CN107386305A - Assembly concrete cofferdam and its construction method - Google Patents

Assembly concrete cofferdam and its construction method Download PDF

Info

Publication number
CN107386305A
CN107386305A CN201710544004.XA CN201710544004A CN107386305A CN 107386305 A CN107386305 A CN 107386305A CN 201710544004 A CN201710544004 A CN 201710544004A CN 107386305 A CN107386305 A CN 107386305A
Authority
CN
China
Prior art keywords
concrete
pull bar
board wall
wall module
modular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710544004.XA
Other languages
Chinese (zh)
Inventor
罗柳
崔成华
刘进
王雷
邓波
纪彬
阳建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201710544004.XA priority Critical patent/CN107386305A/en
Publication of CN107386305A publication Critical patent/CN107386305A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of assembly concrete cofferdam and its construction method, including the board wall module being assembled by several concrete modulars;Bed course is provided with the board wall module between bilevel concrete modular, and per the center alignment of layer concrete module in board wall module;It is connected between the board wall module by cast-in-site stripe, and in concrete foundation.The present invention is assembled into board wall module using several concrete modulars, board wall module is connected by cast-in-site stripe forms modular cofferdam, the characteristics of with being easy to remove and installing, and also repeat and utilize after concrete modular dismounting, in addition, structure of the present invention is novel, strong applicability, construction is simple, safe.

Description

Assembly concrete cofferdam and its construction method
Technical field
The present invention relates to cofferdam technical field, and in particular to be a kind of assembly concrete cofferdam and its construction method.
Background technology
In construction of hydro project field, concrete cofferdam is a kind of structure being often used, and is formed by concrete cofferdam Dry work environment, it is easy to agent structure thing to construct.But traditional concrete cofferdam is usually one-piece casting shaping, although structure It is firm, but remove difficulty and big, with high costs.
The content of the invention
The purpose of the present invention is easy to remove and repeats utilization in view of the above-mentioned problems of the prior art, providing one kind Assembly concrete cofferdam and its construction method.
To achieve the above object, the present invention adopts the following technical scheme that:
Assembly concrete cofferdam, it is characterised in that:Including the board wall module being assembled by several concrete modulars; Bed course is provided with the board wall module between bilevel concrete modular, and per layer concrete module in board wall module Center alignment;It is connected between the board wall module by cast-in-site stripe, and in concrete foundation.
In above-mentioned technical proposal, board wall module is assembled into using several concrete modulars, board wall module passes through cast-in-site stripe It is connected and forms modular cofferdam, facilitates cofferdam demolition and installation, and also repeat and utilize after concrete modular dismounting.
Further, the concrete modular is cuboid platy structure;The left and right side of the concrete modular is all provided with It is equipped with lifting hole(eyelet);The lifting hole(eyelet) is symmetrically distributed in the z of the left and right side of concrete modular to center line both sides, so, can be conveniently mixed The lifting installation and dismounting of solidifying clay model block.
Further, the lifting hole(eyelet) is 2, and is distributed in the y of the left and right side of concrete modular on center line.
Further, the upper and lower surface of the concrete modular is provided with the pull bar perforation of the insertion for installing pull bar; Pull bar perforation be symmetrically distributed in the x on the upper and lower surface of concrete modular to y to center line both sides, and in board wall module Run through up and down per the pull bar perforation in layer concrete module, so, pull bar can be conveniently installed, and between levels concrete module Tensed by pull bar, further increase structural stability.
Further, the pull bar perforation is 4, or for 8.
Further, the pull bar includes pre-buried pull bar and installation pull bar;The pre-buried pull bar is embedded in concrete foundation On;The installation pull bar passes through the pull bar perforation mutually run through in every layer concrete module in board wall module and pre-buried pull bar phase Connect, and the top of pull bar perforation passes through lock nut and upper strata concrete modular is locked.
Further, the installation pull bar is connected by attaching nut with pre-buried pull bar.
Further, it is provided with the center of the joint face of the neighbouring concrete modular for installing sealing rod Groove, to improve the waterproof effect in whole cofferdam.
Further, the bed course is the bed course made of high density extruded sheet.
Further, the cast-in-site stripe is compacted clay cast-in-site stripe, or is cast-in-place expansive concrete cast-in-site stripe.
Construct the method in above-mentioned assembly concrete cofferdam, comprise the following steps:
1) casting concrete basis, and the pre-buried pull bar during concrete foundation pours, then, will connect spiral shell Mother is installed to the top of pre-buried pull bar, with the basic and pre-buried pull bar of fixing concrete;
2) the first layer concrete modular in the concrete foundation upper mounting plate wall module of step 1), then, first Bed course is laid in layer concrete module, and sealing rod is installed on the groove of concrete modular, is repeated the above steps, until board wall Top layer concrete modular is installed in place in module, forms board wall module, wherein, pull bar perforation and concrete in concrete modular On the basis of pre-buried pull bar alignment;
3) installation pull bar is penetrated per the pull bar in layer concrete module along the board wall module of step 2), and with being connected Nut alignment, rotation, until being connected firmly, then, precompressed sandbag are placed on top layer concrete modular and carries out precompressed, are eliminated The deformation of bed course, after precompressed terminates, draw lever locking by top layer concrete modular and is installed using lock nut, unloads sandbag, weight Multiple above-mentioned steps, install remaining each section of board wall module;
4) cast-in-site stripe is poured between each section of board wall module in step 3), each section of board wall module is connected, formation is enclosed Weir.
The invention has the advantages that:
1st, cofferdam agent structure is made up of concrete modular in the present invention, meets standardization and modular trend, and mould Block structure facilitates cofferdam demolition, and repeatable utilization, greatly reduces engineering cost;
2nd, tensed in the present invention between levels concrete module by pull bar, structure is more stable, and concrete sealing The installation of bar, further increase the waterproof effect in whole cofferdam.
3rd, structure of the present invention is novel, strong applicability, construction is simple, safe, solves concrete cofferdam for a long time Problem difficult, that cost is high is removed, there is very high promotional value.
Brief description of the drawings
Fig. 1 is the front view in assembly concrete cofferdam of the present invention;
Fig. 2 is Fig. 1 of the present invention vertical cross section figure.
In figure:Board wall module 1 is (wherein:Concrete modular 11;Concrete modular 11 is perforated including lifting hole(eyelet) 111, pull bar again 112), bed course 2, cast-in-site stripe 3, concrete foundation 4, pull bar 5 be (wherein:Pre-buried pull bar 51, installation pull bar 52), lock nut 6, even Connected nut 7, sealing rod 8, groove 9.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
As shown in figure 1, assembly concrete cofferdam of the present invention, including the concrete mould by several cuboid platy structures The board wall module 1 that block 11 is assembled;It is provided with the board wall module 1 between bilevel concrete modular 11 by highly dense Bed course 2 made of extruded sheet is spent, and per the center alignment of layer concrete module 11 in board wall module 1, wherein, concrete modular 11 Center refer to the x of concrete modular 11 to, y to the intersection point with z to center line;Pass through cast-in-site stripe 3 between the board wall module 1 It is connected, and in concrete foundation 4, wherein, compacting is made using clay compaction in layers or cast-in-place expansive concrete in cast-in-site stripe 3 Clay cast-in-site stripe 3 or cast-in-place expansive concrete cast-in-site stripe 3.
As shown in Fig. 2 the left and right side of the concrete modular 11 is provided with 2 lifting hole(eyelet)s 111;The lifting hole(eyelet) 111 is right The z for claiming to be distributed in the left and right side of concrete modular 11 is distributed in the left and right side of concrete modular 11 to center line both sides The y in face is on center line;In addition, it is provided with the center of the joint face of neighbouring concrete modular 11 for installing sealing The groove 9 of bar 8, sealing rod 8 can be rubber water-proof bar 8, and it is i.e. inflatable that the sealing rod 8 meets water.
And as depicted in figs. 1 and 2, the upper and lower surface of the concrete modular 11 be provided with 4 or 8 be used for install drawing The pull bar perforation 112 of the insertion of bar 5, but pull bar perforation 112 is also not limited to 4 or 8, or the even number numbers such as 12, Size according to concrete modular 11 carries out the setting of respective numbers, and the size of single concrete modular 11 is bigger, pull bar perforation 112 number accordingly increases;Pull bar perforation 112 be symmetrically distributed in the x on the upper and lower surfaces of concrete modular 11 to y to Center line both sides, and run through in board wall module 1 per the pull bar perforation about 112 in layer concrete module 11;
The pull bar 5 includes pre-buried pull bar 51 and installation pull bar 52;The pre-buried pull bar 51 is embedded in concrete foundation 4 On;The installation pull bar 52 passes through the pull bar perforation 112 mutually run through in every layer concrete module 11 in board wall module 1 and passed through Attaching nut (7) is connected with pre-buried pull bar 51, and the top of pull bar perforation 112 passes through lock nut 6 and upper strata concrete modular 11 lockings.
Wherein, above-mentioned x to, y to z to be horizontally oriented respectively, perpendicular to x to z to the direction of plane, vertical side To.
Construct the method in above-mentioned assembly concrete cofferdam, comprise the following steps:
1) casting concrete basis 4, and the pre-buried pull bar 51 during concrete foundation 4 pours, then, by even Connected nut 7 is installed to the top of pre-buried pull bar 51, with fixing concrete basis 4 and pre-buried pull bar 51;
2) the first layer concrete modular 11 in the upper mounting plate wall module 1 of concrete foundation 4 of step 1), then, Bed course 2 is laid on first layer concrete modular 11, and sealing rod 8 is installed on the groove 9 of concrete modular 11, repeats above-mentioned step Suddenly, until top layer concrete modular 11 is installed in place in board wall module 1, board wall module 1 is formed, wherein, in concrete modular 11 Pull bar perforation 112 alignd with the pre-buried pull bar 51 in concrete foundation 4;
3) installation pull bar 52 is penetrated per the pull bar perforation 112 in layer concrete module 11 along the board wall module 1 of step 2), And be aligned, rotate with attaching nut 7, until being connected firmly, then, it is enterprising that precompressed sandbag is placed on top layer concrete modular 11 Row precompressed, the deformation of bed course 2 is eliminated, after precompressed terminates, pull bar 52 by top layer concrete modular 11 and is installed using lock nut 6 Locking, unloads sandbag, repeats the above steps, and installs remaining each section of board wall module 1;
4) cast-in-site stripe is poured between each section of board wall module 1 in step 3), each section of board wall module 1 is connected, formed Cofferdam.
Other parts not being described in detail belong to prior art.

Claims (10)

1. assembly concrete cofferdam, it is characterised in that:Including the board wall mould being assembled by several concrete modulars (11) Block (1);Bed course (2), and board wall module are provided with the board wall module (1) between bilevel concrete modular (11) (1) center alignment in per layer concrete module (11);It is connected between the board wall module (1) by cast-in-site stripe (3), and is located at In concrete foundation (4).
2. assembly concrete cofferdam according to claim 1, it is characterised in that:The concrete modular (11) is rectangular Body platy structure;The left and right side of the concrete modular (11) is provided with lifting hole(eyelet) (111);The lifting hole(eyelet) (111) is symmetrically divided The z of the left and right side of concrete modular (11) is distributed in center line both sides.
3. the assembly concrete cofferdam according to claims 2, it is characterised in that:The lifting hole(eyelet) (111) is 2, and The y of the left and right side of concrete modular (11) is distributed in on center line.
4. the assembly concrete cofferdam according to any claim in claims 1 to 3, it is characterised in that:It is described mixed The upper and lower surface of solidifying clay model block (11) is provided with the pull bar perforation (112) of the insertion for installing pull bar (5);The pull bar is worn Hole (112) be symmetrically distributed in the x on the upper and lower surface of concrete modular (11) to y to center line both sides, and board wall module (1) In run through up and down per the pull bar perforation (112) in layer concrete module (11).
5. assembly concrete cofferdam according to claim 4, it is characterised in that:The pull bar perforation (112) is 4, Or for 8.
6. assembly concrete cofferdam according to claim 5, it is characterised in that:The pull bar (5) includes pre-buried pull bar (51) and installation pull bar (52);The pre-buried pull bar (51) is embedded in concrete foundation (4);The installation pull bar (52) passes through The pull bar perforation (112) mutually run through in every layer concrete module (11) in board wall module (1) is connected with pre-buried pull bar (51), and Locked by lock nut (6) and upper strata concrete modular (11) at the top of pull bar perforation (112).
7. assembly concrete cofferdam according to claim 6, it is characterised in that:The installation pull bar (52) passes through connection Nut (7) is connected with pre-buried pull bar (51).
8. assembly concrete cofferdam according to claim 7, it is characterised in that:The neighbouring concrete modular (11) groove (9) for installing sealing rod (8) is provided with the center of joint face.
9. assembly concrete cofferdam according to claim 8, it is characterised in that:The bed course (2) is to be squeezed by high density Bed course made of mould plate (2);Described cast-in-place (3) band is compacted clay cast-in-site stripe, or is cast-in-place expansive concrete cast-in-site stripe.
10. the method in the assembly concrete cofferdam in claim 1 to 9 of constructing described in any claim, including following step Suddenly:
1) casting concrete basis 4, and the pre-buried pull bar 51 during concrete foundation 4 pours, then, will connect spiral shell Mother 7 is installed to the top of pre-buried pull bar 51, with fixing concrete basis 4 and pre-buried pull bar 51;
2) the first layer concrete modular 11 in the upper mounting plate wall module 1 of concrete foundation 4 of step 1), then, first Bed course 2 is laid in layer concrete module 11, and sealing rod 8 is installed on the groove 9 of concrete modular 11, is repeated the above steps, Until top layer concrete modular 11 is installed in place in board wall module 1, board wall module 1 is formed;
3) penetrated along step 2) in board wall module 1 per the pull bar perforation 112 in layer concrete module 11 and pull bar 52 is installed, and with Attaching nut 7 is aligned, rotated, until being connected firmly, then, precompressed sandbag is placed on top layer concrete modular 11 and carried out in advance Pressure, after precompressed terminates, top layer concrete modular 11 and installation pull bar 52 are locked using lock nut 6, sandbag is unloaded, in repetition Step is stated, remaining each section of board wall module 1 is installed;
4) cast-in-site stripe is poured between each section of board wall module 1 in step 3), each section of board wall module 1 is connected, form cofferdam.
CN201710544004.XA 2017-07-05 2017-07-05 Assembly concrete cofferdam and its construction method Pending CN107386305A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710544004.XA CN107386305A (en) 2017-07-05 2017-07-05 Assembly concrete cofferdam and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710544004.XA CN107386305A (en) 2017-07-05 2017-07-05 Assembly concrete cofferdam and its construction method

Publications (1)

Publication Number Publication Date
CN107386305A true CN107386305A (en) 2017-11-24

Family

ID=60335426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710544004.XA Pending CN107386305A (en) 2017-07-05 2017-07-05 Assembly concrete cofferdam and its construction method

Country Status (1)

Country Link
CN (1) CN107386305A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114737582A (en) * 2022-05-20 2022-07-12 中交第一航务工程局有限公司 Assembled gravity type concrete cofferdam and construction method thereof
CN114875938A (en) * 2022-05-12 2022-08-09 南京西部路桥集团有限公司 Assembled reinforced concrete cofferdam and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5826107A (en) * 1981-08-10 1983-02-16 Motoyuki Nakada Cut-off work by concrete block
EP0399870A1 (en) * 1989-05-26 1990-11-28 Siplast S.A. Prefabricated element for the construction of a dam facing and construction method for such a dam
CN1231013A (en) * 1996-09-19 1999-10-06 鲍尔建材有限公司 Fiber bale composite structural building system
CN204626427U (en) * 2015-03-18 2015-09-09 李伟 Assembling cofferdam
CN204662362U (en) * 2015-04-07 2015-09-23 中国电建集团贵阳勘测设计研究院有限公司 Riverbed type factory building normal state concrete water retaining structure
CN204715379U (en) * 2015-05-13 2015-10-21 广西壮族自治区水利电力勘测设计研究院 Step concrete cofferdam
CN206941624U (en) * 2017-07-05 2018-01-30 中交第二航务工程局有限公司 Assembly concrete cofferdam

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5826107A (en) * 1981-08-10 1983-02-16 Motoyuki Nakada Cut-off work by concrete block
EP0399870A1 (en) * 1989-05-26 1990-11-28 Siplast S.A. Prefabricated element for the construction of a dam facing and construction method for such a dam
CN1231013A (en) * 1996-09-19 1999-10-06 鲍尔建材有限公司 Fiber bale composite structural building system
CN204626427U (en) * 2015-03-18 2015-09-09 李伟 Assembling cofferdam
CN204662362U (en) * 2015-04-07 2015-09-23 中国电建集团贵阳勘测设计研究院有限公司 Riverbed type factory building normal state concrete water retaining structure
CN204715379U (en) * 2015-05-13 2015-10-21 广西壮族自治区水利电力勘测设计研究院 Step concrete cofferdam
CN206941624U (en) * 2017-07-05 2018-01-30 中交第二航务工程局有限公司 Assembly concrete cofferdam

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114875938A (en) * 2022-05-12 2022-08-09 南京西部路桥集团有限公司 Assembled reinforced concrete cofferdam and construction method thereof
CN114875938B (en) * 2022-05-12 2024-03-08 南京西部路桥集团有限公司 Assembled reinforced concrete cofferdam and construction method thereof
CN114737582A (en) * 2022-05-20 2022-07-12 中交第一航务工程局有限公司 Assembled gravity type concrete cofferdam and construction method thereof

Similar Documents

Publication Publication Date Title
KR101400295B1 (en) Form for wave dissipating block and forming method thereby
CN105424437A (en) Mould for manufacturing three-dimensional compound rock stratum circular tunnel and using method thereof
CN107386305A (en) Assembly concrete cofferdam and its construction method
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN206941624U (en) Assembly concrete cofferdam
CN210737843U (en) Prefabricated assembled concrete shear force wall
CN211872847U (en) Wall body transformation structure suitable for old flood control wall
CN107988994B (en) Universal prestress ecological landscape combined revetment
JPS6245809A (en) Construction for dam
CN103225282B (en) Structure for mending and reinforcing undermining area at bottom of underwater structure of gravity wharf and method
CN207686288U (en) The manufacture of the horizontal hole to be provided of wall and plugging device
KR100934980B1 (en) Precast concrete forms for the capconcrete of caisson and the construction method using the same
CN108972869B (en) Die and method for producing embedded type post-grouting precast tubular pile
CN209114422U (en) A kind of sealing template
CN116290078B (en) Prefabricated assembled barricade
CN109267543A (en) A kind of sealing template
CN218521840U (en) Self-embedded retaining wall and protective net combined body
CN110644645A (en) Prefabricated column wall and construction method of vertical joint of prefabricated column wall
CN105133664A (en) Combined frame type isolation protection system and construction method thereof
JP2000230240A (en) Stack block for retaining wall
CN109989431A (en) The underground structure and its construction method of buoyancy force of underground water are resisted using campshed
JP2004263490A (en) Underground composite wall
CN210507505U (en) Prefabricated assembling type sheet mould
CN109577456A (en) The construction method of environmental prefabricated assembling type reinforced concrete chute drainage system
JPS60233224A (en) Continuous wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171124