CN211872847U - Wall body transformation structure suitable for old flood control wall - Google Patents

Wall body transformation structure suitable for old flood control wall Download PDF

Info

Publication number
CN211872847U
CN211872847U CN201921533423.4U CN201921533423U CN211872847U CN 211872847 U CN211872847 U CN 211872847U CN 201921533423 U CN201921533423 U CN 201921533423U CN 211872847 U CN211872847 U CN 211872847U
Authority
CN
China
Prior art keywords
wall
water retaining
shaped water
flood prevention
old flood
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921533423.4U
Other languages
Chinese (zh)
Inventor
林晓波
谭斌
常琨
李渭东
徐闯
李晓静
李鹏
尹科伟
夏忠明
程相晓
许欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Original Assignee
Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd filed Critical Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority to CN201921533423.4U priority Critical patent/CN211872847U/en
Application granted granted Critical
Publication of CN211872847U publication Critical patent/CN211872847U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a wall body transformation structure suitable for old flood walls, which comprises a plurality of L-shaped water retaining walls standing on the old flood walls, wherein staggered structures which can be mutually occluded are respectively arranged at two ends of the wall body of the L-shaped water retaining walls; reserving a plurality of connecting holes on the split level surface of the split level structure; and two adjacent L-shaped water retaining walls are mutually meshed, combined and installed together and are fixedly connected through the connecting holes by bolts. The utility model discloses simple structure, the construction is convenient, quick, with low costs, and can install in multiple old flood prevention wall structurally on the basis of not destroying former flood prevention wall structure to improve the flood prevention ability of former flood prevention wall.

Description

Wall body transformation structure suitable for old flood control wall
Technical Field
The utility model relates to a flood prevention engineering technical field, in particular to wall body transformation structure suitable for old flood prevention wall.
Background
When an urban river is treated, in order to improve the flood prevention capability of the river, river flood prevention walls are built on river banks on two sides of the river. At present, the well-known wall structure of the urban river flood control wall comprises: pile wall structure, earth and stone structure and building block structure. The flood control wall has various shapes including a slope shape, an L shape, a ladder step multi-stage greening shape and the like. The flood control system can adapt to the basic situation of the river channel no matter what structure or shape is in the initial construction, and can achieve the due flood control capability.
However, as the running time of the urban river channel increases, the river water sludge is precipitated, the bottom of the river bed is continuously improved, and the original flood prevention capacity is greatly weakened.
In order to solve the problems, the traditional method is to excavate and remove the silt. However, this approach is not only very engineering intensive, but also requires a lot of time and capital. In addition, due to the fact that the climate is warmed, the magnitude and the frequency of rainstorm are increased year by year, and new pressure is brought to urban flood control safety work.
SUMMERY OF THE UTILITY MODEL
The utility model aims at: the utility model provides a wall body transformation structure suitable for old flood prevention wall, it not only can be applicable to current multiple flood prevention wall structure, but also can install on original flood prevention wall on the basis that does not change wall body structure to play the effect that strengthens flood prevention ability, improve the urban landscape.
The utility model provides a technical scheme that its technical problem adopted is:
a wall body transformation structure suitable for old flood walls comprises a plurality of L-shaped water retaining walls standing above the old flood walls, wherein staggered structures capable of being mutually occluded are arranged at two ends of the wall body of each L-shaped water retaining wall respectively; reserving a plurality of connecting holes on the split level surface of the split level structure; and two adjacent L-shaped water retaining walls are mutually meshed, combined and installed together and are fixedly connected through the connecting holes by bolts.
As the preferred technical scheme, the L-shaped water retaining wall comprises a vertical surface and a horizontal surface; the connecting holes are formed in the vertical surface of the L-shaped water retaining wall, and a green belt is arranged on the horizontal surface of the L-shaped water retaining wall.
As a preferred technical scheme, the top end of the vertical surface of the L-shaped water retaining wall is provided with a landscape protective guard.
As a preferred technical scheme, the L-shaped water retaining wall is a prefabricated reinforced concrete member, so that the construction speed can be accelerated.
As the preferred technical scheme, the staggered floor structure is provided with the water stop rubber strip which can expand when meeting water, so that water leakage between joints of the two L-shaped water retaining walls can be prevented.
As a preferred technical scheme, limiting members are respectively arranged at the front and the rear of the L-shaped water retaining wall, are installed on the embedded bars of the old flood control wall and are fixed through pouring concrete.
As a preferred technical scheme, the limiting component is in a strip shape or a block shape.
As a preferred technical scheme, the L-shaped water retaining wall is fixedly connected with an old flood prevention wall by adopting a pile wall structure.
As a preferred technical scheme, the L-shaped water retaining wall is fixed on an old flood prevention wall in a cast-in-place mode.
As the preferred technical scheme, an expansion joint is arranged between two adjacent L-shaped water retaining walls.
The utility model has the advantages that: the utility model discloses simple structure, it is convenient to be under construction, and can install in multiple old flood prevention wall structurally on the basis of not destroying former flood prevention wall structure to improve the flood prevention ability of former flood prevention wall. The scheme can enlarge the utilization space, beautify the environment, and the combination of the new flood control wall and the old flood control wall reduces the construction cost, is quick to construct, and reduces the pressure brought to urban traffic during construction.
Drawings
FIG. 1 is a right side schematic view of an L-shaped water retaining wall.
Fig. 2 is a left side structure schematic view of the L-shaped water retaining wall.
Fig. 3 is a schematic view of a pile wall type old flood control wall modification structure.
Fig. 4 is a schematic view of a prefabricated masonry type old flood control wall reconstruction structure.
Fig. 5 is a schematic view of a modified structure of the earth-stone masonry old flood control wall.
In the figure: 1-L-shaped water retaining wall, 2-connecting hole, 3-water-stopping adhesive tape, 4-bolt, 5-limiting component, 6-pile wall type flood prevention wall, 7-landscape protective fence and 8-green belt; 9-pile wall, 11-split structure, 61-prefabricated masonry flood control wall and 62-earth-stone masonry flood control wall.
Detailed Description
The following is combined with the attached drawings. The utility model is further explained.
The utility model provides a wall body transformation structure suitable for old flood prevention wall is formed by 1 concatenation combinations of a plurality of L type breakwater, and stands on old flood prevention wall.
Wherein, the specific structure of the L-shaped water retaining wall 1 is as shown in fig. 1 and 2, two staggered structures 11 capable of being engaged with each other are respectively arranged at two ends of the wall body of the L-shaped water retaining wall 1, and two connecting holes 2 are reserved on the staggered surface of the staggered structures 11
The L-shaped water retaining wall 1 comprises a vertical surface and a horizontal surface. Wherein, two connecting holes 2 are vertically arranged on the vertical surface of the L-shaped water retaining wall 1 in parallel. Two adjacent L-shaped water retaining walls 1 are mutually meshed, combined and installed together and are fixedly connected together through connecting holes 2 by bolts 4.
In addition, in order to prevent water leakage between the joints of the two L-shaped water retaining walls 1, a water-stopping rubber strip 3 is arranged on the staggered structure 11, and the water-stopping rubber strip 3 can expand when meeting water, so that the gaps can be blocked.
Example 1: fig. 3 shows a modified structure of a pile wall type old flood control wall, which comprises: the pile wall type flood prevention wall 6 is supported at the bottom through the original front row piles and the original rear row piles, and greening is arranged on the pile wall type flood prevention wall 6. Therefore, when the construction and reconstruction are carried out, firstly, green belt planting soil on the original pile wall type flood prevention wall 6 is removed, the hole planting bars are firstly drilled on the original pile wall type flood prevention wall 6, concrete is poured, and then the limiting member 5 is formed, wherein the limiting member 5 is a reinforced concrete block structure, and the front row and the rear row are arranged.
Pouring a small amount of mortar in the stop block structure, hoisting the L-shaped water retaining wall 1 into the front and rear two rows of limiting members 5, shaking for leveling, backfilling planting soil, and arranging a green belt 8 on the horizontal plane of the L-shaped water retaining wall 1. The top end of the vertical surface of the L-shaped water retaining wall 1 is provided with a landscape protective guard 7.
Example 2: fig. 4 shows that a prefabricated brickwork formula old flood prevention wall reforms transform structure, to the old flood prevention wall of this kind of structure, when reforming transform it, newly-built L type breakwater 1 stands on prefabricated masonry formula flood prevention wall 61 through cast-in-place mode. The method comprises the steps of dismantling the surface of an old flood control wall structure, weaving new flood control wall reinforcing steel bars, installing templates, pouring concrete, arranging an expansion joint every 6m or so, backfilling planting soil and greening.
Example 3: what figure 5 shows is an old flood wall of earth and stone masonry structure reforms transform structure, to the old flood wall of this kind of structure, when reforming transform it, newly-built L type breakwater 1 adopts the fixed connection mode of pile wall 9 to erect in earth and stone masonry formula flood wall 62, can alleviate the upper portion load of old flood wall like this. Firstly, driving piles or drilling piles, breaking pile heads to expose reinforcing steel bars, connecting the reinforcing steel bars of the newly-built L-shaped water retaining wall 1 with the pile head reinforcing steel bars of the pile wall 9, and pouring a concrete structure to form an integral structure.
In addition, when a new L-shaped water retaining wall 1 is built, an emergency repair channel which is convenient for equipment and personnel to enter and exit is suggested to be added at a certain distance.
The basic principles and the main features of the solution and the advantages of the solution have been shown and described above. It will be understood by those skilled in the art that the present solution is not limited to the embodiments described above, which are described in the specification and illustrated only to illustrate the principles of the solution, but that various changes and modifications may be made to the solution without departing from the spirit and scope of the solution, and these changes and modifications are intended to be within the scope of the claimed solution. The scope of the present solution is defined by the appended claims and equivalents thereof.

Claims (10)

1. The improved wall body structure suitable for the old flood prevention wall is characterized by comprising a plurality of L-shaped water retaining walls standing above the old flood prevention wall, wherein staggered structures capable of being mutually occluded are respectively arranged at two ends of the wall body of each L-shaped water retaining wall; reserving a plurality of connecting holes on the split level surface of the split level structure; and two adjacent L-shaped water retaining walls are mutually meshed, combined and installed together and are fixedly connected through the connecting holes by bolts.
2. The wall body transformation structure suitable for the old flood prevention wall according to claim 1, wherein the L-shaped water retaining wall comprises a vertical surface and a horizontal surface; the connecting holes are formed in the vertical surface of the L-shaped water retaining wall, and a green belt is arranged on the horizontal surface of the L-shaped water retaining wall.
3. The wall body transformation structure suitable for the old flood prevention wall according to claim 2, wherein a landscape protective fence is arranged at the top end of the vertical surface of the L-shaped water retaining wall.
4. The wall body transformation structure suitable for the old flood prevention wall according to claim 1, wherein the L-shaped water retaining wall is a prefabricated reinforced concrete member.
5. The wall body reconstruction structure suitable for the old flood control wall according to claim 1, wherein a water stop rubber strip is arranged on the staggered layer structure.
6. The wall body transformation structure suitable for the old flood prevention wall according to claim 1, wherein limiting members are respectively arranged at the front and the rear of the L-shaped water retaining wall, are installed on the planting bars of the old flood prevention wall, and are fixed by pouring concrete.
7. The wall body transformation structure suitable for the old flood prevention wall according to claim 6, wherein the limiting members are in a shape of a strip or a block.
8. The wall body transformation structure suitable for the old flood prevention wall according to claim 1, wherein the L-shaped water retaining wall is fixedly connected with the old flood prevention wall by adopting a pile wall structure.
9. The wall body transformation structure suitable for the old flood prevention wall according to claim 1, wherein the L-shaped water retaining wall is fixed on the old flood prevention wall in a cast-in-place mode.
10. The wall body transformation structure suitable for the old flood prevention wall according to claim 9, wherein an expansion joint is arranged between two adjacent L-shaped water retaining walls.
CN201921533423.4U 2019-09-16 2019-09-16 Wall body transformation structure suitable for old flood control wall Active CN211872847U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921533423.4U CN211872847U (en) 2019-09-16 2019-09-16 Wall body transformation structure suitable for old flood control wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921533423.4U CN211872847U (en) 2019-09-16 2019-09-16 Wall body transformation structure suitable for old flood control wall

Publications (1)

Publication Number Publication Date
CN211872847U true CN211872847U (en) 2020-11-06

Family

ID=73241265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921533423.4U Active CN211872847U (en) 2019-09-16 2019-09-16 Wall body transformation structure suitable for old flood control wall

Country Status (1)

Country Link
CN (1) CN211872847U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863210A (en) * 2021-09-23 2021-12-31 中国二十冶集团有限公司 New and old flood control wall connection method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863210A (en) * 2021-09-23 2021-12-31 中国二十冶集团有限公司 New and old flood control wall connection method

Similar Documents

Publication Publication Date Title
CN110158600A (en) A kind of Adjacent Pit synchronizes the construction method of the asynchronous backfill of excavation
CN201762710U (en) Pile-wall combined enclosing structure for offshore deep foundation pit
CN106522236A (en) Structure for shoring of foundation trench and construction method
CN110777806B (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
CN211872847U (en) Wall body transformation structure suitable for old flood control wall
CN212561606U (en) Row pile retaining wall with permanent retaining structure
CN210263073U (en) Supporting construction that adjacent foundation ditch synchronous excavation was asynchronously backfilled
CN102296620B (en) Curtain water-stop slope wall and construction method thereof
CN216640647U (en) Mountain area is faced river steep bank slope pile foundation platform
KR100641355B1 (en) Construction method of corrugated steel pipe structure
CN212316937U (en) Composite steel plate wall semi-rigid cantilever foundation pit supporting system
CN105625299B (en) A kind of wall board type Novel underground diaphragm wall and its construction method
CN114263187A (en) Foundation pit bottom plate force transmission structure and construction method thereof
CN211872848U (en) Prefabricated assembled flood prevention view dykes and dams structure
CN1204714A (en) Method for forming retaining wall
CN112942377A (en) Novel support shear-resistant structure and construction method thereof
KR200369479Y1 (en) The land-side protection wall panel
CN206233244U (en) The supporting construction of foundation ditch
CN113202137A (en) Row pile retaining wall with permanent retaining structure and construction method
CN205742292U (en) A kind of to the protection structure of existing tunnel below newly-built underground engineering
CN207176697U (en) A kind of buttress type diaphragm wall foundation pit supporting construction
KR200225641Y1 (en) Structure of caisson soil protection four concrete caisson of bridge
CN215441921U (en) Novel support shear structure
CN216515668U (en) Anchor draws fender formula stake siding wall structure
CN212153396U (en) Outer T type roof beam supporting construction of foundation ditch hole

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant