根支撑横梁的两端分别利用联结螺栓与一个钢盖板托架的中部相连接,并且挂钩上的钩尖向内;作为底模的钢盖板一端置于一片钢箱梁的顶板外侧边缘上,另一端置于与该钢箱梁同一侧的多个钢盖板托架的挂钩上;多根支撑横梁的顶端上位于钢盖板正上方的部位设置至少两条纵楞;拉杆垂直贯穿纵楞和支撑横梁设置,并且下端连接在钢盖板上,上端利用垫片和螺母固定。In order to achieve the above purpose, the steel-concrete combined box girder concrete wing formwork provided by the present invention includes multiple supporting beams, multiple supporting longitudinal beams, two columns of supporting columns, multiple tie rods, multiple nuts, multiple gaskets, multiple Longitudinal corrugation, multiple steel cover plate brackets and multiple steel cover plates; two rows of supporting columns are symmetrically installed on the outer edge of the top plate of the two steel box girders that have been erected along the longitudinal direction of the bridge, and the top surface of the upper end A steel plate is provided, and a supporting longitudinal beam is horizontally installed on the steel plate in the same direction as the supporting column; multiple supporting beams are horizontally installed on the top of the supporting longitudinal beam at equal intervals along the transverse direction of the bridge; the steel cover plate bracket is a rod-shaped structure , a hook is formed at the lower end, and the two ends of each supporting beam are respectively connected with the middle part of a steel cover plate bracket by connecting bolts, and the hook tip on the hook faces inward; one end of the steel cover plate as the bottom mold is placed in a On the outer edge of the top plate of the steel box girder, the other end is placed on the hooks of multiple steel cover plate brackets on the same side as the steel box girder; at least two The longitudinal corrugation; the tie rods are vertically set through the longitudinal corrugation and the supporting beam, and the lower end is connected to the steel cover plate, and the upper end is fixed by a gasket and a nut.
所述的支撑立柱与钢箱梁的顶板、支撑纵梁和支撑立柱顶面上的钢板、支撑横梁和支撑纵梁之间的连接均采用焊接方式。The connection between the support column and the top plate of the steel box girder, the support longitudinal beam and the steel plate on the top surface of the support column, the support beam and the support longitudinal beam all adopts welding method.
所述的支撑立柱、支撑纵梁和支撑横梁均由两根槽钢并列焊接而制成。The supporting columns, supporting longitudinal beams and supporting beams are all made by welding two channel steels side by side.
本发明提供的钢混结合箱梁混凝土翼板模板施工方法包括按顺序进行的下列步骤:The steel-concrete combined box girder concrete wing plate formwork construction method provided by the invention includes the following steps carried out in order:
1)首先在两片已架设好的钢箱梁的顶板外侧边缘上沿桥的纵向对称安装两列支撑立柱,下端焊接在钢箱梁的顶板上,并在上端顶面上设置钢板;1) First, install two rows of supporting columns symmetrically along the longitudinal direction of the bridge on the outer edge of the roof of the two steel box girders that have been erected.
2)在每列支撑立柱顶面的钢板上安装一根与支撑立柱排列方向相同的支撑纵梁,下端焊接在支撑立柱上;2) Install a support longitudinal beam in the same direction as the support column on the steel plate on the top surface of each row of support columns, and weld the lower end to the support column;
3)在支撑纵梁的顶部沿桥的横向等间距水平安装多根支撑横梁,下端焊接在支撑纵梁上;3) On the top of the supporting longitudinal beams, multiple supporting beams are installed horizontally at equal intervals along the transverse direction of the bridge, and the lower ends are welded to the supporting longitudinal beams;
4)在每根支撑横梁的两端分别利用联结螺栓与一个钢盖板托架的中部相连接,并且钢盖板托架上挂钩的钩尖向内;4) Connect the two ends of each supporting beam with the middle part of a steel cover bracket with connecting bolts, and the hook tip of the hook on the steel cover bracket faces inward;
5)将钢盖板的一端置于一片钢箱梁的顶板外侧边缘上,另一端置于与该钢箱梁同一侧的多个钢盖板托架的挂钩上,以将钢盖板临时固定;5) Place one end of the steel cover plate on the outer edge of the top plate of a steel box girder, and place the other end on the hooks of multiple steel cover plate brackets on the same side as the steel box girder to temporarily fix the steel cover plate ;
6)在多根支撑横梁的顶端上位于钢盖板正上方的部位设置至少两条纵楞,然后将拉杆同时贯穿纵楞和支撑横梁,并将其下端连接在钢盖板上;6) Set at least two longitudinal corrugations on the top of multiple supporting beams directly above the steel cover, and then connect the tie rods through the longitudinal corrugations and supporting beams at the same time, and connect their lower ends to the steel cover;
7)利用旋转拉杆的方式来调节钢盖板的标高,标高调整完成后将拉杆的上端利用垫片和螺母固定在纵楞上;7) Use the method of rotating the pull rod to adjust the elevation of the steel cover plate. After the adjustment of the elevation is completed, fix the upper end of the pull rod on the longitudinal corrugation with gaskets and nuts;
8)将钢盖板与钢箱梁的顶板接触处焊接固定,由此制成钢混结合箱梁混凝土翼板模板;8) Weld and fix the contact between the steel cover plate and the top plate of the steel box girder, thus making the steel-concrete combined box girder concrete wing plate formwork;
9)最后在钢盖板上方的空间中绑扎混凝土翼板钢筋并浇注混凝土,待混凝土达到设计强度后即形成混凝土翼板,最后按照上述步骤相反的次序拆除本钢混结合箱梁混凝土翼板模板即可完成施工过程。9) Finally, in the space above the steel cover slab, bind the reinforcement of the concrete wing slab and pour concrete. After the concrete reaches the design strength, the concrete wing slab will be formed. Finally, the concrete wing slab formwork of the steel-concrete combined box girder will be removed in the reverse order of the above steps. The construction process can be completed.
所述的支撑立柱、支撑纵梁和支撑横梁均采用两根20号槽钢并列焊接在一起而构成;纵楞采用10号槽钢;拉杆采用20号精轧螺纹钢。The support columns, support longitudinal beams and support beams are all formed by welding two No. 20 channel steels side by side; the longitudinal corrugations use No. 10 channel steels;
本发明提供的钢混结合箱梁混凝土翼板模板及施工方法是在已架设好的钢箱梁顶板上设置钢盖板,使钢盖板与钢箱梁形成模板体系,不仅能够解决跨路施工无支架施工的问题,而且在具体施工中,无需大型吊装设备配合,仅需人工操作即可完成安装,并且能够非常方便、精确地调节底模标高,所以精度高。另外对于不同尺寸的翼板,只需制作不同规格的模板设备,所用模板设备材料较少,均为常用工程用结构钢,加工难度小,使用简单,有利于现场施工使用,因此能够缩短工期,施工成本低。The steel-concrete combined box girder concrete wing slab formwork and construction method provided by the invention are to install a steel cover plate on the top plate of the erected steel box girder, so that the steel cover plate and the steel box girder form a formwork system, which can not only solve the problem of cross-road construction There is no problem with the construction of the bracket, and in the specific construction, there is no need for large-scale hoisting equipment to cooperate, and the installation can be completed only by manual operation, and the elevation of the bottom mold can be adjusted very conveniently and accurately, so the precision is high. In addition, for wing plates of different sizes, it is only necessary to make formwork equipment of different specifications. The formwork equipment materials used are less, and they are all commonly used engineering structural steel. The processing difficulty is small, the use is simple, and it is conducive to on-site construction. The construction cost is low.
附图说明Description of drawings
图1为本发明提供的钢混结合箱梁混凝土翼板模板结构立面图。Fig. 1 is the elevation view of the formwork structure of the steel-concrete combined box girder concrete wing plate provided by the present invention.
图2为本发明提供的钢混结合箱梁混凝土翼板模板结构平面图。Fig. 2 is a structural plan view of the steel-concrete combined box girder concrete wing plate formwork provided by the present invention.
具体实施方式Detailed ways
下面结合附图和具体实施例对本发明提供的钢混结合箱梁混凝土翼板模板及施工方法进行详细说明。The steel-concrete combined box girder concrete wing plate template and construction method provided by the present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.
现以某工程为例进行说明:该工程位于北京五环路上方,梅市口公路桥中间,采用36m钢混结合箱梁。由于箱梁上跨五环路施工,施工过程受五环路上行车的影响,混凝土翼板的施工难度非常大,施工时考虑翼板底模采用不拆钢模板形式,以此来减小跨五环路施工的难度。钢箱梁两侧翼板长2.358m,因此钢混结合梁混凝土翼板模板单块设置长2.358m。Now take a certain project as an example: the project is located above the Fifth Ring Road in Beijing, in the middle of the Meishikou Highway Bridge, and uses a 36m steel-concrete combined box girder. Due to the construction of the box girder spanning the Fifth Ring Road, the construction process is affected by the traffic on the Fifth Ring Road, and the construction of the concrete wing plate is very difficult. During construction, it is considered that the bottom formwork of the wing plate should be in the form of non-demolition steel formwork, so as to reduce the span of five rings. Difficulty of ring road construction. The length of the flanges on both sides of the steel box girder is 2.358m, so the length of the concrete flange formwork of the steel-concrete composite beam is 2.358m.
如图1-图2所示,本发明提供的钢混结合箱梁混凝土翼板模板包括多根支撑横梁1、多根支撑纵梁2、两列支撑立柱3、多根拉杆4、多个螺母5、多片垫片6、多条纵楞7、多个钢盖板托架8和多块钢盖板10;其中两列支撑立柱3沿桥的纵向等间距对称安装在两片已架设好的钢箱梁11的顶板外侧边缘上,上端顶面上设有钢板,并且钢板上水平安装有一根与支撑立柱3排列方向相同的支撑纵梁2;多根支撑横梁1沿桥的横向等间距水平安装在支撑纵梁2的顶部;钢盖板托架8为杆状结构,下端形成有一个挂钩12,每根支撑横梁1的两端分别利用联结螺栓9与一个钢盖板托架8的中部相连接,并且挂钩12上的钩尖向内;作为底模的钢盖板10一端置于一片钢箱梁11的顶板外侧边缘上,另一端置于与该钢箱梁11同一侧的多个钢盖板托架8的挂钩12上;多根支撑横梁1的顶端上位于钢盖板10正上方的部位设置至少两条纵楞7;拉杆4垂直贯穿纵楞7和支撑横梁1设置,并且下端连接在钢盖板10上,上端利用垫片6和螺母5固定。As shown in Figures 1-2, the steel-concrete combined box girder concrete wing formwork provided by the present invention includes multiple supporting
所述的支撑立柱3与钢箱梁11的顶板、支撑纵梁2和支撑立柱3顶面上的钢板、支撑横梁1和支撑纵梁2之间的连接均采用焊接方式。The connections between the
所述的支撑立柱3、支撑纵梁2和支撑横梁1由两根槽钢并列焊接而制成。The supporting
所述的相邻支撑横梁1之间的距离为1.250m。The distance between the adjacent supporting
本发明提供的钢混结合箱梁混凝土翼板模板施工方法包括按顺序进行的下列步骤:The steel-concrete combined box girder concrete wing plate formwork construction method provided by the invention includes the following steps carried out in order:
1)首先在两片已架设好的钢箱梁11的顶板外侧边缘上沿桥的纵向对称安装两列支撑立柱3,支撑立柱3采用两根20号槽钢并列焊接在一起而构成,下端焊接在钢箱梁11的顶板上,并在上端顶面上设置钢板;1) First, install two rows of supporting
2)在每列支撑立柱3顶面的钢板上水平安装一根与支撑立柱3排列方向相同的支撑纵梁2,支撑纵梁2采用两根20号槽钢并列焊接在一起而构成,下端焊接在支撑立柱3上;2) On the steel plate on the top surface of each
3)在支撑纵梁2的顶部沿桥的横向等间距水平安装多根支撑横梁1,支撑横梁1采用两根20号槽钢并列焊接在一起而构成,下端焊接在支撑纵梁2上,相邻支撑横梁1之间的距离为1.250m;3) Multiple supporting
4)在每根支撑横梁1的两端分别利用联结螺栓9与一个钢盖板托架8的中部相连接,并且钢盖板托架8上挂钩12的钩尖向内;4) The two ends of each supporting
5)将钢盖板10的一端置于一片钢箱梁11的顶板外侧边缘上,另一端置于与该钢箱梁11同一侧的多个钢盖板托架8的挂钩12上,以将钢盖板10临时固定;5) Place one end of the
6)在多根支撑横梁1的顶端上位于钢盖板10正上方的部位设置至少两条纵楞7,纵楞7采用10号槽钢,然后将拉杆4同时贯穿纵楞7和支撑横梁1,拉杆4采用20号精轧螺纹钢,并将其下端连接在钢盖板10上;6) Set at least two longitudinal corrugations 7 at the top of the multiple supporting
7)利用旋转拉杆4的方式来调节钢盖板10的标高,标高调整完成后将拉杆4的上端利用垫片6和螺母5固定在纵楞7上;7) Adjust the elevation of the
8)将钢盖板10与钢箱梁11的顶板接触处焊接固定,由此制成钢混结合箱梁混凝土翼板模板;8) Weld and fix the contact between the
9)最后在钢盖板10上方的空间中绑扎混凝土翼板钢筋并浇注混凝土,待混凝土达到设计强度后即形成混凝土翼板,最后按照上述步骤相反的次序拆除本钢混结合箱梁混凝土翼板模板即可完成整个施工过程。9) Finally, in the space above the
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310328543.1A CN103362069B (en) | 2013-07-31 | 2013-07-31 | Steel-concrete combined box girder concrete wing plate formwork and construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310328543.1A CN103362069B (en) | 2013-07-31 | 2013-07-31 | Steel-concrete combined box girder concrete wing plate formwork and construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103362069A true CN103362069A (en) | 2013-10-23 |
| CN103362069B CN103362069B (en) | 2015-07-08 |
Family
ID=49364275
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310328543.1A Expired - Fee Related CN103362069B (en) | 2013-07-31 | 2013-07-31 | Steel-concrete combined box girder concrete wing plate formwork and construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103362069B (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103846597A (en) * | 2014-01-27 | 2014-06-11 | 中铁宝桥集团有限公司 | Integral assembling and welding device for mobile type steel box girder segments and adjusting method |
| CN106677068A (en) * | 2016-12-26 | 2017-05-17 | 中铁十九局集团第工程有限公司 | Construction method capable of preventing hollowing at box girder support plate |
| CN106758743A (en) * | 2017-02-28 | 2017-05-31 | 浙江大学 | It is a kind of to improve the method that steel reinforced concrete combines many case continuous bridge hogging moment area stress performances |
| CN110700112A (en) * | 2019-10-31 | 2020-01-17 | 广西路建工程集团有限公司 | Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method |
| CN110983987A (en) * | 2019-12-24 | 2020-04-10 | 德州市公路工程总公司 | Construction method of steel-concrete combined beam |
| CN112411390A (en) * | 2020-11-30 | 2021-02-26 | 中交路桥建设有限公司 | Concrete bracket for bridge deck of steel-concrete composite beam and construction method thereof |
| CN114232502A (en) * | 2022-01-18 | 2022-03-25 | 中铁十四局集团第三工程有限公司 | Self-propelled sliding formwork truss and using method thereof |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000087316A (en) * | 1998-09-10 | 2000-03-28 | Gifu Kogyo Kk | Method and device for construction of floor slab |
| CN103174095A (en) * | 2013-03-18 | 2013-06-26 | 中国建筑第八工程局有限公司 | Box girder concrete pouring structure with rear-expanding flanges and construction method thereof |
| CN203475310U (en) * | 2013-07-31 | 2014-03-12 | 中铁六局集团有限公司 | Formwork for concrete slabs of composite steel-concrete box girders |
-
2013
- 2013-07-31 CN CN201310328543.1A patent/CN103362069B/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000087316A (en) * | 1998-09-10 | 2000-03-28 | Gifu Kogyo Kk | Method and device for construction of floor slab |
| CN103174095A (en) * | 2013-03-18 | 2013-06-26 | 中国建筑第八工程局有限公司 | Box girder concrete pouring structure with rear-expanding flanges and construction method thereof |
| CN203475310U (en) * | 2013-07-31 | 2014-03-12 | 中铁六局集团有限公司 | Formwork for concrete slabs of composite steel-concrete box girders |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103846597A (en) * | 2014-01-27 | 2014-06-11 | 中铁宝桥集团有限公司 | Integral assembling and welding device for mobile type steel box girder segments and adjusting method |
| CN103846597B (en) * | 2014-01-27 | 2017-01-04 | 中铁宝桥集团有限公司 | Movable steel box girder segment integral assembling and welding equipment and adjusting method |
| CN106677068A (en) * | 2016-12-26 | 2017-05-17 | 中铁十九局集团第工程有限公司 | Construction method capable of preventing hollowing at box girder support plate |
| CN106758743A (en) * | 2017-02-28 | 2017-05-31 | 浙江大学 | It is a kind of to improve the method that steel reinforced concrete combines many case continuous bridge hogging moment area stress performances |
| CN110700112A (en) * | 2019-10-31 | 2020-01-17 | 广西路建工程集团有限公司 | Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method |
| CN110700112B (en) * | 2019-10-31 | 2024-09-13 | 广西路建工程集团有限公司 | Movable formwork for steel-concrete composite Liang Xuantiao wing plate concrete construction and construction method |
| CN110983987A (en) * | 2019-12-24 | 2020-04-10 | 德州市公路工程总公司 | Construction method of steel-concrete combined beam |
| CN110983987B (en) * | 2019-12-24 | 2021-07-13 | 德州市公路工程总公司 | Construction method of steel-concrete combined beam |
| CN112411390A (en) * | 2020-11-30 | 2021-02-26 | 中交路桥建设有限公司 | Concrete bracket for bridge deck of steel-concrete composite beam and construction method thereof |
| CN114232502A (en) * | 2022-01-18 | 2022-03-25 | 中铁十四局集团第三工程有限公司 | Self-propelled sliding formwork truss and using method thereof |
| CN114232502B (en) * | 2022-01-18 | 2023-09-29 | 中铁十四局集团第三工程有限公司 | Self-propelled sliding template truss and use method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103362069B (en) | 2015-07-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103362069B (en) | Steel-concrete combined box girder concrete wing plate formwork and construction method | |
| CN105696747A (en) | Construction method for aerial large-span reinforced concrete beam | |
| CN103161126A (en) | Road bridge variable section hollow high pier slip-form construction method | |
| CN101781878A (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
| CN103669655A (en) | Construction technology for pouring concrete of walls on two sides of deformation joint | |
| CN105649213B (en) | A kind of construction method of intensive cloth muscle area large-scale steel structure built-in fitting | |
| CN106522102A (en) | Side span construction support, rigid frame bridge side span and rigid frame bridge | |
| CN207878262U (en) | A kind of high pier shaft binder concrete construction strutting system | |
| CN202176343U (en) | Self-propelled multifunctional template trolley combining device | |
| CN106320183A (en) | Assembly type bent cap formwork system | |
| CN116290911A (en) | Post-pouring belt supporting device and construction method thereof | |
| CN203475310U (en) | Formwork for concrete slabs of composite steel-concrete box girders | |
| CN103321153A (en) | Construction method for medium and small span trough girder bridge | |
| CN207244460U (en) | A kind of reinforcing bar binding platform suitable for large size, thin walled hollow pier | |
| CN103572707A (en) | Box girder steel outer template and construction method thereof | |
| CN206625134U (en) | A kind of side form frock for cast-in-situ box girder | |
| CN206374016U (en) | A kind of prefabricated case beam framework of steel reinforcement fetal membrane | |
| CN204919605U (en) | Prefabricated assembled reinforced concrete utility tunnel and production mould thereof | |
| CN107386119A (en) | A kind of variable cross-section beam sections type variable framework of steel reinforcement construction moulding bed device | |
| CN207998793U (en) | A kind of multifunctional box shaped steel bracket structure | |
| CN204940144U (en) | A kind of Wavelike steel webplate temporary reinforcing device | |
| CN204081483U (en) | A kind of structure of rotten when preventing pouring reinforcement concrete post suspension column | |
| CN104153386B (en) | Pile foundation support table periphery facade bed course tool-type punching block and construction method thereof | |
| CN112008856A (en) | Be applied to bed-jig of prefabricated case roof beam framework of steel reinforcement shaping and bellows installation | |
| CN102587649A (en) | Template profiled bar supporting system of high and large cantilever structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150708 |